K. Long, June 11, 2022 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions

Project Manager’s report

  • Upload
    quasar

  • View
    62

  • Download
    1

Embed Size (px)

DESCRIPTION

Project Manager’s report. Status/progress since CM18 Looking forward Organisation Conclusions. Status (progress since CM18): . CM18. Status (progress since CM18):. CM19: Status reports on Phase I equipment and progress towards Phase II. Accomplishments: head lines:. Target: - PowerPoint PPT Presentation

Citation preview

Page 1: Project Manager’s report

K. Long, April 24, 2023

Project Manager’s report

Status/progress since CM18 Looking forward Organisation Conclusions

Page 2: Project Manager’s report

Status (progress since CM18):

J une 16, 2007 Wrap-up and Action I tems-Zisman 6

I ntroduction (4)— making some progress on understanding beam line

o review planned later this summer— G4BL low emittance cases are helped by thinner diff user

10 mrad case 30 mrad case

-20-19-18-17-16-15-14-13-12-11-10

-9-8-7-6-5-4-3-2-10123456789

1011121314151617181920

0 2 4 6 8 10 12 14 16

G4BL NoDec xrms

G4BL NoDec yrms

TTL NoDecIP + Qd Sli xrms (f rom 16599)

TTL NoDecIP + Qd Sli yrms (f rom 16599)

QQQQQQB2

-20-19-18-17-16-15-14-13-12-11-10

-9-8-7-6-5-4-3-2-10123456789

1011121314151617181920

0 2 4 6 8 10 12 14 16

TTL NoDecIP + Qd Sli xrms(from 16599)

TTL NoDecIP + Qd Sli yrms (f rom 16599)

G4BL NoDec xms

G4BL NoDec yrms

QQQQQQB2y y

xx

Schedule:

Much work to do, many details Electronics, trigger, DAQ Will push HARD to preserve cosmic test in

July

Missed, but close

At risk, but ‘project’ OK

M. Bonesini - MICE CM18 RAL 16/06/07 30

Conclusions

TOF0/1 counter construction is progressing; readout scheme worked out; software issues tackledsome installation issues to be spotted outlaser calibration system to be finalizedstill some delays arising from INFN situation not fully worked out (NTA approval, funding [up to now we are at 0 E] …)

J une 16, 2007 Wrap-up and Action I tems-Zisman 3

I ntroduction (1)•Progress continues

— spectrometer solenoid fabrication well under wayofirst magnet delayed, hopefully by December 2007

— RF power source refurbishment moving forward at Daresburyofirst 300 kW amplifier completed in J une

— H2 R&D system tender completed— Phase I I MI CE proposal was funded for year 1

Center, E1, M1 windings complete Cryomech compressor at vendor

J une 16, 2007 Wrap-up and Action I tems-Zisman 9

I ntroduction (7)•Reached important milestone

— all items beyond crane coverage have been installedo should facilitate parallel installation activity from now on

CM18

Page 3: Project Manager’s report

Status (progress since CM18):

CM19: Status reports on Phase I equipment and progress towards Phase II

Page 4: Project Manager’s report

Accomplishments: head lines: Target:

Routine operation with multi-million actuations Progress on bearing materials

Paper to Technical Board this week Cabling and installation plan in hand Removal of old target: MS&RA in preparation

Upstream beam-line: Magnetic elements in place Services being prepared

Radiation shielding: Decay Solenoid Area ‘block house’ built Additional shielding on plinth to allow working in DSA

Not quite out of the woods! Downstream beam line:

D2 installed Q35 stands procured:

Base plates and lower girder boxes Upper girder boxes soon

Q35 refurbishment progressing well But seeking to accelerate

Services: De-mineralised water plant on order, temporary water will be needed Electrical services designed, now being implemented

CKOV/TOF0 stand: Ready for production readiness review (PRR)

Page 5: Project Manager’s report

Accomplishments: head lines: PSI solenoid:

Vacuum testing complete and successful Pressure testing complete and successful Alignment/refurbishment programme in hand

Linde refrigerator: Contractors have started So far (1 week in) maintaining schedule

Issue is radiation in Hall Priority to Linde in MICE Hall programme

Plinth: Rails installed and aligned (0.2mm) before additional shielding installed

