Project Report --Water Shut Off

Embed Size (px)

Citation preview

  • 7/28/2019 Project Report --Water Shut Off

    1/18

    Page 1 of18

    PROJECT REPORT ON

    WATER SHUT OFF IN PRODUCTION WELLS

    Under the guidance of Sri R K ANAND CE(P)

    Submitted by:

    1) Satish kumar duggi AEE(P)

    2) Gautam kumar AEE(P)

    3) Rajiv Sharma AEE(P)

    4) Nizamuddin khan AEE(P)

    5) Fasil PM AEE(P)

    6) Siddharth Priya Nath AEE(P)

    ON 07.06.2013

    ONGC GT(I) -2013

  • 7/28/2019 Project Report --Water Shut Off

    2/18

    Page 2 of18

    ACKNOWLEDGEMENT

    We would like to express our sincere gratitude to our supervisor RK

    Anand CE(P),IOGPT, Oil & Natural Gas Corporation Limited, Panvel, Navi

    Mumbai for his perceptive suggestions and comments that helped us to

    remain motivated and enthused in completing this work. He has provided

    various facilities during the course of this project work. His infallible

    supervision and guidance has made this work a more rewarding

    experience for me.

    I would like to thanks to Mr. & other library assistant for

    cooperating during my project work.

    We would like to thank to all the employees and staff members who

    have contributed directly or indirectly in successful completion of ourproject work.

  • 7/28/2019 Project Report --Water Shut Off

    3/18

    Page 3 of18

    INDEX

    CONTENTS PAGE NO

    1. Abstract 42. Introduction 53. Water sources4. Water problems5. Candidate well selection6. Diagnostic Methods7. Water control Technologies8. Post Job Evaluation & Success criteria

  • 7/28/2019 Project Report --Water Shut Off

    4/18

    Page 4 of18

    ABSTRACT

    This project report draws attention towards water problems in oil &

    gas reservoirs due to multiple reasons. Selection of candidate wells for

    water problems and their proper diagnostics has been detailed out.

    Accordingly the proper water shut off job and treatment techniques

    has been explained to fix the water problem in the wells . A number of

    new technologies have been put to explain the development going on

    in the field of excessive water problem & their countermeasures.

  • 7/28/2019 Project Report --Water Shut Off

    5/18

    Page 5 of18

    INTRODUCTION

    Excessive water production causes major economic problems in terms of

    loss of oil production, as well as lifting, separating and disposing of largeamounts of wastewaters. In addition, water production causes scale,

    corrosion and emulsion problems, major environmental

    problems.Therefore, every effort should be made to minimize excessive

    water production. Produced water can be reduced or avoided by using

    mechanical or chemical means. Mechanical means include drilling

    horizontal wells, placing a liner then perforating the target zone, or using

    downhole separation equipment, e.g., a hydrocyclone.

    Another problem that is caused by the presence of high permeability

    zones is differential pressure sticking, which occurs during drilling across

    porous and permeable formations. Differential pressure sticking occurs

    when the drill pipe becomes stuck in the filter cake on a permeable

    formation during drilling , mud and filtrate are lost into permeable zones

    when the mud hydrostatic pressure in the wellbore, Ph, is greater than

    the formation pore pressure, P. As the filtrate is lost, the solids in the mud

    are deposited on the formation face as filter cake. The characteristics of

    the filter cake depend on the type and amount of solids present in the

    mud. A mud with high native solids content leaves a thick sticky filter

    cake, while a mud with bentonite produces a slick thin filter cake.

    Selection of a specific water shut-off treatment depends on the sources

    of water, which include: coning, casing leaks, high permeability streaks,

    and natural fractures. Understanding reservoir characteristics and watermovement in the reservoir are key factors that determine the success of

    these treatments.

  • 7/28/2019 Project Report --Water Shut Off

    6/18

    Page 6 of18

    WATER SOURCES

    Water is present in every oil field and is the most abundant fluid in the

    field.No operator wants to produce water, but some waters are betterthan others. When it comes to producing oil, a key issue is the distinction

    between sweep, good (or acceptable), and bad (or excess) water.

    Sweep waterSweep water comes from either an injection well or an

    active aquifer that is contributing to the sweeping of oil from the

    reservoir. The management of this water is a vital part of reservoir

    management and a determining factor in well productivity and theultimate reserves.

