Page 1: Proposal Naperville Illinois PROJ600

Proposal

8/9/2009PM 600 Section C

Tina Finch

Team A:Jennifer BrowerTom Menning

Fred ParlinThomas Rampley

Page 2: Proposal Naperville Illinois PROJ600

Table of Contents1.0 Executive Summary............................................................................5

2.0 Technical Proposal..............................................................................8

2.1 Project Purpose.........................................................................8

........................................................................................................

2.2 Project Benefits.........................................................................8

2.3 Statement of Work (SOW)..........................................................9

2.3.1 Scope...........................................................................9

2.3.2 Tasks (Level 2 WBS)......................................................9

2.3.3 Deliverables................................................................10

2.3.4 Acceptance Criteria.....................................................13

2.4 Project Plan.............................................................................14

2.4.1 Technical Description.................................................14

2.4.2 Project Schedule.........................................................15

2.4.3 Project Risk................................................................16

2.4.4 Critical Success Factors...............................................18

2.4.5 Assumptions...............................................................21

3.0 Management Proposal.......................................................................22

3.1 Corporate Organizational Structure..........................................22

3.2 Project Organizational Plan......................................................23

3.2.1 Work Breakdown Structure (Level 3 WBS)....................23

3.2.2 Project Organizational Structure..................................23

3.2.3 Project Team...............................................................23

3.3 Management Systems Overview...............................................24

3.3.1 Supplier Selection and Management............................24

3.3.2 Monitoring Quality, Cost, and Schedule........................25

3.3.3 Management of Scope and Change Orders....................26

3.4 Corporate Strengths...............................................................28

3.4.1 Technical and Manufacturing.......................................28

3.4.2 Business and Financial................................................28

3.4.3 Facilities.....................................................................29

4.0 Cost Proposal....................................................................................31

4.1 Project Costs...........................................................................31

4.1.1 Total Project Cost........................................................31

4.1.2 Breakdown of Project Costs........................................31

4.1.3 Progress Payments.....................................................35

Page 2 of 41

Page 3: Proposal Naperville Illinois PROJ600

4.2 Customer-Provided Resources..................................................35

4.3 Terms and Conditions..............................................................36

5.0 Conclusion........................................................................................38

Appendix A: List of Figures ....................................................................39

Figure 1 Gantt Chart ..................................................................39

Figure 2 Organization Chart for Customer....................................40

Figure 3 Work Breakdown Structure ...........................................41

Figure 4 Organization Chart for Project.......................................43

Appendix B: List of Tables..........................................................................

Table 1 Acceptance Criteria.......................................................44

Table 2 Breakdown of Total Project Cost.....................................47

Page 3 of 41

Page 4: Proposal Naperville Illinois PROJ600

This page intentionally left blank.

Page 4 of 41

Page 5: Proposal Naperville Illinois PROJ600

1.0 Executive Summary

The team strongly recommends that the City of Loganville take the time and effort to establish an up to date emergency response plan. The City of Loganville is a growing community in dire need of an up to date emergency response plan. As a growing community, the city must be prepared to provide the utmost level of safety and peace of mind to its citizens and visitors. This Project will provide an emergency response plan for the City of Loganville.

Scope

The emergency response plan will include:

Detailed plan documentation Process improvements to the existing plan Training of local officials and volunteers Emergency response simulation test for the city

Costs

The total cost of the project is $735,000, including project costs and project premium. The project premium which covers the team costs to deliver the project is $167,500 while the project costs total $567,500. The project costs are broken down by milestone as follows:

Milestone Description Cost

  Emergency Response Initiative $567,500.00

1 Director of Emergency Response $50,000.00

2 Subject Matter Expert Conference $7,500.00

3 Emergency Response Center of Operations $245,000.00

  Hire Architect $10,000.00

  Hire Real Estate Agent $5,000.00

  Purchase Land for Operations Center $50,000.00

  Build Operations Center $175,000.00

  Emergency Leadership moved into Operations Center $5,000.00

4 Shelter Setup $126,500.00

 

Stock Shelters with Emergency Supplies

(Medical/Food/Communication) $50,000.00

  Create signage for shelters (ie. Emergency Shelter) $1,500.00

 

Install Emergency communication (radio system) to Operations

Center $75,000.00

5 Communication Plans $28,500.00

  Hire Web Site Designer $7,500.00

 

Setup Automated Emergency Response information line (Where to

go, What to do) $5,000.00

  Conduct Townhall Meetings at New Operations Center. $10,000.00

Page 5 of 41

Page 6: Proposal Naperville Illinois PROJ600

 

Radio notifications of Townhall Meetings and Emergency Response

Website/Phone Line $2,000.00

 

TV notifications of new Emergency Response Plan and

Website/Phone Line $4,000.00

6 Volunteers/Training $10,000.00

  Draft of Volunteer Incentive Program $10,000.00

7 Emergency Notification System $100,000.00

  Set up Alert Sirens throughout Community $100,000.00

8 Emergency Response Test $0.00

Note: If the City of Loganville wishes to further reduce costs, the project could be completed

for $485,000 by eliminating the construction of new Operations Center and the facilitation of

Townhall Meetings to communicate the new Emergency Response System.

Schedule

The project will run from August 9, 2009 through May 9, 2010 as shown in the chart below:

Milestones Duration in DaysSelection of Director of Emergency Response 34

Subject Matter Expert Conference 26Emergency Response Center of Operations 181

Shelter Setup 14Communication Plans 219

Volunteer Training 4Emergency Notification System 30

Emergency Response Test 3

*A complete breakdown of the schedule is provided in the Gantt Chart in Appendix A, Figure 2.

Benefits

This project will provide many benefits to the city's visitors and inhabitants.

1. The emergency response plan will improve the quality of life by providing a safe, healthy, beautiful and harmonious place to live and work.