LH2 test cryostat: Issue of shrouding of top of cryostat vessel under discussion

Issue is prevention of ingress of oxygen YI has contacted ‘experts’ and prepared paper defining design modification:

Paper presented to, and reviewed by TB Updated paper to TB this week, then pass to RAL safety

RF power: Power from 4616 amp (June)

170 kW achieved September (200 kW required for MICE) Progress on refurbishment of 116 amp:

At DL – mechanical AT CERN – mechanical

Focus-coil tender exercise: Tender exercise essentially complete – discuss this week

Page 6: Project Manager’s report

Accomplishments: head lines: MICE Local Control Room:

Preparation started Racks:

First rack bases to be installed next week First racks (network and PPS) to be installed the week after

Partitioning: On order; expect to be complete by end Oct07

Services: Air-con, power, etc. to follow

Expect completion mid/late November Expect ToF 0/1 to be delivered to RAL early Nov07

In time for cosmic integration test Components of CKOVa (upstream module) at RAL:

Window modification in R12 w/s Anticipate delivery of CKOV components in mid October

In time for cosmic integration period in November KL presampler:

Anticipate delivery to RAL in time for cosmic test

Page 7: Project Manager’s report

Accomplishments: head lines: Tracker:

Station acceptance rig: recovered from power failure Debugging readout – production end this week?

Completion of first tracker delayed: Milestone: 15Oct07 – likely delayed by a week or two

Tracker group decision: Complete QA!

Sandwich calorimeter: First prototype module produced in Trieste

Spectrometer solenoid: Ship to FNAL for field measurements in December Expect shipment to RAL in Feb08

Absorber: MICE prototype absorber tested at KEK: Demonstrated need for LN2 pre-cooling Schedule to be reviewed this week

Page 8: Project Manager’s report

MICE instrumentation: Detector integration using cosmic rays: Cosmic test-stand to be set up in R12 Schedule:

Tracker: Tracker arrives in R12:30Oct06 VLPC system commissioned in R12: 02Nov07 Trigger system commissioned in R12: 09Nov07

DAQ: Update DAQ system in R12: 09Nov07

CKOV: Commission CKOV in R12: 30Oct07

To be confirmed with CKOV team TOF:

Delivered to R12: 15Nov07 Integrated into cosmic test 22Nov07

Cosmic test starts:09Nov07

Page 9: Project Manager’s report

Status: layout ‘issue C’:

Page 10: Project Manager’s report

Excellent progress, but, much to doLooking forward:

Need to plan and prepare carefully!

Page 11: Project Manager’s report

Planning & organisation!

(Headlines) Looking forward: Phase 1:

Upstream beam line: Target:

Negotiate running in January Dust issue

Install services Q1 – 3, D2:

Vacuum vessels Alignment Sevices (power, water)

Instrumentation Downsteam beam line:

D2, Q4 – 5, Q6 – 9 Services Magnet refurbishment, magnetic testing

Instrumentation: TOF0/TOF1 CKOV

Stands Tracker DAQ Spectrometer solenoid

Infrastructure: PPS MLCR Magnetic sheilding False floor, plinth Rolling platforms Air-conditioning De-mineralised water Electrical services Network services Data link and data storage

Phase II: Absorber/focus-coil module:

Absorber Focus coils Integration

RFCC module: Cavity R&D (MuCool) Cavity design finalisation Cavity fabrication Coupling coil manufacture Integration

RF power: 4*2 MW amplfiers

Missing: driver amplifier Distribution system

Vacuum: Vacuum infrastructure

Liquid-hydrogen 4 production systems

Infrastructure: Cable management Cryogenic management

Page 12: Project Manager’s report

Organisation:

Project Manager/Technical Coordinatorand MICE Operations Managers

Collaboration Board

Project-management team:

Page 13: Project Manager’s report

Acting Project Manager: K. Long Managing the work in the MICE Hall:

Weekly ‘MICE Hall Planning Meetings’: Tuesday’s 09:00 Anyone wishing to carry out work in Hall MUST attend:

Parallel working all need to be aware/cooperate One of the CDM ‘controls’

