69
E-425 VOL. 11 People's Republic of China World Bank Financed Jiangxi No.2 Highway Project Suichuan County Connecting Road Environmental Impact Assessment Report (Third Edition) Research Institute of Highway, MOC December 2000 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

E-425VOL. 11

People's Republic of China

World Bank Financed Jiangxi No.2 Highway Project

Suichuan County Connecting Road

Environmental Impact Assessment Report

(Third Edition)

Research Institute of Highway, MOC

December 2000

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

People's Republic of China

World Bank Financed Jiangxi No.2 Highway Project

Suichuan County Connecting Road

Environmental Impact Assessment Report

(Third Edition)

Research Institute of Highway, MOC

December 2000

Page 3: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Research Institute of Highway

Director Chen Guojing

Chief Engineer Liu shutao

Environment Protection Division

Division Head : Ye Huihai

Chief Engineer :Li zongyu

Examiner Ye Huihai

Project Team Leader : Yan Xiaolin Associate Research Fellow

(EIA Professional Competence Certificate. No. 0060 Beijing)

Project Team Member Shen yi, Associate Research Fellow (EIA Professional

Competence Certificate. No. 2116 );

Li xiyun, Senior Engineer(EIA Professional Competence

Certificate, No. 0909 Beijing);

Dong bochang, Engineer(EIA Professional Competence

Certificate, No. 08380):

Wang Fang, Engineer (EIA Profesional Competence

Certificate, No. 0098 Beijing):

Fan qingchun, Engineer (EIA Profesional Competence

Certificate, No. 0995 Beijing)

I

Page 4: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Contents

Chapter 1 General Provisions ........................................................... I

1.1 Foreword ..........................................................I1

1.2 Assessment Basis .......................................................... 1I

1 .3 Assessment Scope, Duration and Criteria .......................................................... 3

1.4 Targets for Environmental Protection ........................................................... 5

1.5 Assessment Factors and Method ......................................................... 6

1.6 Assessment Category and Key Points .......................................................... 7

Chapter 2 Project Overview .......................................................... 8

2.1 Alignment and Major Controlling Points ..........................................................8

2.2 Scale of Construction, Technical Standards & Quantities of Main Works ... 8

2.3 Traffic Volume Estimate ........................................................... 9

2.4 General Outline of Project ........................................................... 9

2.5 Investment Estimate and Financing .......................................................... 10

2.6 Time Arrangement for the Project ......................... ................................. 10

Chapter 3 Current Environmental Description & Assessment ................................... 11

3.1 Natural Environment .......................................................... 11

3.2 Social Environment .......................................................... 12

3.3 Ecological Environment .................... 14

3.4 Acoustic Environment .................... 16

3.5 Atmospheric Environment .................... 17

Chapter 4 Environment Impact Prediction & Assessment .................................... 18

4.1 Social Environment Impact Assessment ...................................................... 18

4.2 Ecological Environmental Impact Prediction & Assessment . . 20

4.3 Acoustic Environmental Impact Prediction & Assessment ...............................--. 22

4.4 Ambient Air Impact Prediction & Assessment .................................................. ..31

4.5 Environment Impact of Building Materials Quarries and Transport ................. 34

Chapter 5 Environmental Mitigation Measures ..................................................... 36

5.1 Design Stage ...................................................... 36

5.2 Construction Stage ...................................................... 36

5.3 Operation Stage ...................................................... 38

[

Page 5: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 6 Alternatives Analysis ....................................................... 40

6.1 "Without the project" analysis ..... .................................................. 40

6.2 Alignment selection procedure .................... ................................... 40

6.3 Environmental Benefits of the Proposed Project ............................................... 40

Chapter 7 Environmental Monitoring and Management ............. ......................... 41

7.1 Environmental Monitoring ....................................................... 41

7.2 Environmental Management Organizations ....................................... 42

7.3 Budget Estimate for Environmental Monitoring .................................. .... 46

Chapter 8 Public Participation .. .................................... 47

8.1 Survey Method and Contents ...................................... 47

8.2 Summary of the Survey .................. 47

8.3 Information Disclosures and Feedback ...................................... 49

8.4 Brief Summary ...................................... 50

Chapter 9 Assessment Conclusions ............................ ......... 51

9.1 Social Environment ...................I................... 1

9.2 Ecological Environment (including soil erosion, water environment) .. 1. I

9.3 Acoustic Environment ........................................ . .......... 52

9.4 Ambient Air .................................................... 53

9.5 Public Participation .................................................... 53

9.6 Environmental Investment and Management Plan ................ .............I .......... 54

9.7 Comprehensive Assessment .................................................... 54

Annex I Overview of the Assessment Unit and Staff MemberAnnex II ReferenceAnnex III Public Participation and Questionnaires (group inquiry)Annex IV Environmental and Resettlement Bulletin for the World Bank Financed

Jiangxi No.2 Highway Project Taihe-Ganzhou ExpresswayAnnex V List of Tables and FiguresAnnex VI List of relevant reports

11

Page 6: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 1 General Provisions

1.1 Foreword

Suichuan linking road-a part of Jiangxi No. 2 highway financed by the World

Bank loan is an important entry-exit passage connecting Suichuan county, Jinggangshan

City with Gan-Yue Expressway. The construction of it will play a very important role in

realizing the hub function of Gan-Yue Expressway, improving local comprehensive

transport network. It provides an important basic condition of opening to the outside

world for Suichuan countv.

According to the requirements and suggestions of the World Bank experts, we have

made the Envirorunental Assessment Report for this linking road separately.

The Research Institute of Highway (RIOH) under the MOC completed the EIA of

Suichuan Linking Road (Version 1) for Gan-Yue Expresswav Taihe-Ganzhou Section in

June.2000. In accordance with the suggestions in the aide-memoire at the second

preparatory mission by the World Bank environmental experts for Jiangxi NO.2

highway. the RIOH made modification and compiled this EIA report.

In December 2000, the EIA team again modified this EIA report in accordance with the

aide-memoire at the pre-evaluation mission of Gan-Yue Expressway (Taihe-Ganzhou Section) of the

World Bank environmental experts.

1.2 Assessment Basis

(1) People's Republic of China Law on Environmental Protection (26 Dec.. 1989):

(2) People's Republic of China Law on Water Pollution Control (I 5 Mav. 1996);

(3) People's Republic of China Law on Atmospheric Pollution control (29 Dec.,

1995)

(4) People's Republic of China Law on Environmental Noise Pollution Control (29

Oct.. 1996);

(5) People's Republic of China Law on Water and Soil Conservation (29 June.1991)

I

Page 7: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

(6) People's Republic of China Law on Land Management (29 Aug.,1998)

(7) Act of Environmental Protection and Management for Construction Projects

[The State Council, C. 253] (18 Nov., 1998);

(8) Announcement on Further Management of Environmental Impacts Assessment

of Construction Project Loaned From Intemational Financial Institution [(1993) No.324

Document on Environmental Supervision, issued by China National Environmental

Protection Bureau etc.];

(9) World Bank Operation Handbook OP/BP/GP 4.01 Environmental Assessment,

March 1999:

(10) Technical Guiding Provisions for Environmental Impacts Assessment

(HJ/T2.1-2.3-93, HT/T2.4-1995. HJ/T19-1997. issued by China National Environmental

Protection Bureau);

( 11) Environmental Protection and Management Measures for Construction

Projects of Communication (The Ministry of Communications. C.(90) 17);

(12) Specifications of Environmental Impacts Assessment for Construction Projects

of Highway (Tentative) [JTJO05-96, The Ministry of Communications]:

(13) Act of Environmental Protection for Jiangxi Provincial Construction Projects

(29 April. 1995);

(14) Program of Environmental Impacts Assessment for Taihe-Ganzhou Road

Section of Gan-Yue Expressway (Highway Research Institute. The Ministry of

Communications, March. 2000);

(15) Reply to the Reviewing Opinions on Program of Environmental Impacts

Assessment for Taihe-Ganzhou Road Section of Gan-Yue Expressway [(2000 No.58

Document on Environmental Supervision. issued by China National Environmental

Protection Bureau. 14 April. 2000);

(16) The Letter on Approval of Environmental Impacts Standard of Gan-Yue

Expressway (Taihe-Ganzhou Road Section) [(2000) No.14 Document on Ganzhou

Environment and Development. Jiangxi Provincial Environmental Protection

2

Page 8: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Department];

(17) Feasibility Study Report for Suichuan Linking Road Works of Taihe-Ganzhou

Road Section of Gan-Yue Expressway (Jiangxi Provincial Communications Design

Institute, Feb., 2000).

(18) Two-stage Preliminary Design of Gan-Yue Expressway (Suichuan Linking

Road) by Jiangxi Province Communications Design Institute, May, 1999.

(19) Two-stage Preliminary Design of Gan-Yue Expressway (Suichuan Linking

Road) by Jiangxi Province Communications Design Institute, September,2000

1.3 Assessment Scope, Duration and Criteria

1.3.1 Assessment Scope

The assessment scope is shown in Table 1- 1.

Table 1-1 Assessment Scope of Environmental Impacts of the Proposed Road

No. Environment Elements Assessment Scope

Area vw ithin 200m from twNo sides of the central line of the proposedI Acoustic Environment road and extending to 300m if there are sensitive locations as

schools. hospitals

Area 0ithin 200m from two sides of the central line of the proposed2 Atmospheric Environment road and extending to 300m if there are sensitive locations as

schools. hospitals

Area within 200m from two sides of the central line of the proposed3 Water Environment road. and Nvater regime within 200m upstream and 200m

dow nstream from the location of road bridge across the ri ver

Area within 200m from tv%o sides of the central line of the proposed4 Ecological Environment road. eanh borrow. v6aste areas and quarries

5 Social En. ironment The project impacted areas

1.3.2 Assessment Time Horizon

Construction: 2002.8-2004.8

Operation: 2004.2015 and 2023

1.3.3 Assessment Standards

According to the Letter on Approval of Environment Impacts Standard of Gan-Yue

Expressway (Taihe-Ganzhou Section) in Document [(2000) No.14 Ganzhou]. by Jiangxi

Province Environmental Protection Bureau, the following criteria are used for the

3

Page 9: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

assessment.

(1) Water: The main river that Suichuan linking road passes through is Suichuan

river. According to the status and function requirement of water, class III standard in

GHZB1-1999 Ground Surface Water Quality Standard is used for the assessment of

water quality, while Class I standard in GB5084-92 Farmland Irrigation Water Quality

Standard is used for SS assessment, shown in Table 1-2.

Table 1-2 Standard Limits for Water Quality Assessment mg/L (except pH)

Indicator pH CODc, Petrol-oil SS Remarks

Standard limits for Class I standard in GB5084-92 is usedwater quality 6.5-8.5 -20 (0.05 S 150 for SS assessment. the rest will applyassessment class Ill of GHZB 1-1999 standard

(2) Acoustic:

GB 12523-90 Construction WVork Sites Noise Limits Standard is used for the

assessment of noise during the construction, in which Class IV standard is used for the

dense residential quarters and first row of the buildings within the assessment scope of

road sides; and Class I standard is used for the schools and hospital wards. shown in

Table 1-3 and Table 1-4.

Table 1-3 GB12523-90 Standard of Noise Limit for Construction Work Site (Unit: Leq (dB)

Noise limitConstruction phase Mlain sources of noisc

Da! time Ni2ht time

Earth & stone %%ork Bulldozer. exca%ator. loader. etc. 75 55

Piling Various piling machines 85 Work prohibited

Structure Concrete mixer. X ibrating spear. electric saw. etc. 70 55

Finishinz Crane. lifter. etc. 65 55

Table 1-4 Noise Criteria for Urban Area (extracts) Leq:dB

Type or Sensitive Points Daytime Nighttime

GB3096-93 Class IV Standard 70 55

Class I Standard 55 45

4

Page 10: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

(3) Ambient air

Construction: Class II standard in Environment Air Quality Standard is applied to

TSP assessment.

Operation: Class II Standard in GB3095-1996 Ambient Air Quality Standard is

applied . Refer to Table 1-5

Table 1-5 GB3095-1996 Ambient Air Quality Standard (extracts) (mg/ m3)

Pollutant TSP Nitrogen Oxides Carbon Monoxide

Daily Avera2e 0.30 0.10 4.00ConcentrationLimit

I -hour Average 0.15 10.00

1.4 Targets for Environmental Protection

The impact factors on the ecological environment are land occupation. woodland

vegetation damage, soil erosion, water quality pollution cause by bridge construction.

The protective targets include: farmland. woodland, pond. high filling/cutting section

(KO+000-K2+750.K4+200-K4+750). earth borrowing area (K14+400-K14+680).

Meijiang river and canals. The impact factors on acoustic and ambient air include

construction noise. secondary dust. Traffic noise and tail gas. The protective targets are

presented in Table 1-6.

As the construction of this road is the up-grade on the existing old road, no great

impact would occur from the point view of ecological environment.. The main impact

on the surrounding residents, schools and living comes from construction noise and

traffic noise as well as tail gas in operation phase. Therefore environmental protection

targets in this project are the sensitive locations to noise and ambient air along the

road.

Page 11: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 1-6 Sensitive Locations to Noise and Air along the Road

Distance from HouseholdsNo. Name Location Central Line of /Number of Environmental Features

Road People

Hongshan . 330 Enclosing wall around the school.I Central KO+600 60m at right from students. 20 playground and open ground before the

Primary School the classroom teachers teaching building

2 Huanggang K3+500 Left 50m 30 /120 Farmland along the old road

T3irough the Paddy field. vegetable plot and households3 Dongtang K7+550 village. 14m after 7/300 along the old road forming as a street

remove

4 Jiangchexia K8+200 Through the village. 40160 Paddv ftrid20m after remove

5 Shanjiaoxia K8+700 Left 20m 18/75 At the foot hill with vegetable plot. paddy____________ ________________ ~~~~ ~~field

6 Zhanetang K 10+200 Left edge 80.20 e Households distributing along the old road

Zhangtan 30m nght of the 1807 gPrimari K10+100 classroom. through students.6 Enclosing wall around the school.