2. The plan will help provide peace of mind to the community as it grows. The city must be safe and provide a haven to its citizens in order to promote growth.

3. This project will facilitate communication during a desperate situation. Help will be delivered to those who need it. And those who provide help in cases of emergency will be able to act with precision and confidence while proving information to the federal response team that will take over afterward.

Page 6 of 41

Page 7: Proposal Naperville Illinois PROJ600

4. In the unfortunate event of emergency, the community will have peace of mind and have the ability to obtain food, shelter, and safety from the elements and individuals who wish to harm others. In these times of great danger in the world, it is the responsibility of the City of Loganville to offer peace of mind. and the ability to provide intelligence to federal responders. The community will be able to immediately step into action via first responders.

Page 7 of 41

Page 8: Proposal Naperville Illinois PROJ600

2.0 Technical Proposal

2.1 Project Purpose

The need to prepare for disasters is real. Being prepared can reduce anxiety,

fear, and the losses that typically accompany disasters.

The purpose of this project is to create a comprehensive disaster recovery

plan that will leave Loganville, South Carolina much better positioned and

prepared to respond to the needs of its citizens in the event of catastrophe

than it was prior to the creation of a disaster recovery response plan.

2.2 Project Benefits

This project will provide many benefits to the city's visitors and inhabitants.

The emergency response plan will improve the quality of life by

providing a safe, healthy, beautiful and harmonious place to live and

work.

The plan will help provide peace of mind to the community as it grows.

The city must be safe and provide a haven to its citizens in order to

promote growth.

This project will facilitate communication during a desperate situation.

Help will be delivered to those who need it. And those who provide

help in cases of emergency will be able to act with precision and

confidence while proving information to the federal response team that

will take over afterward.

In the unfortunate event of emergency, the community will have peace

of mind and have the ability to obtain food, shelter, and safety from

the elements and individuals who wish to harm others. In these times

of great danger in the world, it is the responsibility of the City of

Loganville to offer peace of mind and the ability to provide intelligence

to federal responders. The community will be able to immediately step

into action via first responders.

2.3 Statement of Work (SOW)

2.3.1 Scope

The scope of this project is to develop and administer an emergency response

plan for the City of Loganville, South Carolina. This plan will ensure that local

officials and volunteers are adequately prepared and able to provide

Page 8 of 41

Page 9: Proposal Naperville Illinois PROJ600

immediate assistance to their community in the event of a disaster until

outside agencies are able to respond.

2.3.2 Tasks (Level 2 WBS)

The Work Breakdown Schedule (WBS) lists the various tasks that will be

completed during the project. The WBS is shown below in the following chart:

WBS Code Emergency Response Initiative

1.1 Director of Emergency Response1.11 Create Job Opening - Director Of Emergency Response1.12 Collect Resumes1.13 Conduct Interviews of Qualified Candidates1.14 Hire Director of Emergency Response

1.2 Subject Matter Expert Conference1.21 Identify SME to invite to Conference1.22 Plan for Conference. Food/Hotels1.23 Conduct Conference with SMEs1.24 Collect SME Feedback.1.25 Create Emergency Response Plans

1.3 Emergency Response Center of Operations1.31 Hire Architect1.32 Hire Real Estate Agent1.33 Locate Land for Operations Center1.34 Purchase Land for Operations Center1.35 Design Operations Center1.36 Build Operations Center1.37 Emergency Leadership moved into Operations Center

1.4 Shelter Setup1.41 Select Community Buildings to double as Emergency Shelters

1.42 Stock Shelters with Emergency Supplies (Medical/Food/Communication)

1.43 Create signage for shelters (i.e. Emergency Shelter)1.44 Post Signage in front of Shelters

1.45 Install Emergency communication (radio system) to Operations Center

1.5 Communication Plans1.51 Hire Web Site Designer1.52 Create Emergency Response Website

1.53 Setup Automated Emergency Response information line (Where to go, What to do)

1.54 Conduct Town hall Meetings at New Operations Center.

1.55 Radio notifications of Town hall Meetings and Emergency Response Website/Phone Line

1.56 TV notifications of new Emergency Response Plan and Website/Phone Line

1.6 Volunteers/Training1.61 Draft of Volunteer Incentive Program1.62 Collect List of Volunteers1.63 Train Volunteers1.64 Assign Volunteers to Shelter Locations

1.7 Emergency Notification System

Page 9 of 41

Page 10: Proposal Naperville Illinois PROJ600

1.71 Work with TV Stations to Issue Alert Notification1.72 Work with Radio Stations to Issue Alert Notification1.73 Set up Alert Sirens throughout Community

1.8 Emergency Response Test1.81 Select 100 Community Members (From Volunteers)1.82 Trial Alert issued1.83 Measurement of Emergency Response Plan Effectiveness

2.3.3 Deliverables

2.3.3.1 Hazard Identification, Risk Level, and Risk

Response Plan

This deliverable involves identifying all potential hazards along

with an assessment that rates the likelihood and the impact of

each one.

For hazards identified as being high risk, the scope of work

calls for the creation of a full documented risk mitigation plan

detailing methods meant to lower the impact or reduce the risk

of each hazard.

For hazards identified as being medium risk, a risk mitigation

plan will be created for each hazard, but to a lesser degree of

detail than that of the high risk hazards.

For hazards identified as being low risk, the scope of work calls

for a simple statement explaining the best way to mitigate the

risk of each hazard.

2.3.3.2 Warning System and Signals

This deliverable involves detailing how the plan intends to

provide for the initial warning of both the community, as well

as, local public officials of the existence of a hazard. The scope

of work calls for a tiered system causing the higher risk hazards

have higher priority in the communication plan.

