Project Water Sanitation-Carazo “Promote hygiene in rural families” In 15 Communities in the Dry Zone of Carazo Nicaragua 2010-2013 Report for the Environmental Mitigation Monitoring for Construction of 22 water storage basins The creation of this document was possible thanks to the support of the United States Agency for International Development (USAID) below are the terms of cooperation -524-A-00-10-00004. The opinions expressed in this document are those of the authors and do not necessarily reflect the opinions of USAID or the United States Government. Jinotepe 10/30/2013

Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Embed Size (px)

Citation preview

Page 1: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Project Water Sanitation-Carazo “Promote hygiene in rural families”

In 15 Communities in the Dry Zone of Carazo Nicaragua 2010-2013

Report for the Environmental Mitigation Monitoring for

Construction of 22 water storage basins The creation of this document was possible thanks to the support of the United States Agency for International Development (USAID) below are the terms of cooperation -524-A-00-10-00004. The opinions expressed in this document are those of the authors and do not necessarily reflect the opinions of USAID or the United States Government.

Jinotepe 10/30/2013

Page 2: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

1

Table of Contents

I. PRESENTATION REPORT ON ENVIRONMENTAL MITIGATION MONITORING ........................................ 2

A INTRODUCTION ...................................................................................................................................... 3

B JUSTIFICATION FOR WATER STORAGE BASINS CONSTRUCTION ........................................................................... 3

C ACTIVITY DESCRIPTION............................................................................................................................. 4

1. Choosing basin location ................................................................................................................. 5 2. Materials purchase, transport and delivery to communities ........................................................... 5 3. Water storage Basin construction .................................................................................................. 5

III. IMPLEMENTED ENVIRONMENTAL MITIGATION MEASURES................................................................. 6

A SITES SELECTION ..................................................................................................................................... 6

B WORK CONSTRUCTION............................................................................................................................. 6

1. Work Team groups for cleaning and proper solid waste deposition ............................................... 6 2. Personal protection gear use, such as: gloves, helmets .................................................................. 6

C WORK USE AND MAINTENANCE .................................................................................................................. 6

IV. ENVIRONMENTAL MITIGATION MEASURES ......................................................................................... 8

Ilustration Table

ILUSTRATION 0-1: WATER STORAGE MEANS IN LOS GUERREROS AND LOS DÍAZ COMMUNITIES.............................................. 5

List Tables

TABLE II-1: WATER STORAGE BASINS BUILT BY THE PROJECT .......................................................................................... 6 TABLE IV-1: MITIGATION IDENTIFICATION PLAN COMPLIANCE (TABLE NO. 2) ..................... ¡ERROR! MARCADOR NO DEFINIDO. TABLE IV-2: ENVIRONMENTAL SURVEILLANCE: EVALUATION, MONITORING AND FOLLOW-UP (TABLE NO. 3) ¡ERROR! MARCADOR

NO DEFINIDO.

Page 3: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

2

I. Presentation Report on Environmental Mitigation Monitoring

Title of activity: Construction of 16 water storage basins

Project IP: Project Water Sanitation –Carazo

Name of executor: Asociación de Desarrollo Comunitario del Departamento de Carazo (ADECA)

Finance period September 2010 to March 2014

Level of resources (US$): 10,044.64

Report Prepared by: Ivania Cárdenas García

Date of previous EMRN: does not apply (yes applies)

Status of Completing the Mitigation and Monitoring Measures NO EMR initial describing deputy mitigation plan (YES o NO)

YES EMR annual describing the progress of mitigation measures is established and annexed (YES or NO)

_NO__ Some of the mitigation conditions cannot be satisfied and the remedy have been provided in the EMPR (YES o NO) Authorization of EMPR of the USAID Mission Technical Delegate Recruitment Officer COTR___________ Date: _____ Environment Official of the Mission: __________________ Date: ___________ Regional Environmental Advisor: ____________________ Date: ______________

