Project Management Lvl a Prt II 2009_11_edn 3

Embed Size (px)

Citation preview

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    1/139

    Project Management:

    ISCD: Level A Part II

    Bijoy S Guha,

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    2/139

    References

    Project Management: Harvey Maylor(Pearson Education, 3rd Edition)

    Project Management for Business &Technology: John M Nicholas (

    Projects: Prasanna Chandra (Tata McGrawHill, 6th Edition)

    Project Management: SMU Publication(B0915 Edition: Fall 2008)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    3/139

    Project?

    Routine, repetitive &

    ongoing throughout;

    Necessary to sustain the

    business;

    Incremental

    improvements set.

    Unique, temporary &

    goal directed;

    Create strategic

    initiatives/Products; New paradigms are put

    in place.

    Organizational Work

    ProjectsOperations

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    4/139

    Project? (contd.)

    Any non-repetitive activity;

    A low-volume high variety activity;

    a temporary endeavour undertaken to create a unique

    product or service;

    Any activity with a defined start and finish;

    a unique set of coordinated activities, with definite

    starting and finish points undertaken to meet specificobjectives within defined schedule, cost and

    performance pararmeters. (BS 6079: 2000)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    5/139

    Project? (contd.)

    Projects come in many shapes and sizes:

    By number of tasks (complexity)

    By time required to complete (duration)

    By resources (thus money) needed

    Combination of these factors

    Other Characteristics:

    Project teams are born to die!

    New paradigms become the S.O.P

    Contributes to organizations learning & growth

    Can (re)shape the Organization

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    6/139

    Project? (contd.)

    Projects come in many shapes and sizes:

    By number of tasks (complexity)

    Diversity of competencies

    Efforts of many people

    By time required to complete (duration)

    Changing nature of requirements

    Tracking

    By resources (thus money) needed Financial outlay

    Risk

    Combination of these factors

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    7/139

    Project Typology

    Compl

    exity

    Duration

    Improvement Projects

    Crisis

    Solving

    Product

    Design

    Orgn.

    Restruct.

    Mergers &

    Acqzn.

    R&D

    New to

    World

    Area of the bubbles

    indicate the quantity

    of projects.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    8/139

    Project? (contd.)

    Time

    Perform

    ance

    S/State 1

    Breakth

    rough

    Improv

    ement

    Continuous

    Improv

    ement

    S/State 2

    Stabilization

    Project for

    Development

    & Growth

    Series of mini

    projects

    Mega

    Project: Start

    of Business

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    9/139

    Project? (contd.)

    For business continuity, this activity is on-going

    and is referred to as the S-Curve of a Firms

    life e.g. Tatas Automotive Business

    SSSEngineering. &Locomotive

    Trucks &

    Construction.

    Equipment.

    Passenger cars

    TATA MOTORS

    TELCO

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    10/139

    RESOURCES (Money)

    TIME SC

    OPE

    Principally, Project Management, like in anyfield of management, is bound by:

    And Priorities always change!

    Project Management: What is it?

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    11/139

    Project Management: What is it? (contd)

    Project managers have to balance and integrate competing

    demands to implement all aspects of the project: Project Scope: specific work to be done

    Project Time: Duration with milestones

    Project Cost: tracking the budget

    Human Resources: competent team

    Procurement: adequate material & equipment

    Communication: progress vis-a-vis changes

    Quality: establishing and delivering acceptable

    Risk: analyzing and planning adequate response

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    12/139

    The required knowledge areas & Processes are:

    Project Management: What is it? (contd)

    Communicn

    Management

    Scope

    Management

    H.R.

    Management

    Time

    Management

    Procurement

    Management

    Risk

    Management

    Quality

    Management

    Cost

    Management

    Integration

    Management

    PROJECT

    MNANAGER

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    13/139

    Project management is the coordinating effortto fulfill the

    goals of the project, headed by a Project Manager; who uses

    knowledge, skills, tools and methodologies to:

    Identify the goals, objectives, requirements and limitations of theproject - Specification

    Coordinate the needs (and expectations) of the project

    stakeholders viz. team, customer, society/ sponsor & supplier

    Buy-in

    Plan and deliver the identified objectives & goals - Execution

    Close the project when completed - Closure

    Capture (for dissemination) the knowledge accrued - Continuity

    Project Management: What is it? (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    14/139

    Mindset: Timeliness: how to reduce and then deliver on time

    Responsiveness: to ever changing circumstances

    Information Sharing: for involvement and clarity

    Flexibility: adapting to the situational need

    Structured Planning: towards efficient resource use & priority

    Ability to work with ill-defined organization & support structures

    Coping with uncertainty: no two projects are exactly the same

    Analytical yet speedy: no analysis paralysis

    Good communication, team-building & networking skills

    Project Manager: Characteristics

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    15/139

    Project Management: development

    Projects start after an authoritative stakeholderdecides toimplement a project, involving: Fair amount ofCapital outlay A commitment ofHuman Resourcesfor (extended) period of time

    Irreversibilityand attendant risk Andprioritization/choice from a wide to do list

    Possible Projects have to be analyzed and feasibilityassessed before start.

    Funds have to found for Feasible Projects, which includes aRisk Analysis

    Finally Projects have to be implemented and, Closed!

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    16/139

    Project Management: development (contd)Phases of a Project

    Design it Do it Close/Develop itDefine it

    Day to day

    controlHow, who

    & When

    What

    & why

    Continuous

    Improvement

    Time

    Activity/Cum.C

    ost

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    17/139

    Project Management: Conceptn (contd)

    Phases of a Project

    Time

    Man-hrs

    FeasibilityPreparation Implementation

    Closure

    Time

    F

    P

    IC

    F

    P

    I

    C

    Save

    Concurrent

    Model

    Sequential or

    stage-gate Model

    X X

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    18/139

    Project Management: Conceptn (contd)

    Project Analysis - Feasibility

    IdeationInitial

    Screen

    Reject/

    shelveNo Go

    Investigate

    Go Market Study

    Tech/Ecol. Study

    Fin./Eco Study OK?

    Terminate

    No

    Project Funding

    Plan

    Yes

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    19/139

    An Idea is not an outcome oflogical deduction alone: There are no defined methods or theories to guide the task;

    it is often an outcome of a triggering process;

    They fall-out from either significant technologicalbreakthroughs; or from a rearrangement of the path to an

    existing end (reengineering).

    These can be stimulated by: (Periodic) Strategic Planning exercise, stimulating some

    out-of-box thinking and redefined operational objectives;

    Creating a quasi-crises situation: if it aint broken, break it!

    Creating a culture of innovation and learning from failures;

    Project Management: Conceptn (contd)

    Project Analysis - Ideation

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    20/139

    These lead to identifying the Key Success Factors from:

    Benchmarking key processes of existing top-class/world-class

    industries; Examining sourcing, import/export and input/output practices;

    Environmental Scanning & wandering around Suggestions/analyses of research, financial & development

    agencies;

    Generating a host of project ideaswhich require initial screening beforecommitting time and effort for further investigation:

    Compatibility with promoter/shareholder viewpoint; Consistency with laws of the land and legislative priorities; Reasonableness of cost, risks and adequacy of markets; Checking out barriers to entry

    Project Management: Conceptn (contd)

    Project Analysis - Ideation

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    21/139

    Project Management: Conceptn (contd)

    Project Analysis - Facets

    Market AnalysisMarket Potential/Size

    Market Share

    Techn. AnalysisTechnical viability

    Sensiblealternatives

    Financial AnalysisRisk

    Return

    Economic AnalysisBenefits and costs

    Knock-on impacts

    Ecology AnalysisEnvironmental impact

    Restoration/containment

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    22/139

    The starting point is the impact of the project on the top-line of the business: What is the likely aggregate demand for the product or service?

    What share of market will the product/service influence?

    The analysis takes place in the flow:

    Situational analysis& specification of

    Objectives.

    Collection ofSecondary data

    Conduct ofMarket survey

    CharacterizationOf Market

    DemandForecast

    MarketingPlan

    Project Management: Conceptn (contd)

    Project Analysis: Market & Demand

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    23/139

    Analysis of technical, engineering & ecological aspects is

    done continuously when a project is being evaluated &

    formulated: To ensure technical feasibility especially in respect of inputs,

    To arrive at the best solution balancing technology/location/scale,

    The examination is based on common sense and economic logic,

    technology & ecology being in the expert domain.

