Project Procedure IMP 16

Embed Size (px)

Citation preview

  • 8/18/2019 Project Procedure IMP 16

    1/22

  • 8/18/2019 Project Procedure IMP 16

    2/22

     

    AMENDMENT SHEET 

    ISSUE/ 

    REV. # 

    SUBJECT OF THE AMENDMENT  REVIEWED BY 

    & SIGNATURE

     

    AUTHORIZED BY 

    & SIGNATURE

     DATE

     

    1/0  First Issue  M.R  MD  27/01/2013 

    1/1 

    Clause 5.3  Project Execution   – 

    A stamp “issued for fabrication” is added.  M.R  MD  12/10/2013 

    1/1 

    Clause 5.3  Project Execution   – 

    Material  Delivery  (SDRF):  Internal  Order 

    Equipment List

     [IMS

    ‐PJD

    ‐10]

     

    ‐ PJD‐02 form has been updated. M.R

     

    MD 

    12/10/2013 

    1/2 Forms  IMS‐PJD‐05  ,  07  &  09  were 

    updated M.R  MD  12/06/2014 

    1/3  Forms IMS‐PJD‐05 is updated  M.R  MD  04/12/2014 

  • 8/18/2019 Project Procedure IMP 16

    3/22

     1.  Purpose and Scope 

    To  define  the  mechanism  to  be  adopted  by  the  Projects  Department  for  ensuring  proper 

    planning of  Project activities and achieving practical completion on time. Ensure all Projects 

    administration and

     construction

     activities

     are

     identified,

     planned

     and

     carried

     out

     in

     a 

    controlled manner. Ensure Project mobilization  is achieved  in a  smooth and  timely manner 

    and so minimize disruption to future construction works. 

    Ensure that Execution, monitoring, controlling and closed out for the Projects are carried out 

    as Planned for the project. 

    To established

     correlation

     between

     various

     departments

     reporting

     to

     Projects

     Department

     whose functionality either related to projects or Projects Department. 

    This procedure is applicable to the following operations: 

    1.  All type of  Projects  jobs carried out in the site and the installation at sites. 

      Safe handling of  products to ensure safety to products and personnel. 

      Control of  material returned from sites. 

      Safety of 

     personnel

     in

     sites.

     

      Identification of  products to establish traceability. 

      Monitoring and measurement of  integrated management system 

      Compliance to legal and other requirements 

    3.  Responsibility 

    Project Manager:

     

    Responsible  for  planning,  Execution  of   Project,  Managing  Communications,  Managing 

    Stakeholders,  Managing  Risks  and  Controlling  drawings  (Shop  drawings  &  Constructions 

    drawings) and specifications. 

    Site Engineer/Supervisor: 

    Supervision of   installation  / erection  jobs Coordination with  client’s  representative  for  site 

    inspections. 

    QC In‐charge: 

  • 8/18/2019 Project Procedure IMP 16

    4/22

     4.  Definitions and Abbreviations 

    Sub‐contracting: Any  job which  is  issued to another agency / organization, which has to be 

    returned to MW. 

    5.  PROCESS 

    5.1  Initiation of  Project 

    Once  the  Project  Notification  MEMO  is  received  by  Projects  department  from  Sales 

    department/Management,  Project  Manager  will  depute  the  Project  Engineer/s  for  the 

    Project, who

     will

     be

     coordinating

     with

     various

     departments

     for

     successful

     completion

     of 

     the

     project. 

    He  will  look  into  the  contract  financial  agreement  and  will  raise  the  invoice  request 

    (Performance Bond /bank guarantee request) accordingly. 

    5.2  Planning 

    The Project

     Engineer

     will

     create

     a project

     plan/schedule

     and

     Project

     Manager

     will

     ensure

     that

     

    project  is  planned  as  per  Contractual  Requirements  and  communicate  to  all  other 

    departments. 

    Projects Department shall ensure that issues related to Procurement and Purchase, selection 

    of  subcontractors, deployment of  workforce (allocation of  work force as per the project plan) 

    and execution at site are regularly monitored. 