Page 4: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

3

II. Narrative Report on Environmental Mitigation Monitoring

A Introduction In 2008 a Rural Participative Diagnostic (DRP) was developed in 15 rural municipalities of Diriamba, Jinotepe, Santa Teresa and La Conquista by Association de Development Communitarian de Department Carazo (ADECA); population situation was evaluated on health aspects: sanitary hygiene conditions, gender, food security and environment, among the findings we identified the deficit on water storage infrastructure. For this reason 15 communities were selected to execute the Water Sanitation Project “Promoting hygiene among rural families”, with financing from the United States Agency for International Development (USAID), with the end goal of “Contribute to improving health conditions and the quality of life of rural families”. In compliance to this covenant, an environmental mitigation plan was elaborated for the construction of water infrastructure works for activity 2.7 Construction of 16 water storage basins. This document reports the monitoring activities on Environmental Mitigation for activity 2.7 Construction of 16 water storage basins and describes compliance to the Environmental mitigation Plan (PMA) presented to and approved by the agency in the III quarter 2012.

B Justification for Water Storage Basins Construction

In the year 2011 the Water Sanitation Project achieved the initial baseline, and found that families in the 15 communities had deficit on water storage infrastructure, families prioritized water storage only for human consumption limiting water disposition for personal and home hygiene actions. Greater capacity water recipients for storing water were metal and plastic barrels which did not satisfy the whole family water demand. Families had the need for a greater water storage capacity infrastructure to guarantee showering, house cleaning, laundry and washing dishes at home.

Page 5: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

4

Illustration I-1: Water storage means in the communities of Los Guerreros and Los Díaz

Due to the situation described above, the Water and Sanitation Project-Carazo stated activity 2.7 Construction of 16 water storage basins within its framework. This action would be realized between the second and third quarter FY2013.

C Activity Description The Water and Sanitation Project-Carazo stated the construction of water storage basins in 5 communities located in the municipalities of Diriamba and Jinotepe. Basins construction was realized in an area of family home selected under technical and organization criteria; benefitted families lent their labor during the whole construction process. On August 30th 2013, 22 water storage basins construction was concluded, benefitting approximately 106 families of the communities Paso Real, Tepano, Los Guerreros, Los Baltodanos and Los Díaz; such basic infrastructure increased water availability in their homes, which in turn brings conditions for adopting personal and environmental hygiene habits. In the communities Los Guerreros, Tepano and Los Baltodanos, water storage basins are filled with potable water that reaches them temporarily; in the case of communities Los Díaz and Paso Real, they only work with rain water during the rainy season. A detailed number of constructed basins per community follows:

Page 6: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

5

Table II-1: Distribution of the Water storage basins built by the Project

N° Community Municipality No. Basins constructed

No. benefitted families

1 Paso Real Jinotepe 3 11

2 Tepano Diriamba 7 30

3 Los Guerreros Diriamba 4 24

4 Los Baltodanos Diriamba 2 5

5 Los Díaz Diriamba 6 36

Total 22 106

The 22 basins constructed ease water storage for 106 families in their house chores and personal hygiene practices, contributing to decrease women chores’ burden and less time spent on transporting water home from the source. To guarantee work construction and quality, the following actions were taken: (1) Choose basin location, (2) Materials purchase, transport and delivery to communities and (3) Basin construction

1. Choosing basin location

Basin was located at a minimum distance of 10 meters from latrine and 20 meters from running water, river and creeks.

2. Materials purchase, transport and delivery to communities

Materials used for basin construction were bought in stores from the department of Carazo, transported to each community and delivered to the members of water and sanitation committee (CAS). This activity was conducted by the task team who coordinated with CAS for delivery and distribution of materials in each community. CAS members were responsible for storing, protect and distribute the amount of material previously diagnosed to each benefitted family.

3. Water storage Basin construction

The basin was built with materials such as quarry stone, cement, sand, gravel and iron; they have a square shape with a capacity of 3.5 cubic meters approximately, depending on the number of benefitted families. A basin with a 3 cubic meters dimension would be of 3 meters long by 1 meter wide by 1 meter deep. In the case of a 5 cubic meters basin, its dimensions would be approximately 2 meters long, 2 meters wide by 1.25 meters deep.