    Good waterThis is water that is produced into the wellbore at a rate

    below WOR economic limit. It is an inevitable consequence of water

    flow through the reservoir, and it cannot be shut off without losing

    reserves. Good-water production occurs when the flow of oil and water

    is commingled through the formation matrix. The formation water flow is

    dictated by the natural mixing behaviour that gradually increases the

    WOR .

    Bad waterBad water can be defined as water that is produced into

    the wellbore and produces no oil or insufficient oil to pay for the cost of

    handling the waterwater that is produced above the WOR economic

    limit. In individual wells, the source of most bad-water problems can be

    classified as one of ten basic types. The classification of water problem

    types presented here is simplisticmany variations and combinations can

    occurbut it is useful for providing a common terminology.

  • 7/28/2019 Project Report --Water Shut Off

    7/18

    Page 7 of18

    WATER PROBEMS

    Casing, tubing or packer leaksLeaks through casing, tubing or packers

    allow water from non- oil-productive zones to enter the productionstring. Detection of problems and application of solutions are highly

    dependent on the well configuration. Basic production logs such as fluid

    density, temperature and spinner may be sufficient to diagnose these

    problems. In more complex wells, WFL Water Flow Logs or multiphase

    fluid logging such as the TPHL three-phase fluid holdup log can be

    valuable. Tools with electrical probes, such as the FlowView tool, can

    identify small amounts of water in the production flow. Solutions typically

    include squeezing shutoff fluids and mechanical shutoff using plugs,

    cement and packers. Patches can also be used. This problem type is a

    prime candidate for low-cost, inside-casing water shut- off technology.

    Channel flow behind casingFailed primary cementing can connect

    water-bearing zones to the pay zone (below middle). These channels

    allow water to flow behind casing in the annulus. A secondary cause is

    the creation of a void behind the casing as sand is produced.

    Temperature logs or oxygen-activation-based WFL logs can detect this

    water flow. The main solution is the use of shutoff fluids, which may be

    either high-strength squeeze cement, resin-based fluids placed in the

    annulus, or lower strength gel-based fluids placed in the formation to

    stop flow into the annulus. Placement is critical and typically is achieved

    with coiled tubing.

    Moving oil-water contactA uniform oil- water contact moving up into

    a perforated zone in a well during normal water-driven production can

    lead to unwanted water production (below right). This happens wherever

    there is very low vertical permeability. Since the flow area is large and the

    rate at which the contact rises is low, it can even occur at extremely low

    intrinsic vertical permeabilities (less than 0.01 mD). In wells with higher

  • 7/28/2019 Project Report --Water Shut Off

    8/18

    Page 8 of18

    vertical permeability (Kv > 0.01 Kh), coning and other problems

    discussed below are more likely. In fact, this problem type could be

    considered a subset of coning, but the coning tendency is so low that

    near-wellbore shutoff is effective. Diagnosis cannot be based solely onknown entry of water at the bottom of the well, since other problems

    also cause this behavior. In a vertical well, this problem can be solved

    easily by aban- doning the well from the bottom using a mechan- ical

    system such as a cement plug or bridge plug set on wireline. Retreatment

    is required if the OWC moves significantly past the top of the plug.

    Watered-out layer without crossflowA common problem withmultilayer production occurs when a high-permeability zone with a flow

    barrier (such as a shale bed) above and below is watered out (above). In

    this case, the water source may be from an active aquifer or a waterflood

    injection well. The watered-out layer typically has the highest

    permeability. In the absence of reservoir crossflow, this problem is

    easily solved by the application of rigid, shutoff fluids or mechanical

    shutoff in either the injector or producer. Choosing between placement

    of a shutoff fluidtypically using coiled tubingor a mechanical shutoff

    system depends on knowing which interval is watered out. Effective

    selective fluids, discussed later, can be used in this case to avoid the cost

    of logging and selective place- ment. The absence of crossflow is

    dependent on the continuity of the permeability barrier.

    Horizontal wells that are completed in just one layer are not subject to

    this type of problem. Water problems in highly inclined wells completed

    in multiple layers can be treated in the same way as vertical wells.