2.3.3.3 Emergency Plan Documentation

This deliverable requires that the plan provide local officials

with easily understood documentation to aid them in

implementing the emergency response plans. These documents

(checklists) are to be accessible to local officials online for

review. The scope calls specifically for the following:

updated area maps

escape routes (a plan to manage highway traffic)

Page 10 of 41

Page 11: Proposal Naperville Illinois PROJ600

communications plans, shutting off utilities, handling

those with special needs (such as the elderly)

handling animals (pets)

basic safety skills

2.3.3.4 Disaster/Hazard Supply

This deliverable calls for the creation of a method for educating

the general public and local officials concerning how to prepare

themselves for hazards and providing for their own basic needs

for a period of several days. Basic needs are defined as water,

food, first aid, clothing and blankets. The scope calls for the

development of lists of emergency supplies people should have

in their workplaces, homes, schools, and cars.

2.3.3.5 Shelters

To meet the scope of this deliverable, the plan must identify

several community buildings to be used as mass care shelters.

In addition to identifying these locations, the plan is expected to

address a method for the stockpiling and dispensing of basic

supplies at each shelter: water, food, first-aid and sanitary

facilities, as well as, addressing security concerns.

2.3.3.6 Communications Plan

The communications plan is two-fold.

First, this deliverable requires the development and testing of a

method for local officials to use to communicate with one

another during a disaster.

The second piece of this deliverable calls for the development

of a means of informing the community of actions to take

during a disaster rather than merely informing them that a

disaster is occurring. In addition, the scope declares that the

plan instruct the community to go to a website that will have

further instructions for them, as well as links to other pertinent

government websites.

2.3.3.7 Community Plan

This deliverable requires that the plan detail a method for the

creation and operation of a group of community volunteers that

will report to a designated city official. This group and their city

official will create a community emergency response plan.

Page 11 of 41

Page 12: Proposal Naperville Illinois PROJ600

2.3.3.8 Practicing and Maintaining Plan

This deliverable calls for the development of methods for

practicing the emergency response plan for each of the various

disaster scenarios. These methods should be created such that

emergency communications methods and equipment are tested

to assess their functionality.

In addition, this deliverable requires that the plan include a

process for maintaining and updating the emergency response

plan going forward as the needs of the city change and to

communicate those changes to the appropriate parties.

2.3.4 Acceptance Criteria

The criteria and requirements that the project must meet before the

Customer will accept delivery are as follows:

All deliverables and work performed are subject to Customer’s

written approval.

All deliverables and work performed will be provided in a

manner consistent with and on the dates detailed in the

proposal.

During acceptance testing, the project team will make

themselves reasonably available to the customer.

During acceptance testing, if the customer determines that any

deliverable does not meet the requirements agreed upon in

writing, the customer will notify the project team in writing with

specifics. The project team has ten (10) business days to

correct the deficiencies. Then, acceptance testing will once

again resume. This will continue until the deliverable is

accepted. Hpwever, the customer may terminate the

agreement after two (2) successive acceptance failures. If the

agreement is terminated, the project team must refund within

thirty (30) days all monies paid by the customer at that point

and the customer must return all deliverables in their

possession.

2.4 Project Plan

2.4.1 Technical Description

The technical approach the team intends to take is to utilize generally

accepted project management best practices and principles as defined

Page 12 of 41

Page 13: Proposal Naperville Illinois PROJ600

by the Project Management Institute (PMI). The project will follow the

processes and philosophies of PMI as described in Project Management

Body of Knowledge (PMBOK), 4th Edition.

The team will incorporate a traditional phased approach to the project;

i.e. the project will begin with the initiation phase. At that time, the

new project’s existence will be formally recognized. Also, a Project

Charter will be created and the Project Manager will be named.

Next, the development phase will be done. This phase will include

project planning. A Project Plan will be created with the help of the City

of Loganville via team interviews, etc.

The implementation phase will follow the development phase. During

this phase, the project plan will be executed, monitored and controlled.

Monitoring will require that pertinent data be routinely acquired and

analyzed so that action can be taken when progress fails to match

plans and meet objectives. Additionally, a Change Management board

will be formed to handle requests for changes related to scope,

schedule, and cost.

The final phase of the approach to the project will be the closing phase.

At that time, all outstanding contractual issues will be completed and

documented in preparation for turning over the end result to the

clients for acceptance and sign-off. The team will also request

customer input for the lessons learned document.

2.4.2 Project Schedule

The Project Schedule lists the tasks, duration, start and end dates for the project. The project will run from August 9, 2009 through May 9, 2010 as shown in the chart below:

Milestones Duration in DaysSelection of Director of Emergency Response 34

Subject Matter Expert Conference 26Emergency Response Center of Operations 181

Shelter Setup 14Communication Plans 219

Volunteer Training 4Emergency Notification System 30

Emergency Response Test 3

A copy of the Gantt Chart is included in the next graphic:

Page 13 of 41

Page 14: Proposal Naperville Illinois PROJ600

2.4.3 Project Risk

The following chart outlines the risks associated with the City of

Loganville project as well as the plan of action to reduce, eliminate,

and/or mitigate those risks:

Risks Likelihood Impact Contingency Plan

Financial Low High $735,000 has been set

Page 14 of 41

Page 15: Proposal Naperville Illinois PROJ600

Obligation

aside for this project. Budgeting for shortfalls /

maintenance may be necessary

Communication Breakdown Low High

Regularly scheduled meetings will reduce

breakdowns

Community Acceptance Moderate Moderate

Promote and educate the community on the

importance of this project via town hall meetings

and advertising

Logistics Moderate High

Continual coordination and maintenance of

resources. Additionally, planning and training are

key

Technical Support Low ModerateSeek assistance from Emergency Managers

from nearby cities

Coordination Low Moderate

Notifications and communication

requirements through training will reduce this

Resource Availability (Personnel)