School the playground teachers ~~playground before the teaching buildingSchool the platground teachers

8 Meijian KI 1+350 lliroughthevillage. 60/240 Households distributinp along the oldvillage 14m aflter remove road. farmland

9 Shaoxi K 1 2+200 Right 80m 90/400 Households distributing along the old9 Shaoxi K I 2-'-200 Right 80m 90/400 road, farmland

10 Catingxia K12+900 Right 75m 34/128 | Canals. padd) field

II Sheshane K13+900 Through the village. 40/160 1 Households distributing along the old14m afer remove i road, farmiand

68 On the side of the old road. being oldSheang two-storev timber-strcture buildingPma2 K13+0 Left 60m studentss3 classroom is vertical to the road . a clinicPrimary school ~~~~~~~teachers ina~

13 WanneiYangcu K16+SS0 niht 10 120/500 Paddy field. pond. counur roadn _________ __________________ ___________ J surrounding

14 Anxia K 17+400 Left edge 57/240 Small road. paddy field

15 Chitang K 17+700 Left edge 80'320 Drn canal. pond. padd\ field. small______________ ___________ quantities of resettlement

16 Zhangw-uli K18+150 Left 25m 60/240 Pond. paddy fields. small roads

17 Lubei K18+400 Right 100 10/160 | Close to national highwax 105. paddy1 LueK_840 Rih10401 field. dr! canals

Yuezili18 jilh K}19-fi700 Right 30m 22/88 Small roads. paddy fieldIjianshang_I

19 Zijzhitouxia 20st Through the v-illage. 120/480 1 Small road. padd\ field(Xitou) on 20m after remove

1.5 Assessment Factors and Method

1.5.1 Assessment Factors

(1) Acoustic environment: equivalent acoustic level (A): LAeq;

(2) Atmospheric environment: NON, CO. TSP.

1.5.2 Assessment Method

In this report. the environment noise and atmospheric environment are assessed by

6

Page 12: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

status monitoring and surveying statistic analysis, and predicted by analogic analysis

and module computation. The analogic analysis is used for the prediction assessment at

the construction stage, while the module computation is employed for the prediction

assessment in the operation stage. According to the predicted results, the range up to the

standard is given and used as a basis for the developmental activity conducted by the

planning / construction department. Meanwhile, the locations sensitive to noise / waste

gas environment are predicted and assessed.

The ecological environment, water, and soil-and-water loss are assessed by

surveying combined with analogic analysis, while the social environmnent, living quality

and public participation are assessed by surveying analvsis.

1.6 Assessment Category and Key Points

This works is the expanding construction and rebuilding project. There are

environmental sensitive locations as schools and residential areas along the road within

the range of assessment. The building of bridge has a certain influence on water

environment. but smaller influence on ecological environment and soil-and-water

erosion. According to Technical Guiding Provisions for Environmental Impacts

Assessment, it is required that the assessment of special subject is analyzed. in which

ecological environment (including soil-and-water loss) is assessed to be Category 111,

water environment and atmospheric environment be Category III respectively, and

acoustic environment be Category 11. According to features and pollution of this project,

the assessment of acoustic environmental impacts is a key point in the assessment of

this project.

7

Page 13: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 2 Project Overview

2.1 Alignment and Major Controlling Points

The proposed road starts from Suichuan interchange of the main road, via Daquan,

Hongshan, Huanggang, Zhongping, Dongtang, Zhangtang, Meijiang, Shaoxi, Hongtaxia

(Niutou Computer station), Yangcun, Anxia, Jihe, Shangmaocheng, Zhuzitouxia,

Xizhuang and ends at Jinggangshan highway, with a total length of 20.596km. Basically,

the proposed road runs along the old road and is built by Class II highway standard. The

design speed is 80 km/h with 12.Om for roadbed width.

2.2 Scale of Construction, Technical Standards & Quantities of Main Works

According to the prediction of traffic volume. by reference to the regulations in

JTJOO 1-97 Technical Standard for Highway Engineering and JTJO 11-96 Highway

Alignment Design Specifications (The Ministry of Communications). the whole road is

built by Class II highway standard with design speed of 80 km/h . and its main technical

indicators and quantities of main works are shown in Table 2-1.

Table 2-1 Quantities of Main Works/ Technical Indicators

Item Name Unit Quantity

Landform Plain. hill! land.

Highwav class Class 11

Calculated Running Speed Km/h 80

Running Lane Width m 9.0

Pavement wvidth m 12

Max longitudinal grade 3.889

Earth'%ork and Stone%%ork for Roadbed lOOOm3 798.038

Land occupied .AlM 818.4

Removed Buildings m 25549.5

Mliddle Bridge m/place 236/4

Small Bridge m/place 153.015

Cul'.ert m/place 1568.17/82

Road pavement Asphalt-injected pavement

Source: T\xo-stage preliminar\ design of Gan-Yue Expresswa\ (Suichuan linkibng road). b\JPCDl.Sept..2000.

8

Page 14: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

1S2-1 ri' eaOl)iitRiFigure 2-1 Geographical position of the proposed road in Jiangxi province

Hubei province " Anhui province

- G316 De'an 9,ijan i /< D e'/ Jiujiangg / ressway/

-t \ \ ,\ D 7Ti1§g|enejianggprovince _ / _ _ >4tkt - _ _ \ e2ien vorovinc%\ o s > ~~~~~~~Y<ongxiu DI

Hu'nan 0 f province ! aa NanchanAj \ A Hengfeng ShanZ

MiX%@ iv \ tflO^Jinxian " / G32 Guangfe;g

WanzaA a Shanggao ew nj ia- aaBMCh , */m -' % ngt

Sj5X Tr- ~~~~ ,, }QC \ ~~~Nanin *'--' 1e 4t~ * / I zh

( i t 4lishui \ f ZNgn~~~~~~~~feng

Fujian province{ r b igS~~~~~Taihe / iaghang

J ffi 5sneg ngshan P 1* Legend

L s ~~~~~~~~~~~~~~~~~~~~~~Seat of provincial governiment

ai e-Ganzbo anz °u connection roa Seat of local government

Shangy g Gahou Seat of county govemrnment

! gRIPNo-; Na<|<l /Ruip ~~~~~~~~~~~~~National road

fl* ~ ~ ~ ~- EAM11Xinfeng I National trnmk built

National tnk to be builtGuangdong I<province ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~proposed Taihe-Gaozbouexrwy

Jt; < / .1i-- >. \ v Road Improvement Program (RIP)Note: RIP No.I is Suichuan.linggmnphan road;

Egg o so 100~~~~~~~~~~lo km~ RI Nol2 is Yutian.Xinjiaag road:__0 _ 50_100__ _ RIP No.3 is si-Wngusdu road,

_ * RIP No.4 is Tan.iang.Domhan tad.

Page 15: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

-~~~~~~~A -- - V

| Figure 2-2 Rouse Alignment Scheme of Suichuanconnectio road (I )

Figure -2 Roue Alignent Sceme ofSuichuan connection od 1

Page 16: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Meijiang medu brdg * IT+* ~, Banci nmediuin bridge

4- 41 /9~~~~~~~~~ *

O a, road ~ ~ ~ I~ >~* y,

Figure 2-2 Route Alignment Scheme of Suichuan connection road (2)

Page 17: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

-Cta owma roadbed

1200

ISO - 0 sQ5o

Border ofhighway §t X land area ItC KI ICO / e

m /,~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~5 IN \1

Borderof.highway t#A.Ufil HiHay ladd ue r

1-d

I N 1~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~N

2. jj'O61 I. *I-S. *XVVM; I7a

Mi2-3 Mit * MMX+W7% 1Figure 2-3 Standard section of the rowadbed t ?ffia 2S

Page 18: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

2.3 Traffic Volume Estimate

The produced traffic volume of this proposed road consists of both trend and

induced traffic volume. The predicted results are shown in Table 2-2.

Table 2-2 Prediction of Traffic Volume Middle-sized vehicles/ dayYear 2004 2015 2023

Trend 2764 5365 6985

Indced 202 268 279

Total 2966 563 3 7264

Source: FIS report of Gan-Yue Expressway Taihe-Gangzhou (Suichuan linkibng road), byJPCDI, Feb.,2000.

2.4 General Outline of Project

2.4.1 Roadbed and Drainage Prevention

(I) Standard cross-section of roadbed

The roadbed is 12m wide, and its cross-section consists of 1.5m (earth shoulder)

+9m (running lane)+1.5m (earth shoulder ).

(2) Designed elevation of roadbed: elevation of central line of road surface.

(3) Transverse slope: 2% (running lane) and 4% (earth shoulder).

(4) Side slope of roadbed: Generally, the side slope of fill section is 1:1.5. When

the height of fill section is morn than 8m. the grade locating at 8m from top to bottom is

changed into 1:1.5 (top) and 1:1.75 (bottom). and a bermn of 1.5m wide is arranged at

this location. The side slope of excavation is dependent on the geological condition.

When the height of excavation is more than 8m. a platform locating at 8m from bottom

to top is arranged.

(5) Drainage of roadbed

The trench drains along the road are combined with bridges and culverts into a

perfect drainage system so that the stability of both roadbed and side slope is ensured.

Refer to Figure 2-3 for the standard roadbed section profile.

2.4.2 Structure of Road Surface

According to the natural environment along the road, road materials, traffic volume

and construction condition etc., the road is paved by asphalt injection 6cm thick. and the

bedding is a structure of cemented sand and cobble whose layer is 20cm thick. The

9

Page 19: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

bedding course is filled by unscreened crushed stone, with 32cm thickness.

2.4.3 Bridges and Culverts

There are 4 middle-sized bridges and 5 small bridges, 82 culverts , averaging at 4

per kilometer.

2.4.4 Cross-Road Works

The grade crossing is used for the intersection of this proposed road with other

substandard roads. 43 intersections at grade are arranged along the road, in which 2

intersect at grade with Class II highway and 3 insects at Class IV highway. The

methods of grade crossing are to pave the corner lane or divergent turning lane.

2.4.5 Land occupied

The land acquisition (land lease) for this project amounts to 818.4mu, in which

548.7 mu paddy 5 mu dry land, 179.7 mu wood land, 3.5mu pond. 7.7mu wild land,

67.2mu house property, 6.6mu plain land. 71.25mu lease land.

2.5 Investment Estimate and Financing

The funding of Suichuan linking road will be solved by bank loan combined with

the provincial self-financing. The total investment in this section amounts to 98.373143

million Yuan with an average cost of 4.775395 million per kilometer

2.6 Time Arrangement for the Project

The preparatory work started in 1999. the construction will be started in August.

2002 and completed for operation in August. 2004.

10

Page 20: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 3 Current Environmental Description & Assessment

3.1 Natural Environment

(1) Geographic briefing

The Suichuan linking road starts from Suichuan interchange of the main road and

ends at Jinggangshan highway, with a total length of 20.598km.

Coming to Dongtang, this road rises and falls with a ground elevation of 90-1 70m,

the difference of elevation is 40-80m relatively, and the hilly bodies appear to be long

ridge-like mound. From Dongtang to destination. there are Suichuan river and its valley

plain, where the elevation of ground is 90-1 20m. This area is flat, wide and I ow-lying.

(2) Meteorology and Climate

Suichuan county is located in subtropical monsoon climate which is characterized

by distinct four seasons with mild temperature. abundant rainfall. full of sunshine, long

winter and summer, short Spring and Autumn..

The annual average temperature in the road areais 18.6°C; January is the coldest

month, averaging 6.9'C; July is the hottest month. averaging 29.5 C.

The annual average rainfall is 1421.2mm. The region is featured with seasonal

wind, west and northwest ground wind dominated, only south and southwest wind

dominating the months fro May to July.

(3) Hydrology

According to site survey and regional geological data analysis. the underground

water in the region, mainly, is fissure water in red rock stratum and pore water in

Quaternary friable rock stratum.

(4) Geology and Earthquake

According to the data and site surrey. this section of road has a large-area

intermittent uplifting activity. The different activity of fault and fault block is not

obvious. and the activity of earthquake is less than VI Richter scale.

II

Page 21: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

3.2 Social Environment

3.2.1 Status of Social economy in project impact region

(1) Overview

Suichuan county is situated at the eastern foot of southern section of Luoxiao

Mountain, close to the southwestern border of Jiangxi province, in the south of Ji'an

district. And it is located at 25° 58' -26° 42' Nand 113° 56' ,1140 45' E,with

a total area of 3144.17 square kilometer. The east of this county adjoins Wanran couty,

its south borders Nankang county and Shangyou county. its west is adjacent to Guidong

county of Hunan province, its northwest adjoins Jinggangshan city and its north

approaches Taihe couty.

In 1998, the total population in Suichuan was 507,000 people, and GDP was

1.135.78 million Yuan (RMB). in which farmers per capita earned 1468 Yuan, the gross

value of industrial output was 243.27million Yuan and the gross value of agricultural

output 752970000 Yuan.

(2) Developmental situation of national economy

01 Gross national economy

In 1998. GDP in Suichuan was 1136.0 million Yuan. Based on the calculation

according to comparable prices, GDP was 4.04 times higher than 1990 and increased

5.0% higher than 1997. And GDP per capita was up to 2240 Yuan. i.e. 4.2% higher than

1997. Main economic indicators in 1985-1998 are shown in Table 3-I.

02 Industry

Since the reformation and opening, the industrial economy in Suichuan has grown

very quickly: First, the speed of industrial economic development accelerates the

expansion of production scale. In 1998. the gross value of industrial output was up to

243.2 million Yuan (based on prices in that year): second. the sorts of industrial

production have been more complete. The local industrial system consisting of state /

town / individual industry has been established preliminarily in Suichuan county. where

the managerial mechanism has been suited to the law of market economy, with a better

economic benefit.