    Coning or cuspingConing occurs in a vertical well when there is an

    OWC near perforations in a formation with a relatively high vertical per-

    meability (below). The maximum rate at which oil can be produced

    without producing water through a cone, called the critical coning rate, is

  • 7/28/2019 Project Report --Water Shut Off

    9/18

    Page 9 of18

    often too low to be economic. One approach, which is sometimes

    inappropriately proposed, is to place a layer of gel above the equilibrium

    OWC. However, this will rarely stop coning and requires a large volume

    of gel to significantly reduce the WOR. For example, to double the crit-ical coning rate, an effective gel radius of at least

    50 feet [15 m] typically is required. However, eco- nomically placing gel

    this deep into the formation is difficult. Smaller volume treatments

    usually result in rapid water re-breakthrough unless the gel fortuitously

    connects with shale streaks.

    A good alternative to gel placement is to drill one or more lateral

    drainholes near the top of the formation to take advantage of the greater

    dis- tance from the OWC and decreased drawdown, both of which reduce

    the coning effect.

    In horizontal wells, this problem may be referred to as duning or

    cusping. In such wells, it may be possible to at least retard cusping with

    near-wellbore shutoff that extends sufficiently up- and downhole as in

    the case of a rising OWC.

    Fractures or faults between injector and producerIn naturally

    fractured formations under waterflood, injection water can rapidly

    break through into producing wells (above). This is especially common

    when the fracture system is extensive or fissured and can be confirmed

    with the use of interwell tracers and pressure transient testing.6 Tracerlogs also can be used to quantify the fracture volume, which is used for

    the treatment design. The injection of a flowing gel at the injector can

    reduce water production without adversely affecting oil production from

    the formation. When crosslinked flowing gels are used, they can be

    bullheaded since they have limited penetration in the matrix and so selec-

    tively flow in the fractures. Water shutoff is usually the best solution for

    this problem.

  • 7/28/2019 Project Report --Water Shut Off

    10/18

    Page 10 of18

    Wells with severe fractures or faults often exhibit extreme loss of drilling

    fluids. If a conduc- tive fault and associated fractures are expected during

    drilling, pumping flowing gel into the well may help solve both the drilling

    problem and the subsequent water production and poor sweepproblemsparticularly in formations with low matrix permeability.

    In horizontal wells, the same problem can exist when the well intersects

    one or more faults that are conductive or have associated conductive

    fractures.

    Fractures or faults from a water layer Water can be produced from

    fractures that intersect a deeper water zone . These fractures may be

    treated with a flowing gel; this is particularly successful where the

    fractures do not contribute to oil production. Treatment volumes must be

    large enough to shut off the fractures far away from the well.

    However, the design engineer is faced with three difficulties. First, the

    treatment volume is difficult to determine because the fracture volume is

    unknown. Second, the treatment may shut off oil-producing fractures;

    here, an overflush treat- ment maintains productivity near the wellbore.

    Third, if a flowing gel is used, it must be carefully tailored to resist

    flowback after the treatment. In cases of localized fractures, it may be

    appropriate to shut them off near the wellbore, especially if the well is

    cased and cemented. Similarly, a degradation in production is caused

    when hydraulic fractures penetrate a water layer. However, in such

    cases the problem and environ- ment are usually better understood and

    solutions, such as shutoff fluids, are easier to apply.

    In many carbonate reservoirs, the fractures are generally steep and tend

    to occur in clusters that are spaced at large distances from each other

    especially in tight dolomitic zones. Thus, the probability of these fractures

    intersecting a vertical wellbore is low. However, these fractures are often

    observed in horizontal wells where water production is often through

  • 7/28/2019 Project Report --Water Shut Off

    11/18

    Page 11 of18

    conductive faults or fractures that intersect an aquifer. As discussed

    above, pumping flowing gel may help address this problem.

    CANDIDATE WELL SELECTION

    Recovery plotThe recovery plot is a semilog plot of WOR against

    cumulative oil production (above). The production trend can be ex-

    trapolated to the WOR economic limit to determine the oil

    production that will be achieved if no water-control action is taken. Ifthe extrapolated production is approximately equal to the expected

    reserves for a well, then the well is producing acceptable water and no

    water control is needed. If this value is much less than the expected

    recoverable reserves,the well is producing unacceptable water and

    remedial action should be considered.