    The broad areas which require to be examined are:

    Inputs: involves ascertaining and lining-up choices; Plant/Facility: requires assessment of internal factors &

    constraints;

    Project Execution: detailing the project roll-out for road-blocks,

    Project Management: Conceptn (contd)

    Project Analysis: Technical

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    24/139

    Product / Service

    Demand

    Size

    Location TechnologyProduct Cost

    Investment

    ProfitabilitySelling Price

    Project Management: Conceptn (contd)

    Project Analysis: inter-linkages

    Ecology

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    25/139

    SalesPlan

    Prodn.Cost

    Deprn.

    Interest

    Project

    Cost & Time

    Prodn.Plan

    W/CapPlan

    InvestmPlan

    W/Cap

    Advance

    Means of

    Financing

    Interest & loanrepayment

    Cash flowEstimate ofOprn. Result

    Taxes

    Project Management: Conceptn (contd)

    Project Analysis - Financial

    B/Shee

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    26/139

    Cost of Project & Means of Finance

    Cost of ProjectLand, site and building related costs;

    Plant, machinery & equipment related costsHardware

    Technical assistance & training fees

    Start-up / pre-op. expenses Knowledge

    Preliminary Capital issue expenses

    Margin money (working Capital)

    Initial cash losses Financing

    Project Management: Conceptn (contd)

    Project Analysis - Financial

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    27/139

    Cost ofProject & Means of Finance(contd)

    Means of Finance

    Deferred CreditIncentives

    Other sources

    Share CapitalDebenture Capital

    Term Loans

    High cost, control andlower fin. risk

    Lower cost, higher fin. ri

    Bridging loans

    Least cost

    Project Management: Conceptn (contd)

    Project Analysis - Financial

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    28/139

    Project Management: Concepts (contd)

    Feasibility Financial evaluation

    Three Basic Questions: Can we produce the Goods and/or Services? Can we sell them?

    Can we earn a satisfactory Return on Investment made in theProject? OR

    Do we have a favorable Cost Benefit Ratio?

    Financial appraisal gives answers to the last question,factoring: Time value of Money Pay back and Profitability Risk analysis & mitigation

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    29/139

    Project Management: Concepts (contd)

    Time value of money

    A rupee today is more valuable than the same

    rupee a year hence!

    Inflation reduces the purchasing power

    However, money invested productively yields returns

    and increases the value

    People prefercurrentconsumption to future spend.

    In projects, cash flows (i.e. income and

    spending) are at different points of time. For a

    fair analysis, they have to be brought to the

    same (current) point of time

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    30/139

    Project Management: Conceptn (contd)

    Time value of money

    To normalize cash flows we need to reduce themto a common base, usually the Present Value.

    Algebraically:

    PV = Present Value; FV = Future value;

    Ct = Cash flow at the end of the year t

    r = Interest rate

    g = growth rate in cash flows

    n = number of periods over which cash flows

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    31/139

    Project Management: Conceptn (contd)

    Time value of money

    Formula (single sum):

    FVn = PV(1+r)n

    (1+r)n

    is the Future value interest factor The process of investing money as well as

    reinvesting the interest earned is calledCompounding.

    Depositing Rs.1000 in the bank today @10% interest will in 8 years grow to:

    1000(1.10)8 = 1000(2.144) = 2144

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    32/139

    Project Management: Conceptn (contd)

    Time value of money

    The Rule of 72:

    Investors commonly ask when will mymoney

    double?

    A rule of thumb says divide 72 by the interest

    rateE.g. if the interest rate is 12%, the doubling period is

    72/12 = 6 years

    Using the formula: 1000(1.12)6

    = 1000(1.974) i.e.1000 becomes 1974 in 6 years.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    33/139

    Project Management: Conceptn (contd)

    Time value of money

    Returns come in the future. Thus Rs.1000/-

    earned 3 years from now willposses less value

    today. We need to know thepresent value of

    future earnings.

    The process is simply the reverse/inverse of

    compounding and is called Discounting.

    Formula (single sum):

    FVn = PV(1+r)n

    thus, PV = FVn[1/(1+r)n]

    The factor1/(1+r)nis called discounting factor.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    34/139

    Project Management: Conceptn (contd)

    Time value of money

    In financial analysis, more often cash

    flow streams are uneven i.e. not a single

    sum; they vary year to year

    The formula for Present Value foruneven (or even) cash flows is:

    PVn= A

    1/(1+r) + A

    2/(1+r)2 + . A

    n/(1+r)n

    n= At/(1+r)t, where

    t=1A

    t= Cash flow at the end of t year, n = duration of flow

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    35/139

    Project Management: The process

    Investment Criteria

    There are many (over 30 !) criteria which

    can be broadly typed into: Discounting Criteria, mainly:

    Net Present Value

    Benefit Cost Ratio

    Internal Rate of Return

    Non-discounting Criteria, mainly:Payback Period

    Accounting Rate of Return

    Urgency

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    36/139

    Project Management: The Process (contd)

    Investment Criteria Non-discounting

    Urgency: Simply put, projects which have higher

    urgency get priority. Issue: what is the basis for urgency?

    Therefore, used only in crisis situations. Pay Back: Is the length of time to recover the initial

    outlay. Shorter the pay back, more attractive the

    project.

    Issue: does not reflect the true worth, but is a rough and ready reckoner to make quick

    evaluation and benchmarking, for initial assessment

    and for small-value projects.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    37/139

    Payback- the simplest/basic method

    comprises:

    Step1: the income that will be generated withthe initial investment;

    Step2: the amount of time that the revenue will

    need to be generated to cancel out the

    investment. E.g. If Rs. 1 cr. is generated/yr on an initial

    investment of Rs. 10 cr., then the payback is 10

    yrs.

    Project Management: The Process (contd)

    Investment Criteria Payback

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    38/139

    Many companies set this as a hurdle for projects, without going in for detailed

    computations e.g.

    Manufacturing equipment/hardware (Western): 4~5 years;

    Manufacturing equipment/hardware (Japanese): ~10 years;

    Computer/IT facilities: 3 years;

    McDonalds franchise: 12 years.

    While simple, it ignores:

    The life-cycle cost (e.g. disposal or decommissioning) of an item beyond the pay-

    back period a fact which could alter the viability considerably;

    The time-value of money.

    Project Management: The Process (contd)

    Investment Criteria Payback

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    39/139

    Project Management: The Process (contd)

    Investment Criteria Discounting

    Net Present Value:

    represents the sum of all

    the cash flows,

    discountedto the present

    value. If the sum is +ve,

    then the project is

    yielding a surplus on

    date. Thus viable/

    feasible. E.g. given the cash flow

    alongside and a

    discounting of 10%;

    Year Cash Flow

    0 -1,000,000

    1 & 2 200,000

    3 & 4 300,000

    5 350,000

    Applying NPV formula:

    NPV = 200000/(1.10)1

    + 200000/(1.10)2 + 300000/(1.10)3 + ..-1,000,000

    = Rs.5273; i.e. a surplus

    n

    NPV = At/(1+r)t

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    40/139

    @ 12%discountin

    g

    Suppose you were to start a fast-food joint for 3

    years; your estimates are:

    Figs: Rs. lakhs Now Year 1 Year 2 Year 3

    Start-up Costs 50

    Running Costs 30 45 45

    Revenues 40 50 60

    Sale of Joint 70

    NPV positive so worth pursuing

    NPV = NPVyr1 + NPVyr2 + NPVyr3

    = -50 + (-30 +40)/(1+0.12)1 + (-45 +50)/(1=0.12)2 + (-45 +60 +70)/(1+0.12)3

    = 23.415

    Project Management: The Process (contd)

    Investment Criteria NPV (DCF)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    41/139

    Internal Rate of Return (I.R.R): is the

    discounting rate at which the net present

    value of the project is 0. It indicates the

    minimum returns that the project has togenerate annually for its duration. E.g.:

    Yr 0 1 2 3 4

    C/F -100 30 30 40 45

    The rate which returns 100is :

    100 = 30/(1+r) + 30/(1+r)2 + ..

    i.e. ris between 15 & 16%.

    Thus accept project if the rate of return is more than thediscounting rate.

    Project Management: The Process (contd)

    Investment Criteria Discounting

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    42/139

    Alternative2: plot the calculated NPV (2 to 4 iterations)

    on a graph (x-axis: discount rate, y-axis: NPV) and the

    determine the IRR.