12

Page 22: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 3-1 Main Social Economic Indicators in Suichuan

Population GDP (100 I5 2nd Indu 3rd Indust GDP per Income in Living Fanners NetPopulation GDPl00 1st 2nd Inustry (lOOmrilion GP Expense of Income perYears bv Year End million Industy (100 (100nmillion Capita Expens capir

(10000) Yuan) million Yuan) Yuan) Y((Yuan) (ToYu Residents (Yuan)

1985 43.66 1.63 1.12 0.26 0.25 376 870 336

1986 44.44 1.62 1.04 0.31 0.27 367 1035 331

1987 45.14 1.73 1.10 0.33 0.30 386 1035 358

1988 46.37 1.95 1.19 0.42 0.33 426 1263 439

1989 47.17 2.29 1.48 0.43 0.38 490. 1427 482

1990 47.72 2.81 1.76 0.45 0.60 591 1576 490

1991 48.22 3.34 2.05 0.50 0.80 697 1700 589

1992 48.52 3.74 2.13 0.63 0.98 772 1948 659

1993 48.81 4.49 2.37 1.02 1.10 923 2178 691

1994 49.15 6.89 3.30 2.20 1.39 1408 3227 1023

1995 49.47 7.51 3.73 1.75 2.03 1524 3386 1351

1996 49.95 8.89 4.08 2.20 2.62 1781 4094 1678

1997 50.3 10.82 4.53 2.82 3.46 2150 4124 1467

1998 50.7 11.36 4.53 3.18 3.65 2240 4961 1468

Sources: (1) Truly Great Men Competing on Red Land (Edited by Jiangxi Provincial Statistic Department)

and Jiangxi Provincial Statistic Yearbook (1997,1998,1999)

(2) GDP is based on prices in those years.

( Agriculture

Suichuan is characterized by favorable natural conditions. fertile land. abundant

produces and favorable conditions for agricultural production. In 1998. the gross value

of agricultural output was 753 million Yuan (based on prices in that year). The town

enterprises are new enterprises suddenly coming to the fore and have become a main of

rural economy. The output of main farm produces has been grown constantly. in which

grain and tea were 1 86.200t and 5,0t respectively.

a) Tourism

There are many historical relics and scenic spots in this county. In ancient times.

there were "Eight Landscapes in Spring Town" and many famous mountains and

beautiful waters, wonderful peaks and grotesque stones. ancient trees. temples and

ancient buildings etc. Meanwhile. Suichuan has been to be an old revolutionary base

area. with many revolutionary ruins and cultural relics, where a lot of historical sites

enjoy high reputation in China.

13

Page 23: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

3.2.2 Review of current regional highway network

(1) Existent highways

There are 7 arterial highways in total in Suichuan county. 10 highways maintained

by the local highway management stations led by Suichuan County Communications

Department, with a total length of 156.78km. Suichuan Section of National Highway

105 is 50.14km long. Suichuan-Guidong provincial highway is 103.3km, in which a

section of this highway in the county border is 80.3kmn. Hengfeng-Jinggangshan

provincial highway is 57.87km, in which a section in Suichuan county to Fenshuit ao is

18.3krm. In addition, there are such arterial highways as Yutian-Xinjiangkou highway

(50.8km). Shui-Huang highway, Sui_Bi highway and Dao-Xian county highway.

(2) Water transport

Suichuan river is the most important course in this county and has a long history of

navigation. After 1980, trucks and tractors were increased quickly, thus the highway

transport has been increasing busy so that the goods source of water transport has run

short. In addition, the course has been silted up, so it is difficult to find any boats / ships

in Suichuan river in recent years.

3.3 Ecological Environment

3.3.1 Survey of animals and plants

The recovery of forest in Suichuan county is 67.5%. For the most part. the land

along this proposed road is cultivated and planted. And only a few of bush wood or

natural grassland exist. The bush wood consists of masson pine and azalea etc. On the

natural grassland grows the grass family and pteridophyte. The cultivation and

vegetation are crops on farmland, and only a few of woods. economic forest, fruit trees.

greening forest and scenic forest etc. Basically. the farmland vegetation is crops or

industrial crop. for examples: paddy rice., cotton and sugarcane etc.: the woods are pine,

China fir and bamboo etc.; the economic forest includes tea-oil tree. tung tree and tea

tree etc: the fruit trees are tangerine, peach. plum and orange etc; the greening forest and

scenic forest consist of Chinese parasol and willow etc.

14

Page 24: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

The project region is characterized by various vegetation kinds and higher

vegetating recovery. However, under the influence of natural and artificial factors, the

natural broadleaf trees have been reduced, and the artificial coniferous trees have been

increased. For the most part, there are the charcoal-made forest taking masson pine as

main, and the economic forest taking kumquat and tea-oil tree as main, distributing

along the proposed road, without any special protected plants.

The area passed by the proposed road is a region where population is highly

concentrated, the farning activity is intensified. and most of animals are the species

suiting for dwelling of farmland and residential area, for examples: mouse species and

sparrow-like bird species. No rare wildlife has been found in the assessment scope.

3.3.2 Soil type

The soil in Suichuan county is divided into 9 classes (paddy soil. fluviatile loam,

purple soil. red earth, yellow brown earth etc) and 14 subclasses. The paddy soil is

461000mu. which takes up 9.78% of total area of soil in Suichuan county and is the

main farming soil; the fluviatile loam is 8200mu (0.17% of total soil area): the purple

soil is 112600mu (2.4% of total soil area); the red earth is 3 15200mu (66.84% of total

soil area); the yellow brown earth is 131 500mu (2.97% of total soil area).

3.3.3 Survey of land and crops resources

According to the statistic data in 1999, the arable land in Suichuan county is 27634

hectares. in which paddy field is 24737 hectares and dry farmland is 2897 hectares. i.e.

1.5m per capita. In this region, land is valuable and farmland is more precious. The

climate in the project area is temperate and the water temperature is suitable to grow

paddy rice. beans. cotton. sugarcane. tea-oil tree. sesame and tobacco etc.

3.3.4 Survey and assessment of water environment

Suichuan linking road will pass across Suichuan river and its tributary. Suichuan

river is one of 4 major tributaries of Ji'an section (trunk stream of Ganjiang trunk river).

whose catchment area is 3045 square kilometer. main river is 162km long and annual

average flow is 2894 million mi.

According to the survey. the local people take underground water as drinking water.

15

Page 25: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

No water source taken as drinking water has been found in the assessment scope.

3.3.5 Soil and Water Erosion

According to the survey, the soil and water loss in Suichuan county is light, as

shown in Table 3-2. And the soil erosion degree standard is shown in Table 3-3.

Table 3-2 Soil and Water Loss in Suichuan County

Soil erosion Light Middie High Extreme Serious Other Totalcategory (kin2) Lgt Mdl Hih High

Soil erosion area 32.52 18.89 7.92 3.47 6.95 395.33 465.28

Data source: Soil Erosion Remote Sense Survey Report of Ji'angxi Province by Ji'angxi Provincial Water & Soil

Conversation Station. 1997

Table 3-3 Soil Erosion Category Standard

Category Slight light Middle High Extremne SeriousI______________I ______________I_____________high

Average Erosion <200.500100 200.500. 2500-5000 500-80 8000-15000 > 5000Modulus (t/km * a) 0 1000-2500 200

Data source: EIA Specifications of Highwvay Construction Project (trial)

3.4 Acoustic Environment

Ji'an District Environment Monitoring Station did the monitoring work whose

results are shown in Table 3-4.

Table 3-4 Results of Environment Noise Monitoring

Monitoring . Noise Level (dB)Locations Lo | L5o L,, L,q a

Hongshan Central Primary Day 50.4 43.0 37.5 46.4 4.9School (KO+600) Night 44.1 39.1 35.1 40.9 3.4

Zhangtang Primary School Day 55.3 46.5 41.4 51.5 5.4(K 10+ 100) Night 42.4 40.4 39.1 40.9 1.3

Dan 57.4 45.1 40.6 53.0 7.03 Meijiang Village (KI 1+350)

Night 45.0 41.8 39.8 43.2 2.4

Shaoxi Primars School Day 42.0 41.0 40.0 41.2 0.83(K12+200) Night 43.0 42.0 41.0 41.9 0.73

Shangxitou Da! 51.1 49.1 47.5 49.5 1.4I I(K20+00) Night 43.8 41.4 40.1 42.2 1.7

Data source: The monitoring report b% ii an Prefecture Monitoring Stations. April .2000

The monitored results have shown that day and night noise levels at residential

points are 49.5-53dB daytime and 42.2-43.2dB night time respectively. which conform

to Class I standard While day and night noise levels at school points are 41.2-51.5dB

and 40.9-41.9dB respectively. which conform to Class I standard. This shows a good

16

Page 26: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

acoustic environment, and the requirement of all sensitive locations for the acoustic

environmental function can be satisfied.

3.5 Atmospheric Environment

The monitoring point of Suichuan linking road was arranged at Shaoxi Primary

School. The sampling analysis methods were based on the stipulations of National

Environmental Protection Bureau. The monitored results are shown in Table 3-5.

Table 3-5 Monitored Data of Current Ambient Air

Monitoring 1-hour Average Value Daily Average Value Max. bmes Total Daily

Point Concentration Excess Concentration Excess Exceedance (AMrmgeLimit(mg/m3) Rate(%) Limit (mgm3) Ratem(%)

Primaro NO, 0.001-0.009 0 0.003-0.006 0 0 0.004Schooi TSP - 0.233-0.264 0 0 0.246

(K 12+200) _ _ _ _ _ I_ _

Data source: The monitoring report by Ji'an Prefecture Monitoring Stations,April,2000

Table 3-5 has shown that 1-hour and daily concentration limits of NOx are

0.001-0.009 mg/m3 and 0.003-0.006 mg/m3 respectively. and daily concentration limit

of TSP is 0.233-0.264 mg/mr . all of them are lower than that of the National Air

Quality Class II Standard.

17

Page 27: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 4 Environment Impact Prediction & Assessment

4.1 Social Environment Impact Assessment

4.1.1 Social development and living quality

After the construction of the proposed road is completed, the standard of road will

be heightened considerably, the condition of road is improved greatly, the traffic

capacity is remarkably increased, and the transportability can be greatly improved. This

construction will provide a necessary provision for eliminating a traffic congestion,

reducing a traffic accident, promoting the quick exchange of commodities and

information between regions, improving the investment environment in this region and

further extending business by solicit investors to reinvigorate the economy.

With the improvement of communications condition after constructing this road.

the regional construction and development along the road can be promoted, and the

industrial structure and its layout in this region will tend to be more rationalized. The

industrial enterprises are gradually turned from large and middle cities to outskirts, so as

to make commerce, catering trade, tourist trade. building industry, transport service.

processing industry and breeding etc in the impact region develop quickly. With their

gradual rise and development, more chances of social employment will be provided for

people. and it produces higher economic / social benefit.

After the proposed road is put into operation. the economy in this region will be

developed quickly and the economic prosperity is promoted also. The development of

economy will improve the people's living environment and the residential living level.

4.1.2 Impacts on infrastructure facilities

During the construction phase. 129 wire poles and 8040m telecommunication wires

will be relocated. which has a certain impact on family lighting. and electric supply for

communication / town or village industry. Therefore, the protection and removal work

of the public service should be coordinated with the departments concerned before

construction start. Before removing, the electric power and communication lines should

18

Page 28: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

be properly rebuilt to supply power for the surrounding residential area and village

enterprises to ensure their living not impacted..

4.1.3 Land acquisition, removal and resettlement

(I) Analysis of impacts on land acquisition

The farmland is 1.5m per capita in the region along the proposed road, thus the

arable land is very valuable. 818.4mu land is to be purchased and 71.25mu land is

leased for this project. The land occupation will have a certain impact on the

agricultural and forest production in this region along the proposed road. Due to the

social and economic benefit produced from the completion of this road construction, the

value of occupied land will change. Meanwhile. with the completion of the road project,

a new industrial zone will appear and the farmnland is turned to a non-agricultural land.

As viewed from economy, the value of land rises. In order to protect the valuable

farmland resource, it is suggested that the land management department should

strengthen the scrutiny and control of land use for all construction.

(2) removal and resettlement

For this road construction. 25549.5m2 of removal buildings with a concrete-brick

structure of 12785.7 m2 . cob brick structure of 12763.8 m2 will be removed.

The removal and resettlement are related to people's immediate interests.

Therefore, it is required that the construction departments must do well the removal and

resettlement work. By use of "Resettlement Action Plan" . the compensation methods

for land acquisition and the compensation sum for buildings removal are formulated.

The construction departments should be supported greatly by the local governmental

departments to do well the resettlement work. on the basis of following the whole

interests of this road construction.

4.1.4 Impacts on traffic safety and convenience

The proposed road is to be Class II highway. The road is open. so it provides a

good traffic environment for the surrounding residents. It should be noted that there are

3 schools on the sides of this road in the assessment scope. in this case. it is possible

that the students must pass through this road. Therefore, it is required that the road

19

Page 29: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

construction departments should consider to set up the notice board " LOW SPEED " or

overpass bridge at the locations where the students often appear, in order to avoid any

traffic accidents.

4.2 Ecological Environmental Impact Prediction & Assessment

4.2.1 Impact of road-occupied land on pattern of land utilization

The land acquisition for Suichuan linking road amounts to 818.4mu (548.7mu of

paddy field). The occupation of farmland, especially paddy field, will give prominence

to the contradiction of " more population, less land " in the project region, and increase

a pressure on the rest farmland. The occupied land will have a short-term influence on

the income of farmers in the project region. In particular. it has a greater impact on the

land contractors in the local region. The land adjustment by the village-level

,overnment or a new industry developed by use of land compensation expenditure can

reduce this unfavorable impact. In addition, the urbanization effect produced by opening

this highway often makes a vast of good-quality farmland on the sides of this highway

be a nonagricultural land. so the farming production and land utilization will suffer. to a

certain extent. its impact.

