Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017
Agenda
• Advance Utility Relocation (AUR) Schedule
• Southern California Edison (SCE) overview
• Street Impacts
• Sunday work: 10am-6pm
• Left turn restrictions to Beverly and Canon
• Directional closure on S. Reeves
2
Purple Line Extension Project Alignment
3
Sections 1, 2 & 3 Status
4
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Under Construction Forecasted Schedule Section Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.59Miles
New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega
Wilshire/Rodeo Century City/ Constellation
Westwood/UCLA Westwood/VA Hospital
Pre-Construction Activities
Complete 2016 - 2018 2016-2018
Construction 2015 - 2023 2018 – 2024* 2018 – 2024*
Operations 2023 2024* 2024*
3
Rendering of AUR work
• Utility relocations: Clear the way for station construction Telecom, gas, water, power, sewer Ensure continued utility service
• Typical process: Day hours requested by City of Beverly Hills Maintain at least two lanes of traffic in each direction Truck/crew leave and lanes reopen at the end of each work
period Noisiest activities include saw-cutting and jack-hammering
• Traffic Plans: Traffic plans will be approved by Beverly Hills City Council Generally based on CA MUTCD (manual and uniform traffic
control devices)
Pre-Construction Advanced Utility Relocation (AUR)
Wilshire/Rodeo Station Box
4
Wilshire/Rodeo AUR Schedule
5
Q1 Q2 Q3 Q42018
Q1 Q2 Q3 Q42017 2019
Q1 Q2 Q3 Q4
Power Power Cable Pulling
Gas
AT&T AT&T - Cable Pulling
As of April 2017. Schedule subject to change
• SCE Phase 1: July 14, 2017 (earliest) • SCE Phase 2: September 2017 • SCG: September 2017 • AT&T: January 2018 • Wet utilities: April 2018
– Water, storm drain, sewer
Advance Utility Relocation Anticipated Start Dates
Recent AUR work at La Cienega Station 6
Southern California Edison = Red Power
SCE Phase 1, Original Plan
• Relocation of SCE lines located on alley between N. Canon Dr and N. Beverly Dr, crossing Wilshire Bl to S. Reeves Dr.
• First work is civil work, no outages
• Includes installation of traffic control devices, excavation and shoring, placement of temporary trench plates, utility construction, and surface restoration
• Proposed work hours: 9am to 4pm
• Proposed work Days: Monday thru Friday
• Traffic Stages
– Wilshire: 2 lanes each direction
– Alley: Local access only with flagger
– Reeves: Maintain local access with flagger
– Crosswalk closed south side of Wilshire at Reeves
• Flagger provided for detour south to alley
– EB Wilshire left turn restricted at NB Beverly and Cannon
• Anticipate 22 working days
8
How Did We Determine Days/Hours?
Option Impact
Night Work • Residents • Hotel guests
Weekend Work • Residents • Restaurant Lunch • Tourists
Minimize Work Area • Safety of workers • Liability on non-standard plans • Increased work days • Steel plates on street longer
Reduce Eastbound Wilshire: 1 left turn lane, 1 thru lane
• Safety issue • Traffic backup on Wilshire
Day Work • Restaurant Lunch
SCE Phase 1, Alternative
July 14th thru Fall 2017* • Proposed work hours: 9am to 4pm Mon-Fri, Sunday 10am to 6pm
• Alternative work days:
– Left turn restrictions
– Sunday (10am-6pm) to Wednesday (9am-4pm)
– Wilshire reduced to two lanes each direction
– Longer work window translates to longer duration of steel plates on street
12
*Council approval required. Subject to change.
Schedule Update
13
Original Anticipated* Stage Detour
Total Work days 60 44 Median removal 0 5 1 EB Wilshire left turn to NB Canon* 22 28 2, 3, 4 A, B, F, G WB Wilshire left turn to SB Canon* 19 15 2 C WB Wilshire left turn to SB Beverly* 22 22 2, 4 D EB Wilshire left turn to NB Beverly* 5 7 4 E SB Reeves from Wilshire 0 4 5A R-SB NB Reeves to Wilshire 0 7 5 R-NB
*Closures will overlap
• Adjustments may be made in the field, as necessary • Schedule may change due to unforeseen conditions
Stage 1 – 5 days*
Mon-Fri, 9am-4pm
14
*Subject to change
Stage 2 - 15 days* Sun 10am-6pm, M-W 9am-4pm
15
*Subject to change
Detour A: restaurant valet EB Wilshire to NB Canon, east
16
Detour B EB Wilshire to NB Canon, west
17
Detour C WB Wilshire to SB Canon
18
Detour D WB Wilshire to SB Beverly
19
Stage 3 – 6 days* Sun 10am-6pm, Mon-Wed 9am-4pm
20
*Subject to change
Detour A: restaurant valet EB Wilshire to NB Canon, east
21
Detour B EB Wilshire to NB Canon, west
22
Stage 4 – 7 days* Sun 10am-6pm, Mon-Wed 9am-4pm
23
*Subject to change
Detour D WB Wilshire to SB Beverly
24
Detour E EB Wilshire to NB Beverly
25
Detour F: EB Wilshire to NB Canon, east
26
Detour G EB Wilshire to NB Canon, west
27
Stage 5A – 4 days* Mon-Fri, 9am-4pm
28
*Subject to change
Detour R-SB EB Wilshire to SB Reeves
29
Stage 5 – 7 days* Mon-Fri, 9am-4pm
30
*Subject to change
Detour R-NB NB Reeves to Wilshire
31
Monitoring and Adjustment
• COBH/Metro traffic engineers will monitor traffic
• Signal timing adjustments
• Crosswalk timing adjustments
• Potential to deploy Traffic Control Officers (TCO)
• Potential to deploy BHPD for ticketing
• Any other adjustments as needed to work plans, traffic plans or detours
• Monitor bus stops and zones
32
Construction Philosophy
1.Humans!
2.Construction is dynamic.
3. Adjustments can be made.
33
Out of the Box Thinking • Close Cannon at Wilshire?
• Create roundabout • Pedestrian/event area • Traffic study to analyze
• Full closure of Wilshire? • Create pedestrian friendly zone • Sound walls to block noise • Could reduce overall schedule
*Council approval required.
Next Steps
• City Council on June 13, 2017
• Notification process
• 30 calendar days prior to work starting
• Email, website, social media
• 2 calendar days prior to work starting
• Hand delivered, email, website, social media
• Continued Outreach and Communication • Regularly scheduled community meetings
• “Traffic Alert” in local newspapers
• Newspaper, online and social media
35