Page 7: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

6

III. Implemented Environmental Mitigation Measures From the use of the Environmental Control Application Form (Table 1) for the infrastructure work: 2.7 Construction of 22 water storage basins, it was concluded that the work has a minimum potential to generate adverse substantial environmental effects and thus an Environmental Mitigation Plan (Table 2) was elaborated, where potential impacts of the work were described together with its correspondent mitigation measures. Following, a description of the environmental mitigation measures for the potential impacts in the different phases of activity 2.7 Construction of 22 water storage basins, in its different phases:

A Sites selection

Prior to the construction of water storage basins, task team accompanied user families together with CAS (Water and Sanitation Committee) to evaluate and select ideal sites in order to comply with technical specs and avoid environmental problems in the future for this activity.

B Work construction

1. Work Team groups for cleaning and proper solid waste deposition

User families conducted cleaning labor during and after construction; all waste produced by pit excavation as well as those produced by the water storage basin construction were eliminated and construction.

2. Personal protection gear use, such as: gloves, helmets

People hired for this activity and families participating in the same used the protective equipment handed in by the project (helmets, gloves, mono glasses) and signaled construction area, which helped to avoid accidents and satisfactorily comply with this activity. People transporting materials (sand and gravel) were also oriented to cover it during transport to avoid generation of suspended particles that could harm people or the environment and thus avoid accidents or damages to people.

C Work use and maintenance

1. Families training on use and maintenance of the work

User families are trained on the importance of proper use and maintenance of storage basins through periodic washing to avoid illnesses related to vectors. Also, timely maintenance was promoted to allow for work durability.

Page 8: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

7

2. Keeping water storage basins covered

All 22 storage basins constructed count with built lids, which guarantees that water stored remains clean and avoid vector breeding that could cause illnesses.

3. Use the water just for household chores

Families have been oriented that water stored in basins is exclusive for house chores (wash, shower, garden). Nevertheless, families from the communities of Tepano, Los Baltodanos and Los Guerreros collect water from the domicile net and in shortage moments use it for consumption and cooking by using filters.

4. To not introduce back pumps to avoid contaminating the water (chemicals)

During follow-ups, it was verified that basins are not use by families for activities that could contaminate the water and they were oriented to avoid agro-chemicals introduction.

Page 9: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

8

IV. Environmental Mitigation Measures Table IV-1: Compliance to Mitigation Identification Plan (Table No. 2)

Infrastructure works: Construction of 22 water storage basins

Sub activity or component

Mitigation Measures implemented Goal achieved Compliance

%

Selection of sites

Evaluation of variables: area prone to landslides, proximity to rivers, creeks, springs and latrines.

22 sites selected to construct water storage basins were evaluated on variables: area prone to landslides, proximity to rivers, creeks, springs and latrines.

100

Work construction

To form work groups for cleaning and proper solid waste deposition

22 work groups realized cleaning up and proper deposition of solid waste

100

Use of personal protective equipment such as: gloves, helmets

People that supported with labor during the construction process wore safety equipment provided by the project

100

Use and maintenance of the work

To train user families about proper use and maintenance of work

106 families trained on use and proper maintenance of the work

100

Keeping water storage basins covered 22 working groups used protection equipment

100

Use the water just for household chores 106 families consume water storage basins for household chores

100

Not to introduce back pumps to avoid contaminating the water (chemicals)

22 basins where no back pumps are introduced so water contamination is avoided

100

Page 10: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

9

Environmental Evaluation, Monitoring and Follow-up Table IV-2: Environmental Surveillance: Evaluation, Monitoring and Follow-up (Table No. 3) Monitoring Period: June to August 2013

Activity Mitigation Measures

Description Responsible

Party

Monitoring Methods Estimated Cost $

Results

Recommended adjustments Monitoring

Date Problems

founds Mitigation

effectiveness Indicators Method Frequency

2.7 Construction of

22 water storage basins

Evaluation of variables: area prone to landslides, proximity to rivers, creeks, springs and latrines.

ADECA Technical team

No. sites selected to construct water storage basins were evaluated on variables:

Follow up visits the technical team to sites

1 time before construction work

0.00

June 2013

22 sites selected to construct water storage basins were evaluated on variables: area prone to landslides, proximity to rivers, creeks, springs and latrines.