At the construction stage, the temporary land use has a certain unfavorable impact

on the local agricultural production also. However, the temporary land use. relatively, is

lesser. and these land can be gradually returned to their original function by clearing and

cultivating after the completion of works. After the completion of highway. the land

which is not utilized is more easily to be developed. due to the traffic convenience. In

addition. the construction of highway will promote the economic development in the

whole region. and provides. to the full, the traffic and infrastructure facilities needed by

the farm produces production and the processing industry development. Meanwhile. it

offers increasingly an opportunity to employment for the local people also. In this way,

the local rural economy will be promoted to the deeper development, and the value of

land resource. in the form of utilization, can be converted.

20

Page 30: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

4.2.2 Impacts of highway construction on animals and plants in project region

Because a part of highway is arranged in the farmland and forestland, the

vegetation will be damaged in the process of construction. After the completion of

highway, these damaged lands will be reclaimed and replanted in time.

The animal species in the assessment region, for the most part, are livestock,

poultry and a few of general wild animals, that they can grow in a poor environment and

have a stronger suitability for the artificial impact. The construction of highway will not

make their dwelling environment change more and interrupt their nornal living, so they

can sustain in the project region.

4.2.3 Impacts of soil-borrowing field and dump on ecological environmentIt is necessary to borrow 210266m3 soil for this highway without any waste. The

central borrowing areas located at left of K14+400-K 14+680 with a length of 250m and

150 in width, averaging 6m in height. It occupies woodland area of 56.25 mu with

borrowing volume 230,000m3. The borrowing areas are basically in line with the policy

and requirement as they located in hilly areas. As viewed from the protection of

ecological environment, it is required to level and reclaim the land damaged by earth

borrowing.

4.2.4 Impacts on water environmentThe road overpasses the Suichuan sub- branch and some small rivers and canals.

no large water intakes. The sewage from the workers life-area and pavement runoff in

operation may impact the water qualitv of the farmnlands surrounding, but no big impact

on the water quality of Suichuan river.

4.2.5 Impact on agricultural irrigation pattern

Suichuan linking road is innovation on the old road. 4 middle bridges. 5 small

bridges and 82culverts (averaging at 4 per kilometer) are to be built. The existing

agricultural irrigation pattern will be maintained basically, without any unfavorable

impacts.

21

Page 31: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

4.3 Acoustic Environmental Impact Prediction & Assessment

4.3.1 Analysis of noise impact during construction

The main noise sources during road construction are such construction machinery

as hauling vehicles, road making machines and road-mixer etc. According to the

analogy of the assessment materials, the main machine noise attenuate with distance as

shown in Table 4-1.

Table 4-1 Noise Value of the Main Construction Machines

Machinery Distance from Construction Machinery (m)Description 5 10 20 40 50 60 80 100 150

Loader 90 84 78 72 70 68.5 66 64 61.6

Grader 90 84 78 72 70 68.5 66 64 61.6

Roller 86 80 74 68 66 64.5 62 60 56.5

Excavator 84 78 72 66 64 62.5 60 58 54.5

Paver 85 79 73 67 65 63.6 61 59 55.6

Mixer 87 81 75 69 67 65.5 63 61 57.5

Bulldozer 86 80 74 68 66 64.5 62 [ 60 56.5

Data source: EIA of Gan-V ue Expressway (Taihe-Ganzhou section), August,2000

We can see from the above Table:

) The general construction noise caused by hauling vehicles and road making

machinery etc has a quite big impart on the people in the area close to the construction

site (within 50m);but little impact on those 100m beyond. So the construction noise has

a greater interruption impact on schools and residential area within 50m from the central

line of the highway. Therefore. the construction department should pay attention to

rational arrangement of working time. avoiding class time and nighttime.

{ According to GB12523-90 INoise Limit at Construction Site, Higher noise

produced by construction machinery does great harm to operators. With an increase of

operator's working time, their impairments especially hearing impairment will take

place. in which some impairment are unable to cure. According to the related

information. it has been proved that the deafness caused by noise is related not only to

noise level but also to noise exposure time. In addition, the noise harm can make human

fall variously ill. Obviously. this kind of noise has a greater impact on operators and the

surrounding residents.

22

Page 32: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

4.3.2 Prediction and assessment of traffic noise impact during operation

(1) Model for traffic noise prediction

The related model in Environment Impacts Assessment Specifications for Highway

Construction Project is used for this prediction, i.e.:

(LAcq)iL= L,,i +10 I g N T ALdIi. + ALlv/g,iudmiIal + ALd .face 13

in which

LX, i average radiating sound level of Type i vehicle, dB(A)

N,-day / night average traffic volume of Type i vehicle, vehicle / hour

V; average speed of Type i vehicle, km/h

T-(LAeq) predicting time. 1 hour

A LdiS-running noise of Type i vehicle (attenuation of day/night spacing at r

from noise equivalent driving line).dB

A Lvert.gra correction of traffic noise caused by road vertical grade. dB

A Lrd.face correction of traffic noise caused by road surface, dB

The total value of day "night noise at the predicted point is calculated by:

(L4c, )n =o 10lg[1] 00 1(1J)1 + 1 l'O) + I 00 lt-e,)- AL, - AL, (dB)

in which

(L_eq)trat- value of day / night traffic noise at predicted point. dB(A)

A LI correction of traffic noise caused by road curved line of limited long road

section

A L2 correction of traffic noise caused by barrier between road and predicted

point

(2) Determination of some parameters in model

According to this model. it is shown that the traffic noise during operation is

dependent on traffic volume. vehicle type ratio, running speed. vehicle sound power.

road vertical grade and road face roughness etc.

c( Traffic volume

23

Page 33: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

All of predicted annual traffic volume are shown in Table 2-1, and the factor for

day time (16 hours) is 84.8%.

(©) Vehicle type ratio

The ratio of small / middle / large vehicles is 74.8%, 15.3% and 9.9% respectively.

(©) Running speed

According to Environment Impacts Assessment Specifications for Highway

Construction Project, the running speed is calculated by:

Small Vehicle V=237XN-0 1602

Middle Vehicle V=212 X N-0° 1747

Large Vehicle V=(2 12 X N-0 1'747) X 80%

in which

V calculated running speed

N hour traffic volume. corrected by:

i) When the designed running speed is less than 120 kmlh; the running speed

calculated by the model is decreased in proportion.

2) When the traffic volume of small vehicle is less than 50% of total traffic volume,

its average running speed is decreased in proportion of 30%, if every 100

vehicle runs is reduced.

3) The model above is suitable for dav time, and the calculated value discounted

by 20% is used as night average running speed.

) Single vehicle noise emission source intensity (Lwu1)

The average radiating sound level (Lu.l) for all types of vehicles is calculated by:

Large Vehicle: Lu.i=77.2+0. l8VL

Middle Vehicle: Lu m=62.6+0.32Vm

Small Vehicle: Lv, s=59.3+0.23 Vs

in which

L.M.S-means large (L) / middle (M) / small (S) type vehicle

V-average running speed of vehicle. kmih

24

Page 34: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

( Spacing attenuation ( A Ldi,)

1) The day / night spacing (di) of Type i vehicle is calculated by:

di = 1000 x Vi (m)

in which

Ni day/night average traffic volume per hour of Type i vehicle, vehicle/hour

V, average traffic volume per hour of Type i vehicle, km/h

2) Distance of predicted point from noise equivalent driving line (r2)

r,=D \. * D,.

in which

DN distance of predicted point from near lane, m

DF distance of predicted point from far lane,m

3) Calculation of A Ldis

When r•dj/2, A Ldi, =K, X K2 X 201g(r/7.5)

When r>di/2. A Ld1, =20KI[K2 X lg(O.5dj/7)+Ig ]r/O.5'

in which

di- spacing of Type i vehicle. di=lOOOV,/N1:

r -- distance of predicted point from noise equivalent driving line.

r= D *D,

where DN and DF are the distance of predicted point from near (N) and far (F) lane

respectively;

K1 constant of land surface condition between predicted point and highway

(1.0 for soil surface):

K2- constant related to spacing. shown in Table 4-2

Table 4-2 Constants Related to Vehicle Spacing

Di(m) 20 25 30 40 50 60 70 80 100 140 | 160 250 300

K 0.17 0.5 0.617 0.716078 0.806 0.833 0.84 0.855 0.88 0.885 0.89 0.908

25

Page 35: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

A ALvert.gra

Large Vehicle A Lver,gra=98 X f

Middle Vehicle A Lvert.gra=73 X D

Small Vehicle A Lvert=gra50 X 0

in which: S means the vertical grade of highway, calculated by 0 =3% in this

prediction.

(2) Correction of traffic noise caused by road surface (A Lrd.lace)

The asphalt paving is used for this road making, and the noise value of A Lrd.face is

taken as 0 dB

(®) Correction of traffic noise caused by road curved line or limited long road

section (A LI)

AL,=-lOlg(0/180° )

in which

0 included angle (degree) of sight at predicted point toward the two ends of

road (about 150° taken in this prediction)

( Correction of traffic noise caused by barrier between road and predicted point

(A L2)

A L,= A L2,o.ds+ A L2 buidings+ A L2s,s z

1) AL2 0oods implies the equivalent noise level (A) attenuation caused by woods

barrier.

When the depth of woods is 30m. A L2_0ood,=5 dB; when the depth of woods is

60m, A L2,,ods,=0 dB. The maximal correction is 10 dB.

2) A L2buildings means the equivalent noise level (A) attenuation caused by

buildings barrier.

When the first row of buildings occupies 70%-90% of area between predicted

point and road central-line, A L2buildin2s =5dB; When increase a row of buildings,

A L2bUildings value increases 1.5dB, whose maximal value is lOdB.

3) A L2SS.z denotes the equivalent noise level (A) attenuation measured in the

26

Page 36: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

predicted point located in the sound shadow zone on the two sides of high embankment

or low through cut.

The sound contrast zone and the sound shadow zone of high embankment / low

through cut are shown in Fig 4-1 and Fig 4-2 respectively.Sound Shadow Zone

0 D

Fig 4-1 Sound contrast zone and sound Fig 4-2 Sound contrast zone and soundshadow zone of high embankment shadow zone of low through cut

If D • H + (h, - h) d then the predicted point is located in the sound contrastH

zone-an-A 2S.SZ 4 ifH+(h, -- h2) d. then the predicted point is located in thezone. and A L2s.sz =°: if (H )d.tethprdceponislaednte

H

sound contrast zone. and the value of A L 2 s.S.z is dependent on the difference of sound

interval ( 6 ). The noise attenuation is derived from Fresnel curve.

(3) Predicted results and assessment of traffic noise parameter-taken values

The predicated results of traffic noise of Suichuan linking road are shown in Table

4-3. According to Class IV standard in GB3096-93 (i.e. 70dB in dav time. 55dB in night

time), the distance that the traffic noise on the two sides of road conforms to the

standard is shown in Table 4-4 which shoes:

©0 Noise in day time during operation does not exceed the standard value.

02 The conformity distance of noise at night time in early and middle operation

phase is 20m. and 30m in the long-run operation phase.

(I Because this road section is to be the reformation of old road, and some

residential areas are distributed along the roadsides to make the current highway be

27

Page 37: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

street, the traffic noise along the linking road will have a more directive impact on these

residences.

Table 4-3 Predicted Results of Traffic Noise Along Linking Road During OperationPredicted Resuls of Traffic Noise at Various Horizontal Distance

Road Operation Duration Beyond Road Shoulder (dB)

Section Year mlOm 20m 30m 40m 60m 80m loom 120m MSOm 200m

day time 61.2 57.9 56.1 54.4 51.8 49.5 48.2 46.7 44.9 42.5

nighttnme 55.9 52.6 50.7 49.1 46.5 44.2 42.9 41.4 39.5 37.1Suichuan dav time 63.2 59.9 58.1 56.4 53.8 51.6 50.3 48.8 47.0 44.6Linking 2015 - -- -

Road nighttime 58.0 54.7 52.8 51.2 48.6 46.3 45.0 43.5 41.6 39.2

2023 dav tirne 63.7 60.4 58.6 57.0 54.4 52.1 50.9 49.4 47.6 45.2

nighttime 58.6 55.2 53.4 51.8 49.1 46.8 45.5 44.0 42.2 39.8

Table 44 Attenuating Distance (Traffic Noise Along Suichuan Road up to Class IV Standard) Unit: m

. Distance Approaching to Distance Approaching to Distance Approaching toRoad Section Standard in 2004 Standard in 2015 Standard in 2023

Day time Night time Day time Night time Day time Night time

Suichuan Wbole no <10 no <20 no 20Linkling Road line exceedance exceedance ewceedance

4.3.3 Prediction and Assessment of Environmental Noise At Sensitive Locations

The road section located and its corresponding ground surface covering conditions,

road structure. embankment / trench height, Limited long sound source of highwav.

landform / relief and other factors should be considered to correct the prediction of

environment noise at sensitive location. i.e. the predicted values of traffic noise are

superimposed onto the corresponding background value of acoustic environment. The

superimposition formula is:

L,t(I I:Nm. §rd r Io OI g (IO + I ,, 0 Lo¢".

According to individual acoustic environmental standard. the formula above is

used to calculate the environmental noise and its excess at each sensitive location. The

calculated results are shown in Table 4-5.

As shown in Table 4-5. (1) the environmental in day / night time at all residences

in the first period of operation does not exceed the standard value: (2) the noise in dav

time in the middle period of operation does not exceed either: Noise exceedance in

night time include six locations: Dongtang, Zhanftang, Meijiang.Sheshang. Chitang.