    All necessary contract documents shall be handed over to the Project Engineer/Manger upon 

    his  nomination  (Through  ‘Notification  MEMO’)  by  Sales  Department/Management.  Such 

    documents may include but not limited to; 

      Terms and Conditions of  Contract 

      Contract Specifications 

      Bills of 

     Quantities

     

      Contract Drawings and Amendments 

      Plans of  Existing Services 

      Tender Program 

      Site investigation report, if  any 

    Record of Existing Site Conditions

  • 8/18/2019 Project Procedure IMP 16

    5/22

     The Project Manager shall study the above information and the overall concept of  operations 

    for  the project work and communicate all  the above  to  the project staff   through “Kick off” 

    meeting with Sales. 

    Project Engineer

     will

     prepare

     a drawing

     and

     document

     list

     and

     will

     issue

     a formal

     “design

     

    request”  (IMS‐ PJD‐ 02)  to Design/Engineering  Manager.  Design/Engineering  Manager  will 

    review the  list and will modify  it  if  needed to add/remove any drawings as per requirement 

    he anticipated. 

    The  Project  Manager  along  with  the  Project  Engineer  shall  provide  a  master  execution 

    program/project schedule (via Primavera/MS Project/any program provided by management) 

    for the

     purpose

     of 

     programming,

     co

    ‐ordination

     and

     future

     monitoring

     of 

     work

     progress.

     The

     program  should  include  all  requirements  related  to  the  project  activities  required 

    contractually from start to finish,  including pre‐ and post‐installation/erecting activities (e.g. 

    engineering, procurement, mobilization, execution, project close‐out, demobilization etc.). 

    The  Project  Manager  shall  submit  the  project  Schedule,  PQP  (if   applicable),  HSE  Plan  (if  

    applicable), Drawings, Method of  Statements, and Environmental Management Plan (EMP) if  

    applicable, to the consultant and client for approval. 

    Copies of  document stated must be communicated and distributed to all relevant functions 

    for the purposes of  smooth execution of  projects. 

    The  Project  Manager  and  Engineers  shall  monitor  the  master  program  with  a  view  to 

    procuring  critical  goods,  materials  or  any  subcontract  order  placement.  Special  attention 

    must be given to procurement lead‐in/ delivery periods. A procurement schedule (included in 

    Project Schedule)

     should

     be

     drawn

     up

     by

     the

     Project

     Engineer

     giving

     details

     of 

     goods

     / 

    services required and latest order dates. 

    Material and service requisitions related to the project shall be raised through MRF (Material 

    Requisition  Form  ‐ IMS‐PJD‐03) by project engineer with  authorized  signatory  (MD/Project 

    Manager/Finance Manager) and a log to be maintained for all such request. 

    The project

     Schedule

     should

     be

     regularly

     monitored

     during

     the

     course

     of 

     the

     project

     to

     ensure  that  works  are  proceeding  as  programmed  by  Project  Manager. Any  deviations  or 

    delays to the progress of  the works as shown in the program shall be brought to the attention 

    of  the General Manager for further action. 

    Amendment to the base line of project Schedule shall be forwarded to Consultant and Client

  • 8/18/2019 Project Procedure IMP 16

    6/22

     Where works are behind scheduled program, Project Manager along with the Project Team 

    shall develop and highlight the methods to Management bringing back the delayed works on 

    to the track (i.e., providing extra resources, subletting the work, additional shifts, proposing 

    alternative materials, etc.). 

    5.3  Project Execution 

    The  Project  Engineer/s  is/are  responsible  for  ensuring  that  all  necessary  Project 

    administration works are being addressed  in coordination with Project Manager. These may 

    include (as and where applicable); 

      Project correspondence

     

      Selection of  necessary Project staff  by management. 

      Project organization chart and lines of  communication 

      Project filing system and documentation 

      Necessary contract documentation 

      Project site layout plan 

      Project Quality requirement 

      Health and

     safety

     requirements

     

      Environmental requirements 

      Information receipt and issue control ‐ including drawings, Materials 

      Staff  and subcontractor induction guidelines 

      Preparation of  method statements as applicable 

      Frequency of  progress / co‐ordination meetings 

      Dates and formats for submission of  payment certificate 

      Submission weekly

     and

     monthly

     reports

     

      Drawing Control Log (IMS/DN/01) 

      Internal Order Equipment List (IMS‐PJD‐10) 

      Logistics Request Form (IMS‐PJD‐05) 

      Project Program/schedule 

      Variations logs. 

