PROJECT AUTHORIZATIONS
September 24, 2014
by
Peter Anderson
HQ Area Engineer – Districts 1 and 4
&
Ephrem Meharena
i- Team, Caltrans District 4 + VTA
PROJECT AUTHORIZATIONS
September 24, 2014
Chapter 3
Local Assistance Procedures Manual(LAPM)
PRIOR TO FEDERAL AUTHORIZATION
• All federally funded transportation projects must be included in the current federally approved Federal Transportation Improvement Program/Federal Statewide Transportation Improvement Program
September 24, 2014
FSTIP/FTIP•Must Indentify:
• Project Description:
• Scope of Work & Project Limits
• Project Total Cost
• Project Implementing Agency
• Federally Funded Phases of Work
• Programmed FFY
• Types & Amounts of Federal Funds & Other Funds
September 24, 2014
SAMPLE FSTIP/FTIP SHEET(Line Item Project)
September 24, 2014
LUMP SUM LISTINGS• Non capacity increasing projects must be included
in the respective Lump Sum Project Listing• Highway Bridge Program (non-capacity)• Highway Safety Improvement Program (HSIP)• Most NI (Non Infrastructure)Projects• Don’t forget: Back-up List of Projects
September 24, 2014
SAMPLE FSTIP/FTIP SHEET(Lump Sum Listing)
September 24, 2014
PRIOR TO FEDERAL AUTHORIZATION
• DBE• Local agency must have a signed and accepted
DBE Implementation Agreement (Ex-9A)
• DBE Annual Submittal Form (Ex-9B) for current federal fiscal year.
• Annual ADA Certification Form (Ex-9C)
• ATP/STIP Funds (if any)• Must have been allocated by the CTC
September 24, 2014
PROJECT AUTHORIZATIONS
• QAP- Current local agency approved QAP prior to RFA (Con) submittal (valid for 5 years)• QAP Training for Santa Clara County agencies through the i-Team scheduled for 10/22/2014 @VTA Project authorization is the process that allows the Local Agency to:
• Begin reimbursable work on federal-aid projects• Advertise for construction contracts
September 24, 2014
PROJECT PHASES• Preliminary Engineering (Ex 3-A)• Right-of-Way (Ex 3-B)• Utility Relocation (Ex 3-C)• Construction (Ex 3-D)
• What about Construction Engineering?
• Non-Infrastructure (Ex 3-Q)
September 24, 2014
AUTHORIZATION PROCESS• Local Agency submits hard copy request to DLAE
• Separate request for each federal funding action
• DLAE reviews request for completeness and accuracy and submits E76 (FADS) with back up documentation to HQ
• HQ reviews and submits E76 and support documentation to FHWA
• FHWA authorizes and obligates the federal funds• DLAE issues Notice to Proceed to Local Agency
September 24, 2014
THE E-76• Written confirmation of authorization• Establishes effective date of phase authorization• Reflects federal funds obligated• Establishes federal share of project cost• Establishes scope and limits of project
September 24, 2014
SAMPLE E-76
September 24, 2014
REQUIRED DOCUMENTS• Local Agency to DLAE
• RFA (Ex 3-A, 3-B, 3-C, 3-D, 3-Q & attachments)• DLAE to HQ (Ex 3-G – Federal Project Log Sheet)
September 24, 2014
RFA PACKAGES by Phase
Document PE ROW Con NI
RFA to Proceed 3A 3B 3D 3Q
FTIP/FSTIP Y Y Y Y
Finance Letter 3O 3O 3O 3O
Data Sheets 3E 3E 3E 3E
Field Review Form 7B 7B# 7B#
7B#
NEPA Y Y Y
Estimate Y Y Y
PS&E Certificate 12C
PS&E Checklist 12D
Right of Way Certificate 13A
Local Agency Construction Checklist 15A
PS&E Package 3R
DBE Contract Goal Methodology 9D* 9D* 9D*
# - required if not previously submitted* -Agencies must prepare and submit Exhibit 9D for all construction and consultant contracts.
