HIGHLIGHTS SINCE MASEN CREATION
2009 2010 2013 2015 2016
National energystrategy
Masen creation NOORo I construction launch NOORo II & III
construction launch
NOORo I inauguration
2 000 MW of
solar in 202042% of RE in 2020
New scope for reinforced synergies
52% of RE in 2030
1 OPERATIONAL PROJECT AND SEVERAL UNDER DEVELOPMENT
NOORo I construction launch NOORo I inauguration NOORo II NOORo III
2
RENEWABLE ENERGIES, AT THE HEART OF MOROCCO’S ENERGY STRATEGY
Strong will of increasing renewable energies share within the national mix by 2020 and 2030
Of installed capcity
REs share evolution within the national mix
26% 42%
Roadmap for solar energy deployment with an optimal technological mix in order to meet national needs
52% 2030by
3
Moroccan Energy Strategy targets
20206 000 MW Horizon
MASEN, DEDICATED ACTOR RELYING ON A STRONG INSTITUTIONAL FRAMEWORK
4
Law 57-09 establishing Masen
State-Masen Agreement (decree)
Conditions, technical requirements and guaranty of financial balance for the achievement of the solar plan
Rules, conditions and guarantees for the purchase and supply, transportation and commercialization of electricity produced
State-ONEE-Masen Agreement
A clear institutional framework, supporting Masen action
Object: Development of solar integrated projects with a minimum capacity of 2000 MW by 2020 contributing to reach the new national ambition (52% of RE by 2030) through the development of integrated programs using renewable energies sources including solar, hydro and wind
Governance : Management Board
Capital : 2 250 000 000 dirhams (State, ONE, Hassan II Fund and SIE - equal shares - )
Legal Form: Limited liability company, created in Mars 2010
IMPLEMENTATION THROUGH “INTEGRATED” PROJECTS
5
Our Vision: Optimize solar resource valorization
ELECTRICITY PRODUCTION
2000 MW by 2020 and more by 2030
INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH &
DEVELOPMENT AND
TRAINING
For a competitive industryFor technology
improvement and qualified resources
For an inclusive development
5
RE PROJECTS
ELECTRICITY PRODUCTION
2000 MW by 2020 and more by 2030
INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH & DEVELOPMENT
AND TRAINING
For a competitive industry
For technology improvement and
qualified resources
For an inclusive development
6
NOOR, A MULTI-SITE AND MULTI-TECHNOLOGY PLAN
NOOR Tata
NOOR Midelt
NOOR Laâyoune
NOOR Ouarzazate
NOOR Boujdour
CSP PV
CSP PV
PV
PV
CSP PV
7
5 sites with a minimal capacity of 2 000 MW by 2020
Technologies combination to answer to identified needs while optimizing the overall cost of the kilowatt hour and maximizing synergies
NOOR OUARZAZATE COMPLEX, A GRADUAL DEPLOYMENT OF MORE THAN 550 MW
NOORO III
150 MW
NOORO II
200 MW
NOORO I
160 MW
CSP Parabolic trough
CSP Tower
NOORO IV
~ 70 MW
PV
CSP Parabolic trough
8
R&D Platform
A COMPLEX WITH ALL NECESSARY INFRASTRUCTURES
FENCES
DRAINAGE
TELECOM
ELECTRICITY
ROAD
WATER
Developmentof a large scale
site of 3 000 hectars
9
NOORO I PLANT IN OPERATION
Techno. Concentrated Solar Power using parabolic trough
160 MWe Gross Capacity
3 hours Thermal Energy Storage
Capacity
Storage
Developer
Owner’s Engineer
EPC
Financial Institutions
Key dates Effectiveness Q2 2013 ICOD Q4 2015
(*) Evaluated peak hour tariff 10
11
NOOR OUARZAZATE: A MULTI TECHNOLOGIES COMPLEX
Capacity: 160 MW
Technology: CSP trough
Storage: 3 hours
CO2 emissions avoided: ~ 280 000 tCO2 / year
Capacity: 200 MW
Technology: CSP trough
Storage: > 7 hours
CO2 emissions avoided:~ 380 000 tCO2 / year
Capacity: 150 MW
Technology: CSP Tower
Storage: > 7 hours
CO2 emissions avoided: ~ 250 000 tCO2 / year
Capacity: 70 MW
Technology: PV with tracking system
NOORo I NOORo II NOORo III NOORo IV
A SOLAR COMPLEX OF 580 MW COMBINING 3 DIFFERENT SOLAR TECHNOLOGIES