    Project 

    Manager 

    shall 

    coordinate 

    with 

    various 

    departments 

    to 

    obtain 

    building 

    permit 

    and 

    NOCs  from  SEWA/DEWA/FEWA/ADWEA/Etisalat/DU,  and  all  other  related  authorities  if  

    applicable. 

    Land Surveying: 

  • 8/18/2019 Project Procedure IMP 16

    7/22

     Document Review: 

    The  Project  Manager  /  Engineer  shall  review  all  documents  and  drawings  received  and 

    communicate to all project stake holders. 

    The Project Manager and Engineers are responsible for all site mobilization activities. Prior to 

    mobilization,  the  Project  Manager  and  Engineer  should  visit  the  site  with  a  view  to 

    familiarizing himself  with the location and surrounding facilities. 

    The  Project  Manager  and  Engineers  shall  study  the  project  specification,  drawings  and 

    contract documents and prepare a plan for execution works in accordance with construction 

    industries’ best

     practice.

     The

     Plan

     is

     then

     submitted

     and

     discussed

     with

     General

     Manager

     for

     approval. Project Manager and Engineer shall coordinate with Design Team and prepare a site 

    layout plan which shall be submitted for consultant/client approval. 

    The  Project  Manager  and  Engineer  shall  arrange  for  all  necessary  resources  to  be  made 

    available for site mobilization in coordination with various concern departments. 

    The Project Manager and Engineer are  responsible  for ensuring that all required notices  (IF 

    APPLICABLE) to

     Local

     Authorities

     have

     been

     placed

     or

     are

     being

     arranged

     so

     as

     to

     ensure

     

    timely mobilization and avoid delays when construction work commences. 

    Material Delivery (SDRF): 

    The Project Manager and Engineer shall arrange Internal Order Equipment List [IMS‐PJD‐10] 

    including the Electrical Load Schedule List prior to start the material procurements. 

    Project  Engineer will  issue  a  “Logistics  request  form”  (LRF)  [IMS‐PJD‐05]  to  the  logistic  in‐

    charge for all the material that has been received in MW store to transfer that to site for the 

    installations. 

    All site activities should be regularly monitored and controlled by the Project Manager. 

    Installation & Service Team: 

    Project  Manager/Engineer  will  issue  a  request  for  installation  [IMS‐PJD‐06]  of   delivered 

    material  to  the  Installation  &  Service  Manager  for  the  installation.  This  form  must  be 

    accompanied by 

    ( “ ” ) d b

  • 8/18/2019 Project Procedure IMP 16

    8/22

     Production Team: 

    Project Manager/Engineer will issue a request for Fabrication [IMS‐PJD‐09] to the Production 

    Manager  for any  type of  works needs  to be done within  the workshop. This  form must be 

    accompanied 

    by 

    detailed 

    fabrication/shop 

    drawings 

    stamped 

    with 

    “ISSUED 

    FOR 

    FABRICATION” and signed by Design Department Head. 

    Workmanship: 

    All site activities should be regularly monitored and controlled by the Project Manager or his 

    delegated  deputy  for  correctness  of   work  practices.  Prior  to  the  installation,  the  Project 

    Department must

     submit

     “construction

     drawings”

     along

     with

     installation

     request

     to

     the

     maintenance  department  for  the  work  execution.  Such  instruction  must  be  approved  in 

    accordance with Document Control procedure (IMS/MW/IMP‐01). 

    Payment Valuations: 

    The  Project Manager  /  Engineer  shall  value  completed works,  including off ‐site works  and 

    materials on‐site if  allowed under the contract, at required intervals throughout the duration 

    of   the  contract  and  prepare  a  valuation  accordingly  for  presentation  to  the  Customer’s Representative.  A  copy  of   each  valuation  should  be  given  to  the  Finance  Department  for 

    follow up purposes. 

    5.4  Variations initiated by Client / Consultant or by MENA Water 

    All  instructions  received  from  the Consultant/Client must be  reviewed by Project Manager 

    and where

     MENA

     Water

     considers

     the

     instruction

     constitutes

     a variation

     to

     the

     contract

     this

     

    must be handled as detailed by contract special conditions clause and specifications. 