September 24, 2014
RFA-PE (Ex 3-A) TYPICAL DOCUMENTATION
• Exhibit 3-E (Data Sheets)
• FSTIP/FTIP Reference
• Agency Finance Letter
• Complete Field Review Form
• DBE Contract Goal Methodology Exhibit 9D(For consultant contracts)
September 24, 2014
RFA-R/W (Ex 3-B) TYPICAL DOCUMENTATION
• Exhibit 3-E (Data Sheets)
• FSTIP/FTIP Reference
• Agency Finance Letter
• Complete Field Review (unless previously submitted)
• Approved NEPA Environmental Document
• R/W Cost Estimate
• Exhibit 9D( DBE Contract Goal Methodology) For consultant contracts.
September 24, 2014
RFA-CON (Ex 3-D) TYPICAL DOCUMENTATION
• Exhibit 3-E (Data Sheets)
• FSTIP/FTIP Reference Sheet
• Agency Finance Letter
• Complete Field Review Form (unless previously submitted)
• Approved NEPA Env Document (unless previously submitted)
• R/W Certification
• PS&E Package, Checklist & Certification
• Exhibit 9D DBE Contract Goal Methodology
• Exhibit 15-A (Local Agency Construction Contract Administration Checklist)
September 24, 2014
September 24, 2014
RFA-NI (Ex 3-Q) TYPICAL DOCUMENTATION
• Exhibit 3-E (Data Sheets)• FSTIP/FTIP Reference Sheet• Agency Finance Letter• NI Project Work Plan • Complete Field Review Form (unless previously
submitted)• Approved NEPA Env Document
• NO R/W Certification Required
September 24, 2014
NI PROJECT WORKPLAN(Ex 3-R)
THINGS TO REMEMBER• Current DBE (Ex 9-B) for new RFA’s Required to be
updated each FFY .
HSIP/ HBP Projects:
• Expedited Project Selection Process (EPSP): local agency must have RTPA/MPO approval to advance or delay project RFA funding that is not in the current year of the FSTIP/FTIP
• Approval of Caltrans Program Manager is required.
September 24, 2014
September 24, 2014
THINGS TO REMEMBER• Back-up List for lump sum projects
• Program manager review of RFA scope/limits consistency w/ scope/limits in approved applications/exhibits (HBP, HSIP, etc)
• RFA scope/limits consistency with HPP(High Priority Projects)/Demo legislated scope/project limits.
• Emergency Recovery Projects: NAPA…
UNDERFUNDED PROJECTS• Project phase funded at less than the maximum
federal reimbursement ratio. • Federal reimbursement ratio is established at
authorization by dividing the federal funds by the federal participating cost.
• Reimbursement ratio is subject to the Pro-Rata/Lump Sum requirements
September 24, 2014
LOCAL ADVANCE CONSTRUCTION• Can be used due to insufficient Federal
Funds/Obligation Authority• Used when federal discretionary funds (i.e. TCSP)
have not been allocated by FHWA• Funding must be programmed in the FTIP/FSTIP
at time of authorization & Agency FL must show Local AC
• Federal funds must also be programmed in current FTIP/FSTIP at the time of AC conversion
• Authorizes work but not invoicing since Local AC are Local Funds until after conversion
• AC Conversion is NOT guaranteed (see Ex 3-I – Request for Local Advance Construction)
September 24, 2014
AGENCY FINANCE LETTER• Shows total cost, federal participating cost,
federal, state & local funds for each federally funded phase of the project (Ex 3-O)
• Shows federal participation ratio• Shows federal reimbursement ratio(s)• Shows pro-rata/lump sum designation• By reference part of PSA• Submitted by Local Agency to DLAE to HQ• HQ-AE submits FL to Accounting• Accounting uses FL to encumber funds
September 24, 2014
AGENCY FINANCE LETTER
September 24, 2014
CRS MAPS
September 24, 2014 http://www.dot.ca.gov/hq/tsip/hseb/crs_maps/
CT EARTH
September 24, 2014
September 24, 2014
Sample E-76 – Sequence 3
September 24, 2014
PROJECT AUTHORIZATION
September 24, 2014
RECAP• Only for federally funded projects• For Each federally funded phase of work• Work done prior to authorization is ineligible for
reimbursement• Do not advertise prior to construction
authorization