Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
3/2/16
1
Advanced Techniques In Project Management Part 1: Technical Skills
NK Shrivastava, PMP, RMP, ACP, CSM, SPCCEO/Consultant/Agile Coach - RefineM
www.RefineM.com
Agenda1. WhatisVirtualLunch&Learn2. YourExpectationsfromthisWebinar3. Introduction– Myself4. AdvancedTechniques inProjectManagement
Part1:TechnicalSkills
5. UpcomingLearningOpportunities fromRefineM6. Howtoget1PDUforthisWebinar?7. RewardingOurStarAttendees8. Q&A
3/2/16
2
www.RefineM.com
RefineM’s Virtual Lunch & LearnThisisamonthlywebinardeliveredduringthelunchhourinthefirstweek(Wednesdays)ofeverymonth.
It’sdesignedtohelpyoulearnwhileyoueatlunch,providingarelaxedenvironmenttoenhanceyourexperience.
ThemonthlywebinarswillcoveravarietyofProjectManagement/Agiletopics.
www.RefineM.com
Your Expectations
What are your expectations from this webinar?
Why are you here today?
3/2/16
3
www.RefineM.com
NK Shrivastava, PMP, RMP, ACP, CSM, SPC
∗ CEO/Consultant sinceDec2011∗ AgileCoaching/Adoption∗ ProjectManagement/ ProcessImprovement
ConsultingandTraining∗ ProjectManagementToolkits(forPMs,Executives
andAgilePractitioners)
Helping organizations turn their project management capability into a competitive advantage
Myprofessionaljourneyb/fRefineM ∗ 20+yearsofSuccessfulProject Leadership∗ Led100sofprojectsofallsizes,successfully∗ Recoveredmanyprojects,savedmillionsof$∗ Implementednumerousprocess
improvements∗ Coached/mentored100sofPMs,andsome
executives∗ BoardMember– SWMOPMIChapter(2008-
2014)
Advanced Techniques In Project Management
Part 1: Technical Skills§ OverviewofAdvancedTechniques§ WhoCanUseTheseTechniques?
3/2/16
4
www.RefineM.com
∗ Howdoprojectmanagersovercomeplateaus?
∗ Whatcantheyfocusontobemosteffective?
∗ Howcantheycontinuetomeetdemands oftheirjob?
Learnadvancedtechnicalandleadershipskills
Overview of Adv. Techniques
www.RefineM.com
Advanced Skills
TechnicalSkills LeadershipSkills1. AdvancedStakeholderManagement 1. DevelopingClarity
2. AdvancedScopeandChangeManagement 2. InspiringandMotivating
3. PerformanceMeasurementUsingEVM 3. CommunicatingEffectively
4. AdvancedRiskManagement 4. BuildingRelationships
5. DevelopingOthers
6. ManagingStressonProjects
3/2/16
5
www.RefineM.com
∗ Projectmanagerswhohavesomeexperience
∗ Theymayormaynothaveacertificationsuch asPMP®
∗ PMOLeads/Directors
∗ Projectmanagerslooking totakeonaleadershiprole
Who Can Use These Techniques?
Advanced Technical Skills
§ AdvancedStakeholderManagement- NPS§ AdvancedScope/ChangeManagement- RTM§ PerformanceMeasurement - EVM§ AdvancedRiskManagement- ContingencyReserve
3/2/16
6
Advanced Stakeholder Management
§ OverviewofStakeholderManagement§ UsingNetPromoterScore(NPS)
www.RefineM.com
∗ EffectivestakeholdermanagementhelpsPMwinsupport
∗ Ineffective/nostakeholdermanagement:ü Causes communicationgaps/thingsslippingthroughcracksü Cancausestakeholderstobecomebarriers
∗ ManyPMsalreadydosomestakeholdermanagementü Stakeholderregisterandinfluence/interestgridü Stakeholderengagementmatrix(current,desiredlevels)
Howtogobeyond?
Stakeholder Management
3/2/16
7
www.RefineM.com
∗ NPSisacustomerloyaltymetric∗ NPSisbasedononequestion:
ü “Howstronglywillyourecommendusonascaleof1-10?”ü Thosescoring9-10arepromotersü 7-8arepassives/neutralsü 0-6aredetractors
Use Net Promoter Score (NPS)
[email protected]:https://en.wikipedia.org/wiki/Net_Promoter
Howdoyouapplythistoimprovestakeholderengagement?