    The Variation Updates log (IMS‐ PJD‐ 07) which is used to identify, notify and track any item 

    that may result in time and / or cost impact is maintained by the Project Manager and Sales 

    Manager. 

    5.5  Monitoring and Control 

    The  Managing  Director  shall  conduct  meetings  at  monthly  basis  according  to  project 

    requirement, as applicable, with all Projects Manager/team to discuss. These meetings should 

    be “Minuted” and distributed to all concerns. This meeting may discuss following: 

  • 8/18/2019 Project Procedure IMP 16

    9/22

       Design issues 

      Logistics issues 

      HSE issues 

      Variations 

      Payment status

     

      Risks 

      Other issues related to the project 

    The Project Manager shall conduct monthly progress meeting with the project staff. He shall 

    maintain a progress report. 

    The Project

     Manager

     and

     Engineers

     shall

     attend

     weekly

     and

     monthly

     progress

     meeting

     with

     

    the consultant and client / project staff  as per requirement. During this meeting the progress 

    and  future  short/long  term  requirements  of   the  project  will  be  discussed  with  a  view  to 

    ensuring  that  adequate  resources  are  available  /  planned  to  enable  continuation  as 

    programmed or identification. 

    The Project Manager shall produce a report of  the progress of  the works and submit this to 

    the Client

     Representative

     at

     the

     specified

     intervals,

     if 

     applicable.

     

    Project  Manager  is  solely  responsible  for  entire  site  and  has  rights  to  remove  or  take 

    necessary  action  against  in‐house  sub‐contractors,  external  sub‐contractor  or  client 

    nominated  sub‐contractors  if   they  fail  to deliver quality, environment or Health and  safety 

    requirements. 

    5.6  Quality Control (Inspection and Testing) 

    Material  inspection  request  [IMS‐PJD‐04]  shall  be  issued  by  Project  Engineer  in  case  any 

    equipment/part/whatsoever fabricated outside the MW factory. This inspection will be done 

    by internal QC department 

    In progress inspection request, either in client format or in MW format [IMS‐PJD‐05], shall be 

    raised  by  Project/Site  engineer  and  forward  to  the  client  for  inspection  and  approval.  A 

    proper “Inspection

     Log”

     will

     be

     maintained.

     In

     case

     of 

     projects

     where

     QC

     Engineers

     are

     not

     

    full time, the responsibility of  Inspection will be on Project/site Engineer to obtain necessary 

    approval from consultant/client. The PQP forms (if  applicable) shall be used. 

    5.7  Project Closeout 

  • 8/18/2019 Project Procedure IMP 16

    10/22

     Commissioning request [IMS‐PJD‐08] shall be issued by Project Engineer to the “Operation & 

    Maintenance Engineer” department. 

    This form should include, but not limited to, following 

      O&M manual of  the plant 

      Manufacturer dossier (instruction manuals) 

      Control Philosophy 

      Electrical/  Mechanical/Process  Drawings  (As  built/issue  to  construction  as 

    applicable) 

    Once successful

     internal

     commissioning

     has

     taken

     place

     client

     will

     be

     requested

     (as

     per

     

    client’s protocol) to witness the works and for onwards handing over to the Customer or his 

    Representative.  Such hand over and any subsequent maintenance should be undertaken  in 

    accordance with the contractual requirements. 

    When all the works under the contract are complete or, where phased hand over is required 

    and  the  relevant  phase  is  complete,  the  Project  Manager  and  Engineer  shall  request  the 

    Client’s 

    Representative 

    to 

    inspect 

    the 

    works 

    as 

    required 

    by 

    the 

    contract 

    specification 

    and 

    Local authority regulations. Where unsatisfactory works are  identified this shall be recorded 

    as  snags.  Again,  such  elements  shall  be  re‐inspected  upon  rectification.  Records  of   the 

    snagging inspection and re‐inspection shall be maintained as per PQP. 

    When  all  works  are  complete  to  the  satisfaction  of   the  Client  Representative  the  Project 

    Manager/ Engineer should formally request a Certificate of  Practical Completion to be issued. 