Moderate ModerateCreate a large list of city employees assigned to

positions

Checklist Accuracy

Low Moderate

Checklists continually evolve. Conduct annual reviews to ensure most

current information

Contingency Planning

Low Moderate

Train using exercise scenarios. This allows the identification of shortfalls and operational problems

Liabilities (Risk Management) Moderate Low

Ensuring all parties are insured and documents

are in place to protect the citizens and the

communityLong Term Risks

Lack of Equipment

Low High

Allocate monies over time within the budget to acquire necessary

equipment

Lack of Training Low Moderate

Initial and continual contingency training will ensure responder and community readiness

Mobilization (timeliness)

Moderate High

A checklist will be developed to outline specific mobilization

needs

Page 15 of 41

Page 16: Proposal Naperville Illinois PROJ600

Activation Deficiencies Low Moderate

Within our checklists, activation notifications will

be step one

Lack of Roles and Responsibilities Low Moderate

Training and checklist will provide responders with

knowledge of the Command Response

Center (CRC) and will be trained to manage all aspects of a response

Confusion in Long Term Planning (post response)

Low Low

Following emergencies create an after action

reports and utilize available technical

resources. For instance the EPA is a free phone

callOperations

ControlLow Moderate Teach to maintain open

channel of communication

2.4.4 Critical Success Factors

Standup of a local emergency coordinator position: This position is

designed to manage and coordinate responses and functions as the

local Director or Commander. All information flows to and from this

position. This is the top priority to ensuring effective communication.

Response effectiveness: Bi-annual exercises will improve cooperation

and allow all agencies to work together to strengthen response actions.

Complete identification of all resources available: There are local

resources which when made available would improve our success.

Notification and education of all emergency responders will ensure all

resources are available.

Buy in of local community: Education is the only way to improve the

likelihood the community will stand by the plan. We will provide

information to the community via Television, Radio and the local news.

Additionally, town hall meetings will take place to ensure the

community has the ability to share their concerns and field questions.

Create a Command (Emergency) Response Center: which will act as

the hub for an emergency or natural disaster in a time of need. This is

the major part of the plan and drives a successful response. This will

be our main focus to ensure all appropriate and most accurate data is

represented in checklists and plans developed. Representatives from

the following agencies would be present and consist of:

Page 16 of 41

Page 17: Proposal Naperville Illinois PROJ600

1. Director of Emergency Response (typically the Emergency

Coordinator)

2. Security

3. Environmental

4. Fire

5. Civil Engineering

6. Medical

7. Manpower

8. Safety

9. Chaplain/Pastor/Preacher

10. Red Cross

11. Salvation Army

12. Communications

13. Vehicle Dispatch Perhaps Department of Transportation (DOT)

Coordination: Coordination is extremely important. When multiple

agencies are responding to a scenario, it must be ensured that

everyone is speaking to each other effectively. Proper training will

reduce confusion and increase awareness.

Communication: Communication (internally/externally) is a must! To

ensure communication takes place routine meetings must take place.

Outside agencies are encouraged to attend. Once again, proper

training will reduce confusion and increase awareness.

Low annual cost requirements: In this small community, cost is a major

concern and utilizing resources already available will reduce costs.

Additionally, regular maintenance and repairs will increase the

longevity of resource.

Preparedness: The community has to be able to respond to

emergencies and disasters efficiently and effectively. Training will

ensure they are prepared for the situation and understand how to act

and respond accordingly and are in a position of readiness.

Continuity: The customer must ensure proper guidance is maintained

for those responding. This must try to always be done similarly to

reduce confusion and increase effectiveness. Those managers who

would run response teams and hold positions of authority must all be

trained to the same level of understanding to reduce confusion.

Page 17 of 41

Page 18: Proposal Naperville Illinois PROJ600

Volunteers: With any emergency those who volunteer are the ones

who ensure the response is a success. There are almost no paid

positions in this scenario. Therefore encouraging the community to

stick together and form a bond is a must. Education will improve

community awareness and proved information in case of a disaster.

2.4.5 Assumptions

The local government will gain full control of this project once

completed.

Additional support from the team will be made available to the

customer if needed upon request.

Most current contact information of resources will be set up

prior to completion of the project. It is up to the customer to

maintain accurate contact information following acceptance of

the plan.

Continuity in the form of periodic updates will need to take

place as time progresses and the community grows.

Page 18 of 41

Page 19: Proposal Naperville Illinois PROJ600

3.0 Management Proposal

3.1 Corporate and Project Organizational Structure

The Project Management Team consists of 15 members, each with a unique

set of skills capable of delivering high quality project outcomes to customers.

Each member is responsible for specific work which spans across the entire

project related to a specific end product or deliverable.

Our team members have the ability and are capable of executing focused

implementation business concepts using a high level of operational, technical

and strategic engagements. Additionally, the successful combination of

innovative spirits and business concepts offers the financial power of venture

capitalists and strategic investors.

3.1.1 Project Team

The Project Team is shown in the organization Chart below:

3.2 Project Organizational Plan

3.2.1 Work Breakdown Structure

The Work Breakdown Schedule (WBS) lists the various tasks that will be

completed during the project. The WBS is shown below in the following chart:

WBS Code Emergency Response Initiative

1.1 Director of Emergency Response

Page 19 of 41

Page 20: Proposal Naperville Illinois PROJ600

1.11 Create Job Opening - Director Of Emergency Response

1.12 Collect Resumes

1.13 Conduct Interviews of Qualified Candidates

1.14 Hire Director of Emergency Response

1.2 Subject Matter Expert Conference

1.21 Identify SME to invite to Conference

1.22 Plan for Conference. Food/Hotels

1.23 Conduct Conference with SMEs

1.24 Collect SME Feedback.

1.25 Create Emergency Response Plans

1.3 Emergency Response Center of Operations

1.31 Hire Architect

1.32 Hire Real Estate Agent

1.33 Locate Land for Operations Center

1.34 Purchase Land for Operations Center

1.35 Design Operations Center

1.36 Build Operations Center

1.37 Emergency Leadership moved into Operations Center

1.4 Shelter Setup

1.41 Select Community Buildings to double as Emergency Shelters

1.42Stock Shelters with Emergency Supplies

(Medical/Food/Communication)