28

Page 38: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Zhuzitouxia ( Xitou) with max. exceedance of 0.3 dB; (3) the noise in day time in the

long-run operation phase does not exceed either; as to noise exceedance in night time, in

addition to the above six locations in the middle, there are 3 more as Jiangchexia,

Shanjiaoxia and Zhangliwu with exceedance of 0.4-2.4dB; (4) Zhangtang primary

school exceeds by 3.8dB at nighttime in early operation phase; (5)ln middle operation

phase, Hongshan central primary school and Sheshang primary schools exceed by

0.4dB, Zhangtang primary school exceeds by 5.5dB; (6) In long-run operation phase,

Hongshan central school primary and Sheshang primary schools exceed by 0.6dB,

Zhangtang primary school exceeds by 5.9dB.

From the above exceedance, traffic noise impact on the residential quarters is not

big, but Zhangtang primary school is quite impacted on the normal teaching. As the 3

schools are of small size where there are no boarding students, no assessment at night

has been done.

29

Page 39: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 4-5 Noise prediction and exceedance at sensitive points along Suichuan Linking Road

No. Locations Mileage Distance Noise Noise Prediction (dB) Noise Exceedance( dB)Standard(dB) 2003 2010 2020 2003 2010 2020

Hongshan Central KO+600 day 55 53.7 55.4 55.6 - 0.4 0.61 Prmr colRight 60m - I __-

Primar.v School night 45 48.4 50.1 50.6 3.4 5. 5.6

K3+500 . day 70 55.9 56.8 58.0 -2 Huanggang Right SOm - -. __

night 55 49.9 51.2 54.2 -

3 Dongtang K7+550 14m after day 70 59.2 60.2 62.3 -remove night 55 54.1 55.1 57.3 - 0.1 2.3

4 Jiangchexia K8+200 20m after da) 70 58.1 59.7 61.8remove night 55 53.6 54.6 56.8 - 1.8

5 Shanjiaoxia K8+700 Left 20m day 70 58.1 69.7 61.8 - -night 55 53.6 54.6 56.8 - 1.8

day 70 59.2 60.2 62.3 - -6 Zhangtang K 10+200 Left edge _ -

night 55 54.1 55.1 57.3 - 0.1 2.3

7 Zhangtang Primarx dav 55 58.8 60.5 60.9 3.8 5.5 5.9Schol K IO+ I00 Right 30m- - - - -School . night 45 52.9 54.9 55.4 7.9 9.9 10.4

Through.14 da, 70 60.3 61.0 62.8 - -

8 Pvleijiang Village K11+350 m after . _ -

remove night 55 54.3 55 3 57.4 - 0.3 2.4

dav 70 53.9 55 0 55.3 - - -9 Shaoxi K12+200 Right 80m - -

night 55 47 1 48.6 49.0 -

da\ 70 54 1 55.2 55.5 -10 Catingxia K12+900 Right 75 -I

night 55 47.3 48.8 49.2 -

Through.14 dav 70 59.2 60.2 62.3 -

11 Sheshane K 13+600 m after -

remove night 55 54 1 55.1 57.3 - 0.1 2.3

12 Sheshang Primar K Left 60m day 55 53.7 55 4 55.6 - 0.4 0.612 ~~~~~~~~~K13+550 - - ___ ___

School Night 45 48 5 50.2 50.7 3.5 5.2 5.7

da\ 70 53.2 54 1 54.4 - - -13 \anneiYangcun K16+900 Right l OOm

night 55 46.1 47.3 47.7 - - -

Da\ 70 52.5 53.7 54.0 - -14 Anxia K17+400 Right 90m - -

Night 55 46.3 47.7 48.1 -

da; 70 59.2 60.2 62.3 -I 5 Citan- Kf17-700 Left edge _

night 55 54.1 55.1 57.3 - 01 2.3

daw 70 57.6 58.4 60.4 - - -16 Zhang.uli K18+150 Left2i -. -

night 55 52.2 53.2 55.4 - 0.4

da\ 70 53.2 54.1 54.4 -17 Lubei K18+400 Ripht lOOnm - . -

night 55 46.1 47.3 47.7 -

day 70 56.2 57.2 59.3 -18 Yuzilijianshanp K19-700 Right 30m _ - -

Night 55 51.1 52.1 54.3 -

19 Zultu;a K20+100- 20m afer Day 70 59.6 60.4 62.4 -19 Zhuzitouxia -20- - - - - - -af

destination remos Night 55 54.2 55.2 57.4 - 02 2.4

Note: -- ' implies no excess

30

Page 40: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

4.4 Ambient Air Impact Prediction & Assessment

4.4.1 Ambient Air Impact Prediction & Assessment During ConstructionAccording to the preliminary design, the linking road will be constructed

simultaneously with the main line, the asphalt and stabilizing earth-mixing plants can be

shared at one place, therefore not much impact on the surrounding place of the linking

road. However, the hauling of mixing materials will exert dust pollution.

During construction, hauling and loading/unloading of materials for road making

bring TSP pollution to the road area. According to the results from site monitoring of

dusting caused by the similar site vehicle hauling, it has been shown that TSP

concentration at 150m from roadsides exceeds Class 1I standard, which shows that

dusting caused by transport produces a higher pollution to the district along the road

construction.

4.4.2 Ambient Air Impact Prediction & Assessment During Operation(1) Meteorological Analysis of Pollution

Statistic data shows that yearly prevailing wind is ENE wind whose frequency is

12% in Suichuan county. shown in Table 4-6. The annual frequency of static wind is

23%. The annual wind velocity in Suichuan county is 1.9 m/s. Due to low wind velocity,

the condition of gas dispersion is poorer relatively. The atmosphere stability along the

line is dominated by D category flowed by E-F category.

(2) Calculation of Auto Tail Gas Pollutant Discharge Source Intensity

The gas-state pollutant discharging source intensity is calculated by the following

formula:

Q, -,4, *E,, .3600-',=,

in which

Q,- Class j gas-state pollutant discharging source intensitv. mg/s * m

A, hour traffic volume of Type i vehicle in the predicting year. vehicle/h

E,, single vehicle discharging factor [the recommended value in Environment

Impacts Assessment Specifications for Highway Construction Project (tentative)] of

class j discharge of Type i vehicle in the predicting year under condition of vehicle

running on the special highway. mg - vehicle/m.

31

Page 41: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 4-6 Wind Direction Frequency / Average Wind Velocity / Pollution Coefficient In

Suichuan County (1997-1999)

Spring Summer Autumn Winter Whole Year

LcStWind p Wind Wind Wind WindLocatio ~averag 1OUtD 'VM P dU irectvo g dutlo Wn averag PDllti dhel v rapouIodbvcfio ~~~~~~~~~~~~~~~direj averaog ecopolcloutioaits dfetowind n wind n wind n wind n n ind nn velocity cef velocity cevfe n velocity veildot efle n ,ocity eDeffiCi

fcy(%1 (nibs) nt ftiein vmly nt fi)equen (ris) nt bun (m/s) nt quen vs) ntICy (%) Cy(%) Cy(% NO _ cy(% Cy(%)

N 4 1.7 2.3 2 1.9 1.0 6 2.1 2.9 3 2.3 1.3 3 1.9 1.6

NNE I_ 2-4 4.6 5 2.0 2.5 9 2.8 3.2 13 2.5 2 10 2.6 3.8

NE 10 2.7 3.7 4 1.9 2.1 _I 2.7 4.1 15 2.3 6.5 II# 2.5 4.4

ENE 12 3.0 4.0 5 1.9 2.6 12 2.6 4.6 23 2 7 8.5 12* 2.7 4.4

E 5 2.0 2.5 3 2.7 1 1 6 1.8 3.3 5 2.2 2.3 5 1.9 2.6

ESE 3 1.8 2.9 2 2.4 0.8 2 1.2 1.7 2 1.5 2.3 3 1.8 1.7

SE 3 1.9 1.6 4 2.2 1.8 1 0.9 1.1 I 1.2 1.3 2 1.9 1.0

SSE 4 3.4 1.2 12 2.6 4.6 1 1.2 0.8 I 1.9 0.5 4 2.6 1.5

S 4 3.0 1.3 6 2.7 2.2 0 0.8 0 0 1.8 0 3 2.4 1.2

SSW 4 3.1 1.3 7 2.8 2.5 1 1.3 0.8 1 4.4 0.2 3 3.1 1.0

SW 5 2.9 17 II 2.7 4.1 3 1.2 2.5 2 1.7 1.2 5 2.4 2.1

WSW 9 1.4 6.4 10 1.9 5.3 9 1.1 8.2 7 [.2 5.8 9 1.4 6.4

W 4 1.2 3.3 6 1.5 4.0 7 1.0 7.0 2 1.1 1.8 5 12 4.2

WNW 1 0.8 1.2 3 1.4 2.1 1 0.8 1.2 0 08 0 I 13 08

NW I 1 11 0.9 1 1.3 0.8 1 0.9 111 0 08 0 1 1.2 08

|NN\I | 2 1.3 1.5 I 1.5 0.7 I 1.0 1.0 |I 7 06 _ 15 0'

IC 19 165 1306 4 23

Data source: Based on the normal meteorological data provided by State Nleteorology Center

The forrnula for peak hour source intensity:

Qr(; = Qt A(;

in which: A(; is the coefficient of traffic hours. whose vxalue is taken to be 6.2%.

The formula for average daily source intensity:

Qr., = Q, A,I/R

in which

A, - coefficient of traffic volume in day time. wxhose value is taken to be 84.8%.

R hours in day time. whose value is taken to be 16.

(3) Diffusion Model for Environmental Air Pollutant

(D When included angle of wind direction at line source is 0 < 9 <90°, the

32

Page 42: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

diffusion model is:

CPR = ui S exp -(-() 2eXp[ ) - ) +expi(z+hj]|iu w,- : 2L y2c.2a

in which

CPR-pollutant concentration at predicted point R, caused by Section AB of

road line source, mg/m3 .

U average wind velocity at high location of effective discharge source of

predicted road section, m/s.

Q, Class j gas-state pollutant discharge source intensity, mg/vehicle - m

ac,, horizontal transversal wind direction and vertical diffusion parameter,

m.

Z predicted point to height of ground surface. m.

h-height of effective discharge source, m.

A,B start and end of line source

(2) When wind direction is perpendicular to line source (0 = 900), the diffusion

model is as follows:

2Q, h2-, = AS U -exp - _____

03 When wind direction is parallel to line source, the diffusion model is as

follows:

_( I AQ,

[+ ( ) 2 Jr [y2+(z2e2)]

e =r /a,

in which

r- equivalent distance from microelement to predicted point. m.

e parameter ratio of regular diffusion

Because the atmospheric stability in the region is dominated by Class D which.

therefore is used for calculation in this assessment. As for calculation, the diffusion

parameter must be taken value according to Appendix B in HJ/T2.3-93 Technical

33

Page 43: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Guiding Provisions for Environmental Impacts Assessment: The value of wind velocity

is taken to be 1.9 m/s. The average height of earth filling and the width of roadbed for

Suichuan linking road are 2.Om and 12.Om respectively.

(4) Prediction of Vehicle Tail Gas Concentration Diffusing to Roadsides

The prediction of NQz. and CO concentration diffusion for Suichuan linking road

is shown in Table 4-7. Due to small traffic volume of Suichuan linking road and low

running speed , the discharge of NO,, is less and the tail gas concentration at 16m

from the pavement conforms to the standard.

Based on the prediction, CO in vehicle tail gas is very small.. CO concentration is

less than 10% of that stated in Class II standard of environmental air quality, so little

impact on atmosphere along the road.

Considering the small increase of pollution source, it can conduce that the NO.

and CO pollution have light impact on sensitive locations on the roadsides with no

exceedance.

Table 4-7 Vehicle Tail Gas Diffuision Prediction (Stability D) During Operation Unit: mg/mr3

Road Operation Traffic Distance From Roadsides (m)

Section Stage Condition 10 40 100 200

Peak 0.012-0.020 0.007-0.014 0.004-0.008 0.002-0.0022004

daily average 0.009-0.015 0.006-0.010 0.003 -0.006 0 002-0.002

Nitroge Peak 0.022-0.036 0.013-0.025 0 007-U.014 0.004-0.004n1 2015

Oxides dailx average 0.016-0.027 0.010-0.019 0.005-O0I(I 0.003-0.003

Peak 0.028-0.047 0.017-0.032 0 009-0.018 0 005-0.0052023

dail% average 0.021-0.035 0.013-0.024 0 007-0.013 0.004-0.004

Peak 0.098-0.162 0.060-0.112 0.031-0.061 0.017-0.0172004

daily average 0.073-0.121 0.045-0.083 0.023-0.046 0.013-0.013

Carbon Peak 0.188-0.311 0.115-0.214 0.060-0 11 t 0.033-0.033Oxide 2015 daily averaze 0.140-0.232 0.086-0.160 0.045-0.087 0.025-0.02S

2023 Peak 0.243-0.401 0.148-0.276 0.077-0.151 0.042-0.043

daily a\erage 0.181-0.299 0.111-0.206 U 057-0.113 0 032-0.032

4.5 Environment Impact of Building Materials Quarries and Transport

4.5.1 Excavation of building materials and transport means

The main quarries and transport of Suichuan linking road are as follows:

(1) Wangjiaping stone quarry: located at Nanxi township of Taihe county, the stone

34

Page 44: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

hard and abound is used as pavement materials. There are tow transport means, one

is transport to Suichuan interchange(origin of the linking road) bv Gan-Yue expressway:

another is to transport to the destination by the national highway 105.

(2) Weishaba quarry: located at Zhuxiafengchang of Suichuan Bizhou township,

abound in hard tungsten stone with a storage of over 60,000 m3 . The stones can be

transported to the origin of the linking road by the country road, totaling 14km.