    At  such  time  the  contractual  maintenance  period  shall  commence  and  contractual 

    maintenance shall

     be

     carried

     out

     in

     accordance

     with

     the

     contract

     specifications.

     

    At  the  end  of   the  maintenance  period,  upon  successful  completion  of   all  necessary 

    maintenance works the Project Manager shall formally hand over the works with no further 

    obligation to the contractor and request that the Final Certificate be issued as appropriate. 

    The Invoice shall be raised by Accounts with reference to Project Completion/part completion 

    as requested

     by

     project

     engineer

     time

     to

     time.

     

    Inspection records shall be made available to the client upon request. The inspection records 

    will indicate the inspection status and authority of  inspection. 

    Project Manager/engineer will request design department to issue “as built drawings” of the

  • 8/18/2019 Project Procedure IMP 16

    11/22

     Operation Manuals, Warranty and Guarantees are obtained from various sub‐contractors and 

    submitted to the clients with acknowledgements. 

    6.  Records 

    ‐ Invoice/BG/PB request form [IMS  – PJD ‐ 01] 

    ‐ Drawing Request form [IMS‐ PJD‐ 02] 

    ‐ Project Schedule (via Primavera/MS Project/any program by management) 

    ‐ Material Request form [IMS‐PJD‐03] 

    ‐ Material Inspection (for material fabricated outside factory) [IMS‐PJD‐04] 

    ‐ Logistics Request Form [IMS‐PJD‐05] 

    Installation 

    request 

    form 

    [IMS‐

    PJD‐

    06] 

    ‐ Variation Log [IMS‐PRD‐07] 

    ‐ Commissioning request form [IMS‐PJD‐08] 

    ‐ Fabrication request form [IMS‐PJD‐09] 

    ‐ Internal Order Equipment List [IMS‐PJD‐10] 

    Production/Project  Manager/QC  In‐charge/Maintenance  Engineer  shall  maintain  the 

    following records for the specified period: 

    Project schedule shall be maintained for all  jobs. Retention of  the record  is two years after 

    completion of   jobs. 

    Drawing, In‐process and Final inspection reports and third party inspection reports, if  any, and 

     job completion report shall be maintained for two years after completion of  projects. 

  • 8/18/2019 Project Procedure IMP 16

    12/22

     

    FORMS Ref  No: IMS‐PJ‐01 

    Version: 0.0; Issue Date: 09/10/2012 

    INVOICE REQUEST

    Date Invoice Req. No.

    Project Project/Job No

    Client Contact No.Requested For: (Please tick as required)

    Bank Guarantee Performance Bond Invoice Request(BG) (PB)

    Is there any Particular Client Format for BG/PB? Yes / NoIf yes, attached with request? Yes / No

    Currency to be used (Please tick as required) USD AED Euro SDG Any Other

    Invoicing Details  Amount in Figure

    Contract Amount A

    Variation Contractual Amount B

    New Contract Amount C = A+BInvoiced Before D

     Amount to be invoiced with this

    request E

    Balance amount to be invoiced(after this invoice) C – D – E

     Amount to be invoiced in Words(with this request)

    Requested By Approved by

  • 8/18/2019 Project Procedure IMP 16

    13/22

     Ref  No: IMS‐PJ‐02 

    Version: 0.0; Issue Date: 09/10/2012 

    DESIGN / ENGINEERING REQUEST

    Date Request. No. DR/

    ProjectProject/JobNo

    Client Contact No.

     Any particular Specifications applicable to the contract: Yes/ No

    If yes, Specifications attached: Yes/ NoContractual /Conceptual Drawings available: Yes/ No

    If Yes, drawings attached with request: Yes/ No

     Any Particular Requirement /Constraint from Client Yes/No

    If Yes, Please specify in details 

    Drawings RequiredFill as per requirement (Expand as necessary)

    TypeC/AB/I /F Required Date

    C= Construction Drawing AB = As Built I = Info F = Fabrication

    Requested By: Received By:

    Name:

    Signature:

    Name:

    Signature:

  • 8/18/2019 Project Procedure IMP 16

    14/22

     Ref  No: IMS‐PJ‐03 

    Version: 0.0; Issue Date: 09/10/2012 

  • 8/18/2019 Project Procedure IMP 16

    15/22

     Ref  No: IMS‐PJ‐04 

    Version: 0.0; Issue Date: 09/10/2012 

    INSPECTION REQUEST

    Project/Job No Project/Job No

    Request Date Inspection Date

    Supplier/Manufacturer Contact Person

    Contact No./Cell No. Address

    LPO/Contract No.Latest/ApprovedDrawing No.