    E.g.:

    NPV Discount Rate10

    20

    12.85

    - 6.90

    Project Management: The Process (contd)

    Investment Criteria Discounting (IRR)

    IRR = 15.6%

    Yr 0 1 2 3 4

    C/F -100 30 30 40 45

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    43/139

    The significance of these decision support

    tools are: Payback:

    The most commonly used method for

    evaluating investments of a small size and

    with a short time horizon.

    For investments of a larger size, the average

    rate of return is sometimes used as theprimary criterion, with payback as a

    supplementary criterion.

    Project Management: The Process (contd)

    Investment Criteria Decision Support tools

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    44/139

    DCF:Allows for a quantitative evaluation of alternate uses of

    funds vis--vis a safer option e.g. deposit in a bank; Is a measure of the opportunity cost of money;Offers a very clear-cut, standardized decision criterion,

    e.g. invest if NPV > 0. IRR:

    Represents the return earned on initial investment

    made in a project OR the rate of return on the un-recovered investment balance in the project. It is easy to understand and is easily benchmark-able

    against other financial, economic rates. (NPVs are notso readily comparable to outside world)

    Project Management: The Process (contd)

    Investment Criteria Decision Support tools

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    45/139

    Project Management: Conceptn (contd)

    Investment Criteria Observations

    NPV is expressed in absolute

    terms and does not indicate

    the scale of a Project;

    NPV favors longer term

    projects

    The IRR rule does not

    differentiate lending &

    borrowing; e.g.

    IRR is clearer than NPV & isless sensitive to discounting

    ratio.

    NPV Invest. Ratio

    X +5000 50000 10%

    Y +2500 10000 25%

    C/Fl.

    Yr 1

    C/Fl.

    Yr 2

    IRR NPV@10%

    A -4000 +6000 50% 145

    B +4000 -7000 75% -236

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    46/139

    Project Management: The Process (contd)

    Financial evaluation Discounting Criteria

    Economic analysis: is the methodology to

    evaluate projects from the Societal view point,

    primarily Public investments.

    Social cost/benefits differ from monetary measures

    due to Societal considerations and market

    imperfections;

    UN has formulated an process to assess this under

    the UNIDO Guide, in which societal and market

    considerations have been integrated to assessdesirability of a Project. (Please read handout on

    Bridge Project & River Valley Project as an

    example for the approach)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    47/139

    Project Management: The Process (contd)

    Feasibility -Risk

    Risk analysis is one of the most slipperyaspect of projectevaluation there is no one unique method or dimension: Technique 1 stand-alone risk of a project

    Technique 2 risk of a project in the context of the firm and/or themarket.

    Risk source is event specific and needs to be assessed at feasibilityfor threats to financials as well as impediments for execution(entailing unforeseen fund flow)

    For management of risk, measurement is essential

    Risk is two sided: Alpha Risk: accepting the wrong

    Beta Risk: rejecting the right

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    48/139

    Project Management: The Process (contd)

    Event linked risk measures (Time & Cost)

    Likelihood: the expected probability of an untoward

    occurrence (e.g. earthquake) In real life, this is a geophysical phenomenon and can be

    linked to a region and a value assigned say 0.2

    The expected impacton the project: in case of NPV calculations, the financial impact

    in case of untoward occurrence in implementation, the time

    & cost impact (loss and recovery)

    The product likelihood x impact definesconsequence, thus the ranking of risks.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    49/139

    Project Management: The Process (contd)

    Risk measures of risk (Prioritization)

    HighPriority

    HighPriority

    HighPriority

    MediumPriority

    MediumPriority

    MediumPriority

    Expected Impact on Project

    LowPriority

    LowPriority

    LowPriority

    LowMediumHigh

    Me

    diu

    m

    High

    Low

    Probabili t

    yofOccurrenc

    e

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    50/139

    Project Management: The Process (contd)

    Risk Management

    Project Risk

    Management

    Identification

    External SourcesKey risk symptoms

    Time, Cost & Quality Analysis

    Assumptions

    Quantification

    Likelihood

    Effect/ImpactHideability

    Response Control

    No Action; Ignore

    Contingency & Reserve

    Corrective Actions

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    51/139

    Project Management: The Process (contd)

    FinancialRisk

    Risk Analysis

    Stand Alone Contextual

    SSS Analyses

    Break Even

    Decision Tree

    Corporate Risk

    Market Risk

    Easier to

    measure

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    52/139

    Project Management: The Process (contd)

    FinancialRisk

    Risk Analysis

    Stand Alone Contextual

    SSS Analyses

    Break Even

    Decision Tree

    Corporate Risk

    Market Risk

    Easier to

    measure

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    53/139

    Project Management: The Process (contd)

    Risk to financials sources

    The several sources of risk with respect to projected

    earnings and cash-flows are:

    Project-specific risk projections may be erroneous due to

    Competitive risk affected by unanticipated actions of

    competition or new competition

    Industry-specific risk Unforeseen technologies/ products,

    regulatory changes etc.

    Market risk Unexpected changes in macroeconomic factors

    International risk Extraordinary developments on the

    exchangerate and/or Political climate

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    54/139

    #1 Sensitivity:

    Financial statements are worked out with each

    line changed for optimistic/realistic/

    pessimistic values one at a time, the other

    lines being held at realistic values.

    Investigating the situation whatif a change in

    assumption/projection were to happen

    Indicates the strength of relationship between the

    outcome/result and a given parameter e.g. changein profit if material-costs go up to pessimistic

    levels.

    Project Management: The Process (contd)

    Risk the SSS Analyses of Financials

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    55/139

    Project Management: The Process (contd)

    Risk the SSS Analyses

    12.793

    /

    2.05 11.497

    -

    6.233

    x 5.264

    12.9% 14.8%

    12.793

    -

    1.103 1.219 5.854

    + +

    809 925 11.690 11.573

    %

    P&L 6.30% 7.20% -294 5.854 5.728

    12.793

    Sales

    Purchased

    materials

    Operating

    Income

    Financial

    Income

    Income

    before Tax

    Operating

    expenses

    Other Costs

    Capital

    Turnover

    RONA

    A 'Du-pont" style Report

    Margin

    Sales

    Total Assets

    Interest free

    Liabilities

    Net Assets

    Sales

    BalanceSheet

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    56/139

    #2 Scenario:

    Project Management: The Process (contd)

    Risk the SSS Analyses of Financials

    Variables are interrelated, thus painting different, plausible

    scenarios involving different (but consistent) sets of

    variables is helpful. Usually, the factor(s) chosen represent

    the largest source of uncertainty (e.g. market growth rate),around which the scenarios are built.

    The Best/Worst Case Analysis: where scenarios involving

    best/normal/ worst sets of variables are worked out, e.g.

    BEST: high demand, high selling prices, low operating costsetc.

    WORST: low demand, low selling prices, high operating

    costs etc.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    57/139

    #3 Simulation:

    Project Management: The Process (contd)

    Risk the SSS Analyses of Financials

    Sensitivity analysis indicates what-if nature

    correlations between dependant and various input

    factors, denoting strength of relationships;

    A decision maker would want more certainty i.e. the

    likelihood of such occurrences. Simulation techniques help in developing probability

    profiles of events by combining (randomly) values of

    variables which have a bearing on chosen criteria. It is a powerful technique which permits use of great deal of

    information and a highly efficient medium of communication; It does not replace judgement, contrarily it requires more

    application of judgement;

    A useful technique in the absence of good experience

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    58/139

    Project Management: The Process(contd)

    Risk measures of risk (NPV)

    Risk is measured from:

    Probability of occurrence (Likelihood):

    the variability associated with obtaining

    different results (e.g. NPV)

    A measure of the risk is the range i.e.

    difference between the highest/lowest value i.e.

    900 200 = 700

    NPV Prob.

    200

    600

    900

    0.3

    0.5

    0.2

    The weighted NPV works out

    to: 3E(NPV) = pi NPVi

    i=1

    = 0.3x200 + 0.5x600 + 0.2x900

    = 540

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    59/139

    Project Management: The Process (contd)

    Risk measures of risk (NPV)

    The higher the spread the more the variability and

    risk

    Standard Deviation ( ) of the NPV distribution

    quantifies this:

    = {0.3(200-540)2+ {0.5(600-540)2+ {0.2(900-540)2}= 250

    We can now define a coefficient of variation in which

    we relate the to weighted net present value: CV = /weighted value ; = 250/540 = 0.46

    The higher the CV, the higher the risk ranking

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    60/139

    Lending institutions/financial managers wantto know how much should be sold/producedat a minimum to ensure the project does notlose money?

