Project Planning
QMS Training
Mahindra Satyam Confidential 2
Objective
To define a comprehensive plan for the projectTo ensure that the project plan forms the basis for project tracking and monitoring
Mahindra Satyam Confidential 3
ProcessSelect Process for the Project
Tailor the QMS
Gather Inputs for Planning
Obtain Deviations
Document Project Plan
Review Project Plan
Approve Project Plan
Communicate the plan
Manage the Project Plan
Execute the projectwith a partial plan
Revise the Project Plan
Plan for Maintenance Work Requests
Mahindra Satyam Confidential 4
Select Process for the Project
Based on the project type identified during Project Initiation, PL checks the availability of the relevant process for executionIf the required process is not available in the QMS, PL raises a QMS improvement and informs the Process Management Group (PMG)
Mahindra Satyam Confidential 5
Tailor the QMS
PL with the help of QR Identifies the project specific
activities required for executing the project
Arrives at the tailored project specific process based on the tailoring criteria provided in each procedure
Records the tailoring done, if any, in the Project Tailoring Record
Mahindra Satyam Confidential 6
Gather Inputs for PlanningPL gathers the inputs required for preparation of the project plan: Scope, acceptance criteria, brief intro of the project,
broad estimates, warranty details Requirements and schedules as agreed upon with
the customer Project specific process including the phases, work
products, quality assurance activities, maintenance of records etc.
Risks as identified during contract review stage Estimates from Proposal stage Reusable data from Project Knowledge Base tool Skills and experience of available project team Measurement objectives
Mahindra Satyam Confidential 7
Obtain Deviations
PL obtains concession for QMS Deviation where identified project activities are in a way not defined/recommended in Qualify
Mahindra Satyam Confidential 8
Document Project PlanResources
Estimates
Deliverables
Acceptance Criteria
Project Knowledge Base
Work Management Structure
Scheduling and Tracking
Customer Interaction
Roles & Responsibilities
Review Plan
Risks
Skill Requirement & Training
Metrics
Defect Prevention
Configuration Management DAR
Business Continuity Plan
Customer one assessment Plan
Mahindra Satyam Confidential 9
Resources
PL documents the required resources in the project plan: Requirement Availability Plan for procurement, in case of shortfall
Resources include Personnel Hardware Software, or Any project specific resource
Mahindra Satyam Confidential 10
EstimatesPL revisits the estimates accepted for the project at the contract review stage PL refers to the past data while performing the
estimationIf the PL finds that the project cannot be executed as per the accepted estimates, the project estimates are to be revised In case of any mismatch between the estimates, PL
plans to cover the gap and documents in the Estimates section in the project plan
PL tracks the project estimates during the project execution and revises if required PL revises the project plan whenever there is a
change in project estimates
Mahindra Satyam Confidential 11
DeliverablesPL identifies the deliverables for the projectThe deliverables can be Customer Deliverables - Work products to
be generated as part of project execution that need to be delivered to customer for project sign off
Project Deliverables - Work products generated as part of project execution [which include reusable components], but are not requested by customer as deliverables
PL documents these in the Deliverables section of project plan
Mahindra Satyam Confidential 12
Acceptance Criteria
Acceptance criteria are the conditions under which the customer will accept the delivered softwareAcceptance criteria clearly identifies and understands what customer considers as acceptable softwarePL documents the acceptance criteria as agreed upon with customer in the Acceptance Criteria section of the project plan
Mahindra Satyam Confidential 13
Project Knowledge Base
PL refers to the Project Knowledge Base tool in eSupport for leveraging the experience of other projects to enhance the planning of his/her projectThe Project Knowledge Base containsBest practices Lessons learntSample documents
Mahindra Satyam Confidential 14
Work Management Structure
PL identifies the various phases in the life cycle of the project based on the project specific processPL documents these phases, along with the associated inputs, work products, effort estimates and planned schedule in the Work Management Structure of the project plan
Mahindra Satyam Confidential 15
Scheduling and Tracking
PL documents the mode of scheduling the project and tracking the project progress in the Scheduling and Tracking section of the project planOPTIMA is recommended for
scheduling and tracking
PL also schedules activities such as Metrics Analysis, Defect Prevention meetings and documents them in the relevant sections
Mahindra Satyam Confidential 16
Customer Interaction
PL identifies all modes of customer interactions including periodic formal client feedback and their frequencyTypical modes include telecon /
videocon, status report etc.
PL also identifies the escalation process on both the customer side and Mahindra Satyam
Mahindra Satyam Confidential 17
Roles & Responsibilities
PL identifies the responsibilities of the project team, such as SCM, Testing etc.PL documents these in the Organization Structure section of the project planPL also depicts the communication channel between the project team and customer The project team and the support units
Mahindra Satyam Confidential 18
Customer One assessment Plan
The customer one assessment shall be planned for the project deliverables. The details of these assessment plan activities along with the roles to perform these activities shall be documented in the Customer One assessment plan section. The applicability of Customer one assessments shall be as per the Customer One Assessment Procedure. PL documents the Customer one assessments planned for the project.
