Timeline: 27.07.2015 - 28.09.2015A timeline is a way of displaying a list of events in chronological order, sometimes described as a project artifact. Timelines can use any time scale, depending on the subject and data. Most timelines use a linear scale, where a unit of distance is equal to a set amount of time. This time scale is dependent on the events in the timeline. A timeline of evolution can be over millions of years, whereas a timeline for the day of the September 11 attacks can take place over minutes. While most timelines use a linear timescale, for very large or small timespans, logarithmic timelines use a logarithmic scale to depict time.
There are different types of timelines
Text timelines, labeled as textNumber timelines, the labels are numbers, commonly line graphsInteractive, clickable, zoomable
There are many methods of visualizations for timelines. Historically, timelines were static images, and generally drawn or printed on paper. Timelines relied heavily on graphic design, and the ability of the artist to visualize the data.
Timelines, no longer constrained by previous space and functional limitations, are now digital and interactive, generally created with computer software.
Timeline: 27.07.2015 - 28.09.2015
Timelines are very useful when presenting your schedule to the
audience.
Timeline: 27.07.2015 - 28.09.2015
You can make your timelines with office timeline free TRY it.
Timeline: 27.07.2015 - 28.09.2015
Below is there is a sample where you can edit tasks
milestones dates and other details. Play with it!
Timeline: 27.07.2015 - 28.09.2015
You can use this time line in oil and gas industry also.
Milestone(s)
Date Description
07.27.2015 Contract Award
07.31.2015 Kick off Meeting
Task(s)
Duration(days)
Start Date End Date Description
8 09.21.2015 09.28.2015 Trail
Timeline: 27.07.2015 - 28.09.2015
2015 2019
Today
Q3 Q12016 Q3 Q1
2017 Q3 Q12018 Q3 Q1
2019 Q3
Contract Award27/7/2015
Kick off Meeting31/7/2015
Sanction Gate (Select Concept)16/3/2016
Sanction Gate (Select Definition)14/7/2016
Sanction Gate (Define)11/1/2017
Jetty Detailed Design Study Completion11/1/2017
Long Lead Items Vendor Selection11/1/2017
Jetty Construction Completion8/12/2017
Detailed Engineering Completion8/1/2018
Mechanical Completion & Pre-Commissioning2/9/2019
Commissioning Complete31/12/2019
14/7/2016 - 31/12/2019MANAGEMENT
3/8/2015 - 31/12/2019
ENGINEERING
13/9/2016 - 3/1/2019PROCUREMENT and CONTRACT
16/3/2016 - 8/12/2017Early Works
11/7/2017 - 2/9/2019Construction
Commissioning 2/9/2019 - 31/12/2019