PLANT IN OPERATION PLANT UNDER CONSTRUCTION PLANT UNDER CONSTRUCTION WORKS TO BE LAUNCHED SOON
CO2 emissions avoided: ~ 87 000 tCO2 / year
Industrial integration: 30%*
* Real industrial integration reached: 34%
Industrial integration: 35%Industrial integration: 35%
13
NOOR LAAYOUNE AND NOOR BOUJDOUR: WORKS TO BE LAUNCHED SOON
NOOR BOUJDOUR
Projects financed through green bonds for a total amount of 1 200 million dirhams
NOOR LAAYOUNE
Capacity: 80 MW
Technology: PV with tracking system
CO2 emissions avoided: ~ 104 000 tCO2/year
Capacity: 20 MW
Technology: PV with tracking system
CO2 emissions avoided: ~ 24 000 tCO2/kWh
14
INTEGRATED PROJECTS
ELECTRICITY PRODUCTION
2000 MW by 2020 and more by 2030
INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH & DEVELOPMENT
AND TRAINING
For a competitive industry
For technology improvement and
qualified resources
For an inclusive development
A DEDICATED SUPPORT FOR THE DEVELOPMENT OF A SOLAR INDUSTRY
DEVELOPMENT OF A COMPETITIVE MOROCCAN
SOLAR INDUSTRY …
Skills developmentIndustrial capabilities
reinforcement
… through two missions
Ambition Cluster supported by multisectorial institutions
… and by well-known partners
~ 250 beneficiaries~ 150 hours of trainings
Excellence awards Summer school
Conferences Seminaries
CSP mission in Spain
QHSE trainings, diagnostic, personal assistance
Almeria intership
Several actions
16
INTEGRATED PROJECTS
ELECTRICITY PRODUCTION
2000 MW by 2020 and more by 2030
INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH & DEVELOPMENT
AND TRAINING
For a competitive industry
For technology improvement and
qualified resources
For an inclusive development
PRINCIPALES ACTIONSSTRATEGIC AXES
LOCAL DEVELOPMENT IN HARMONY WITH THE SOLAR POWER PROJECTS
Guidelines
Sustaining actionsCreate a local dynamismEnsure integration1 2 3
AGRICULTURE
Agriculture
Entrepreneurship
Development and facilitation of territories
Education
SANTE
Health
Improving the population’s social environment
Territories’s opening up
Basic infrastructures
Education Sociocultural activities Sports’ activities
Health Infrastructures Agriculture
More than 60 Actions and projects led since 2010
More than 30 000 beneficiaries
6 Areas of intervention
18
Employment
Sponsorship / patronage
INTEGRATED PROJECTS
ELECTRICITY PRODUCTION
2000 MW by 2020 and more by 2030
INDUSTRIAL INTEGRATION LOCAL DEVELOPMENTRESEARCH & DEVELOPMENT
AND TRAINING
For a competitive industry
For technology improvement and
qualified resources
For an inclusive development
RESEARCH AND DEVELOPMENT, A COMPLEMENTARY AXIS OF NOOR PLAN
R&D actions led alongside with national and international actors including:
20
– Qualify new solar technologies
– Create a network between industrials and research institutionsAn R&D Platform, to
This platform hosts:
Demonstration projects in order to test, qualify, and improve plants’ components of all solar technologies
Research projects to support technological transfer and know how on CSP and PV technologies
Commercial services to industrials and universities for a global added value
MASEN: PROMISING FUTURE PROSPECTS
A REGIONAL AND INTERNATIONAL INTEGRATION TO MAKE MOROCCO A SOLAR HUB
22
SOUTH SOUTH COOPERATION1
• Morocco, Hub of expertise in the energy field
SOUTH NORTH COOPERATION2
• Morocco, for a competitive green energyexchange
MENA COOPERATION3
• Collaboration agreements
AN APPROACH TO BE DUPLICATED TO ALL RENEWABLE ENERGY PROJECTS
WIND PROJECTS: OPERATIONAL PROJECTS AND PROJECTS UNDER DEVELOPMENT
WIND PROJECTS
OPERATIONAL PROJECTS
4 projects
550 MW
PROJECT UNDER DEVELOPMENT (2020)
7 projects
1 300 MW
HYDRO PROJECTS: OPERATIONAL PROJECTS AND PROJECTS UNDER DEVELOPMENT
HYDRO PROJECTS
OPERATIONAL PROJECTS
27 projects 1 303 MW
PROJECTS UNDER DEVELOPMENT (2020)
9 projets 126 MW