Howaboutdoingasmallexercise?
Advanced Scope and Change Management
§ OverviewofScope/ChangeManagement§ RequirementsTraceabilityMatrix
§ Example
3/2/16
8
www.RefineM.com
∗ Scope/changemanagement iscriticaltoprojectsuccess
∗ Scopecreepcancause:ü Delaysü Costoverrunsü Customer dissatisfaction
∗ Basicscopeandchangemanagement startswith:ü WBSü Changecontrol system
Howtogobeyond?
Overview of Scope/Change Mgmt
www.RefineM.com
∗ Usedtotracerequirementsbacktotheirsource
∗ Cantierequirementsto:ü Businessandprojectobjectivesü Deliverablesü TestcasesüManyothers
∗ Benefitsprojectmanagersby:ü Bettertrackingofrequirementstomakesuretheygetcompletedü Betterintegrationofrequirementswithbusinessvalue
Requirements Traceability Matrix
3/2/16
9
www.RefineM.com
RTM Example
Project XYZ - Requirement Traceability Matrix (RTM)Id Requirements Deliverables Project Lead Estimated
Duration (Weeks)
Estimated Real Effort (Hours)
Date WBS Created
Date Schedule/MPP Created
Date Code Complete
Date Testing Complete
Date In Production
1 Requirements Set1
2 Requirements Set2
3 Requirements Set3
Performance Measurement Using Earned Value Management (EVM)
§ WhyUseEVM?§ EVMExample§ EVMMetrics
3/2/16
10
www.RefineM.com
∗ EVMisatoolthatmakesprojectmanagerspowerfulü Combinesscope,time,costmanagementinonemetric
∗ Canbesetupwiththefollowing:ü Valueofplannedwork(PV)ü Actualcostsincurred(AC)ü RulesforcalculatingEarnedValue(EV)
∗ Helpsprojectmanagers:ü Integratescope,schedule,andresourcesü Objectivelymeasureprojectperformanceü Effectivelyforecastfutureoutcomes
Why Use EVM?
www.RefineM.com
EVM Example
3/2/16
11
www.RefineM.com
EVM Formulas∗ Variances- apositive#isbetter
ü AlwaysinvolvesEVminussomethingü ScheduleVariance(SV)=EV-PV ü CostVariance(CV) =EV-AC
∗ PerformanceIndices– a#morethan1isbetterü AlwaysinvolvesEVdividedbysomethingü SchedulePerformanceIndex(SPI)=EV/PV
• Foreachdayspent,howmuchisprojectearning?
ü CostPerformanceIndex(CPI)=EV/AC• Foreachdollarspent,howmuchisprojectearning?
Source: PMI’s Practice Standard for Earned Value Management (Second Edition), 2011, Project Management Ins titute.
www.RefineM.com
EVM Metrics for Past PerformanceMetric Description
Planned Value(PV) Valueplannedforworktobeperformed
EarnedValue(EV) Valueearned forworkperformed
ActualCost(AC) Cost ofworkperformed
CostVariance(CV) Differencebetweenearnedvalue, actual cost
CostPerformanceIndex(CPI) Valueearned perdollarspent
ScheduleVariance(SV) Differencebetweenplanned, earnedvalue
SchedulePerformanceIndex(SPI) Valueearnedperdayspent
3/2/16
12
www.RefineM.com
EVM Exercise
Activity % Complete Cost
Side1 100% 1200
Side2 100% 1000
Side3 75% 750
Side4 50% 500
Side5 0% 0
Side6 0% 0
YouaretheProjectManagerforasmallproject.Youneedtobuild astructurewith6sidesin6days.Eachside shouldcost$1000.00.Todayistheendofday3.
Thefollowing isanextractfromtheSiteManager’sReport.
Solvethefollowing:
www.RefineM.com
Parameter Calculation Result
PVEVACBACCVCPISVSPI
EVMExerciseAnswers
$1,000 + $1,000 + $1,000 $3,000$1,000 + $1,000 + $750 + $500 $3,250$1,200 + $1,000 + $750 + $500 $3,450
$1,000 + $1,000 + $1,000 + $1,000 + $1,000 + $1,000 $6,000$3,250 - $3,450 ($200)$3,250 / $3,450 .94$3,250 - $3,000 $250$3,250 / $3,000 1.08
3/2/16
13
Advanced Risk Management§ OverviewofRiskManagement§ BasicQuantitativeAnalysis§ RiskContingencyReserve
www.RefineM.com
∗ Riskmanagement iscriticaltoprojectsuccess
∗ Withoutit,projectmanagerscanexpect:ü Lotofsurprisesand“ohno”momentsduetothingsmissedü CostlydelaysandoverrunsüMissedopportunities
∗ Basicriskmanagement startswith:ü Riskregisterü Identifyingresponsestrategiesü Basicqualitativeanalysis
Howtogobeyond?