1.43 Create signage for shelters (i.e. Emergency Shelter)

1.44 Post Signage in front of Shelters

1.45Install Emergency communication (radio system) to Operations

Center

1.5 Communication Plans

1.51 Hire Web Site Designer

1.52 Create Emergency Response Website

1.53Setup Automated Emergency Response information line (Where to

go, What to do)

1.54 Conduct Town hall Meetings at New Operations Center.

1.55Radio notifications of Town hall Meetings and Emergency Response

Website/Phone Line

Page 20 of 41

Page 21: Proposal Naperville Illinois PROJ600

1.56TV notifications of new Emergency Response Plan and

Website/Phone Line

1.6 Volunteers/Training

1.61 Draft of Volunteer Incentive Program

1.62 Collect List of Volunteers

1.63 Train Volunteers

1.64 Assign Volunteers to Shelter Locations

1.7 Emergency Notification System

1.71 Work with TV Stations to Issue Alert Notification

1.72 Work with Radio Stations to Issue Alert Notification

1.73 Set up Alert Sirens throughout Community

1.8 Emergency Response Test

1.81 Select 100 Community Members (From Volunteers)

1.82 Trial Alert issued

1.83 Measurement of Emergency Response Plan Effectiveness

3.3 Management System Overview

Finding and selecting the correct supplier is crucial to the project's success.

Therefore, the team is committed to most effectively use reliable and trusted

resources to deliver on time, at cost, and with superior quality.

3.3.1 Supplier Selection and Management

The team will provide support with supplier selection and management

according to the project's needs. When selecting Team A to manage

the City of Loganville project, the client is guaranteed access to a

wealth of both independent and objective experience. Through

effective management of resources and experience, the Team has built

an extensive supplier network. The Team is committed to devoting

time and effort toward developing and cultivating collaborative

relationships with both large and small providers. The Team's

extensive knowledge of the marketplace enables the selection of the

best providers.

3.3.2 Monitoring Quality, Cost and Schedule

The Project Quality Assurance Specialist adds value to the selection

process by increasing confidence in the supplier’s ability to deliver

products/services according to the appropriate quality standards. Once

Page 21 of 41

Page 22: Proposal Naperville Illinois PROJ600

an appropriate supplier has been selected, the Team will closely

manage the interaction between that supplier and the project.

Additionally, the Team will be involved in all aspects of the supplier

management process from negotiating contracts to assisting in

protocol writing and design, independent monitoring, technical and

document review, and project completion and close out.

All inclusive project costs have been calculated at $735,000.

The project can reasonably be completed within 9 months time:

3.3.3 Management of Scope and Change Orders

The management of change is a critical factor to the success of a

project. Change Management is a process that will be used to control

unforeseen changes that may arise during the course of a project

which could jeopardize cost, quality, and/or schedule. The focus of the

management of scope and change is on those changes that are

introduced by the stakeholders. Changes to the content of the

deliverable or requirement changes are the most common. Too much

variation from the Project Plan can impact productivity and can lead to

Page 22 of 41

Page 23: Proposal Naperville Illinois PROJ600

a project becoming out of control with different teams working on

conflicting objectives. Managing change is key; reducing and

minimizing confusion with project requirements is essential.

The Team's scope and change management plan focuses on two main

areas. First, the Team provides reference documentation on the scope

and change management procedures for stakeholders. Also, scope and

change management procedures will be provided that include a

description of responsibilities and tasks, including the tools with which

they will interact allowing the process to be implemented and

managed consistently by the Change Control Board. The Change

Control Board will be comprised of members of the project team and

two stakeholders.

The overall goal of the scope and change management plan is to:

Provide guidelines or procedures to manage change

Establish a standard process to initiate change

Facilitate management of change

Ensure proper documentation of the change request

Once a change has been identified, these five steps in the change

control and management process:

Identification and documentation: Description of the proposed

change and the rationale behind it.

Assessment: The change is evaluated with members of the

Change Control Board to decide whether or not the change is a

wise use of resources.

Analysis: The change will undergo an in depth analysis

evaluating the outcome and the impact.

Decision: The Change Control Board will make a

recommendation prior to final approval.

Implementation: The Project Manager will incorporate the

change into the project plans.

3.4 Corporate Strengths

The Team will convert innovative business models by combining years of

experience and the team members' creativity into high performance solutions.

3.4.1 Technical

Page 23 of 41

Page 24: Proposal Naperville Illinois PROJ600

The greatest strength that the Team has is a wide range of experience

both technical and operationally, with the utmost strength being the

team's confidence in resources and each other. By using the team's

staff and resources, the City of Loganville will have the ability to

respond to any disaster with confidence!

Since this project has specific needs, additional resources will be

needed. The resources listed below are the primary resources and

subject matter experts used on previous projects who can assist in

creating the Communication Plan, and then execute the Emergency

Response Plan once the project is complete.

Occupational Safety and Health Administration (OSHA)

Environmental Protection Agency (EPA)

National Guard Resources

HAZMAT / Weapons of Mass Destruction (WMD) Teams

3.4.2 Business and Financial

The benefits the business and finance models will provide the City of

Loganville are:

Cost Reduction

Strategic Flexibility

Focus and Specialization

Rapidly exploit new market/product opportunities

Share or reduce and capital investment

Move from fixed to variable cost

This graphic shows the various business and finance models:

Page 24 of 41

Page 25: Proposal Naperville Illinois PROJ600

3.4.3 Facilities

A conference center with internet access and phone lines will be

needed for the project team. Access to additional facilities or contact

information for local facilities will be necessary for coordination

purposes. This facility will also act as the City's Command (Emergency)

Response Center during future real world scenarios.

