Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Project Steering Committee Kick‐Off Meeting
March 18, 2013
Agenda
• Meeting Purpose• Study Background• PSC Roles• Project Summary – LPA Refinement• New Starts Project Development Process• Q&A / Next Steps
2
3
Atlanta Region Comprehensive Plan ‐Rapid Transit (1961)
Corridor History
4
• Completed in 2012• Evaluated alternatives & selected LPA • Adopted LPA
5
Alternatives Analysis
6
Clifton Corridor LPA
Recap: Purpose & Need Statement
7
The purpose of the Clifton Corridor Alternative Analysis (AA) was to identify a high‐capacity transit investment that provides reliable and competitive travel times to and from the Clifton Corridor by:• Increasing transit accessibility for all users• Improving mobility in the corridor • Integrating with other transit projects
Study Organization
8
Phase 1: Environment Review & Alignment Refinement
Phase 2: Alignment Refinement & EIS
Environmental Review, Alignment Refinement & NEPA
• Horizontal alignment • Engineering reconnaissance• Station locations & design• Environmental impacts • PSC input
• NOI• Detailed engineering• Alignment & cost refinement • Environmental analyses &
mitigation• Community outreach• Public hearings • Draft & Final EIS
Assess Impacts to:
• Historic & Archeology
• Geology & Subsurface Conditions
• Community & ROW
• Traffic
(Jan – June 2013) July 2013 to 2015 (TBD)
PSC Roles & Expectations
9
Phase 1: Phase 2:
• Confirm & Expand PSC membership• Identify potential SAC & TAC
members• Provide input on technical findings
from Phase 1• Reconfirm/Refine Purpose & Need
• PSC to convene as SAC & TAC to better inform the EIS process & ensure a quality outcome
• SAC to ensure community goals & concerns are addressed
• TAC to guide the process & provide input on technical & policy issues
SAC TACPSC
PSC & Community Input Framework
10
• Integrate analysis results with recommendations from TAC & SAC
• Integrate analysis results with recommendations from community
• Balance technical feasibility & cost
Community Residents
Stakeholder Advisory
Committee
Technical Advisory
Committee
Analysis Results, Technical & Cost Factors
Refined LPA
Current LPA = Baseline
Issues & Considerations
11
• Alignment– At‐grade, underground, aerial– Station locations & configuration
• Traffic – Roadway sections, circulation, analysis, safety
• Cost – Alignment options– Project evaluation – New Starts
• Community concerns • Other environmental issues
12
LPA Refinement Trade‐offs
•At‐grade
alignm
ent o
n Scott
•Signals, con
trol, &
access
•Ae
rial structure
•Traffic
circulation
BeltLine Interface
Tunn
el u
nder N Decatur/Scott
LPA Refinement
13
At‐grade vs. Grade‐separated
14
Exclusive - Median
Exclusive - SideMixed Traffic
Bridge
Elevated/Aerial
Tunnel vs. Aerial
15
Tunnel Portal
Tunnel Portal
Aerial / Retained
Aerial / Bridge
Traffic & Circulation
16
Intersection TurnMixed Traffic
Shared Turn LaneSafety / Z-crossing
Station Location & Configuration
17
Side Platform LRT
Side Platform LRT
Side Stop Streetcar
Median Platform BRT
Great Streets & Betterments
18
Platform LRT & Sidewalk
LRT & Fountain
LRT, streetscape & TOD
Vehicles
19
70% low-floor
Traditional & Modular Light Rail Vehicles
20
Traditional, 4 x 82’, high floor
Modular, 140’, low floor Modular, 95’, low floor
Modular, 130’, partial low floor
New Starts Process
21
New Starts Project Development Process
22
Alternatives Analysis
Preliminary Engineering
FinalDesign
Full Funding Grant
Agreement
• Develop & review alternatives
• Select locally preferred alternative (LPA)
• Adopt LPA into fiscally constrained long range transportation plan
• Complete environmental review process
• Gain commitments of at least 50% of non‐New Starts funding
• Gain commitments of all non‐New Starts funding
• Complete sufficient engineering & design
Under SAFETEA‐LU (2005‐2012)
Complete environmental review process including developing & reviewing alternatives, selecting LPA, & adopting it into the fiscally constrained long range transportation plan
• Gain commitments of all non‐New Starts funding
• Complete sufficient engineering & design
Project Development Engineering
Full Funding Grant
Agreement
Under Moving Ahead for Progress in the 21st Century (MAP‐21)
Construction
Construction
= FTA evaluation, rating, & approval
= FTA approvalLegend
OLD vs. NEW ‐ New Starts Process
23
Cost & OptionsMAP‐21 = Cost per Rider
24
Increase Riders
Lower Cost
Upcoming Activities ‐ Phase 1
• In the coming weeks, the project team will:• Develop horizontal alignment• Conduct engineering reconnaissance
‐ tunnels, structures, utilities, right‐of‐way
• Verify station locations & configuration• Identify preliminary impacts to natural & cultural resources
• PSC Meetings planned in April & May
25
We Need Your Help!
26
Data Needs Major UtilityPlans
Recent Aerial Photo
CampusExpansion Plans
Construction Plans
Intersection Plans
Other
DeKalb County
Briarcliff/ Clifton
Medline LCI StudyBoundary
City of Atlanta
Emory University
Emory Hospital
Clifton/Haygood
DeKalb Medical
CDC
Jason Morgan, AICPMARTA Project Manager2424 Piedmont Rd, NEAtlanta, Georgia [email protected]
Derek Crider, PEConsultant Project Manager
One Midtown Plaza1360 Peachtree Street, Ste 500
Atlanta, Georgia [email protected]
27
Project Management
Visit us at http://www.itsmarta.com/clifton‐corr.aspx & Find us on Facebook!