    Viewpoint 1: Accounting i.e. a value thatensures return of principal without availing ofany opportunity (via the time-value principle).Projects breaking even this way may have ve NPV

    Viewpoint 2: Financial - the focus is on valuecreation i.e. the level at which the project willyield at least 0 NPV.

    Project Management: The Process (contd)

    Risk the Break Even

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    61/139

    Interest

    Factor

    12%,10yrs

    PbT=0.33Sls 3M

    Tax = 0.33 PbTPaT = .667 PbT

    Sls 9M

    V.C. 6M

    F.C. 1M

    Depr 2M

    PbT 0M

    Project Management: The Process (contd)

    Risk the Break Even

    P & L Forecast for a new Plant

    Head Yr0 Yr1-10

    Investment 20,000

    Sales 18,000

    Var.Cost 12,000

    Fixed Cost 1,000

    Deprn. 2,000

    Pre-tax Profit 3,000

    Taxes(@ 33.3%) 1,000

    P.a.T 2,000

    Cflow (Oprn) 4,000

    Net Cflow 20,000 4,000( Figs. Rs 000)

    Accounting BEven:

    Sales = (Fixed Costs + Deprn.)/

    Contribution Margin ratio

    = (1,000+2,000)/0.333

    = Rs. 9 M

    Financial BEven(12% rate):

    Cash Flow = Deprn.+ P.a.T

    =0.667(0.333x Sales Rs.3M)+ Rs.2M

    = 0.222 x Sales

    PV = 0.222 x Sales ( Discounted)= 0.222 x Sales x 5.650

    i.e.20,000 = 0.222 x Sales x5.650

    = Rs. 15.94 M

    Contribution

    margin %

    Sales =

    33%

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    62/139

    i.e. Tot. accruals/

    Tot. Debt burden

    In addition to Break Even, financial institutionsalso assess: Break Even Point for Capacity Evaluation (BEPCU):

    Projects reach capacity outputs over time. Only on

    reaching this point can stable operations start. The Fixed Cost/Contribution ratio is multiplied by

    %age capacity utilization to derive BEPCU

    Debt Service Coverage Ratio (DSCR):Borrowers ability to service a debt is important!

    DSCR = (P.a.T + Deprn & amorzn + Interests +

    Lease rentals)/{Repayment & Interest of term debt

    + Lease rentals} all values cumulatedover theperiod under consideration.

    Project Management: The Process (contd)

    Risk the Break Even

    All ratios

    are furthersubjected

    to

    Sensitivity

    Analysis

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    63/139

    A tool developed and used for aiding sequential

    decision making in face of risk involved at every

    stage e.g. oil-field development.

    Identifying the problem and alternatives; Delineating the decision tree: diagrammatic

    representation of the nature of decisions situations;

    Specifying the probabilities, impacts and outcomes;

    Evaluating the decision alternatives.Study handout on the example of a decision tree

    analysis Spectrum with their electric moped.

    Project Management: The Process (contd)

    Risk the Decision Tree Analysis

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    64/139

    Organizing for Projects

    Projects are carried out by Institutions themselves

    (e.g. Aircraft Coys) Or outsourced to Pure Project

    Organizations (e.g. MMRDA).

    Pure Project Organizations have a core, leanmanagement team and engage man-power from a

    Contractor Pool allowing forflexibility in both

    nature and quantum of Human Resources.

    Institutions borrow personnel from internal expertgroups to form Project Teams (who in turn might

    outsource specifics) to execute Projects.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    65/139

    Organizing for Projects(contd)

    Pure Project e.g.

    Construction

    C.E.O

    Housing PortsRoads

    PM 1

    PM 2

    PM 1

    PM 2

    PM 1

    Contractor Pool

    Project Team e.g. Auto-

    mobile

    Director

    Design Markt.Manf.

    Mgr 1

    Mgr 2

    Mgr 1

    Mgr 2

    Mgr 1

    Mgr 2

    PM

    Rafting or Matrix Structure

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    66/139

    Planning Work in Projects

    Elements

    Objectives

    Activities (What ?)

    Schedule (When ?)

    Budget ( How much ?)

    Organization (Who ?)Work methods (Procedure, Standards )

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    67/139

    Planning Work in Projects (contd)

    Project Planning & Control System

    Objective

    Budgets

    Reports(Time, cost,Performance)

    ManagementDecision making

    Detailing:

    (SoW, WBS)

    Scheduling:

    PERT, CPMetc.

    Tracking:Time/Cost/Performance

    Feedback

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    68/139

    Planning Work in Projects (contd)

    Major Project Plan Documents 1. Statement of Work/Scope of Work (SoW)

    A general description of the work to be performed- called deliverables

    work excluded

    Overall schedule of project

    Construction of House

    Construction, painting, internal electrical wiring, provision of electrical points,plumbing as per the design of the Architect and the work specifications

    Electrical fittings and Sanitary fittings to be supplied by the owner(exemption)

    Completion date- 6th June 2004

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    69/139

    Planning Work in Projects (contd)

    2.Work Breakdown Structure (WBS) The breaking of overall project into sub elements Could be further broken down Enables preparation of individual work schedules, their inter

    relation ships and precedence Enables estimation of Resource requirements Enables realistic Costing

    It is the basis for costing and scheduling & is monitored in the

    project control process to compute variance with actual costsand schedules.

    Identifies the Functional divisions/ Managers, Contractors to be

    involved for apportioning responsibilities

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    70/139

    Planning Work in Projects (contd)

    Example of WBS - Construction of a building

    1. Excavation

    2. Foundation

    3. Frame

    4. Walls

    5. Ceilings

    6. Electrical wiring

    7. Plumbing

    8. Painting

    Each of these will have a detailed Specification

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    71/139

    Planning Work in Projects (contd)

    3. Specifications

    The requirements to be met

    Could be compatibility with established standards ora new specified requirement

    Helps in realistic costing

    Avoids ambiguity and consequent cost and time

    over runs & legal issues

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    72/139

    Planning Work in Projects (contd)

    A typical User (Customer) Contractor Exchange (in

    absence of clear specifications)

    Contractor: The lighting for the office is finished. As we

    agreed, I wired 20 ceiling lights

    Customer : But you said there would be enough lights tomake the room bright. This room seems kind of dark

    Contractor : For a room this size, 15 lights are standard.

    As we agreed, I put in 20 just to be sureCustomer: Yes, but you said 20 would make the room

    bright and they dont. You will have to put in more lights

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    73/139

    Planning Work in Projects (contd) Constructing process maps is a method

    currently favoured by Project Managers,

    e.g. 4-fields mapping . It captures Projectphases, Tasks in the phases, Responsibilitymatrix for Tasks & the Standards for tasks

    #3 Task flow

    #1 Team Members# 4 Standards

    Listed for eachtask**********

    *****

    #2 Phases (WBS)

    With start/endCriteria. A

    B

    C

    (ResponsibilityMatrix)

    Eachphase hasmanytasks

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    74/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    The Project Planning process stages are: Identify the constituent activities; Determine their logical sequence; Prepare estimates of time & resources;

    Present the plan in a readily readable format.

    The general approach to planning involves starting with arough overview and then conducting revisions of thisthrough an iterative process i.e. going through the cycle

    several times to test the effect of the revisions made on theoutcomes;

    The objective is to make major revisions early in theplanning cycle and then make minor refinements in the plan.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    75/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    The development ofdetailed time plans have varyingcomplexity, in line with the nature of the project, howeverthe significant area of commonality is: A construction of comprehensive but understandable picture

    of the project activities; Communication with others.

    The preference forgraphical techniques hinges on theability of people to understand what is going on i.e.visibility, illustrating inter-relations between activities

    and time. The 3 most commonly used charts are: The Gantt Chart Program Evaluation & Review Technique: PERT charts Critical Path Method: CPM charts.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    76/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Gantt (Bar) Charts: Simple to construct and understandSimple to construct and understand Can track progress of individual Activity easilyCan track progress of individual Activity easily Good for small projects; e.gGood for small projects; e.g Boil Water for TeaBoil Water for Tea

    Activities:1. Fill kettle. 02mins.2. Put on the stove..01min

    3. Light the stove. 01min.4. Wait for boiling . 05mins.5. Take off kettle . 01min.6. Put off stove . 01min.

    Actualactivity

    Plannedactivity

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    77/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Network Scheduling

    Developed to address the drawbacks of Ganttchart esp. inter relationships/ inter dependenciesbetween Activities

    Suited for complex projects involving manyactivities.

