Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
2
Project Team
• NYSDOT Region 9 Local Projects Unit
• Federal Highway Administration (FHWA)
• Delaware County Dep’t of Public WorksOwner
• Modjeski & Masters, P.C.Design Engineer, Construction Inspection, Construction Support
• R. DeVincentis Construction, Inc.General Contractor
3• Located in Hamlet of Corbett, NY• Town of Colchester, Delaware County
Location
4
Bridge Description
• Suspension bridge (170 ft. main span)• Only one side span – not suspended
5
Bridge Description
• Single lane (11 ft. wide)• AADT of 477 vehicles (DCDPW 2004)
6
Bridge Description
• Load posted for 8 tons• Controlled by truss bottom chord
7
Bridge Description
• South: Side span not suspended• Through-girder (42 ft. simple span)
8
Bridge Description
• North: Intersection with NYS Rt. 30• Backstay crosses Rt. 30 (22 ft. clear)
9
Bridge Description
• Steel stiffening truss• Open grid deck
10
Bridge Description
• 2 inch diameter wire rope main cable• 1-1/2 inch diameter suspender rods
11
Bridge Description
• Suspenders attached using cable clips• Cable clamps at saddles
12
Bridge Description
• North anchorage2-3/4 inch diameter U-bolt (original)
13
Bridge Description
• South anchorage2-1/2 inch diameter U-bolt (new)
14
Bridge History
“Styled after the famousBrooklyn Bridge”
15
Bridge History
Hint: Brooklyn is the one on the left
16
Local History• Hamlet of Corbett, NY built in 1921 by the firm
of Corbett & Stuart
• Wood acid factory and mill town
• Reported to have largest wood acid plant ever built (used to make wood pulp for paper)
• Plant closed in 1934 when new production method developed not requiring wood acid
• Mill remained in operation until 1948
17
Bridge History
• Original Construction – 1926• Built by John A. Roebling’s Sons Co.
18
Bridge History
• Featured in Roebling’s Sons publication
19
Bridge History
• Original construction photos – 1926
20
Bridge History
• Original construction photos – 1926• Note original pier and tower
21
Bridge History
• Original pier upstream of currentlocation
22
Bridge History
• Original timber stiffening truss• Removed 1945 (replaced with steel)
23
Bridge Rehabilitation
Blaise A. Blabac, PEModjeski & Masters
24
Bridge Rehabilitation
• Objective: Restore and Maintain 8-ton load posting
• Level 1 Load Rating performed in 2004 resulted in lowering posting to 4-tons
• Structural Deficiencies– Stiffening truss angles– Anchorage U-bolts
• Other Ancillary work– Cleaning and Painting– Substructure concrete repairs– Miscellaneous steel repairs
25
Bridge Rehabilitation
• Award Date: April 25, 2006
• Start Date: June 1, 2006
• Completion Date: December 14, 2006
• Final Acceptance Date: January 8, 2007
• Engineer’s Estimate: $565,000.00
• Final Cost: $626,453.90
26
Bridge Rehabilitation
• Cleaning and Painting• Class A containment
BeforeAfter
27
Bridge Rehabilitation
• Guide rail improvements• Bridge and intersection with Rt. 30
Before
After
28
Bridge Rehabilitation
• South abutment repairs• Install stone bank protection
Before
After
29
Bridge Rehabilitation
• Concrete pier repairs• Install stone bank protection
BeforeAfter
30
Bridge Rehabilitation
• North abutment repairs• Install stone bank protection
Before
After
31
Bridge Rehabilitation
• North anchorage protection
Before
After
32
Bridge Rehabilitation
• South anchorage protection• Drainage improvements
Before
After
It is in there!
33
Bridge Rehabilitation
• South anchorage “protection”
Before
34
Bridge Rehabilitation
• South anchorage retaining walls
Before
After
35
Bridge Rehabilitation
• South anchorage U-bolt replacement
Before
After
36
Bridge Rehabilitation
• Stiffening Truss strengthening
37
Bridge Rehabilitation• Structural Deficiencies
– Stiffening Truss members– Anchorage U-bolts
38
Stiffening Truss
• Buckling of single angle diagonals• NO evidence of vehicle impact
39
Stiffening Truss
• Only end diagonals were bent• Improperly ascribed to vehicle impact
40
Stiffening Truss
• Original timber truss designed for 15-ton truck
• Steel stiffening truss installed in 1940’s
• Not included in previous load ratings
• End connections consist of two (2) ¾ inch diameter rivets in single shear
• Analysis indicated L 2-1/2 x 2-1/2 x 5/16 buckle, rivets overstressed due to H-15 truck
• Lowered posting to 4-tons from 8-tons
41
Stiffening Truss
• Change single angles to double angles• Dome head TC bolts to match rivets
42
Stiffening Truss
• Lessons learned:
– Single angle compression members are vulnerable to buckling about z-axis (low rz)
– Importance of rating connections
– Proper assessment of structural behavior
43
Anchorage U-Bolts
• Section loss of U-bolt dueto corrosion
44
Anchorage U-Bolts
• Unfortunate location
45
Anchorage U-Bolts
Water!
Ice!
• Inadequate drainage• 80 years worth of exposure
46
Anchorage U-Bolts
• Area prone to flooding
47
Anchorage U-Bolts
• Area prone to flooding
48
Anchorage U-Bolts
• Area prone to flooding
49
Anchorage U-Bolts
• Original 2-3/4 inch diameter U-bolts• Corrosion had reduced diameter to 2-1/8 inch
up to 1/4 inch pitting (1-7/8 inch remaining)• Section loss of 54%!• Original capacity = 190 kips• Reduced capacity = 88 kips• Max. cable force = 63 kips (with H-15 truck)• Inventory level rating of H 17
– Did not control posting (!)
50
Anchorage U-Bolts
• How do you replace U-bolts?
• Need to off-load anchorages
• Use Jacking System to transfer cable reaction:– Cable clamps to grip main cable– Helical anchors driven into embankment– Jacking frame to transfer loads
• Bridge closed to traffic
• Completely designed, detailed on plans– Constructed per design
51• Install helical anchors• 60 kips ultimate capacity each
Jacking System
52• Install helical anchors• 60 kips ultimate capacity each
Jacking System
53• Install jacking frame
Jacking System
54• Install jacking frame• Install cable clamp
Jacking System
55• Jack until anchorage is off-loaded• Jacking load was 56 kips per cable
Jacking System
56
Helical Anchors
• Installed with conventional skid-steerwith hydraulic torque head driver
57
Helical Anchors
• Anchor is advanced until a specifictorque value is attained
58
Helical Anchors
• Anchor is tested in place to verifyrequired capacity (60 kips ultimate)
59
Jacking Frame
• Placement of Jacking Frame
60
Jacking Frame
• Jacking beam connected to extensionrods from helical anchors
61
Jacking Frame
• Center-hole hydraulic jacks connectedto extension rods
62
Jacking Frame
• Jacking beam transfers jacking loadsto cable clamp
63
Jacking Frame
• Cable clamp (tested for 88 kips)• Grips cable using 4 Crosby clips
64• Looks good on paper… will it work?• Contractor played it safe…
Jacking System
65• Cutting existing U-bolts
Jacking System
66
Jacking System
• Success!
65
Jacking System
• New U-bolts installed
66
Questions?Questions?