Shelters located in various community buildings are necessary for

possible shelters in a time of need. These shelter locations will have

the ability to provide water, food, medicine, and basic sanitary

facilities. Written plans will be developed for the management of these

facilities to include dispensing supplies.

Page 25 of 41

Page 26: Proposal Naperville Illinois PROJ600

4.0 Cost Proposal

4.1 Project Costs

This section will discuss the various costs involved in the project for project cost

clarity. The purpose of this section is to itemize all costs so the customer may have

the ability to customize their cost where possible.

4.1.1 Total Project Cost

The total project proposal is offered at a price of $735,000. Terms and

Conditions for payment are proposed in later sections of this proposal.

4.1.2 Breakdown of Project Costs

A breakdown of project costs is provided for cost clarity in the event

the customer wishes to alter the cost structure if possible by

adding/subtracting pieces of the proposal. The project consists of 8

major milestones all with varying costs. These milestones are outlined

in order below along with their corresponding costs.

1. Hire Director of Emergency Response: $50,000/Year.

a. This is a re-occurring salaried position which is deemed a

necessary. The most successful processes have process

champions therefore successful implementation and

continuity is dependent upon maintaining a process

Page 26 of 41

Page 27: Proposal Naperville Illinois PROJ600

champion. The salary is estimated using freely available

salary databases of persons with similar title and

responsibilities.

2. Subject Matter Expert Conference: $7,500

a. This is a one time project expense deemed necessary to

formulate the best possible Emergency Action Plans to be

utilized by the Shelter Network. At times of crisis; its highly

possible communication plans will be cut between a Shelter

and the Operations Center necessitating Emergency Action

Plans to guide Shelter leaders of appropriate actions during

times of lost communication. The $7,500 cost essentially

pays lodging and travel expenses incurred by Subject Matter

Experts. It also pays for a modest conference style forum

with food and beverage provided.

3. Emergency Response Center of Operations: $245,000

a. This is a one time project expense which is deemed optional

however highly recommended by the project team. Times

of crisis call for clear leadership and the construction of a

new Operations Center accomplishes this. It would also

increase communication efficiencies across the already

established emergency response teams in Loganville by

centrally locating the heads of those functional areas all in

one place. These costs are estimates based on previously

constructed Operations Centers in other communities

nearby Loganville. The breakdown of these costs are as

follows:

i. Hire Architect: $10,000

ii. Hire Real Estate Agent: $5,000

iii. Purchase of Land for Operations Center: $50,000

iv. Construction of Operations Center: $175,000

v. Moving Expense: $5,000

b. All but $5,000 of the above expense could be avoided by

designating an existing town building to service this need.

The moving expense would still remain since functional

heads should still move into this existing building. Also, by

utilizing an existing town building, as much as 60 days may

Page 27 of 41

Page 28: Proposal Naperville Illinois PROJ600

be cut out of the total project duration. Possible Optional

Savings: $240,000.

4. Setup of Shelter Network

a. This is mostly a one time necessary expense with the

exception of emergency supplies. The Shelter Network will

consists of several pre-existing buildings spread throughout

the community which will act as “safe zones” for community

members. Since not all community members can fit within

the Operations Center, the Shelter Network is of extreme

importance. The breakdown of costs are as follows:

i. Stock shelters with emergency supplied: $50,000

1. Yearly replenishment costs of $10,000 will

apply

ii. Signage to indicate shelter location: $1,500

iii. Emergency Communication Radio Systems: $75,000

5. Communication Plans

a. These costs relate mostly to the communication process of

the new Emergency Response System. Most of the cost will

be upfront “marketing” type cost which are deemed

necessary by the project team. If community members are

not aware of the new Emergency Response System, it

ceases to have any value. Communications will be made in

all media types.

i. Create Website: $7,500

ii. Automated Emergency Response Telephone Hotline:

$5,000

iii. Townhall Meetings: $10,000

iv. Radio Notifications: $2,000

v. TV Notifications: $4,000

b. The website, automated telephone hotline, radio, and tv

notifications are considered necessary. The town hall

meetings are optional but suggested since many people will

appreciate the person approach which more easily

facilitates 2 sides question and answers. Possible

Optional Savings: $10,000

6. Volunteer Selection/Training

Page 28 of 41

Page 29: Proposal Naperville Illinois PROJ600

a. These costs are re-occuring yearly since the project team

believes volunteers will require certain incentives in order to

volunteer. The project team suggest yearly tax breaks

given to volunteers for service

i. Volunteer incentive program: $10,000/Year.

ii. Volunteer Training: $0 to be facilitated by Director of

Emergency Response and existing Loganville

emergency response teams (Police, Fire Dept, Etc).

7. Emergency Notification System

a. These costs are a necessary one time expense. All the

advertising in the world will not inform a bystander on the

street of an impending emergency.

i. Setup Emergency Sirens throughout the community:

$100,000

8. Emergency Response Test

a. This will accomplished at no cost since all preceding costs

are necessary to accomplish this step.

The final cost of the project proposal consists of the Project Premium to

deliver the project. This cost essentially covers the project team's cost

to deliver the proposal over 8 months as well as a reasonable return.

Total Project Premium: $167,500.