Overview of Risk Management
3/2/16
14
www.RefineM.com
∗ ExpectedMonetaryValue(EMV)isoneexampleü Probabilityofriskoccurrencetimesimpactofoccurrence
∗ Example:Computersgodown,costis$5,000toreplace.ü Theprobabilityofcomputersgoingdownis20%üWhatistheEMV?ü EMV=$5,000x20%=$1,000
∗ BenefitsofEMVü Exposetherealimpactofariskü Setupriskcontingencyreserve
Basic Quantitative Analysis
www.RefineM.com
∗ Timeorcostsetasidetomanageidentified risks
∗ ContingencyReservecovers“knownunknowns”
∗ BenefitsofContingencyReserveü Improvespredictabilityofoutcomesü Effectivecommunicationtoolforrisks
Risk Contingency Reserve
3/2/16
15
www.RefineM.com
Risk Impact on the Project
www.RefineM.com
∗ MasterthefollowingtoovercomeyourPMplateau
Conclusion
3/2/16
16
www.RefineM.com
∗ Nextmonthwewilldiscuss stakeholdermanagement
∗ Inthemeantime,findwaystopracticetheskills
∗ Regularpracticewillhelp youdeveloptheseskills
Withtheseskillsyoucanmanageanyproject
Evenalargeandcomplexproject
What’s next?
www.RefineM.com
Please visit https://refinem.com/training/ for more details.
More Training Opportunities From RefineM
Training Title Springfield Kansas City St. Louis Instructor-Led Online
Tips/TricksforStakeholderEngagement Mar14
First-TimeManager Mar16 Mar30 Jun01
LeadershipSkillsforProjectManagers Mar17 Mar31 Jun02
Adv.TechniquesinRiskManagement Mar21
IsQualityReally Important? Mar23 May02 Apr07
Lean 101 Mar30 May03 Apr08
ChangeManagement Apr04 May04 Apr09
AgileFundamentals/Agile101 Apr07 May04-05 Apr04-05
PMI-ACP®ExamPrep May04-06
PMP®ExamPrep May09-12
Risk ManagementforProjects Nov14 Jun01
3/2/16
17
www.RefineM.com
We also offer customized trainings, On-site & Virtual
Topics include ∗ Agile, ∗ Project Management, ∗ Process Improvement, ∗ Leadership and ∗ PMI & SAFe Certifications.
RefineM Customized Training
More info at https://refinem.com/training/
Contact us at [email protected]
www.RefineM.com
∗ Adv.TechniquesInPM:StakeholderManagementüHowdoyougobeyondstakeholdermanagementbasics?üHowcanyoumaximizestakeholdercommunication?
∗ Wednesday,April6,12:00-1:00PMCentral
RegisterToday- Don’twaitforthelastMinute
Next Lunch and Learn
3/2/16
18
www.RefineM.com
∗ PDU Category – B, Continuing Education∗ Program Title – Webinar on “Advanced Techniques in
Project Management Part 1: Technical Skills”∗ Talent Triangle – 1.00 Technical ∗ Date Started – Today’s date∗ Date Completed – Today’s date∗ Hours Completed – 1.00∗ Provider
ü Name – RefineMü Phone # 417-763-6762ü Email – [email protected]
∗ PDUs Claimed – 1.00 Technical
How to Claim 1 PDU for this Webinar?
www.RefineM.com
Rewarding Our Star Attendees
∗ Anyonewhoattends3LunchandLearnWebinarsinarowisaStarAttendeeandiseligibleforaprizedrawingfora$10Amazongiftcard.
There are no Star Attendees this month.Stay tuned for our next drawing in April.
3/2/16
19
www.RefineM.com
__________________________________________________________________
NK Shrivastava, MBA, PMP, RMP, ACP, CSM, SPCCEO/Consultant, RefineMNixa, MO 65714, [email protected], www.refinem.com
http://www.linkedin.com/in/nkshrivastava @jujustrightpm
Questions?