36
Project Management

Project Netwok

Embed Size (px)

Citation preview

Page 1: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 1/38

Project Management

Page 2: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 2/38

Project

• A project is a temporary endeavour 

involving a connected sequence of activities

and a range of resources, which is designedto achieve a specific and unique outcome

and which operates within time, cost and

quality constraints .

2

Page 3: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 3/38

3

Characteristic of a project

q A unique, one-time operational activity or effort

q Requires the completion of a large number of interrelated

activities

q Established to achieve specific objective

q Resources, such as time and/or money, are limited

q Typically has its own management structure

Page 4: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 4/38

4

Examples

 – Constructing houses, factories, shopping malls.

 – Developing military weapons , aircrafts, new

ships

 – Launching satellite systems

 – Introducing new products into market

Page 5: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 5/38

5

What is project management

• The application of a collection of tools and

techniques to direct the use of diverse resources

towards the accomplishment of a unique, complex, one

time task within time, cost and quality constraints.

Page 6: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 6/38

6

Project Management Process

• Project  planning

• Project scheduling

• Project control

• Project team

 –  made up of individuals from various areas and departments

within a company

Page 7: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 7/38

7

Work breakdown structure

• A method of breaking down a project into individual elements

( activities and tasks) in a hierarchical structure which can be scheduled

and cost

Page 8: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 8/38

8

Project Planning

• Resource Availability and/or Limits – Due date, late penalties, early completion

incentives

 – Budget

• Activity Information

 – Identify all required activities

 – Estimate the resources required (time) to complete

each activity

 – Immediate predecessor(s) to each activity needed

to create interrelationships

Page 9: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 9/38

9

Project Scheduling and Control Techniques

Gantt Chart

Critical Path Method (CPM)

Program Evaluation and Review Technique (PERT)

Page 10: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 10/38

Graph or bar chart with a bar for each project activity that shows passage of time

Provides visual display of project scheduleProvides visual display of project schedule

Gantt Chart

Page 11: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 11/38

Project Network 

• Use of nodes and arrows

Arrows ² An arrow leads from tail to head directionally –  Indicate ACTIVITY, a time consuming effort that is required to perform a

 part of the work.

Nodes A node is represented by a circle

- Indicate EVENT, a point in time where one or more activities start and/or 

finish.

• Activity

 –  A task or a certain amount of work required in the project

 –  Requires time to complete

 –  Represented by an arrow

• Dummy Activity

 –  Indicates only precedence relationships

 –  Does not require any time of effort

Page 12: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 12/38

• Event

 –  Signals the beginning or ending of an activity

 –  Designates a point in time

 –  Represented by a circle (node)

•  Network 

 –  Shows the sequential relationships among activities using nodes

and arrows

Activity-on-node (AON)

nodes represent activities, and arrows show precedencerelationships

Activity-on-arrow (AOA)

arrows represent activities and nodes are events for points intime

Project Network 

AOA P j N k f H

Page 13: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 13/38

13

AOA Project Network for House

32 0

1

3

1 1

11 2 4 6 7

3

5

Lay

foundation

Design house

and obtain

financing

Order and

receive

materials

Dummy

Finishwork 

Select

carpet

Select

paint

Buildhouse

AON Project Network for House

13

22

43

31 5

1

61

71Start

Design house and

obtain financing

Order and receivematerials Select paint

Select carpet

Lay foundations Build house

Finish work 

Page 14: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 14/38

Situations in network diagram

AB

C

A must finish before either B or C can start

A

B

C  both A and B must finish before C can start

D

C

B

A both A and C must finish before either of 

B or D can start

A

C

B

D

Dummy

A must finish before B can start

 both A and C must finish before D can start

Page 15: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 15/38

CPM calculation

• Path

 – A connected sequence of activities leading from

the starting event to the ending event

• Critical Path

 – The path where there no time buffer, i.e. slack is

zero.

• Critical Activities

 – All of the activities that make up the critical path

F d P

Page 16: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 16/38

Forward Pass

• Earliest Start Time (ES)

 – earliest time an activity can start

 –  ES = maximum EF of immediate predecessors

• Earliest finish time (EF)

 –  earliest time an activity can finish

 – earliest start time plus activity time

EF= ES + t 

Latest Start Time (LS)

Latest time an activity can start without delaying critical pathtime

LS= LF - t 

Latest finish time (LF)

latest time an activity can be completed without delayingcritical path time

LS = minimum LS of immediate redecessors

Backward Pass

Page 17: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 17/38

CPM analysis

• Draw the CPM network 

• Analyze the paths through the network • Determine the float for each activity

 –  Compute the activity’s float

float = LS - ES = LF - EF

 –  Float is the maximum amount of time that this activity can be

delay in its completion before it becomes a critical activity,

i.e., delays completion of the project

• Find the critical path is that the sequence of activities and events

where there is no “slack” i.e.. Zero slack  –  Longest path through a network 

• Find the project duration is minimum project completion time

Page 18: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 18/38

CPM Example:

• CPM Network 

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

 j, 12 j, 12 j, 12 j, 12

Page 19: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 19/38

CPM Example

• ES and EF Times

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

 j, 12 j, 12 j, 12 j, 12

0 6

0 8

0 5

 