Total Project Cost: $735,000

Total Project Cost Utilizing Potential Savings: $485,000

Note: Savings Cost of $485,000 does not include construction of

new Operations Center ($240,000 Savings) or the facilitation of

Townhall Meetings to communicate the new Emergency

Response System ($10,000)

4.1.3 Progress Payments

Proposed payments are to follow progress of the rollout of the new

Emergency Response Plan. Proposed payments are as follows:

1. Upon Project Initiation – 20%

2. Upon Completion of SME Conference – 20%

3. Upon Completion of Shelter Network Setup – 20%

4. Upon Completion of Emergency Notification System – 20%

5. Upon Completion of successful Emergency Response Test – 20%

4.2 Customer Provided Resources

Page 29 of 41

Page 30: Proposal Naperville Illinois PROJ600

The customer will make available existing emergency response personnel as

well as town leadership to provide support for volunteer training as well as

communication plans necessary to socialize the existence of the new

Emergency Response Plan. Primary examples include (but are not limited to):

1. Police Department

2. Fire Department

3. Loganville Mayor

The newly hired Director of Emergency Response will work with and utilize

necessary town resources, which includes essentially any person who is

directly compensated by the city of Loganville. In order to ensure

cooperation, the project team recommends dotted line reporting to the

Director of Emergency Response in all things related to the new Emergency

Response system.

4.3 Terms and Conditions

Limits

The delivery date of proposal is given as August 9, 2009 with proposal

expiration 60 days thereafter, or October 9, 2009. After October 9, 2009, the

proposal will no longer be valid. Upon acceptance of the proposal, Project

Initiation will commence 7 days later upon receipt of the first progress

payment of 20% from the customer. The project initiation date will mark the

beginning of the project schedule and will be communicated to the customer

by the project team upon acceptance of the proposal.

Contact

All inquiries both before and during (should the proposal be accepted) the

project concerning the proposal should be directed to Tom Menning, Project

Team Lead.

Completion Metric

A successful implementation of the Emergency Response plan will be

determined by the following criteria:

1. Milestones 1-7 outlined above in section 4.1.2 Breakdown of

Project Costs are completed.

2. 50% Success Rate of test subjects in milestone 8; Emergency

Response Test. A success rate is defined simply as whether or not

a test subject responds to the emergency test by going to the

correct shelter in the shelter network.

Page 30 of 41

Page 31: Proposal Naperville Illinois PROJ600

Customer Default of Payments

In the event the City of Loganville does not make payment within two weeks

of a scheduled progress payment, the project team reserves the right to

cancel the remainder of the proposal and require an additional 20% surcharge

of whatever monies are yet unpaid. If such problems are foreseen by the

customer, it is requested that the customer communicate these problems to

the project team in order to avoid such measures. If customer remains in

default, the project team will pursue other necessary modes of collection to be

paid by the customer with the primary mode of collection including civil court

with all fees (including attorney and court) to be covered by the customer.

Project Extension

In the event the project extends beyond its original timeline, an additional

payment equal to one tenth of the total project costs will be due on the first of

each additional month. As an example, If total projects costs equal $735,000,

a payment of $73,500 will become due on the first day of each month beyond

the original timeline. This is done only to provide cost coverage for the project

team during unplanned work time. The one tenth payment does not provide

the project team with any premium payment whatsoever so incentive to

complete at or ahead of schedule is still high.

Page 31 of 41

Page 32: Proposal Naperville Illinois PROJ600

5.0 Conclusion

It is best to be prepared AND able to communicate the plan when it is needed. The plan developed by Team A described in this document will satisfy the requirements listed in the Request for Proposal. Variables such as project cost and completion time have been carefully evaluated and incorporated into the custom designed plan in order to fit the needs of the City of Loganville.

The emergency response plan prepared by Team A will provide a top-notch coordinated plan that will facilitate communication in the event of a disaster. A well-developed emergency response plan will not stop a disaster from occurring. However, the plan will bring peace of mind and confidence while simplifying the tasks to be done after that disaster occurs.

Team A's emergency response plan will provide a vital service to the community. It will aid in making the City of Loganville a better place to live, work, and play. The plan created by Team A effectively meets the needs of the City of Loganville and it is highly recommended that the plan is accepted.

Page 32 of 41

Page 33: Proposal Naperville Illinois PROJ600

Appendix A

Figure 1. Gantt Chart

Page 33 of 41

Page 34: Proposal Naperville Illinois PROJ600

Figure 2. Organization Chart for Customer

Page 34 of 41

Page 35: Proposal Naperville Illinois PROJ600

Figure 3. WBS

WBS Code Emergency Response Initiative1.1 Director of Emergency Response

1.11 Create Job Opening - Director Of Emergency Response1.12 Collect Resumes1.13 Conduct Interviews of Qualified Candidates1.14 Hire Director of Emergency Response

1.2 Subject Matter Expert Conference1.21 Identify SME to invite to Conference1.22 Plan for Conference. Food/Hotels1.23 Conduct Conference with SMEs1.24 Collect SME Feedback.1.25 Create Emergency Response Plans

1.3 Emergency Response Center of Operations1.31 Hire Architect1.32 Hire Real Estate Agent1.33 Locate Land for Operations Center1.34 Purchase Land for Operations Center1.35 Design Operations Center1.36 Build Operations Center1.37 Emergency Leadership moved into Operations Center

1.4 Shelter Setup1.41 Select Community Buildings to double as Emergency Shelters

1.42 Stock Shelters with Emergency Supplies (Medical/Food/Communication)

1.43 Create signage for shelters (i.e. Emergency Shelter)1.44 Post Signage in front of Shelters

1.45 Install Emergency communication (radio system) to Operations Center

1.5 Communication Plans1.51 Hire Web Site Designer1.52 Create Emergency Response Website

1.53 Setup Automated Emergency Response information line (Where to go, What to do)

1.54 Conduct Town hall Meetings at New Operations Center.

1.55 Radio notifications of Town hall Meetings and Emergency Response Website/Phone Line

1.56 TV notifications of new Emergency Response Plan and Website/Phone Line

1.6 Volunteers/Training1.61 Draft of Volunteer Incentive Program1.62 Collect List of Volunteers1.63 Train Volunteers1.64 Assign Volunteers to Shelter Locations