    Details of Inspection Required:

    Dimensional Interim Painting Final

    Any Special Requirement

    Observations

    Inspection Result : Pass Fail 

    Requested By Inspected By

    Project Engineer /Manager QC Engineer

    To Be Filled By QC Engineer

  • 8/18/2019 Project Procedure IMP 16

    16/22

     Ref  No: IMS‐PJ‐05 

    Version: 2.0; Issue Date: 12/06/2014 

    LOGISTIC REQUEST FORM

    To be submitted 5 – 7 days prior to the required shipping dateDate IPO / LPO No.

    Project PMA / SCT No.

    ClientDelivery SiteContact No.

    Tentative Delivery / Arrival Date:

    Means of Transport: By Air By Sea By Road

    Incoterms: Insurance:

     All Material in Store Direct from Supplier to Client:Detail of Material:

    Description of material to be Transferred/Received Attached Documents

     

    Special ArrangementsCrane/Machinery required for loading & unloading Yes/ NoIf yes, please specify

    Gate Pass/ Any particular permission required to access site: Yes/ NoIf yes, please specify Yes/ No

    Requested By Received by Logistic In-charge

    Material Verified by QC Material Ready and Packed by Store in-charge

    Name & Signature: Name & Signature:

    Date: Date:

  • 8/18/2019 Project Procedure IMP 16

    17/22

     Ref  No: IMS‐PJ‐06 

    Version: 0.0; Issue Date: 09/10/2012 

    INSTALLATION/SERVICES REQUEST FORM

    (This request to be issued at least 10 days in advance)

    Date Request. No. FS/

    Project

    Project/Job

    No

    Client

    Site Contact

    Name & No.Installation/Services Starting Date: -------------------------------------------------------------

    Date of Equipments/Materials availability at Site: ----------------------------------------Site Preparation Works Required before Start the Job? Yes/No If Yes, please specify

    Requested Completion Date: -------------------------------------------------------------Drawings Attached (with Construction Stamp) 3 sets of hard copy or soft copy in pdfformat.

    P&ID Mechanical Electrical Installation Manual

    Specify Drawings No. attached (with Revision No’s)

    Special Arrangements/Restriction by Client Any arrangements to be done by Field Services/Restriction Yes/ No

    If yes, please specify

    Scope of Work is attached: Yes/ No

    Requested By: Received By:

    Name:

    Signature:

    Name:

    Signature:

  • 8/18/2019 Project Procedure IMP 16

    18/22

     Ref  No: IMS‐PJ‐07 

    Version: 1.0; Issue Date: 12/06/2014 

    Variation Request Form

    Date Request. No.

    Project

    Project/Job

    No

    Client

    Requested by

    Variation Details:

    Scope Drawings Time Costs

    Estimated Variation (Attach detail variation estimate with this form)

    Reason of Request

    Origin of Variation

    Requested by Client Internal Request

    If requested by Client, please specify

    Name Designation

    Request DateRequest ref # (Email,Letter, verbal

    Request Attached  Yes/No Other Details/ Risks/Payment Method

    Requested By Approved by Approved by Approved by

  • 8/18/2019 Project Procedure IMP 16

    19/22

     Ref  No: IMS‐PJ‐08 

    Version: 0.0; Issue Date: 09/10/2012 Commissioning Request 

    Ref.  :  Date  : 

    To  :  Fax  : 

    Attn.  : 

    From  : 

    Project  :  Plot # : 

    Client  :  Area  : 

    Consultant  : 

    Description 

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    ……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    …………………………………………………………………………………………………………………………………………………………………

    ……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………… 

    For any assistance at site, please contact 

    Mobile No. 