    PERT developed for US Navy to manage complexPolaris Missile Program.

    CPM developed in 1957 in an industrial setting (for Plantconstruction project for DuPont), and gives relatively

    more importance to project cost.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    78/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Concepts in Network DiagramsConcepts in Network DiagramsActivity-on-Arrow (AoA)Activity-on-Arrow (AoA)

    Activity Symbol of Activity Time required

    Fill kettle A 01 min.

    Event- Beginning or End of an Activity

    Beginning of fillingEnd of filling

    A

    01min.1 2

    IMPORTANT RULE:

    There can be ONLY ONE Arrow (Activity) between two events!

    Pl i W k i P j ( d)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    79/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Concurrent Activities Activities that can be carried out concurrently / simultaneously

    Not interdependent

    1

    2

    3B

    A A = Fill kettle

    B = Light stove

    C

    2D

    3 4

    5

    C Preceding Activity

    D Succeeding Activity

    Activity Symbol of Activity Time required

    Observing for water to boil C 5 mins.

    Take kettle off stove D 1 min

    1

    Succeeding/Preceding Activities

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    80/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    1 2

    3

    4

    AB

    C

    Example of two Activities with a Common immediate Predecessor

    Dummy Activity- An imaginary Activity which does not consume resources

    but included in the Network diagram to maintain network logic and

    understand inter dependency of Activities

    2 4

    A: Fill Kettle

    B: Set up tea cups

    C: Wait for water to boil

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    81/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Activities:

    Description Predecessor

    A. Fill kettle. 02mins. Start

    B. Place on the stove..01min A

    C. Light the stove. 01min. StartD. Observe boiling . 05mins. C

    E. Take off kettle . 01min D

    F. Put off stove . 01min. E

    e.g. A-o-A chart for Boiling of water for tea:

    A B

    C

    D E F

    0 1

    2

    3 4 5 6

    Note: If we were to include set up tea cups as an activity and we would do it while

    waiting for water to boil; activity D would then become a dummy & activity set uptea cu s would be a real activit .

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    82/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    The Critical Path

    The major use of networks is for determining: how longthe project will take & when each activity should be scheduled.

    The project duration is determined by finding the longestpath through the network: A path is any route comprised of one or more arrows

    (activities) connected in sequence; The longest path from the origin node to the terminal node is

    called the Critical Path; This gives the expected duration of the project.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    83/139

    The Critical Path: an Example

    DA

    St 1

    B

    C

    2 3

    E

    F

    En

    4

    A Shopping (H&W) - 1

    B Prepare to cook (W) A

    C Cooking (W) B 2

    D Bathe & dress (W) C 1E Tidy house (H) A 1

    F Bathe & dress (H) E

    Project: Dinner party (H & W)

    There are TWO paths: #1 St 1 -2 3 En ( i.e. A-B-C-D) &

    #2 St 1 4 En (i.e. A-E-F)

    Path # 1 takes: 1 + + 2 + 1 = 4 H

    Path # 2 takes: 1 + 1 + = 3 H

    The Project requires 4 H and path #1 determines the duration: thus Critical

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    84/139

    Activities not on the critical path can be delayed

    without delaying the project however, by how

    much?

    The logic is to determine the latest allowable time that the activitycan be completed without delaying the completion of the project, i.e.

    the start can be late (or early);

    The time difference between early start and late start is called

    slack orfloat;

    The total slack time is the maximum delay that can occur for non-critical activities. Once this slack is used up, non-critical activities

    become critical and any further delays will extend the project

    completion.

    The Critical Path

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    85/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Estimating Activity Duration( PERT)Estimating Activity Duration( PERT) The target Project completion date is dependent on the

    proper estimation of duration of all Activities involved

    Estimation of Activity duration is not always a straightforward process because of an element of uncertainty

    PERT addresses the uncertainty in the duration by using

    three time estimates

    Optimistic

    Most likely

    Pessimistic

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    86/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Estimating Activity DurationEstimating Activity Duration contdcontd

    Optimistic Time estimate a- Every thing goes accordingto plan with minimum difficulties

    Pessimistic time estimate b Maximum possible time forcompletion considering all unfavourable conditions

    Most likely Time estimate m - Lies between Optimisticand Pessimistic time estimates. Time required to

    complete in normal conditions

    Estimates are obtained from, experience, people &experts knowledgeable about the difficulties involved

    Pl i W k i P j t ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    87/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Expected Time (tExpected Time (tee) for completion of activity) for completion of activity

    PERT assumes that a, b are equally like to occur, whereas m isfour times more likely to occur

    Thus, te = (a+4m+b)/6

    Variance, v = {(b-a)/6}2 is the measure of variability inthe activity completion time

    Standard Deviation, = v1/2

    The larger the difference between a & b, the larger thevariance and uncertainty with te; i.e the higher thelikelihood of completing earlier or later than te.

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    88/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Probability of Project CompletionProbability of Project Completion The expected Project Completion Time is the SUMof the

    Expected completion time te of ALLactivities on the CriticalPath;

    The Standard Deviation, , for Project Completion Time isthe Square root of the sums of Variances of ALLactivitiesalong the Critical Path:

    = ( v1 + v2 + vn)1/2

    The probability of completing the project in the given

    completion duration, ts,is determined by the number ofstandard deviations separating them:

    z = (ts te)/ , the corresponding probability can befound from a standard z-table.

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    89/139

    Planning Work in Projects (contd)

    Designing & Tracking Tools

    Probability of Project Completion (example)Probability of Project Completion (example)

    Avity to

    (a)(a)

    tp

    (b)

    tm

    (m)

    te/v

    A 2 10 3 4/1.78

    B 3 5 4 4/0.11

    C 4 12 5 6/1.78

    D 5 7 6 6/0.11

    E 5 9 7 7/0.44

    F 4 12 5 6/1.78

    Path PathVariance

    path Z (ts = 11days)

    Prob. in11 days

    A-D 1.78+0.11 1.37 (11-10)/1.37 0.7673

    B-E 0.11+0.44 0.74 (11-11)/0.74 0.5000

    C-F 1.78+1.78 1.87 (11-12)/1.87 0.2981

    A

    B

    C

    D

    E

    F

    The probability

    of finish in lessthan 11 days =

    .7673 x.5 x.2981

    = 0.1143 i.e.

    < 12% chance

    te = (a+4m+b)/6; v = {(b-a)/6}

    2 path = ( v1 + v2 + vn)

    1/2

    z = (ts te)/ ath

    (ts = 11days)

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    90/139

    Planning Work in Projects (cont d)

    Designing & Tracking Tools

    Avity to

    (a)(a)

    tp

    (b)

    tm

    (m)

    te

    A 2 10 3 4

    B 3 5 4 4

    C 4 12 5 6

    D 5 7 6 6

    E 5 9 7 7

    F 4 12 5 6

    A

    B

    C

    D

    E

    F

    The Critical Path

    Path A-D (S-1-E): 4 + 6 = 10 days

    Path B-E (S-2-E): 4 + 7 = 11 days

    Path C-F (S-3-E): 5 + 7 = 12 days

    i.e. the project is not expected tobe completed in less than 12 days.

    The longest Path is C-F (S-3-E) and

    is critical, defining the duration.

    S E

    1

    2

    3

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    91/139

    Planning Work in Projects (cont d)

    Designing & Tracking Tools

    Developed in 1957 gives relatively more importance to

    project cost, when Project activities are more accurately

    forecast-able and a definite relationship between time and

    cost can be established for each activity.

    The CPM assumes that the estimated completion times can

    be influenced by applying resources to particular key

    activities that the time for any activity is variable,

    depending on the amount of resources applied.

    The PERT method has been criticized because it is based

    on assumptions that sometimes yield uncertain results!

    The Critical Path Method(CPM)

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    92/139

    Planning Work in Projects (cont d)

    Designing & Tracking Tools

    CPM and PERT: a comparisonCPM and PERT: a comparison

    Both employ Network diagrams & analysis of criticalpaths

    CPM, however, use a deterministic approach in timeestimates for each Activity: only one time estimate isused. Thus, in CPM there is no statistical treatment ofuncertainty.