1.7 Emergency Notification System1.71 Work with TV Stations to Issue Alert Notification1.72 Work with Radio Stations to Issue Alert Notification1.73 Set up Alert Sirens throughout Community

1.8 Emergency Response Test1.81 Select 100 Community Members (From Volunteers)1.82 Trial Alert issued

Page 35 of 41

Page 36: Proposal Naperville Illinois PROJ600

1.83 Measurement of Emergency Response Plan Effectiveness

Page 36 of 41

Page 37: Proposal Naperville Illinois PROJ600

Figure 4. Organization Chart For Project

Page 37 of 41

Page 38: Proposal Naperville Illinois PROJ600

Appendix B Items

Table 1. Acceptance Criteria

Deliverable Criteria Standard

Hazard Identification,

Risk Level, and Risk Response

Plan

Identify all potential hazards along with an assessment that rates the likelihood, impact and a course of action for each.

For hazards identified as being high risk, the scope of work calls for the creation of a full documented risk mitigation plan detailing methods meant to lower the impact or reduce the risk of each hazard. For hazards identified as being medium risk, the scope of work calls for the development of a risk mitigation plan for each hazard - but to a lesser degree of detail than that of the high risk hazards. For hazards identified as being low risk, the scope of work calls for a simple statement explaining the best way to mitigate the risk of each hazard.

Warning System and

Signals

Provide for the initial warning of the community and local public officials of the existence of a hazard.

A tiered system where the higher risk hazards have higher priority in the communication plan.

Emergency Plan

Documentation

This deliverable requires that the plan provide local officials with easily understood documentation to aid them in implementing the emergency response plans.

These documents (checklists) are to be accessible to local officials online for review. The scope calls specifically for the following: updated area maps, escape routes, communications plans, shutting off utilities, handling those with special needs, handling animals, basic safety skills.

Disaster/ Hazard Supply

Educating the general public and local officials concerning how to prepare themselves for hazards and provide for their own basic needs for a period of several days.

Basic needs are defined as water, food, first aid, clothing and blankets.

Page 38 of 41

Page 39: Proposal Naperville Illinois PROJ600

Shelters Identify several community buildings to be used as mass care shelters. Address a method for the stockpiling and dispensing of basic supplies at each shelter.

Specifically: Water, food, first-aid, sanitary facilities, security.

Communications Plan

Develop and test method local officials are to use to communicate wit one another during a disaster. Develop means of informing the community at large of actions to take during a disaster.

Direct community to website with further instructions.

Community Plan

Create group of community volunteers that will report to a designated city official.

This group and their city official will create a community emergency response plan for small business owners.

Practicing and Maintaining

Plan

Create a process for practicing the emergency response plan for each disaster scenario. Also, create a process for maintaining and updating the emergency response plan.

The practicing/testing process should be created such that emergency communications methods and equipment are tested for functionality. The maintaining and updating process should be created such that changes are communicated to the appropriate parties.

Page 39 of 41

Page 40: Proposal Naperville Illinois PROJ600

Table 2. Breakdown of Total Project Costs

Milestone Description Cost

  Emergency Response Initiative $735,000.00

1 Director of Emergency Response $50,000.00

  Create Job Opening - Director Of Emergency Response $0.00

  Collect Resumes $0.00

  Conduct Interviews of Qualified Candidates $0.00

  Hire Director of Emergency Response $50,000.00

2 Subject Matter Expert Conference $7,500.00

  Indentify SME to invite to Conference $0.00

  Plan for Conference. Food/Hotels $0.00

  Conduct Conference with SMEs $7,500.00

  Collect SME Feedback. $0.00

  Create Emergency Response Plans $0.00

  Complete SME Conference $0.00

3 Emergency Response Center of Operations $245,000.00

  Hire Architect $10,000.00

  Hire Real Estate Agent $5,000.00

  Locate Land for Operations Center $0.00

  Purchase Land for Operations Center $50,000.00

  Design Operations Center $0.00

  Build Operations Center $175,000.00

  Emergency Leadership moved into Operations Center $5,000.00

  Complete New Operations Center $0.00

4 Shelter Setup $126,500.00

  Select Community Buildings to double as Emergency Shelters $0.00

 

Stock Shelters with Emergency Supplies

(Medical/Food/Communication) $50,000.00

  Create signage for shelters (ie. Emergency Shelter) $1,500.00

  Post Signage in front of Shelters $0.00

 

Install Emergency communication (radio system) to Operations

Center $75,000.00

  Complete Shelter Setup $0.00

5 Communication Plans $28,500.00

  Hire Web Site Designer $7,500.00

  Create Emergency Response Website $0.00

 

Setup Automated Emergency Response information line (Where to

go, What to do) $5,000.00

  Conduct Townhall Meetings at New Operations Center. $10,000.00

  Radio notifications of Townhall Meetings and Emergency Response $2,000.00

Page 40 of 41

Page 41: Proposal Naperville Illinois PROJ600

Website/Phone Line

 

TV notifications of new Emergency Response Plan and

Website/Phone Line $4,000.00

  Complete Communication Plans $0.00

6 Volunteers/Training $10,000.00

  Draft of Volunteer Incentive Program $10,000.00

  Collect List of Volunteers $0.00

  Train Volunteers $0.00

  Assign Volunteers to Shelter Locations $0.00

  Complete Volunteer Gathering $0.00

7 Emergency Notification System $100,000.00

  Work with TV Stations to Issue Alert Notification $0.00

  Work with Radio Stations to Issue Alert Notification $0.00

  Set up Alert Sirens throughout Community $100,000.00

  Complete Emergency Notification System $0.00

8 Emergency Response Test $0.00

  Select 100 Community Members (From Volunteers) $0.00

  Trial Alert issued $0.00

  Measurement of Emergency Response Plan Effectiveness $0.00

Page 41 of 41