Mahindra Satyam Confidential 19
Review Plan
PL plans the reviews or inspections for the work products identified from each of the project execution phasesPL documents these in the Review Plan section of the project plan
Mahindra Satyam Confidential 20
Risks
PL revisits the risks identified at the
Contract Review stage identifies potential risksestimates their impact on the project,
and plans for the mitigation and handling
of risks in the risk management tool
Mahindra Satyam Confidential 21
Business Continuity Plan
Business continuity planning has to be done for project specific Business continuity requirements Project BCP includes preparation of project
specific Risk mitigation plans for Disasters Disaster recovery plans & Contingency plans
This shall be done in accordance with Mahindra Satyam’s Business Continuity Management System (BCMS)The PL communicates project BCP details to the BCL of the business unit for inclusion in business unit BCP
Mahindra Satyam Confidential 22
Skill Requirement & Training
PL arrives at a comparison of the skills required for the project versus the available skills in the team If the skills required are not available in the
team, PL prepares a training plan PL includes the schedule for acquiring the
training in the project plan in the Training Plan section
Maintains detailed schedule for each training separately
Identifies and documents Waivers, if any
Mahindra Satyam Confidential 23
MetricsPL documents metrics plan by
Identifying Goal Metrics Goal metrics are the ones which quantify the project targets. There are Mahindra Satyam
mandated Goal metrics which are defined w.r.t effort, time, quality and, scope. Apart from the Mahindra Satyam mandated metrics, project team would capture additional metrics when:
There are any customer mandated metrics as per the Contract Corporate mandate(STARTRAC) Customer sets any Improvement targets for project performance parameters like
productivity improvement, defect reduction, cycle time reduction, etc Identifying Control Metrics
The metrics that affect the performance of goal metrics are called control metrics which would be computed and tracked during the project execution. Based on the statistical co-relation analysis,
relationship between goal metrics and control metrics are identified . Identifying Process performance models
Process performance models help in effective planning thereby help the project to predict the performance of the project. Based on the project goals, project would select the appropriate Process Performance Models available and document the same in the metrics plan. For eg if the project manager wants to monitor the effort variance of the project so as to execute the project with in estimated effort, projects may choose to use the EV process performance model. This model helps the PL/PM determine optimum effort that needs to be planned and to be spent for Project management, Reviews and Testing activities to achieve project EV goal.
Setting target values (Goal, Upper and Lower limits) for Goal and Control metrics The target values are set as per organization baselines/customer targets / corporate mandate.
The goal setting of the same is automated in process performance model sheets which are derived based on statistical analysis.
Documenting the section “Strategy for achieving goals” In case if the goals for any particular metric is stringent (based on contractual
agreement/project FLCB performance targets) than the existing goals at Unit/Organization level, then the strategy for achieving the same needs to be documented in the metrics plan.
Mahindra Satyam Confidential 24
Defect Prevention
PLDefines the Defect Prevention
activities for the project Identifies the periodicity of the Defect
prevention meetings and criteria for evaluating the effectiveness of the defect prevention actions in the project
Documents these in the Defect Prevention section of the project plan
Mahindra Satyam Confidential 25
Decision Analysis and Resolution
PL Identifies instance where DAR needs
to be implementedSelects the DAR techniqueCompiles the Possible SolutionsApplies the DAR technique
Mahindra Satyam Confidential 26
Configuration Management
PL identifies the configuration management aspects to be implemented in the projectidentifies the affected group to whom configuration status should be reporteddocuments in the Configuration Management section of the project plan in detail includes the periodicity of the configuration
status reports
Mahindra Satyam Confidential 27
Review Project Plan
PL submits the project plan to QR for inspection/reviewThe project plan goes through an inspection at the time of first preparation and when major changes occur in the plan In case of minor changes, a review
may be sufficient
Mahindra Satyam Confidential 28
Review Project Plan
QR identifies the inspection /review team for inspection/review of the project planQR uses the Project Plan Review checklistPL tracks and closes the inspection/review findings In case of any conflict between the PL
and QR during the review, the matter will be escalated to the PM and Head (TQA)
Mahindra Satyam Confidential 29
Approve Project Plan
PM approves the project planThis implies that the PM takes the
responsibility for the execution of the project based on the plan
PM ensures that the project plan is inspected, approved and version controlled before the project execution starts
Mahindra Satyam Confidential 30
Communicate the Plan
The project plan indicates all the relevant recipients of the plan as audience to the planAfter the approval, the plan is communicated to all the relevant recipients Subsequent major changes to the plan also be communicated to all relevant recipients
Mahindra Satyam Confidential 31
Manage the Project Plan
The project plan shall bemanaged and controlled
Mahindra Satyam Confidential 32
Execute the Project with a Partial Plan
If all the inputs required for preparing the project plan are not available at the project execution start time, PL prepares a partial plan with available inputs The sections for which relevant information is not
available are tagged as TBDs TBDs will have possible timelines to obtain the
information Partial plan is reviewed, approved for project
execution The TBDs will be cleared as and when possible The review of the plan will be repeated
Mahindra Satyam Confidential 33
Revise the Project Plan
If any section of the project plan needs to be revised, PL verifies if any other sections get
impacted and need a revision It is mandatory to re-validate:
Estimates Risk Management Reviews Metrics Defect Prevention Work Management Structure
PL gets the project plan reviewed, approved and version controlled after each revision
Mahindra Satyam Confidential 34
Plan for Maintenance Work Requests
The Maintenance projects Will have an over all project plan for the
project Get the work in the form of Work Requests
Work requests with an effort greater than 5 calendar days, will have a Work Request Plan [WRP]For work requests with an effort less than 5-calendar days, WRP is optional the activities for these requests can be
scheduled and tracked using the MS project
Mahindra Satyam Confidential 35
Objective Met
A comprehensive plan for the project is documentedThe project plan forms the basis for project tracking and monitoring
Mahindra Satyam Confidential 36
Project Tracking and Monitoring