    CPM is more Activity oriented. Hence it is possible to

    measure percentage completion of an Activity CPM more suited for well defined projects, withrelatively small uncertainties like construction or in theProcess industries

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    93/139

    Planning Work in Projects (cont d)

    Designing & Tracking Tools

    CPM and PERT: a comparisonCPM and PERT: a comparison

    CPM includes a mathematical procedure for estimatingthe trade off between Project duration and Cost

    PERT, puts greater emphasis on uncertainties and onEvents (Mile stones)

    PERT is more suitable for R&D type of projects where

    uncertainties are more and duration of an Activity cannotbe estimated accurately

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    94/139

    Planning Work in Projects (cont d)

    Analyzing Networks

    For analyzing networks, e.g. to determine CriticalPath, Slack, Probable Completion Times, etc. weneed information on: Activity & Interrelations (preceding/succeeding)

    Earliest event time & latest event time (to bedetermined)

    Conventionally, these are included in the nodesas under (for a single activity):

    Event Label

    10

    Earliest Event Time

    0

    Latest Event Time0

    205

    5

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    95/139

    Planning Work in Projects (cont d)

    Analyzing Networks: Constructing

    An example:

    A project consists of the activities, deterministic times andsequence as under:

    Activity No. Duration (days) Sequence

    A 5 with startB 3 after A finishes

    C 4 after A finishes

    D 5 after A finishes

    E 6 after B finishes

    F 7 after C finishesG 5 after D finishes

    H 8 after F,G & H finishes

    On finishing H, the project is completed.

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    96/139

    Planning Work in Projects (cont d)

    Analyzing Networks

    10 00

    20

    A

    5

    30B

    3

    50

    D

    5

    40C4

    60

    E

    6

    F7

    G

    5

    70H8

    Constructing the Network Diagram (Activity on Arrow)

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    97/139

    Planning Work in Projects (cont d)

    Analyzing Networks

    10 00

    20

    30

    40

    50

    60 70

    A

    5

    B

    3

    D

    5

    C4

    E

    6

    F7

    G

    5

    H8

    5

    8

    9

    10

    16

    Latest !

    24

    Estimation of Earliest Event Times

    Forward Pass

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    98/139

    Planning Work in Projects (cont d)

    Analyzing Networks

    10 00

    20

    30

    40

    50

    60 70

    A

    5

    B

    3

    D

    5

    C4

    E

    6

    F7

    G

    5

    H8

    5

    8

    9

    10

    16

    Latest !

    24

    Estimation of Latest Event Times

    2416

    10

    9

    11

    5

    Earliest Reverse Pass

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    99/139

    Path with no

    Slack OR Float!

    Planning Work in Projects (cont d)

    Analyzing Networks

    10 00

    20

    30

    40

    50

    60 70

    A

    5

    B

    3

    D

    5

    C4

    E

    6

    F7

    G

    5

    H8

    5

    8

    9

    10

    16

    Latest !

    24

    Determination of Critical Path

    2416

    10

    9

    11

    5

    Earliest

    Planning Work in Projects (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    100/139

    What do we do with determination of Critical

    Path?

    Provides us the key to prioritization

    Provides us the back bone for further analysis:Of Resource needs and costs

    Impact of adjusting Project Schedules

    For reporting on an agreed base

    If we can establish a Time-Cost relationship.

    Planning Work in Projects (cont d)

    Analyzing Networks

    Analyzing Networks: Time-Cost

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    101/139

    Analyzing Networks: Time-Cost

    Relationship (CPM)

    In repeat or standard projects, duration & costof activities are reasonably well established: Resource requirements per unit of work is defined Technological or other minimum time to finish a job is

    known A standard or normal time and cost can be

    established

    The Critical Path in a network are derived usingthe standard times.

    But client requirements and/or deadlinepressures may require a Project to be expedited. With additional resource inputs, time reduction is

    possible

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    102/139

    Time-Cost Relationship: CPM (contd) Definitions:

    Standard Time: the time

    usually/normally required

    to carry out an activity: Ts

    Crash Time: the

    minimum time requiredto carry out an activity.

    Reduction impossible: Tc

    Standard & Crash Costs:

    Costs for resources

    associated with theseTimes: Cs, Cc

    Time

    Cost

    TsTc

    Cc

    Cs

    Cost Slope:

    Cost per time-unit

    of activity.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    103/139

    Assumptions: Time required for an activity can be

    crashed (i.e. reduced) to its crash time to

    reduce its duration; Additional costs are incurred, proportional to

    the time reduction effected to cover the

    added resource deployment;

    To reduce the project duration, only

    activities on the critical path need to be

    crashed.

    Time-Cost Relationship: CPM (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    104/139

    Example:Activity T

    sT

    cCs C

    cSequence

    A 5 3 30 60 Start

    B 9 5 50 90 After A

    C 8 7 50 100 After A

    D 6 4 20 50 After BE 3 2 10 20 After C

    F 4 1 50 80 After D, E

    1 2

    3

    4

    5 6A

    B

    C

    D

    E

    F

    4/1

    3/2

    6/4

    8/7

    9/5

    5/3 13

    0 5

    14

    20 24

    0 5 2420

    14

    17

    Project

    Duration: 24W

    Cost:

    Rs.210m

    Time-Cost Relationship: CPM (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    105/139

    1 2

    3

    4

    5 6A

    B

    C

    D

    E

    F

    4/1

    3/2

    6/4

    8/7

    9/5

    5/3 13

    0 5

    14

    20 24

    0 5 2420

    14

    17

    If the Client wants a 1W reduction we will need to crashsome activities. Which one?

    Activity Ts Tc Cs Cc

    A 5 3 30 60

    B 9 5 50 90

    C 8 6 50 100D 6 4 20 50

    E 3 2 10 20

    F 4 1 50 80

    Project

    Duration: 24W

    Cost:

    Rs.210m

    We want to reduce the

    Project Duration. So we look

    for activities on the Critical Path:

    A, B, D or F?

    Reduction must be at theleast cost/time unit. So we look

    for activity with lowest cost slope.

    B has the least slope: we

    reduce B, adding Rs.10m to

    Cost.

    Cost Slope

    15

    10

    5015

    10

    15

    Project

    Duration: 23W

    Cost:Rs.220m

    8/5 23

    13

    19

    2319

    16

    Time-Cost Relationship: CPM (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    106/139

    1 2

    3

    4

    5 6A

    B

    C

    D

    E

    F

    4/1

    3/2

    6/4

    8/7

    8/5

    5/3

    If the Client now wants to execute at the least possible time.What can the Project manager offer?

    Activity Ts Tc Cs Cc

    A 5 3 30 60

    B 8 5 50 90

    C 8 7 50 100D 6 4 20 50

    E 3 2 10 20

    F 4 1 50 80

    Cost Slope

    15

    10

    5015

    10

    15

    We can crash B by 3 more

    weeks to 5 at an additional

    cost of Rs.30m. B then is at

    Crash. This reduces the Project

    duration to 20W.This makes the other Path i.e.

    A, C, E & F Critical too! So any further reduction will

    need to effect both Paths.

    A-B-D-F: 23 W

    A-C-E-F: 20 W

    Time-Cost Relationship: CPM (contd)

    0 5

    13

    2323

    1919

    13

    1316

    505/5

    20 W,

    250m

    10

    1620

    2016

    13

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    107/139

    1 2

    3

    4

    5 6A

    B

    C

    D

    E

    F

    4/1

    3/2

    6/4

    8/75/3

    If the Client now wants to execute at the least possible time.What can the Project manager offer?

    Activity Ts Tc Cs Cc

    A 5 3 30 60

    B 8 5 50 90

    C 8 7 50 100D 6 4 20 50

    E 3 2 10 20

    F 4 1 50 80

    Cost Slope

    15

    10

    5015

    10

    15

    5/520 W,

    250m

    We can reduce F by 3

    W, costing 45 m & A by

    2 W, costing 30m. A & F

    are crashed. C, D & E are not yet at

    crash. D can be reduced

    by 2 W, costing 30m.

    C & E can be crashed by

    1 W each, costing 60m.

    14 W,

    Rs. 415m

    Project

    Duration: 24W

    Cost:

    Rs.210m

    14

    14

    10

    10

    6

    6

    3

    3

    0

    0

    7

    7

    Time-Cost Relationship: CPM (contd)

    3/31/1

    325 m4/4

    7/7 3/3

    415

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    108/139

    To run a Project, an establishment need to be setup to coordinate the activities. Establishment is relatively independent of the Activities

    e.g. Project Office, Communication, Security etc. the

    extent may vary with nature of Projects. This set-up exists for the entire duration of the Project

    and is minimally affected by activity variance. Thus, the cost for this is fixed/structural in nature and

    has to be incurred for the duration of the project and is

    directly proportional to time. Activity is inversely proportional to time.

    Activity Cost and Establishment costs displaycontrary time-trends.

    Time-Cost Relationship: CPM (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    109/139

    Time-Cost Relationship: CPM (contd)

    Time

    Cost

    Activity

    Establishment

    Total

    The Total Cost passes is

    is U shaped i.e. passes through

    a minimum point. Thus crashing a Project is also

    determined by the establishmentcost to determine the Optimum

    or least cost.

    E.g. In our previous example if we

    were asked for the Optimum Cost,

    given the establishment cost is

    @ Rs.15m/week. We would needto factor in this cost along with the

    crashed activity costs.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    110/139

    Time-Cost Relationship: CPM (contd)

    Duration Activity Cost Estabish--ment Cost @

    Rs.15 m /w

    Total Cost

    24 W Rs.210m Rs.360m Rs.570m

    23 W Rs.220m Rs.345m Rs.555m

    20W Rs.250m Rs.300m Rs.550m

    14W Rs.415m Rs.210m Rs.625mCrashedDuration

    NormalDuration

    Optimum

    Duration

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    111/139

    Project Control

    The basic questions that need toanswered are: Is the project as a whole (and its parts) on/

    ahead /behind Schedule? Has the cost of the Project as a whole (and

    its parts) as per/ more than/ less thanbudget?

    What is the trend in performance? The Standard Variance analysis

    approach is inadequate!

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    112/139

    Project Control (contd)

    E.g. (Costs in Rs. 000)

    Activity A Activity B

    Bud. Cost in Period 50 30

    Cum. Bud. Till Date 200 75

    Actual cost in Period 55 28

    Cum. Actual till date 240 80

    Standard Budgetory Control Variances:Variance for Period: - 5 2

    Cum. Variance till Date - 40 - 5

    Is work on

    schedule?

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    113/139

    Project Control (contd)

    Definitions:

    Budgeted cost of work Scheduled (BCWS): represents

    the total cost budgets for all work packets to be

    completed and work-in-progress scheduledto be

    finished on date;

    Budgeted cost of work Performed (BCWP): represents

    the total cost budgets for all work packets to be

    completed and work-in-progress executed on date;

    Actual cost of work Performed (ACWP): represents thetotal cost budgets for all work packets to be completed

    and work-in-progress executed on date;

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    114/139

    Project Control (contd)

    With these 3 parameters, a Project may be

    monitored:

    Cost Variance = BCWP ACWP

    Cost Performance Index: BCWP/ACWP Schedule Variance = BCWP BCWS (in cost terms)

    Schedule Performance Index: BCWP/BCWS

    Estimated Cost Performance Index: BCTW/(ACWP +

    ACC)Where, BCTW = Budgeted cost of total work & ACC = Additional

    cost for completion)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    115/139

    Project Control (contd)

    E.g. Project Start 01/01; End 30/10 andreview 30/06 i.e. 24 w (figs. In Rs. L)

    BCWS: 15

    BCWP: 14

    ACWP: 16BCTW: 25(40 w)

    ACC: 12

    Cost Variance: BCWP ACWP (14 -16) = -2

    Schedule Var.: BCWP BCWS (14 15)= -1

    Time Variance: Status date Date at which BCWS=BCWP

    Est. Cost Index: {BCTW/(ACWP+ ACC)} {25/(16+12)} = 0.89

    SpentMore

    Behind

    Schedule

    Will spend more;

    funds required

    Project Control (contd)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    116/139

    Project Control (cont d)

    25

    40Weeks

    Rs. L

    BCTW

    Review Date

    24

    BCWS

    BCWP

    Time.Var.

    ACWPCost Var.

    Schedule

    Var.

    X ACWP

    + ACCOverspend

    1615

    14

    P j t C t l ( td)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    117/139

    Project Control (contd)What do these terms really indicate?

    A project manger can charge the client at pre-agreed ratesfor work completed on date of review This is BCWP andrepresents the Earned value of the project.

    The manager has paid out at actual to his supplier for thework performed This is ACWP.

    If the Actual is less then Earned, then the cost is successfullymanaged!

    However, if the progress is behind schedule then the clientpays only for completed task and the Projects earnings areless than budgeted. Schedule variance is this shortfall.

    P j t C t l (P ti P bl )

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    118/139

    Project Control (Practice Problem)

    You have employed a Contractor to install 10000computers @ 20 computers/day and @ Rs.200 /installation. Every 10 days, there is a review andpayment. At the end of the 30th Review, you find:

    #s installed 5800Bill raised Rs.62000/-

    A) Determine: Time, Cost & Schedule Variances

    B) What is the earned value for the Contractor?

    C) What do you report to your management about theCompletion of the project, assuming the Contractorhas put his best efforts and unforeseen situationshave arisen in work execution.

    P j t C t l (P ti P bl )

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    119/139

    BCWS: 30x10x20 x Rs.200= Rs.1.2 M

    BCWP: 5800 x Rs.200/- = Rs.1.16 M

    ACWP: Rs.0.62 M

    Cost Variance: Rs.1.16 Rs.0.62 = Rs. 0.54 M

    Schedule Var.: Rs.1.16 Rs.1.20 = - Rs. 0.04 M

    Time Variance: 1 weeklate (5800 should have been installed by the 29th

    review!)

    Earned Value: 5800 x Rs.200 = Rs.1.16 M, (contractor has probably

    under billed.)

    Project will be at least 1 week late and will complete the project within

    the budget, subject to bill verification.

    Project Control (Practice Problem)

    Project Control (Practice Problem)

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    120/139

    BCWS = Rs.1.2 M; BCWP = Rs.1.16 M ACWP: Rs.1.18 M Cost Variance: Rs.1.16 Rs.1.18 = - Rs. 0.02 M Schedule Var.: Rs.1.16 Rs.1.20 = - Rs. 0.04 M Time Variance: 1 weeklate (5800 should have been installed by the

    29th review!) Earned Value: 5800 x Rs.200 = Rs.1.16 M, contractor will be paid

    this amount. The Rs.0.02 M excess has to be examined. Project will be at least 1 week late and the projectwill overshootthe

    budgetif the billing is found correct. Then the installation rate worksout to (Rs.1.18M/5800) Rs. 204/- per installation

    ACC: (10000-5800) x Rs.204 = Rs.0.87 M; Projected Cost: Rs.(1.18+ 0.87) = Rs.2.05M againstBCTW: Rs.

    (10000 x Rs.200) = Rs.2.00 M

    Project Control (Practice Problem)

    If the billing is corrected to Rs.1.18 M

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    121/139

    j g

    Constraints

    In real life, there will be constraints on availability &use of resource: Not every resource required will be freely available

    influencing design of project activities

    Particularly true when multiple activity/ projectsrequires the same resource e.g. Specialist skills

    Further, crashing will need to take this constraintinto consideration

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    122/139

    Project Scheduling with Resource

    Constraints ctd.

    Resource Loading is the amount of resource necessary forthe Project:

    Changes through the duration of the execution since nature

    and type of activities vary with time

    Results in variable requirement/loading of a resource over

    time The usual resource loading pattern is:

    A slow but steady build-up

    Intense peaking at a certain point in time

    A gradual decline

    Most Projects require few resources at early and latestages and many in the middle.

    This problematic for mangers who would like to deal

    with uniform pool of workers, equipment etc.

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    123/139

    j g

    Constraints ctd.

    The process of smoothening the resourcerequirements though the Project duration is

    termed Resource Leveling: Aimed at sequencing the project activities to level the

    requirement of the constrained resource, e.g. shiftworking on bottle-neck machine.

    The results in resource requirements for the overall

    project is maintained at a fairly constant level

    Fair amount of leveling can done by juggling the

    activities around: Taking advantage of Slack

    Delaying non-critical activities.

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    124/139

    j g

    Constraints ctd.

    Consider a Maintenance Project involving overhauling amachine using a team of mechanics. The machine has

    different sub-systems which can be independently

    worked upon: Hydraulic, Electrical & Mechanical. The

    Project details are given as under:

    Activity days team strength

    A) Disassembly (1-2) 2 3

    B)Ohaul Hydraulic (2-3) 2 2

    C)Ohaul Mechanical (2-4) 4 3

    D)Ohaul Electrical (2-5) 1 1E)Assembly (4-6) 2 3

    Note: No mechanic can work more than 5 days at a stretch

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    125/139

    j g

    Constraints ctd.

    A B C D E

    Gang 1 1 1 1 1

    Man /day

    2 2 3 1 3

    Durn. 2 2 4 1 21 2A

    2

    3

    4

    5

    6

    B

    2

    4C

    D

    1

    2E

    1 2 3 4 5 6 7 8

    2 2 6 4 3 3 3 3

    1 1 3 2 1 1 1 1

    Man Reqd.

    Gang Reqd.

    Day

    Project Scheduling with Resource

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    126/139

    j g

    Constraints ctd.

    A B C D E

    Gang 1 1 1 1 1

    Man /day

    2 2 3 1 3

    Durn. 2 2 4 1 21 2A

    2

    3

    4

    5

    6

    B

    2

    4C

    D

    1

    2E

    1 2 3 4 5 6 7 8

    2 2 3 4 5 5 3 3

    1 1 1 2 2 2 1 1

    Man Reqd.

    Gang Reqd.

    Day

    1 mechanic can join from day 3, 1 more

    from day 4, 1 more from day 5 and 2

    mechanics can leave from day 7; so no

    mechanic works more than 5 days

    Improvement Projects

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    127/139

    Improvement Projects

    Many Projects which are done in companies are

    aimed at improving the current status or solving

    recurring problems, e.g.: In Operations: reduction of rejections

    In Design: reducing documentation & testing time In Finance: reducing accounts receivable & bad debts

    Though the subjects are different, most of these

    require the same approach based on utilizing in-

    company knowledge and experience Thus there is a standard process for these

    Projects, developed from the TQM philosophy.

    Improvement Projects: Information & Decision

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    128/139

    Improvement Projects: Information & Decision

    When work is delegated or distributed two dimensions, Responsibility

    and Authority are prime concerns. But there is more, especially during aset-up/change process;

    People have to "do" something to make the processes happen. Thereforeit is useful to describe what should be done by whom

    The RASCI model is a relatively straightforward tool that can be used for

    identifying roles and responsibilities R = Responsible - owns the problem / project A = to whom "R" is Accountable - who must sign off (Approve) on work

    before it is effective S = can be Supportive- can provide resources or can play a supporting

    role in implementation C = to be Consulted- has information and/or capability necessary to

    complete the work I = to be Informed - must be notified of results, but need not be

    consulted

    RASCI Chart for Road Repair

    Information & Decision contd

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    129/139

    IRIA

    I, SIRA

    RAIC

    IRCA

    RASCI Chart for Road Repair

    Resume trafficflow

    Repair road &certify

    Divert & usealternate route

    Stop access

    for period

    PublicPoliceContractorMunicipality

    Information & Decision contd

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    130/139

    Providing Information and granting Decision Rights requires to be

    supported by decision-making abilities. Decision-making is a universally important competence in business.

    Some decisions clearly have a greater impact on the businessthan others, but the underlying skill is the same;

    The difference is in the scope and depth of the process you go

    through to reach your decision In day-to-day operations, these are mostly in the domain of:

    Choice making Problem-solving/Improvements

    In these areas, the people need to be supported with simple tools/aids,

    viz. Decision support tools for making a choice quantitatively

    Problem Solving tools E.g. The 8-D methodology, Six Sigma

    Decision Making: informed choice

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    131/139

    Decision Making: informed choice

    One reason why decision-making can be so problematic is that the mostcritical decisions tend to have to be made in the least amount of time.

    People feel pressured and anxious;

    The time pressure means taking shortcuts,jumping to conclusions, or

    relying heavily on instinct to guide your way.

    The other extreme is the guy who simply can't make a decision becausehe analyses the situation to death!

    Between instinct and over-analysis is a logical and practical approach to

    decision-making that doesn't require endless investigation, but helps

    weigh up the options and impacts is needed.

    Decision-making is a skill setthat needs be learned and improved; One such approach is called the Kepner-Tregoe Matrix. It provides an

    efficient, systematic framework for gathering, organizing and evaluating

    decision making information.

    Making an informed choice

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    132/139

    Kepner-Tregoedescribes the following steps to approach

    decision analysis:

    1. Prepare a decision statement having both an action and a

    result component;

    2. Establish strategic requirements (Musts), operational objectives

    (Wants);

    3. Generate alternatives. Check if Musts are met by eachalternative;

    4. Rank objectives (Wants) and assign relative weights;

    5. Assign a relative score for each alternative on an objective-by-

    objective basis;

    6. Calculate weighted score for each alternative and identify top

    two or three;

    7.Make a final, single choice between top alternatives.

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    133/139

    ALTERNATIVES

    MUSTS

    W

    AN

    TS

    1 23

    Problem Solving

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    134/139

    The problem with problems is not that they occurin spite of our bestefforts, stuff happens. Unforeseen circumstances will always conspire

    against us to disrupt the smooth operation of our production and

    operations systems and upset our plans.

    The problem with problems is that we fail to prevent them from

    happening again. Problems do not confine themselves to organizational niches or

    structures: they encompass many parts, even the whole organization.

    Solutions, therefore, more often than not require a team effort to find a

    lasting cure:

    Engaging different skills, knowledge & aptitude Requiring divergent resources

    These reside scattered in different parts of the organization

    Problem Solving: Team approach

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    135/139

    Ford Motorsis credited with formalizing TOPS (Team Oriented Problem Solving)

    methodology:

    Involvement: cross-functional and cross-hierarchical,

    Knowledge & Information sharing,

    Camaraderie and bonding,

    Multi-dimensional, thus a holistic solution,

    Using the 8D (8Disciplines) process, renamed Global 8D (G8D):

    Step-by-step (P-D-S-A) approach: subsequent steps based on soundly established previous steps, few come-backs,

    Problems tackled in bite-size pieces

    Provisions for emergency response, escape and recurrence preventing measures

    The 8-D method of problem solving is appropriate in "cause unknown"situations and

    is not the right tool if concerns center solely on decision-making or problem

    prevention

    8 D Process

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    136/139

    D 0 - The Planning Stage:. 8-D is especially useful as it results innot just a problem-solving process, but also a standard and a

    reporting format.

    Does this problem warrant/require an 8D? If so comment why and

    proceed.

    Is an EmergencyResponseAction needed? D 1 - Establishing the Team: Establish a small group of people

    with the process/ product knowledge, allocated time, authority and

    skill in the required technical disciplines to solve the problem and

    implement corrective actions.

    Team to set Objectives & Goals: brings belief, commitment &

    realism

    8 D Process

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    137/139

    D 2 - Problem Definition:

    Provides the starting point for solving

    the problem or nonconformance issue. Need to have correct problem description (photos, verbatim

    statements, eye-witness accounts) to identify causes. 5Ws + H approach in is and is not answers e.g. Who is or is not

    affected by the problem

    Need to use terms that are understood by all. D 3 -Developing Interim ContainmentActions:

    Temporary actions to contain the problem and fix until permanentcorrection is in place - document actions in an Action Item Table.

    D 4 -Identifying & Verifying Root Cause: Analyze for Root

    Cause of the problem. Brainstorming, 5 Whys, Ishikawa Diagrams, DOE etc. document actions in an AIT.

    Identify and verify the Escape Point

    8 D Process

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    138/139

    D 5 - Identify Permanent Corrective Actions:

    solutions that address and correct the root cause. Solutions determined to be the best of all the alternatives. Document and verify the Permanent Corrective Action (PCA) in the

    AIT.

    D 6 -Implementing & Validating the PCA

    Implement and validate to ensure that corrective action does what itis supposed to do. Detect any undesirable side effects. Document this on the AIT. Return to root cause analysis, if necessary

    D 7 - Preventing Recurrence: determine what improvements in

    systems and processes would prevent problem from recurring. Ensure that corrective action remains in place and successful Address similar systems Revise related documentation (Design/Process/Q-Systems)

    8 D Process

  • 8/6/2019 Project Management Lvl a Prt II 2009_11_edn 3

    139/139

    D 8 - Congratulate Your Team: ( ensure: was this problem solvingexercise effective? Has it been verified with a follow-up? ) Use all forms of employee recognition and document as necessary. Celebratesuccessful conclusion of the problem solving effort. Formally disengage the team and return to normal duties OR

    Go for the next round of problem solving for the remaining issues

    PD 0,1,2

    & 3

    AD 7 & 8