Project Manager Reports
Ron Remillard (MIT) & Tom Booler (Curtin, Aurecon)
MWA Project Meeting December 5, 2011
Outline
Part 1: Ron Remillard (overview) Review Project Office and Science Leads Status of MWA groups at different Institutions Overview of Project Elements Project Element Interfaces & Recent Developments Management Challenges 2012
Part 2: Tom Booler (building 128T) Site Construction Plan Cost and Schedule Relations with CSIRO and AAL Questions & Discussion
Project Office and Science Package Leaders
Project Office Officer Official Term Project Director Steven Tingay (Curtin) Dec. 2012
Project Scientist Judd Bowman (ASU) June 2012
Systems Engineer Bob Goeke (MIT, Curtin) June 2012
Project Manager (Tom Booler (Curtin) agenda: Thurs. Board Meeting)
Deputy Project Manager for IndiaUday Shankar June 2012
Deputy Project Manager for US ?
Science Groups Leader
Science Council Stuart Wyithe (Melbourne)
EoR Science Package Jackie Hewitt (MIT)
Solar, Heliosphere, IonosphereAnthea Coster (MIT Haystack)
Transients David Kaplan (UWI-M)
Galactic & ExtragalacticLister Stavely-Smith (U. W. Au.)
Status: MWA Teams in Australia
Institution Emphasis Membersa
Curtin University Buildout; Project Office; Correlator; Archive; 11
Commissioning; Operations; EoR; Surveys
University of Melbourne RTS; Archive; EoR 4
University of Sydney Transients; GEG 4
Australian National University EoR; GEG 2
U. Western Australia GEG; M&C 2
Swinburne University GEG 1
__________________
a counting PhDs and graduate students
Status: MWA Teams Outside of Australia
Institution Emphasis Membersa Funding
RRI, India Receiver production; EoR, Transients 9 long term
Victoria U., New Zealand RTC; GEG 2 long term
USA:
MIT Kavli Rec. support; EoR; Archive; Trans. 9 current & pending
MIT Haystack BF Tests; EoR; SHI 5 current & pending
U. Washington M&C; EoR 4 current & pending
Harvard-SAO EoR; SHI; surveys 3 current
Arizona State EoR; surveys 3b current & pending
U. Wisconsin-Milwaukee Transients 1 current__________________
a counting PhDs and graduate studentsb plus 2 undergrads building a beamformer characterization/calibration instrument
Project Elements in the Project Management Plan
Project Element Leader
1. Site & InfrastructureSteven Tingay (Curtin)
2. Antenna / Beamformer TBD needs attention
3. Receivers Brian Crosse (Curtin)
4. Correlator Steve Ord (Curtin)
5. Monitor & Control SystemMiguel Morales (U Wash.)
6. RTS & RTCDaniel Mitchell (Melbourne) & need a RTC/Network manager
7. Data Archive David Pallot (Curtin)
8. Operations Dave Emrich (Curtin)
Suggested Revision to Project Elements
Project Element Leader 2012 outlook
1. Site & InfrastructureSteven Tingay (Curtin) √
2. Antenna / Beamformer TBD needs attention
3. Receivers Brian Crosse (Curtin) √
4. Correlator Steve Ord (Curtin) √
5. Monitor & Control SystemMiguel Morales (U Wash.) √
6. Real Time SystemDaniel Mitchell (Melbourne) √
7. MWA Computers & Networking TBD needs attention
8. Data Archive David Pallot (Curtin) √
9. Commissioning (Randall Wayth ?) funding? Board?
10. Operations Dave Emrich (Curtin) √
Some Project Element Interfaces
Project Element Interfaces Definition Issues
1. Site & Infrastructure
2. Antenna / Beamformer
3. Receivers
4. Correlator
5. Monitor & Control System M&C Correlator
6. Real Time System
7. RTC and Networks
8. Data Archive MRO disks Perth archive
9. Commissioning Commissioning Plan
10. Operations
Project Review of M&C Project Review of RTS MRO computer plan
Interface and Planning: Recent Developments
Will we save correlator data? yes
Where will RTS run? MRO
Second RTS version running in Perth? likely (test revisions; test algorithms; archive re-processing)
How do we transfer data from MRO to Perth fiber link + disk backup
Estimated load (100% duty cycle) on 10 GBS link, MRO to Perth
Correlator auto- and cross-correlations 16%
(256 ccors and 32640 xcors every 0.5 s; scaled, 16-bits per array)
RTS data (HEALpix files at 200 s; also use 16 bit, scaled?) 18%
Double the data rate load if 32-bit words are necessary
Backup Plan for Link Outages: disk costs ~$60K.
2 weeks (100% duty cycle) x 2 sets (transportation)
Management Challenges for 2012 (Systems Level)
Project Review of M&C; early 2012 (complete ICDs; test expansion to 128T)
Project Review of RTS; early 2012 (complete ICDs; simulations for 128T)
Complete Computer & Networking Plan; 1st quarter 2012 (RTC + others)
Complete Data Products and Archiving Plan; 1st quarter 2012
Complete Commissioning Plan; 2nd quarter 2012
(Commissioning is complex & coming fast; needs organization & automation)
Accepted Operations Plan; 1st quarter 2012 (now in draft 3; topic Tues. & Thurs.; needed for Operations proposal(s))
Additional Comments: Management Challenges for 2012
Tom will need help with system-level project management tasks, while he is working on site preparation, procurement, hardware deployment, CSIRO relations, and AAL communications during the Construction Phase in early 2012.
Science package leaders must refresh their organizationsfor: team members, data needs, science software, and involvement in Commissioning phase.