(3) Banei quarry: located at up-stream Suichuanjiang river in Baneicun of

Quanjiang town, abound in sand gravels which is used for base course, bottom base

course and structures for bridges and culverts. It is convenient for transport. A hauling

road of 200m will lead to the linking road.

(4) Cement . asphalt and steel: the cement is from Wan'an Cement Plant, asphalt

will be imported and the steel comes from Xinyu Iron & Steel Plant. All these materials

can be transported to the construction site by national highway 105.

4.5.2 Environmental Impact of the Materials Transport

(I) The above materials transport can all be transported to the construction site by

national highway 105 and country roads except that of sand. gravels which need

building a 200m hauling road. This will certainly increase the traffic crowding and the

likelihood of accidents. giving inconvenience to the people along the line.

(2) The new construction of hauling road and quarry excavation will bring some

damage to the landform and vegetation. The interrupted soil structure will reduce the

anti-erosion ability. thus causing soil erosion.

(3) The stone excavation adopts blasting which produce noise and vibration. The

hauling of the materials will exert noise pollution on the sensitive locations at the

roadsides.

(4) The transport brings to secondary dust pollution, including road dust and

spillover. particularly. in dry season when the pollution is more serious.

35

Page 45: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 5 Environmental Mitigation Measures

5.1 Design Stage

(1) In alignment design of the road, it tries to occupy less farming land, avoiding

poor geological sections and cultural/ historical sites.

(2) When designing bridges, culverts, drainage ditches, they take into

consideration flood discharge capacity of river, and not destroying local irrigation

system and preventing pavement runoff. From entering into river and canals.

(3) Selection of quarries, earth borrowing and waste areas are far away from

residences, schools or other sensitive locations.

(4) Planting works design has been done simultaneously with that of the main

works.

(5) Subgrade drainage and protection works have designed. such as intercepting

ditch. side ditch, berm, retaining wall. etc.. which not only stabilizing the road bed but

also preventing from soil erosion.

(6) The project has established Suichuan Countv Resettlement Office.

5.2 Construction Stage

(1) Occupied land should be planned and used in a proper way. temporary land

occupation size should be as small as possible, the occupied duration should be reduced

and the occupied land should be reclaimed promptly.

(2) waste is prohibited to be discharged into water body so as to prevent water

pollution. riverbed compression and blocking.

(3) The hauling vehicles shall not run on farmland and woodland.

(4) Water and soil conservation measures in construction phase are as follows:

O the earth-stone works shall avoid July- the storm season;

© Ladd platform construction method will be adopted so as to prohibit random

excavation on the slope;

36

Page 46: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

(M) Reduce the damage to the vegetation and plant on time so as to restore

vegetation in the work site;

( In cut road section, a platform for heaping soil and broken rock should be set

up outside the side ditch and intercepting ditch shall be set on the slope of the cut.

®) Set aside the original surface soil if the borrowing area in woodland and

reclaim back after the completion of the construction.

(5) If large-size, residence exists within 1OOm from the construction site,

high-noise machinery shall be stopped from 22:00 to 6:00. The larger-size residences

are Dongtang (K7+000), Zhangtang (KlO+050), Meijiang towenship (Kl 1+100),

Shaoxi (Ki2+±300). Wanneiyangcun (Ki7+000), Zhuzitouxia (K20+600).

(6)At the time of day construction, it is necessary to take the temporary shielding

measures on the construction site within 150m where there are schools (Hongshan

Central Primary School, Zhangtang Primary School, Sheshang primary school), so as to

prevent the construction noise from impacting on the teaching. Meanwhile. the

noise-monitored points are arranged at the sensitive locations on the sides of

construction site.

(7) The hauling road should be far away from schools. hospitals and residents

concentration area. and can not pass through the locations sensitive to acoustic

environrment. If there is no way to avoid. temporary measures shall be taken or some

economic compensation through consultation with the local residents. Meanwhile. noise

monitoring shall be carried out for hauling road at Nanxi township in Taihe county,

necessary measures shall be taken in accordance with the monitoring results.

(8) To protect the health of construction workers. shift-working system is

recommended so that workers exposed to high noise have time to restore their hearing.

(9) The construction sites and quarries shall be sprinkled frequently or

covered .The contractors shall take sealed covering measures to prevent spillover

w hen hauling easily-flying materials. Meanwhile monitoring points shall be set up for

supervision to prevent TSP exceeding the standard. The bulk materials bank shall be

200m away from the sensitive places as schools and residential quarters.

37

Page 47: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

(10) In dry season or without raining for a long time, the contractors are

required to spray water on temporary roads. In addition, the monitored point close to the

temporary construction road is arranged to make a random examination. Once any

problems occur, they should be solved in time.

(11) During construction, the Cultural Relics Law should be forcefully

publicized. Should any relics be found during construction, work should be stopped and

report immediately to local relics authority for identification. Construction may not

continue until the authority handle with it.

(12) During construction, traffic management should be enhanced. Effective

measures should be taken to prevent accidents.

(13) The solid waste and living sewage should be cleared and properly disposed.

(14) Construction workers should be educated not to damage wildlife, not to cut

trees at will.

(15) Complaint telephone number for environmental complains should be

conspicuously marked at the construction camp. For complaint problems. the local

environmental department shall be contacted and such problem should be handled

within 48 hours.

The above measures shall be implemented by contractors and specified in

bidding documents

5.3 Operation Stage

(1) Planting works will be completed simultaneouslv with the main works. strength

the road maintenance and planting works to prevent water and soil erosion.

(2) Water quality monitoring will be carried out in Meijiang river and

supplementary measures shall be taken in accordance with the monitor results.

(3) The acoustic environment monitored will be carried out at Dongtang.

Zhangtang. Meijiang village. Wannei.Yangcun. Zhuzitouxia (Xitou) and Hongshan

central primary school: ambient air monitoring will be carried out in Meijiang town.

then based on the monitored results, the proper environmental protection measures

38

Page 48: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

should be taken.

(4) Sound barrier (take into consideration the fence wall of the school) will be built

at Zhangtang primary school to alleviate the noise impact. The sound barrier is of 1 50m

in length, 2.5m in height at a cost of 180,000 yuan.

(5) At the road sections where schools stand, "LOW SPEED" sign board or

overpass bridge should be set up to protect the safety .

(6) It is suggested that planning authority would not consider new residences

within 50m from the roadside, neither schools and hospitals or other buildings sensitive

to acoustic environment within 1 00m from the roadside.

39

Page 49: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 6 Alternatives Analysis

6.1 "Without the project" analysis

The traffic infrastructure of Suichuan County is rather backward without any

railways. The transport depends mainly on highways that are in low class, low speed

and poor road condition, causing traffic jam and frequent traffic accidents.

On the roadsides, there are many large-size village, township, schools, some road

sections are already becoming street. It will result in social, economic loss or even

serious environmental issues if there is no new construction of highway. For example:

vehicles are bumping on the poor roads with high homing. In addition, due to slow

speed, the increased tail gas worsens the air pollution. Traffic safety is another problem.

In sum, if no changes on the existing road, problems concerning social. economic and

environmental respect are becoming outstanding.

6.2 Alignment selection procedure

The design unit carried out the feasibility study in June. 1998. draw up the

alignment on the 1/10.000 map and made site reconnaissance. They also consulted

widely with the local government and relevant departments in respect of the draft

alignment and bridge location. A detailed survey has been done for the regional social

& economical development. traffic trend. municipal/county program. road condition and

take into consideration the tourism. Land occupation. resettlement and environmental

pollution. Based on this. the proposed road will be on the improvement and expansion

of the existing old road.

6.3 Environmental Benefits of the Proposed Project

As the proposed road will be on the improvement and expansion of the existing old

road. it is beneficial to agricultural ecological environment from the viewpoint of

farmland occupation. Land in this area is precious with so many people. it's very

important to reduce the farmland occupation, in particular. the permanent land

occupation.

The road construction. though brings traffic noise impact on some residents. but

release more residents and schools as Shaoxicun, Shaoxi primary school from noise, tail

gas and secondary dust impact on the old roads. So. it gains the public support on the

line.

40

Page 50: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 7 Environmental Monitoring and Management

7.1 Environmental Monitoring

7.1.1 Objective and Philosophy

Based on the environmental impacts listed in the EIA and the mitigation measures

in this EAP, an environrmental monitoring plan has been worked out as to provide

accurate environmental informnation of this project, to check the effectiveness of the

mitigation measures and take correcting action when necessarv.

7.1.2 Monitoring targets and itemsAccording to the environmental impact forecast and assessment results, the items to

be monitored in the operation period are TSP, bitumen smoke, construction noise and

water quality. In the operation phase are traffic noise, ambient air and water

environment.

7.1.3 Environmental Monitoring PlanAccording to the predicted results, the following monitoring plan is developed as

shown in Table 7- 1, Table7-2 and Table 7-3.

Table 7-1 Ambient Air Monitoring Plan

Stage NMonitoring Monitoring Monitoring Sampling Executive UnitinCh SupervisoryI e _ _ Site Item Frequency Time Department n i arge partent

unpavedConstructi construction road. Once/wteek. or Once/momineon phase and residential area ad hoc once! aftcmoon Supervision

near the excess road JAFMI__JA_ AEMS CltvEPBJPHCHA IMP

Operation Nleijiang township Once'year I -2 day.24 hour JANICBphase (K l 1+350) (winter) running

*JPHCHA-Jiangxi Provincial High-Class Highwas Administration

JAEMS-Ji an Environmental Monitoring Station

JAM'ICB-Ji'an Mvtunicipal Communications Bureau

JANIEPB- Ji'an Niunicipal Environmental Protection Bureau

41

Page 51: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 7-2 Noise Monitoring Plan

Monitoring Monitoring Monitoring Time Sampling Executive Unit in SupervisorStage Site items Frequency horizon Time charge Departmen

_ _ _ _ _ _ _ _ _ _ _ _ _ ________ Dep mran anent_ _

Nanxi township in Taihe

Construction oithin 10Cmr rhere there Construction Once/week. t da Twice per Supervisionstage a r o noise or ad hoc . da\ engineer

_ are residences or sensitivelocation as schools Supervision

Dongtang( K7+550) corp.. AMEPzhangtang(K 10+200. T% ice/daN. JPHCHA JAMEPBMei~jiang(K I 1+350). once JAMCB

Operauion WanneiYangcun(Ki16+900. Ambient 4 timesi da" time 10 00-11 00- JMEMSstage Zhuzitou-xia noise year . 22:00 23:00

(Xitou)(K20+ 100). onceHongshan central school nighttime

11 KO-600)JPHCHA-Jiangxi Pro% incial High-Class Highw a Administration

JAEMS-Ji'an Environmental Monitoring StationJlAMCB-Ji an Municipal Communications Bureau

.IAIEPB- Ji'an Nlunicipal En\ ironmental Protection Bureau

Table 7-3 Water Monitoring Plan

Stage Monitoring Nlonitorin Monitoring Monitoring Executive Unit in Charge SupervisonSite Section Items frequency Department Department

I 00m once /cdav for 2Consructi upstream davs running in200m . Supervisionon phase Mezjian pH. CODcr. drn and mean corp A

Water season. JAEMS cop. JAMEPBbridge stream SS. petroleum JPHCHA

(K] 3t240) JAMCBOperation 50m down 4 times/vearphase stream

7.2 Environmental Management Organizations

7.2.1 Environmental Management Organization

Jiangxi Provincial Communications Department is responsible for the organization

of the environmental management for the proposed road and Jiangxi Provincial

High-Class Highway Administration (JPHCHA) is in charge of the specific

implementation of the environmental management work.. The organizations of the

environmental management in the construction and the operation period are shown in

Figure 7-1 and Figure 71-2 respectively.

The Planning Division of Jiangxi Provincial Communications Department is

42

Page 52: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

responsible for the environmental protection work in this sector in the province,

including forrnulation of environmental protection measures and rules, the provincial

environmental protection plan and supervision of the implementation of the

environmental protection plan.

The World Bank Loan Project Office of JPCD, Jiangxi Provincial High-Class

Highway Administration (3 persons) and Suichuan County Traffic Administration (3-6

persons with one environmental expert) are the executive organization of this project.

The main responsibilities are to deal with the environmental issues in construction and

operation phase, such as environmental management and resettlement in construction

and operation, checking the enforcement of environmental terms stated in the contract.

assisting the environmental engineer in signing monitoring contract with local EMS,

checking the implementation of monitoring plane and reporting to higher authority.