To be chaired by Hall Manager From week after next Chaired to date by KL

W. Spensley will take over after Christmas Shutdown Reviews work done Identifies work to be done:

Agrees priorities Agrees resources Identifies potential conflicts Assigns responsibilities

Project-management: arrangements:

Page 14: Project Manager’s report

MHPM o/p example:

Page 15: Project Manager’s report

Project-management: arrangements: Have initiated ‘bottom-up’ review of MICE WBS:

Assign/confirm responsibility for the various tasks Ensure schedules are planned by those responsible for

carrying them out Ensure resource requirements are discussed

To do this have initiated: Weekly ‘MICE Schedule Planning Meetings’

Thursday’s 13:30 Gathers schedule information and prepares/discusses

schedules for i/p to, consideration by Technical Board Have begun with MICE Muon Beam and MICE Hall

This week (13Sep07) MICO meeting, so begin to expand into international MICE deliverables

To be chaired by Project Manager Presently chaired by KL To be chaired after CM19 (Oct07) by RA/AN

Page 16: Project Manager’s report

Work breakdown structure: revision

MICE Level 2 Level 3 Level 4 Apsimon/Nichols2.0-MICE-Muon-Beam Long

2.0.1 Upstream beam line Long2.0.1.1-Target Booth2.0.1.2-Vacuum-vessels Kearsley2.0.1.3-Vacuum-services Hughes, Shaun2.0.1.4-Electrical-services Hughes, Martin2.0.1.5-Water-services Govans2.0.1.6-Alignment Loughry

2.0.2-Downstream-beamline Long2.0.2.1-Q35-refurbishment Spensley2.0.2.2-Linde-refrigerator Courthold2.0.2.3-PSI-solenoid Courthold2.0.2.4-Q4--9-installation Spensley

2.0.3-Beam-monitors Tilley2.0.3.1-Monitors Sellberg2.0.3.2-Installation-upstream Kearsley2.0.3.3-Installation-downstream Spensley

2.0.4-XMas2007-shutdown Hayler2.1-MICE-Hall and infrastructure Nelson

2.0.2.1-Magnetic-shielding-walls Nelson2.0.2.2-MICE-Hall-floor Nelson

2.0.2.2.1-plinth Nelson2.0.2.2.2-false-floor Nelson

2.0.2.3-Rolling-platforms Nelson2.0.2.4-Water Govans2.0.2.5-Air-conditioning Govans2.0.2.6-Power Griffiths2.0.2.7-Liquid-hydrogen-system Ivanyushenkjov2.0.2.8-MLCR Kyberd2.0.2.9-Networking Brandwood2.0.2.10-Cabling Griffiths2.0.2.11-PPS Alexander

Muon Ionisation Cooling Experiment: WBS -- Draft 02Oct07

Page 17: Project Manager’s report

Work breakdown structure: revision

Plan for this week: Review at TB Present revised version to CB

Page 18: Project Manager’s report

Critical path & risk:

Phase I: … getting it done

Phase II: WORK SMART

Page 19: Project Manager’s report

Schedule revision: Revision of schedule started:

Phase I: Since July, through MSPM and MICO meetings

Phase II: Initiated at CM18 Next step this week

Delayed because of pressure of work

Original goal: ‘Baseline’ schedule at CM19 TB agree schedule review date this week

Page 20: Project Manager’s report

Schedule revision: example:

Uses: Monitor progress Review resource assignments

For Q35s have: Parallelised preparation Increased effort

Q35 refurbishment:

Goal:

All six ready at endof Christmas shutdown

Page 21: Project Manager’s report

Christmas shutdown: Hayler

Page 22: Project Manager’s report

Technical Board:

After TB discussion → CB

Review membership: TB meeting

Review modus operandi: TB meeting

Page 23: Project Manager’s report

Significant progress since CM18: Technical:

All aspects of MICE project: Phase I Phase II

Organisational: New Project Management team in place

Even more to do: As acting Project Manager, I’ve enjoyed:

Strong support from MICE collaboration Local MICE team The Rutherford Appleton Laboratory (ASTeC, ISIS, PPD, TBU, …)

For the project to succeed: Richard and Andy must enjoy the same support

I am confident that MICE will drive the project through!

Conclusions: