Training
Project Management / Seminar Planning
I NSTRUCTIONS FOR THE TRAINER
Number of participants: 11 - 25
Duration: 3 - 4 hours (depending on evaluation)
Material needed: IFP Brochure
Text Markers, Pens
Problem Cards (to be filled in by trainer during the game)
Cards (to be filled in by the teams during evaluation, and to be put on chronological table)
Team Labels
Materials for the teams (6 copies each): "Your Task", Task definition for teams, evaluation
Chronological Table (big, at least 2 flip chart papers)
Flip Chart papers for evaluation:
- motivation diagram
- table: motivation killers/ boosters
- team chart
- Table: problems/ solutions
l f th H d f OC
7/27/2019 Project Management - Instructions for the Trainer
http://slidepdf.com/reader/full/project-management-instructions-for-the-trainer 2/5
role of the Head of OC
In order to do your job properly, you will need information from the other teams, and will have to
forward information to other teams or to the head of OC. For this purpose, you can go over to other
teams/ head of OC and ask/ tell. But only one member of your team is allowed to communicate with
other teams at a time.During the whole 1.5 hours, there will be unforeseen situations or problems, to which you will have to
react and might have to change your plans accordingly. Like in real life, the information will not
necessarily reach the relevant team first, but might be told to some other team who then will have to
forward the information to all relevant people.
Let whole group determine the main facts:
(write on top corner of chronological table)
- Seminar Topic: within the IFP (concrete topic to be determined during the game)
- Number of participants
- Duration
- Date: 6 months from now (write start date of seminar)
- City (not necessary)
3. Game (1.5 hours + Teambuilding game)Tasks of the trainer:
Monitor time (15 min = 1 month => 1.5 hrs) , announce whenever one month is over
Put in problem cards (for suggestions, see table below, page 3)
Reply to sponsor-, hotel-, printer- or any other approaches made by the participants
After 30 min: Distribute hand-out ("A project management training has helped you to define your
tasks more clearly...") to the teams
After 45 min (= 3 months): short teambuilding game (suggest it to head of OC and explain that
there will be a time out during the teambuilding If he agrees ask him to summon the
7/27/2019 Project Management - Instructions for the Trainer
http://slidepdf.com/reader/full/project-management-instructions-for-the-trainer 3/5
7/27/2019 Project Management - Instructions for the Trainer
http://slidepdf.com/reader/full/project-management-instructions-for-the-trainer 4/5
Possible Problems:
Finance Marketing Academic Programme Logistics Relating whole group
Tax adviser informs you that there is
35% tax on each donation/sponsorship received
IB calls you to tell that the seminar
cannot be announced as ELSA
seminar if maximum participation feeis exceeded
Well-known law-firm offers a lot of sponsorship, if they in return get half
an hour between the lectures to
present their firm to the audience
approached sponsor agrees to give
money if offered exclusivity
other sponsor agrees if they can alsohave one of their partners as speaker/
lecturer
Trouble with IB / Other NG's: you
have violated Fundraising regulations!
Important spelling mistake in
marketing material: 100 brochures/
posters printed in vain
Press representatives
want to participate - if invited to a nice dinner
Printer calls to tell that
seminar posters will
not be ready in time.
one speaker cancels
short-term, due tosudden illness
Other student
organisation plans
event on similar topic within the very
same week
offered seminar room
has no microphones,
but you may rent
some for 25 EURO per day
approached hotel/ youth hostel
doesn't have enough free roomsavailable
10 Italians apply - but don't speak
English
10 applicants cancel short-term
Sponsors and patrons of ELSA
International unexpectedly want
to part icipate in opening
ceremony
because of recent strikes, petrol
prices double right before theseminar starts
car breaks down; to repair it costs300 EURO
weather forecast says it's gonna be
bed weather during the whole
week.
One of the teams is
completelyexhausted, meets in
your favourite pub.
They get totally
wasted and wake up
at the police station
where they'll haveto stay for a couple
of days if you don't
find a good excuse
for them.
Love-drama within
the group
5.000 EURO-offer by firm of ELSA
senior
you receive in-kind sponsorship
Patronage of important
person confirmed
Copy Shop sponsors1000 leaflets
well-known newspaper
publishes a big articleon the event on
prominent page
the top speaker has
confirmed
University wants tosupport the event
academically
Hilton offers 20 double rooms for
half-price
3 Shuttle buses sponsored
Teambuilding
weekend was great
(distributechocolate/ drinks)
Project management/ Seminar planning 5 Trainer instructions