Planning Division, JPCD (3 persons)

Jiangxi Province High-Class Highway Administration

Project Office and Suichuan County Communication Bureau (3 - 6persons)

I Design ] Environmental Contractor ProvincialProtection pro) Environmental

Supervision ( person) MonitoringEngineer(]) Center

En%ironmental Monitorin2 SEation (EMS) | Ji'an EMS

Figure 7-1 Environmental management organization in construction period

43

Page 53: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Planing Division. JPCD (3 persons)

Jiangxi Province High-Class Highway Administration

Environmental Protection Division of Jiangxi Provincial High-gradeHighway Administration. (3 persons)

Suichuan County Environmental staff ofCommunications Suichuan ManagementAdministration (I person) Agency (I person)

Figure 7-2 Environment Organization Chart in Operation Phase

7.2.2 Environmental Management Plan

An environmental management plan has been worked out for the purpose of the

prompt handling of the environmental issues for this project. refer to Table 7-4

44

Page 54: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 7-4 Environmental Management Plan for Proposed Project

Potential negative impact Mitigation measures action | chargea

1. Planning & design period1. Reduced flood discharge capacity 1. Thoughtful design Design unit WBLPO2.Removing and resettlement for the 2.formulate and implement the proper Suichuan Ji-an Municipal

project land acquisition resettlement plan & compensations policy County Govemment3. Loss of land resource 3. Minimum farm land occupation Resettlement Suichuan County4. Soil erosion to the area belovk the 4. With enough proper outlets of the drainage Office Government

subgrade caused by the cutoff trench to avoid small waterfall. wvith stone and Design unitor weep drain cement finishing for water outlet area Design unit

5. Pollution from pavement run-off 5. Not directly discharged into water body or Design unitirrigation system

11. Construction period.1. Increase of river deposits caused b) 1. Protect the sensitive surface with fiber

newv road cutting and construction as cover and plants as soon as possible ewNell as the wastes

2. Dust. noise and air pollution at work . Sprinkle water regularlk on temporarysite and excess road road . mitigation measures shall be adopted

for the sensitive locations on the road sides3. Underground cultural relics and ad hock monitoring is necessary

discovered during construction 3. Stop construction if there is cultural relicsdiscovered and inform the competent

4. Terrain surface broken at the authoritycutting/filling and quarry sites 4. Proper treatment of the damaged ground

by design to make in harmony u ith the5. Disturb to the utility facilities terrain and environment WBLPO(pow% er!telecommunication) 5. Sign an agreement with the utility agenc%. Ji'an Municipal

notification goes before relocation to Contractors Gosemment6. Impact on existing road traffic minimize the impact Suichuan County

6. Strengthen traffic management at possible Government7. Sev%age and solid wastes at traffic conflict placesconstruction sites 7. Proper toilet and dustbins. enhance8. Possible disease among the local env ironmental managementpeople and wsorkers 8. Periodic health check. handle it properl.9. Germ (mosquito) temporarybreeding place such as dead pond 9.Necessarv action shall be taken to a%oid10. Impact on the land produce caused breeding placeby large earth borrow%ing 10.Centralized banking of surface soil. le%el

the ground after construction as soon aspossible and reclaim the surface soil.minimize the time of temporary landoccupation

Ill. Operation period1. Air and noise pollution produced by I. Noise barrier & other measures.vehicle operation enforcement of vehicle technical condition to

reduce air pollution. enhance publictransportation and traffic management

2. Continuous soil erosion 2. Careful maintenance'planting increase JPHCHA JPHCHAprotection works JA a MCB JAMCB

3. Pollution from pa%ement run-off 3. Run-off not directlh discharged into farm SCCB SCCBland irrigation s stemw\%ater body

4. Roadside in disorder 4. Proside treatment facilities. formulateregulations to prohibit trom throw ing %%astes

*JPHCHA-Jiangxi Provincial Hieh-Class Highway Administration WBLPO-the World Bank Loan Project Office

JALMCB-Ji an Mlunicipal Communications Bureau SCCB - Suichuan County Communications Bureau

45

Page 55: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

7.3 Budget Estimate for Environmental Monitoring

The environmental protection investment estimate is shown in Table 7-5. The total

cost is 725,600 Yuan, accounting for 0.74 percent of the total.

Table 7-5 Environmental Protection Investment Estimate

No Items Contents Quantity Unit Cost (10T000 Xuan)

I Planting Planting of earth 56.25 mu 4,000vuan /mu 22.5

Monitoring TSP. construction2 during noise. water 2 years 30,000yuan/year 6.0

construction quality_Environmental Water spraying.

3 protection cost wastes and 3 vears 50.000yuan/vear 15.0during sewage treatment, .construction vehicle cover

Noise. ambientMonitoriniz air. water qualitv

4 Monitonno air. water quality 3 years 20.000vuanivear 6.0during operation

5 Speed limit sign Make sign board 6 places 1.000 uan/place 0.6at school place

Sound barrier6 building during Zhangtang school 150m 1.200% uan/m 18.0

operation phase

Technical training

7 Training Cost for environmental 2 man/time 5000 uan man 1.0managementpersonnel

8 Contingenc% 3.46

Total 72.56

46

Page 56: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 8 Public Participation

8.1 Survey Method and Contents

In December 1999 and April 2000, the environmental assessment department,

under the assistance of the employer, design department and relevant departments, made

the public participation surveying on Suichuan linking road in way of visiting and

meeting, which includes individual interview (household), formn filling and discussion

meeting (group).

The main individual interviewers are those residents who are to be impacted by

land acquisition. resettlement. The purpose is to understanding their family condition.

their attitude to the highway construction. awareness of state policies concerned.

potential unfavorable impacts on their living, what opinions and suggestions they have.

etc. Group Interview undertakes the form of group discussion attended by department

leaders, ordinary staff member. Township director and ordinary peasants. There are two

topics for group interview: one is the favorable impact of the highw-ay construction to

the local social and economic development; the other is negative impact of the highwaN

construction and its mitigation measures.

8.2 Summarv of the Survev

8.2.1 Individual interview

The results are presented in Table 8-1. The people interviewed are 80. of whom. 20

have high school education. taking up 25 percent; 35 have middle school education.

accounting for 44 percent. 25 have primary school education, accounting for 31 percent:

2 females accounting for 2.5 percent. The annual income of the 80 persons range

between 5000-6000 yuan. which mainly depends on farming. breeding and work

outside.

47

Page 57: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Table 8-1 Summary of the statistics of the public participation survey

No. Questions Optional answers Percentage Remarks

Yes 98.8%

Do you support the construction of the No 2.5%highway? No idea 0

No answer 0

State 100%O

Who wvill be benefited from the Collectives 92.5%0/highway? Private person 91.3% m hoie

No answer 0

Some of the farmlands are going to be No 95.0%3 occupied and some households to be Yes 2.5%

resettled, do vou have an, comments No idea 2.5%on the land occupation? No answer 0

Yes 8.8%/0Do you know the compensation policy Know a little 23.8%

4 for land acquisition andresettlement? Do not kno's 71.3%

No answer 40o%

Yes 35.0%Yes. but

Do you folloN% the land acquisition and conditionally 63.8%resettlement arrangement? No

No answer 1 .2%

Noise 88.8%

Which is the most serious impact on Vehicle emission 1.30%6 you arisinp from the high%sa% Dusts 58.80% more than onechoice

construction' Other 0

No answer 0

Planting 93.8%Sound barrier 8.8%

7 Suggestions for mitigation measures? Away from village 1.3% choice

Other 1 3 %No answer 0

8.2.2 Group interview

Group interview was arranged two times which one was held in Hongshan Central

Primary School and Zhangtangcun of Meijiang township in Suichuan county. totaling

20 persons, shown in Annex 3.

All the attendants believe that the highway construction will improve the transport

condition. boom the economy. spur on the tertiary industry. It has gained the public

support as it's beneficial to both the state and people. Meanwhile. they also express their

concerns about the land acquisition. resettlement, economic compensation. construction

48

Page 58: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

interruption. noise impact on school teaching in both construction and operation, traffic

security of the students due to the increases speed . etc. Therefore they put forward the

following requirements:

(1) Make public the compensation standard for land acquisition and deliver the

compensation fee directly to the hands of the households to be removed. Reassign the

farmland, make resettlement and residential building base promptly which shall not

below the former living standard .

(2) Take into consideration the security measures for students, such as "speed

limit" sign and change the direction of school entrance.

(3) The negative impacts as dust. tail gas and traffic noise shall be mitigated by

planting and building of sound barrier.

(4) During the design and construction of road. it is suggested to keep close

contact with the local to well arrange the locations of culverts. bridges and underpasses

and try use the local surplus labor as much as possible during construction.

8.3 Information Disclosures and Feedback

(1) Television, broadcasting. newspaper and bulletin should be used to release

information to the public regarding the significance. alignment, resettlement and

environmental protection for this project. The Owner has released related circular concerning

the environmental and resettlement in Nanchang Evening dated Oct.9. Jingangshan DadlY dated Oct

IO (Refer to Annex IV)

(2) All the environmental documents such as the EIA and EAP will be exposed to

the public. The Owner has put all environmental documents in Suichuan County

Reference room. The address and complaint telephone number were published in the

newspaper. In this case. the public can have access to related information not through

governrmental organizations.

(3) The Owner will set up EP complaint telephone in Suichuan County Resettlement

Office. a full-time person gathering and recording the public's complaint on

environmental protection. Upon receiving the complaints. the Owner will come to the

49

Page 59: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

site to solve it along with Suichuan County envir-onmental protection department within

48 hours.

8.4 Brief Summary

The construction / design departments pay high attention to the public opinions and

give full consideration to their opinions in the road design.

As for the possible environmental problems caused by this project, the

environmental assessment department and the design department have presented the

corresponding measures as planting and diversions etc. More suggestions are as

follows:

(D At the design and construction stages of the proposed road, the departments

concerned should make contact with the local govermnents along the road. and adopt

their rational and feasible opinions in time.

(2) Promulgate by median of broadcast, TV, libraries, cultural center the state

policies related to resettlement and compensation, provide the free consulting place for

environmental protection documents and complaint telephone

(a) The governments along the road should handle affairs according to the national

policies. do well the surveving on land acquisition / removal families. designate the

building land and hand out the acquisition / removal fee to the removal families in time.

so as to ensure their living standard not to lower.

40 The environmental protection measures provided by the EIA should be put in

place one by one so as to minimize the impacts of road construction on environment.

50

Page 60: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Chapter 9 Assessment Conclusions

9.1 Social Environment

(I) The construction of proposed road will promote economic development, and

tourist resource development in Ji'an prefecture and Suichuan county; improve the

local investment environment; give impetus to the structural adjustment and

development of three major industries.

(2) The operation of proposed road will alleviate the pressure of the original

highway, improve traffic environment and decrease traffic accidents.

(3) Inevitably, the construction of proposed road will occupy some land and

farming land, but its impact is little on the whole. By means of land adjustment and

allocation as well as conversion of land use value, impacts caused by land occupation

on agricultural economy, can be reduced.

(4) It is necessary to do well removal and resettlement. And the policies of removal

and resettlement stipulated by the local government must be carried out conscientiously.

As this road is not a closed one. it has little impact on their living convenience of

residents along the road.

(5) The Owner shall enhance the promulgation of cultural relics. protection

measures should be take promptly in case there are underground cultural relics

discovered in construction.

9.2 Ecological Environment (including soil erosion, water environment)

(1) The status of ecological environment in the assessment scope of the proposed

road is good. Land occupied by the road is about 818.4 mu. whose types are paddy field.

dry farming land. pond. woodland and wild land etc. The road construction will make

agricultural economy suffer a certain loss. but cannot have obvious impact on the

distributing pattern of land and vegetation.

(2) The proposed road is an improvement on the old road. Therefore. the impact on

the landform caused by works as roadbed cutting and earth/stone filling is relatively

small.

51

Page 61: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

(3) According to the survey, there are no wild animals sanctuary, neither

distribution of rare and endangered animals and plants in the districts along the

proposed road. The main impacts of this construction on vegetation are the woodland,

fruit trees, flower, grass, bush and crops within the land acquisition area during

construction. Meanwhile, agricultural produce will also suffer from artificial felling,

uprooting. burying and treading. These impacts above can be mitigated by planting.

(4) At the road construction stage and in the first year of road operation, the

excavated slope along the road will produce a certain amount of soil and water loss.

However, as this road is rebuilt on the old road. the design, construction. completion

and acceptance of protective works will keep pace with the main works, so actual soil

and water loss is very small. In addition, the road planting will make partial slope

restore its vegetation and reduce its soil and water loss.

(5) At the bridge construction and operation stages. the impact on water body is

smaller.

(6) The impact of the proposed road on the surrounding channels. ponds and

agricultural irrigation system etc is not great either.

9.3 Acoustic Environment

(1) The general construction noise caused by hauling vehicles and road making

machinery etc has a quite big impart on the people in the area close to the construction

site and excess road (within 50m);but little impact on those lOOm beyond. So the

construction noise has a greater interruption impact on schools and residential area

within 50m from the central line of the highway. Therefore. the construction department

should pay attention to rational arrangement of working time. avoiding class time and

nighttime.

(2) In the middle operation phase. noise exceedance at nighttime include six

locations: Dongtang. Zhangtang. Meijiang. Sheshang. Chitang. Zhuzitouxia (Xitou)

with max. exceedance of 0.3 dB: as to noise exceedance at nighttime in the long-run

operation phase. in addition to the above six locations in the middle. there are 3 more as

Jiangchexia, Shanjiaoxia and Zhangliwu with max. exceedance of 2.3-2.4dB, but not

much.

(3) Hongshan central primary school and Sheshang primary schools 60m away

52

Page 62: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

from the road will exceed by 0.4-0.6dB in daytime in the middle and long-run operation.

Zhangtang primary school close to the road exceeds by 3.8-5.9dB in the operation

phase. The EIA recommends the building of sound barrier of 1 50m in length and 2.5m

in height.

(4) Noise monitoring will be carried out for those locations with no exceedance but

close to the proposed highway, where there are large residential quarters and schools

and corresponding measures will be taken in accordance with the monitoring results.

9.4 Ambient Air

(1) The monitored and surveyed results have shown that NO\ and TSP pollution

along the proposed road is light, and NO, has much leeway for environmental capacity.

The most places passed by this road are countryside fields where environmental air

quality keeps up the natural level. no large -size stationary pollution source and current

environmental air quality is good.

(2) As the asphalt-melting and lime-earth mixing plants are located at the main line,

the main environment pollution during the construction are TSP. Spray water and

clean the construction road in time. The hauling vehicles should be covered. The

material store should be far away from residences and be covered. And the roadbed is

timely watered during filling to reduce the unfavorable impact to certain extent.

(3) According the prediction. NO, concentration at 16m from the central line of

Suichuan linking road conforms to Class II standard value.

(4) CO concentration at 16m from the central line of Suichuan linking road satisfies

Class II standard limiting value also.

(5) NOx monitoring will be carried out for Meijiang Township in the middle and

long-run operation phase and corresponding measures will be taken in accordance with

the monitoring results.