To form work groups for cleaning and proper solid waste deposition

Technical team

No. of sites clean and situated correctly the solid waste generated in the work

Task team follow-up visit to the work

2 times during construction 0.00

June-July 2013

22 sites clean and solid waste generated in the work correctly situated

Use of personal protection gear

Technical team

No. work groups carrying appropriate safety equipment

Task team follow-up visit to the work

2 times during construction 0.00

June-July 2013

22 work groups carry adequate safety equipment

Page 11: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Environmental Mitigation Monitoring Report for Construction of 22 Water storage basins.

Water and Sanitation Project-Carazo

10

Activity Mitigation Measures

Description Responsible

Party

Monitoring Methods Estimated Cost $

Results

Recommended adjustments Monitoring

Date Problems

founds Mitigation

effectiveness Indicators Method Frequency

To train user families about proper use and maintenance of work

Technical team

No. of families trained on proper use and maintenance

Training workshop for the families

One (1) time after the work

400.00

August-December

2013

None

100% of user families trained on proper use and maintenance

Keeping water storage basins covered

Technical team

N° of basins kept with lid on

Task team follow-up visit to the work

Two (2) time after the work

0.00 June-July

2013 None

100% of basins keep their lids on to avoid proliferation of illnesses transmitter vectors

Use the water just for household chores

Technical team N° of families

that do not consume water stored in constructed basins

Visits of the technical team supervises and sensitize families on the use of water from the water storage basins

Two (2) time after the work

0.00 August-

December 2013

Families of Tepano, Los

Baltodanos, Los Guerreros

communities that collect domiciliary

water network, water used for consumption situation of shortages.

106 families consume water storage basins for household chores

families use water for human consumption batteries in shortage situation were provided filtrones

Not to introduce pumps for fumigation

to avoid contaminating the water (chemicals)

Technical team

N °. Water storage basins free of chemical contamination

Visits the technical team to supervise and sensitize families on pollution

One (1) time after the work

0.00 September

2013 None

22 Water storage basins free of chemical contamination

Page 12: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Stack water storage, community Los Baltodanos

Water and sanitation project

“Promoting hygiene in the rural family”

in 15 communities of the Dry Zone in Carazo 2010-2014

Photographic Memory Environmental mitigation monitoring construction of water storage basins

in the communities of Los Díaz, Los Guerreros, Los Baltodanos and Tepano in the

municipality of Diriamba and Paso Real in Jinotepe.

June 2013 to September 2013

Page 13: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Digging the pit of water storage stack

Comunidad Santa Lucia

Paso Real

Signaling construction site of the pit, Los Guerreros Bricklayers carrying protective equipment, Los Díaz

Bricklayers arming iron structure, Los Baltodanos

Page 14: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

1. Transfer and delivery of materials for construction of water storage batteries

Paso Real

Delivery of stones, Los Guerreros

Slip material for water storage stack, Tepano

Delivery of sand, Tepano

Page 15: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

Construction of water storage stack

Comunidad Santa Lucia

Paso Real

Rise of the walls of the pit and work

cleaning of solid waste, Los Díaz Waterproofing thin walls of

water storage stack with plaster, Los Guerreros

Waterproofing thin stack of water storage with plaster walls,

Los Baltodanos

Free sites of solid waste from the excavation of the pit and the

construction of water storage stack, Los Díaz

Page 16: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

1. Construction cover and channel water storage stack.

Comunidad Santa Lucia

Stack protected water storage with lid, in the

community Los Díaz

Feed for filling water storage stack, Los Díaz

Beneficiaries Pile cap building water storage, Los Baltodano.

Page 17: Project Water Sanitation-Carazo “Promote rural families”. Mitig. Enviroment. 22... · Project Water Sanitation-Carazo “Promote hygiene in rural families” ... (YES o NO) Authorization

1. Monitoring construction of water storage stack.

Comunidad Santa Lucia

Paso Real

Monitoring process of building water storage stack,

Los Guerreros Beneficiaries trained in use and maintenance

of water storage batteries, Tepano

Monitoring the use and management of water storage stack,

Los Baltodanos Monitoring the use and management of water storage stack,

Paso Real