  • 8/18/2019 Project Procedure IMP 16

    20/22

     Ref  No: IMS‐PJ‐09 

    Version: 1.0; Issue Date: 12/06/2014 

    FABRICATION REQUEST FORM (This request  to be issued at  least  3 days in advance) 

    Date  Request. No. 

    Project  

    Project/Job 

    No 

    Client   Site L/C No. 

    Fabrication completion required date: ……………………………………………………..……………...

    Drawings: with “ISSUED FOR FABRICATION” Stamp.

    Fabrication Mechanical Electrical

    Specify Drawings No. attached (with Revision no’s) 

    Special  Arrangements/Restriction by Client  

    Any arrangements to be done by Field Services / Restriction (at site) Yes/ No

    If yes, please specify

    Requested by Approved by Received by Received by Works final

    completed on

    Works final

    inspected on

    Project  

    Engineer 

    Project  

    Manager 

    Production 

    Manager 

    QC 

    in‐charge 

    Production 

    Manager 

    QC 

    in‐charge 

    Dated: Dated: Dated: Dated: Dated: Dated:

  • 8/18/2019 Project Procedure IMP 16

    21/22

     

    -----------------------------------------------------------------------------------------------

    PRINTED VERSION OF THIS DOCUMENTS SHALL BE CONSIDERED AS UNCONTROLLED…

    DISCLAIMER:

    This document is the property of  MENA WATER FZC. No part of  this publication may be reproduced, stored in a retrieval system in any form, or transmitted by any means, without the prior written permission of  M/s. 

    MW Managing

     Director.

     

    ISSUE / REV.: 1/ 2 

    DATE: 12/06/ 2014 

    ISO 9001‐2008, EMS 14001‐2004 and OHSAS 18001‐2007 

    FILE: IMP 16  Page 21 of  22 

    Ref  No: IMS‐PJ‐10 

    Version: 0.0; Issue Date: 12/10/2013 

    Internal Order Equipment list 

    Delivery date: Delivery Address Invoice Address In charge total sale

    Order date Sale: total costProject: Project

    Manager:Factor #DIV/0!

    Product: Engineering:

    Order No. Logistic

    Client :

    Location ForeignPurchase

    Coordinator: Coverage Rate Local Purchase

    conditions: Total cost Total sale Manufacturing

    COST WITHOUT

    OVERHEAD

    Item No Sub. Item DESCRIPTION Qty UNIT PRICE IN EUROTOTAL

    PRICE IN

    EURO

    UNITPRICE IN

    EURO

    TOTALPRICE IN

    EURO

    SUPPLIERITEM

    ART

    DELIVERY IN

    WEEKSSTATUS

    1.00 1.00

    1.01

    1.02

    2.00 2.00

    2.01

    2.02

    TOTAL PRICE

    * MANF MANUFACTURE

    REQUIREMENTS BY OTHERS *FP Foreign purchase

    *LP Local purchase

    *STC Stock

  • 8/18/2019 Project Procedure IMP 16

    22/22

     

    -----------------------------------------------------------------------------------------------

    PRINTED VERSION OF THIS DOCUMENTS SHALL BE CONSIDERED AS UNCONTROLLED…

    DISCLAIMER:

    This document is the property of  MENA WATER FZC. No part of  this publication may be reproduced, stored in a retrieval system in any form, or transmitted by any means, without the prior written permission of  M/s. 

    MW Managing

     Director.

     

    ISSUE / REV.: 1/ 2 

    DATE: 12/06/ 2014 

    ISO 9001‐2008, EMS 14001‐2004 and OHSAS 18001‐2007 

    FILE: IMP 16  Page 22 of  22 

    ELECTRICAL LOAD SCHEDULE 

    S.NO  ITEM  CAPACITY  QTY POWER SINGLE 

    AGGREGATE (KW) 

    RATED VOLTAGE 

    (AC/50 HZ) 

    CONNECTED 

    POWER (KW) 

    OPERATIONAL 

    POWER(KW) 

    DAILY RUN 

    TIME(H) 

    DAILY POWER 

    CONSUMPTION 

    (KWH/DAY) 

    Total Connected Load  kW 

    35% 

    Spare 

    Load 

    kW 

    Total load  A 

    Incomer Size  A