9.5 Public Participation

(1) Make public the policies and compensation standard for land acquisition and

resettlement, deliver the compensation fee directly to the hands of the households to be

removed. Reassign the farmland. make resettlement and residential building base

promptly which shall not below the former living standard.

53

Page 63: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex IOverview of the Assessment Unit and Staff Member

Research Institute Of Highway (RIOH) is the largest and comprehensive nationalhighway research , experiment and technical development base under the directleadership of the MOC, holding class A Certificates for EIA issued by NEPA.

Environmental Engineering Office of RIH is mainly engaged in environmentimpact assessment (EIA) of highway and independent bridges; environment engineeringdesign, planting design and basic environmental research concerning construction andcommunications. It now owns 20 specialists in the fields of highway engineering,automobile engineering, environment engineering, chemical analysis, garden planting,biochemical engineering., of whom. 10 persons have high-level professional titles and 6have middle-level professional titles. Up to the present, we have carried out EIA forabout 100 freeways and independent bridges, taken charge of the compiling ofEnvironmental Impact Assessment Specifications for Highway Construction Projectspromulgated by the MOC. Having good theoretic fundamentals and hands-onexperience, the Environmental Engineering Office also has the EIA working experiencefor the projects financed bv the World Bank and the Asia Development Bank. Inaddition to this, it undertook the environmental design of freeway sound barrier, sewagetreatment, planting and construction work.

The following is an outline of the assessment personnel for this project:Shen Yi. male, born in 1962. graduated from Huatong Institute of Water

Conservancv and Electric Power. He is associate research felloxw and the depute directorof Environmental Engineering Office., in charge of the coordination with the Ownerand design unit in this project

Yan Xiaolin, male. born in 1969, M.S. graduated from Research Institute ofEnvironmental Science of Beijing Normal University. He is an associate research fellow.in charge of the EIA (the main line) compiling and the acoustic assessment in thisproject

Li Xiyun. female, born in 1941, graduated from Fudan University, senior engineer.in charge of the EAP compiling and the ambient assessment in this project

Wang fang. female, born in 1957. graduated from Electronic engineering., assistantengineer, in charge of the social environment assessment in this project

Dong Bochang. male. born in 1974. M.S araduated from EnvironrmentalEngineering of Jilin Universitv. assistant research fellox. in charge of ecologicalenvironment and soil erosion assessment in this project

Fan Qinchun. female. born in 1974. graduated from Beijing Industrial University,engineer. in charge of the water environment assessment in this project

55

Page 64: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex IIReference

(1) World Bank Operational Manual OP /BP/GP4.01, March, 1999(2) "EIA Technique Guidelines" [HJ/T2.1-2.3-93. HJ/T2.4-1995. HJFT19 - 1997, NEPA];(3) "Specifications Concerning EIA for Highway Construction Project"(Trial) [JTJO05 -

96, MOC];(4) Li Zhongkai, Meteorological Principles of Air Pollution and Its Application,

Meteorology Press. 1985.(5) Ren Wentong, Traffic Noise and Control. Remen Communication Press,1985.(6) Yearbook of Jiangxi Province (1999), Jiangxi Provincial Statistics Bureau(7) Remote Censoring Survey Report of Jiangxi Province Soil Erosion, Jiangxi

Provincial Water Conservancy Office, Nanjing Soil Research Institute of ChinaAcademy of Science, 1997

(8) Atlas of Jiangzxi Province, Jiangxi Provincial Mapping Bureau, March, 1998(9) EIA of Linxiang-Changsha Freeway of Beijing-Zhuhai National Trunck Highway

(Highway IV), RIH of MOC. April 1999.(10)Feasibility Study Report of Suichuang Linking Road of Gan-Yue Expressway

(Taihe-Ganzhou Section), Jiangxi Provincial Communications Design Institute(JPCDI). Feb. 2000

(11)Two-stage Preliminary Design of Suichuang Linking Road of Gan-Yue Expressway(Taihe-Ganzhou Section). Jiangxi Provincial Communications Design Institute(JPCDI), Sept. 2000

56

Page 65: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex III:

Public Participation and QuestionnaireSurvevTopic I . The positive effect of the expressway on the local economy and society

2. The possible negative effects of the expressway. and mitigation measures

Name Sex Age Nationality Occupation Job Title Education Address

Zhang Male 52

lndividua Futian Han Teacher Chief in Normal Group 5# of

I file _ teaching office school Hongshan cun

Xiao Male 48Zeng Han Teacher Deputy Normal Group 4#

masterhead school Dapingcun

Xiao Male 42Xiaopi Han Teacher Chief in Normal Litoucunng teaching school

Lian2% Male 49uan Han Teacher Chief in Normal Lianggangcun

teaching school

Oume Fema 44n le Han 1 eacher Chief in Normal Bizhoucun

teaching school

Records of the intervie%s:

The proposed expressk%av shall be convenient for the entrance of xehicles onto road. There will be some impact

produced b% traffic noise and dust. "xhich can be mitigated bs far distance. change the direction of school gate. in this

regard. hope to provide some economic compensation for school adjustment. The rest impact are wvithin acceptable

level.

Representative (Signature): Surveyor or Recorder(Signature):

Date:

57

Page 66: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Public Participation and Questionnaire

Survey t. The positive effect of the expressway on the local economy and society.Topic 2. The possible negative effects of the expressway. and mitigation measures

Name Sex Age Nationality Occupation Job Title Education Address

Guo Ji Male 38 Han Farmer High school ZhangtangcunMeijiang

Individual Guo Male 39 Han Farmer Viliage Highl school Zhangtangcunfile Wenbang secretary Meij iang

Guo Male 36 Han Self High school ZhangtangcunFuzai operation Meijiang

businessGuo Male 62 Han Farmer Polvtechnic ZhangtangcunZhonglia school Meijiangng _ _ _ _ _

Guo Male 52 Han Farmer Village Normal ZhangtangcunDewan chief school Meijiang

Guo Male 33 Han Farmer Middle ZhangtangcunWenti school Meijiang

Guo Male 19 Han Farmer Middle ZhangtangcunDecai school Mei jiangGuo Male 32 Han Farmer Middle ZhangtangcunShichun school MeijiangGuo Maie 27 Han Farmer Middle ZhangtangcunYahong school MeijiangGuo Male 26 Han Farmer Middle ZhangtangcunGuoshen school MeijianggGuo Male 42 Han Farmer Middle ZhangtangcunWenqi school Meij iangGuo Malae 44 Han Farmer Primar) ZhangtangcunXiaohai school MeijiangGuo Male 46 Han Farmer Primary ZhangtangcunTousheng school MeijiangGuo Male 65 Han Farmer Primary ZhangtangcunWenqi I_ I I school MeijiangGuo Male 44 Han Farmer Primar) ZhangtangcunMingshao school Meijiang

Records of the interviewI. Make the land compensation policy and standard know n to the public.2. Guard wall shall be necessar% if the proposed expressway pass by the school.3. Security measures shall be available to guarantee the entrance-exit of the students4. Drainage ditch shall be set up on both sides of the expressw-ay.5. Tr! to make use of the old road as much as possible so to reduce the occupation of land.6. Hope the road far a% a\ from the %illaee7. Wish the aowernment to construct high%%a) s as quick as possible to help people get ride

of' pox ertn8. Compensation fee for land acquisition and resettlement should be gi\ven to the farmers in

full amount

Representative (Signature): Surveyor or Recorder(Signature):Date:

58

Page 67: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex IV:

The People' s Republic of ChinaEnvironmental and Resettlement Bulletin

for the Jiangxi No.2 Highway Project

For the environment and resettlement information of the Jiangxi No.2 Highway

Project to be inquired by the public, increasing the openness of the work, the

TGEPCO has placed the following complete reports respectively in the resettlement

offices and libraries of Nanchang city, Ji' an city, Ganzhou City, Taihe county,

Suichuan county, Wan' an county, Nankang city, Zhanggong district in Sep.10, 2000.

(1) Resettlement Action Plan for the Taihe-Ganzhou Expressway of the Jiangxi No. 2HighwayProject financed by the World Bank Tanhe-Ganzhou Expressway ProjectConstruction Office (TGEPCO);

(2) Environmental Action Plan for the Taihe-Gan:hou Expressway of the Jiangxi No.2 HighwayProject financed by the World Bank, Tanhe-Ganzhou ExpresswayProject Construction Office (TGEPCO);

(3) Environmental Action Plan for the Ganzhou Connecting Road of the Jiangxi No. 2Highway Project (Taihe-Ganzhou Highwsay) financed by the World Bank,TGEPCO;

(4) Environmental Action Plan for the Suichuan Connecting Road of the Jiangxi No. 2Road Project(Taihe-Ganzhou Highway) financed by the World Bank, TGEPCO;

(5) Environmental Action Plan for the Wan, an C'onnecting Road of the Jiangri No.2 Highway Project(Taihe-Ganzhou Highway) financed by the World Bank.

TGEPCO, Dec.2000

The above reports will be modified according to the suggestion of World Bankdelegation and public, and then be placed in the above resettlement office andlibraries.

Tanhe-Ganzhou Expressway Project Construction Office (TGEPCO)

Sep.22, 2000

59

Page 68: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex V:

List of Tables and Figures

Table 1-1 Assessment Scope of Environrnental Impacts of the Proposed RoadTable 1-2 Standard Limits for Water Quality AssessmentTable 1-2 Standard Limits for Water Quality AssessmentTable 1-4 Noise Criteria for Urban Area (extracts)Table 1-5 GB3095-1996 Ambient Air Quality Standard (extracts)Table 1-6 Sensitive Locations to Noise and Air along the RoadFigure 2-1 Geogrphic Position of the AlignmentFigure 2-2 Map of Alignment StrikeFigure 2-3 Section profile of Standard RoadbedTable 2-1 Quantities of Main Works/ Technical IndicatorsTable 2-2 Prediction of Traffic VolumeTable 3-1 Main Social Economic Indicators in SuichuanTable 3-2 Soil and Water Loss in Suichuan CountyTable 3-3 Soil Erosion Category StandardTable 3-4 Results of Environment Noise MonitoringTable 3-5 Monitored Data of Current Ambient AirTable 4-1 Noise Value of the Main Construction MachinesTable 4-2 Constants Related to SpacingTable 4-3 Predicted Results of Traffic Noise Along Linking Road During OperationTable 4-4 Attenuating Distance (Traffic Noise Along Suichuan Road up to Class IV Standard)Table 4-5 Noise prediction and exceedance at sensitive points along Suichuan LinkingRoadTable 4-6 Wind Direction Frequency / Average Wind Velocity / Pollution CoefficientIn Suichuan CountyTable 4-7 Vehicle Tail Gas Diffusion Prediction (Stability D) During OpemationTable 7-1 Ambient Air Monitoring PlanTable 7-2 Noise Monitoring PlanTable 7-3 Water Monitoring PlanFigure 7-1 Environmental management organization in construction periodFigure 7-2 Environment Organization Chart in Operation PhaseTable 7-4 Environmental Management Plan for Proposed ProjectTable 7-5 Environmental Protection Investment Estimate

Table 8-1 Summarv of the statistics of the public participation survey

60

Page 69: Public Disclosure Authorized E-425 - World Bank...Chapter 5 Environmental Mitigation Measures ..... 36 5.1 Design Stage ..... 36 5.2 Construction Stage ..... 36 5.3 Operation

Annex V 1:

List of Relevant Reports

(1) Environmental Impact Assessment Report for the Taihe-Ganzhou Expressway of theJiangxi No. 2 Highway Project financed by the World Bank, Research Institute ofHighway of MOC , December, 2000

(2) Environmental Action Plan for the Taihe-Ganzhou Expressway of the Jiangxi No. 2HighwayProject financed by the World Bank, World Bank Loan Project Office ofJPCD, Dec.2000

(3) Environmental Impact Assessment Report for the Ganzhou City Connecting Road ofthe Jiangxi No. 2 Highway Project(Taihe-Ganzhou Highway) financed by the WorldBank, Research Institute of Highway of MOC . Dec.2000

(4) Environmental Action Plan for the Ganzhou City Connecting Road of the Jiangxi No.2 Highway Project (Taihe-Ganzhou Expressway) financed by the World Bank, WorldBank Loan Project Office of JPCD, Dec..2000

(5) Environmental Impact Assessment Report for the Suichuan County Connecting Roadof the Jiangxi No. 2 Highway Project(Taihe-Ganzhou Expressway) financed by theWorld Bank Research Institute of Highway of MOC . Dec.2000

(6) Environmental Action Plan for the Suichuan County Connecting Road of the JiangxiNvo. 2 Highway Project(Taihe-Ganzhow Expressway) financed by the World Bank,World Bank Loan Project Office of JPCD. Dec.2000

(7) Environmental Impact Assessment Report for the Wan 'an County Connecting Roadof the Jiangxi No. 2 Highway Projec t(Taihe-Ganzhou Expressway) financed by theWorld1 Bank, Research Institute of Highway of MOC . Dec.2000

(8) Env ironmental Action Plan for the Wan 'an County Connecting Road of the JiangxiNo. 2 Highwvay Project(Taihe-Ganzhou Highway) financed by the PVorld BankWorld Bank Loan Project Office of JPCD. Dec.2000

(9) Environnental Assessment summary for the Taihe-Ganzhou Expressway,Connecting Roads and its binding projects of the Jiangxi No. 2 Highwtay Projectfinanced by the World Bank, Research Institute of Highway of MOC . Dec.2000

( 0) Resettlement Action Plan for the Taihe-Gan:hou Expressway of the Jiangxi No. 2Highi vay Project financed by the World Bank, Resettlement Office ofTaihe-Gan:hou Expressway Project Office, 2000

(I I) Cultural Relics Survey Report forthe Taihe-Ganzhou Expressway of the Jiangxi No.2 Highway Project financed by the World Bank.Jiangxi Provincial Cultural Relics.4rcheology Institute, Dec.2000

61