    Production history plotThis plot is a log-log plot of oil and water rates

    against time (below left). Good candidates for water control usually show

    an increase in water production and a decrease in oil production starting

    at about the same time.

    Decline-curve analysisThis is a semilog plot of oil production rate

    versus cumulative oil. A straight line can be expected for normal

    depletion. Any sudden change in the slope of the usual straight-line

    decline in oil production rate is a warning that excess water, as well as

    other problems, may be affecting normal production.

  • 7/28/2019 Project Report --Water Shut Off

    12/18

    Page 12 of18

    DIAGNOSTIC METHODS

    The key to water control is diagnosticsto identify the specific water

    problem at hand. Well diagnostics are used in three ways:

    to screen wells that are suitable candidates for water control

    to determine the water problem so that a suitable water-control

    method can be selected

    to locate the water entry point in the well so that a treatment can be

    correctly placed.

    A diagnostic log-log plot of WOR versus time can be used to help deter-

    mine the specific problem type by making comparisons with known

    behavior patterns (left). Three basic signatures distinguish between dif-

    ferent water breakthrough mechanisms: open flow through faults,

    fractures, or channel flow behind casing; edgewater flow or a moving

    OWC; and coning problems.7 Edgewater flow interpre- tations have

    been constructed from numerical simulation and field experience.8

    The time- derivative of the WOR also can be used, but the uncertainty or

    noisy nature of field measure- ments generally limits its application. The

    inter- pretation engineer can learn to recognize the many variations in

    these profiles and minimize the problem of nonuniqueness, when

    combined with other data.

    The usefulness of WOR diagnostic plots in determining multilayer water

    encroachment is illustrated by an example in a field operated by a major

    North Sea operating company. A medium- size reservoir with a

    moderate-to-high energy shoreface structure had been heavily

    bioturbated, giving rise to substantial permeability variations (next page,

    top). No significant shale barriers were present, and the 360-ft [110-m]

    thick reservoir from X590 to X950 ft [X180 to X290 m] gently dipped intoan aquifer. The edges of the reservoir were bounded by sealing faults and

  • 7/28/2019 Project Report --Water Shut Off

    13/18

    Page 13 of18

    truncated by an unconformity. A vertical well was perforated across 165

    ft [50 m] in the middle of this unit. No OWC or gas-oil contacts (GOC)

    were present in the reservoir.

    The WOR-diagnostic plot generated from monthly well-test data shows

    the effect of the per- meability variation in the reservoir strata (next

    page, bottom). The plot illustrates watering-out of high-permeability

    layers, which contribute to crossflow in the reservoir. The ratio of

    break- through times (1800:2400:2800) gives an indication of the

    permeability ratios in these layers. The cumulative oil produced and the

    relative perme- ability-height products of the layers might be used toestimate the remaining reserves in the lower permeability parts of the

    formation.

  • 7/28/2019 Project Report --Water Shut Off

    14/18

    Page 14 of18

    Water-Control Technologies

    Each problem type has solution options that range from the simple and

    relatively inexpensive mechanical and chemical solutions, to the morecomplex and expensive reworked completion solutions. Multiple water-

    control problems are common, and often a combination of solutions

    may be required. Today, in addition to the traditional solutions described

    above, there are new, innovative and cost-effective solutions for water-

    control problems.

    Mechanical solutionsIn many near- wellbore problems, such ascasing leaks, flow behind casing, rising bottom water and watered- out

    layers without crossflow, mechanical or inflatable plugs are often the

    solution of choice. The PosiSet mechanical plugback tool can be

    deployed on coiled tubing or wireline, and is a field-proven technology

    that ensures reliable wellbore shutoff in cased- and openhole environ-

    ments (right).

    When the wellbore must be kept open to levels deeper than the point of

    water entry, a through-tubing patch may be the answer. For example, a

    new coiled tubing- or wireline- deployed, inside-casing patch called the

    PatchFlex sleeve has been used successfully in many appli- cations

    worldwide (far right). It is particularly well suited to through-tubing water

    or gas shutoff, injection-profile modifications and zonal isolation. The

    inflatable sleeves are custom-built to match the length of the perforatedintervals and can withstand wellbore crossflow pressures. Once set, the

    sleeve becomes a composite liner inside the casing that is millable using

    through-tubing tech- niques if a subsequent squeeze operation is

    desired, or it can be reperforated later to allow reentry to the zones. The

    only disadvantage of the composite liner is a reduction of less than 1 in.

