Agenda
• Project Overview and Schedule
• Memorandum of Agreement (MOA)
• Advanced Utility Relocation
• Contact Information
• Q&A
2
Section 2 – Construction Process
• Relocation of Third Party Utilities
• Southern California Edison
• Southern California Gas
• AT&T
• Design-Build of Station and Tunnels
• Includes relocation of City Utilities
8
Section 2 - Metro’s Proposed Schedule
Purple Line Extension – Section 2
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Draft SEIS to be complete for public review
3rd Party Utility Relocation
Final SEIS to be complete
Demo Station Entrance*
Design-Builder Utility Relocation*
Piling and Decking*
Station Construction / Tunneling*
Open for Revenue Services
9
North Santa Monica Blvd Reconstruction
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Construction Schedule
*Dates and durations based on Metro’s Assumptions. Design Build Contractor may have different means and methods and may forecast different dates
Purpose of Memorandum of Agreement (MOA)
Ensure that the project complies with the standards and requirements of the City
and minimize the impact to the City residents and businesses.
10
MOA Focus Areas
• Allowable Work Hours and Workdays
• Construction Staging
• Traffic
• Parking
• Noise, Light and Dust Mitigation and Monitoring
• Independent Compliance Monitor for enforcement of permit conditions
• Business Mitigation Assistance
•Eat, Shop and Play Program (Metro)
•Business Interruption Fund (Metro)
•Business Mitigation Program (Metro)
•My Beverly Hills (BH Chamber)
• Tree removal and replacement
• Advance notification system
Section 2 MOA Development & Approval
• Input from community and key stakeholders
• Negotiations between the City and Metro
• City Council approval
• Metro Board of Directors approval
12
North Santa Monica Blvd Reconstruction
2017 2018
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
Construction
Third Party Utilities - Anticipated Schedule
Westside Purple Line Extension – Section 2
2017 2018
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
Southern California Edison (SCE) Q1 2017
Southern California Gas (SCG) Q2 2017
AT&T – Q4 2017
13
Section 2 Items coming to Council:
• Encroachment Permit to install temporary Sound Monitoring Equipment
• Permit application for Southern California Edison for the use of the public right-of-
way
15
• 28 construction work days
• Monday-Friday
• 9 am - 4 pm
• All business access
maintained
Reeves access
maintained with
1 lane
Alley access maintained
Maintain 2 lanes in each direction
Phase 1 – SoCal Edison Civil Work
16
Maintain 2 lanes in
each direction
Alley access maintained
• 22 construction work days
• Monday-Friday
• 9 am – 4 pm
• All business access
maintained
Reeves access
maintained
Phase 2 – SoCal Edison Civil Work
17
Maintain 2 lanes
in each direction
Single-lane Alley access
maintained
• 10 construction work days
• Monday-Friday
• 4 pm – 11 pm
• All business access
maintained
Phase 3 – SoCal Edison Civil Work
Section 2 – SoCal Edison Civil Work
NEXT STEPS
• Request City Council approval for permits associated with third party utilities
• First permit is for the Southern California Edison Civil work
• Planned power outages do not occur until SCE is ready to pull the new electrical cables into the newly installed underground infrastructure.
• Work with community to develop MOA
• Additional community meetings prior to future permits
• Individual outreach meetings with community stakeholders
18
Stay in Touch
City Webpage: www.beverlyhills.org/purpleline
Email: [email protected]
19
Phone:Metro 24-Hour Hotline: (213) 922-6934
Beverly Hills Info Line : (310) 285-2467
Beverly Hills Chamber of Commerce: (310) 248-1000
Nixle: Text BEVHILLS to 888777
@CityofBevHills /CityofBeverlyHills