Page 20: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 20/38

CPM Example

• ES and EF Times

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

 j, 12 j, 12 j, 12 j, 12

0 6

0 8

0 5

5 14

8 21

6 23

6 21

Page 21: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 21/38

CPM Example

• ES and EF Times

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

 j, 12 j, 12 j, 12 j, 12

0 6

0 8

0 5

5 14

8 21 21 33

6 2321 30

23 29

6 21

Project’s EF = 33Project’s EF = 33

Page 22: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 22/38

Page 23: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 23/38

CPM Example

• Critical Path

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

 j, 12 j, 12 j, 12 j, 12

Page 24: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 24/38

PERT• PERT is based on the assumption that an activity’s duration follows a

 probability distribution instead of being a single value

• Three time estimates are required to compute the parameters of anactivity’s duration distribution:

 –  pessimistic time (t p ) - the time the activity would take if things did

not go well

 –  most likely time (tm ) - the consensus best estimate of the activity’s

duration –  optimistic time (to ) - the time the activity would take if things did go

well

Mean (expected time): t e= t p + 4 tm + to

6

Variance: Vt =σ  

 2

=

t p - to

6

2

Page 25: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 25/38

Probability computation

Determine probability that project is completed within specified

time

Z =x - µ

σ

where µ = t p = project mean time

 σ = project standard mean time

x = (proposed ) specified time

Page 26: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 26/38

 Normal Distribution of Project Time

µ = t  p Time x 

 Z σ

Probability

Page 27: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 27/38

PERT Example

Immed. Optimistic Most Likely Pessimistic

Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)A -- 4 6 8

B -- 1 4.5 5

C A 3 3 3

D A 4 5 6

E A 0.5 1 1.5

F B,C 3 4 5

G B,C 1 1.5 5H E,F 5 6 7

I E,F 2 5 8

J D,H 2.5 2.75 4.5

K G,I 3 5 7

Page 28: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 28/38

PERT Example

 

AA

DD

CC

BB

FF

EE

GG

II

HH

KK

JJ

 

PERT Network 

Page 29: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 29/38

PERT Example

  Activity Expected Time Variance

  A 6 4/9B 4 4/9

C 3 0

D 5 1/9

E 1 1/36F 4 1/9

G 2 4/9

H 6 1/9

I 5 1J 3 1/9

K 5 4/9

Page 30: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 30/38

PERT Example

  Activity ES EF LS LF Slack A 0 6 0 6 0 *critical

B 0 4 5 9 5

C 6 9 6 9 0 *

D 6 11 15 20 9E 6 7 12 13 6

F 9 13 9 13 0 *

G 9 11 16 18 7

H 13 19 14 20 1

I 13 18 13 18 0 *J 19 22 20 23 1

K 18 23 18 23 0 *

Page 31: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 31/38

PERT Example

V path = VA + VC + VF + VI + VK 

= 4/9 + 0 + 1/9 + 1 + 4/9

= 2

σ path = 1.414

z = (24 - 23)/σ = (24-23)/1.414 = .71

From the Standard Normal Distribution table:P(z < .71) = .5 + .2612 = .7612

Page 32: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 32/38

PROJECT COST

Page 33: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 33/38

Project Crashing

• Crashing

 –  reducing project time by arranging additional resources

• Crash time

 –  an amount of time an activity is reduced

• Crash cost

 –  cost of reducing activity time

• Goal

 –  reduce project duration at minimum cost

Page 34: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 34/38

Activity crashing

                                                                                                                                                                                                                                                                                                                                       A                                                                                                                                                                                                                              c                                                                                                                                                                                                                                                                                                       t                                                                                                                                                                                                                                                                                                                                                     i                                                                                                                                                                                                                          v       

                                                                                                                                                                                                                                                                                                                                                i                                                                                                                                                                                                                                                                                                 t                                                                                                                                                                                                                             y                                                                                                                                                                                                                                                                                                                                      c                                                                                                                                                                                                                                     o       

                                                                                                                                                                                                                              s                                                                                                                                                                                                                                                                                                       t    

Activity time

Crashing activity

Crash

time

Crash

cost

 Normal Activity

 Normal

time

 Normal

cost

Slope = crash cost per unit time

Ti C d

Page 35: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 35/38

Time Cost data

Activity Normaltime  Normalcost Rs Crashtime Crashcost Rs Allowablecrash time slope

1

2

34

5

6

7

12

8

412

4

4

4

3000

2000

400050000

500

500

1500

7

5

39

1

1

3

5000

3500

700071000

1100

1100

22000

5

3

13

3

3

1

400

500

30007000

200

200

7000

75000 110700

Practice Example

Page 36: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 36/38

darla/smbs/vit

Practice ExampleA social project manager is faced with a project with the following

activities:

Activity Description Duration

Social work team to live in village 5w

Social research team to do survey 12w

Analyse results of survey 5w

Establish mother & child health program 14w

Establish rural credit programme 15w

Carry out immunization of under fives 4w

Draw network diagram and show the critical path.

Calculate project duration.

Practice problem

Page 37: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 37/38

Practice problemActivity Description Duration

1-2 Social work team to live in village 5w

1-3 Social research team to do survey 12w

3-4 Analyse results of survey 5w

2-4 Establish mother & child health program 14w

3-5 Establish rural credit programme 15w

4-5 Carry out immunization of under fives 4w

3

1

2

4

5

Page 38: Project Netwok

8/9/2019 Project Netwok

http://slidepdf.com/reader/full/project-netwok 38/38