    [2.5 cm] in the wellbore diameter. However, other mechanical patch

    remedies take up even more of the available casing inner diameter.

  • 7/28/2019 Project Report --Water Shut Off

    15/18

    Page 15 of18

    Chemical solutionsChemical treatments require accurate fluid

    placement. Coiled tubing with inflatable packers can help place most

    treat- ment fluids in the target zone without risk to oil zones. Coiled

    tubing dual injection is a process of pumping protective fluid down thecoiled tubing to the casing annulus and delivering the treat- ment fluid

    through the coiled tubing (right).

    SqueezeCRETE cement is another key weapon in the armory of

    water-control solutions.17 Its low fluid loss and capability to pene-

    trate microfractures narrower than 160 microns make it ideal for

    remedial treatment of tubing leaks caused by flow behind pipe. Onceset, this cement shows high compressive strength, low permeability and

    high resistance to chemical attack. SqueezeCRETE treatment is often

    used with common cement for shutting off perfora- tions when the

    problem is watered-out layers, or rising bottom water or OWCs. Other

    applications include sealing gravel packs, casing leaks or channels behind

    casing.

    Rigid gels are highly effective for near- wellbore shutoff of excess water

    (right). Unlike cement, gels can be squeezed into the target for- mation to

    give complete shutoff of that zone or to reach shale barriers. They have

    an operational advantage over cement treatments because they can be

    jetted rather than drilled out of the well-bore. Typically based on cross-

    linked polymers, products like MaraSEAL and OrganoSEAL-R systems can

    be easily mixed and have a long working life. They can be bullheaded into

    the formation to treat specific water problems such as flow behind casing

    and watered-out layers with-out crossflow, or selectively placed in the

    water zone using coiled tubing and a packer.18

    Another solution is a flowing gel that can be injected into small faults or

    fractures, but only penetrates formations with permeabilities greater

    than 5 darcies. Large volumes (1000 to 10,000 bbl) [159 to 1589 m3] of

  • 7/28/2019 Project Report --Water Shut Off

    16/18

    Page 16 of18

    these inexpensive fluids often successfully shut off extensive fracture

    systems surrounding waterflood injector or producing wells.19 Like rigid

    gels, products such as Marcit and OrganoSEAL-F systems are cross-linked

    poly- mers that are simple to mix, have a long (up to three days) workingtime before becoming rigid, and can be pumped through completion

    screens.

    Smart or selective fluids in the form of poly- mers and surfactants are

    being developed for for- mation matrix treatments near the wellbore.

    These treatments, called relative permeability modifiers, produce a

    permanent gel-like material to stop flow in water layers, but retain fluidbehaviour in oil layers to allow production to continue.

  • 7/28/2019 Project Report --Water Shut Off

    17/18

    Page 17 of18

    POST JOB EVALUATION

    Justification of a treatment in any well is based on the value of the

    increased hydrocarbon production expected. The key word hereisexpected, which indicates a degree of uncertainty in the analysis. Some

    water-control treatments can guarantee substantial production

    increase. In such circumstances, the primary element of uncertainty is

    the job success itself. When the incremental production is relatively small

    (or was based on several assumptions) not only does job-risk come into

    play, but also the prediction itself becomes a key risk. Therefore, the

    value of a water- control treatment to the operator needs to be quan-

    tified. An analysis incorporating the multifaceted components of risk can

    be undertaken using the methods of quantitative risk analysis.

    Status Oil Production Water Production

    Technical SuccessIncreases Unchanged

    Unchanged Reduces

    Economic Success

    Sustained increase

    equivalent to 10

    times the cost of job

    Increases

    Decrease

    Unchanged

    Economic &

    Technical Success

    Sustained increase

    equivalent to 10

    times the cost of job

    Decrease

  • 7/28/2019 Project Report --Water Shut Off

    18/18

    Page 18 of18

    BIBLIOGRAPHY

    1. www.wikipedia.org

    2. www.petroone.org

    3.