PROJECT MINUTES
Project: New Holbrook PreK-12 School Project No.: 13006
Prepared by: Joel Seeley Meeting Date: 3/16/2016
Re: Permanent School Building Committee Meeting Meeting No: 62
Location: H-CAM Studios Time: 7:00 PM
Distribution: Attendees, E. Kinsherf, (MF)
Attendees:
PRESENT NAME AFFILIATION VOTING MEMBER
Daniel F. Moriarty PSBC Chair Voting Member
James Day PSBC Vice-Chair Voting Member
Patricia Lally HPS Superintendent of Schools Non-Voting Member
Matthew Moore Board of Selectmen Chair Voting Member
Barbara Davis School Committee Voting Member
Patricia Coppola-Lugo HPS Procurement Administrator Non-Voting Member
Timothy Gordon Town Administrator Non-Voting Member
HJSHS Principal Non-Voting Member
Beth Tolson School Committee Voting Member
Tom Taylor Member at Large Voting Member
Peter Mahoney Finance Committee Voting Member
Fred White Member at Large Voting Member
Scott Towne Member at Large Voting Member
Stephanie Trowbridge Member at Large Voting Member
Mike Bolger HPS Director of Facilities Non-Voting Member
Kent Kovacs Flansburgh Architects (FAI)
Vince Dubé Flansburgh Architects (FAI)
Jay Williams Flansburgh Architects (FAI)
Christian Riordan Consigli Construction Company (CCC)
Tim Vautour Consigli Construction Company (CCC)
John Laperle Consigli Construction Company (CCC)
Joel Seeley Symmes Maini & McKee Associates (SMMA)
New Holbrook Pre-K – 12 School
3/16/2016
62
2
Item # Action Discussion
62.1 Record Call to Order, 7:00 PM, meeting opened.
62.2 Record A motion was made by P. Mahoney and seconded by F. White to approve the 2/17/16 Permanent School Building Committee meeting minutes. No discussion, motion passed
unanimous by those attending.
62.3 Record J. Seeley distributed and reviewed the Budget Tracking Form thru 2/29/16, attached, for the Total Project Budget.
62.4 Record J. Seeley distributed and reviewed Change Order No. 7 dated 3/15/16 in the amount of
$93,881.00, Change Order Description Form and the Change Order, GMP Contingency
and Allowance Budget Summary Form, all attached.
Committee Discussion:
1. B. Davis requested an explanation of the term Mechanical Doghouse in CR029?
V. Dube responded that the term doghouse refers to the HVAC ductwork
enclosure on the west side of the gymnasium.
A motion was made by F. White and seconded by B. Davis to approve Change Order No.
7, dated 3/15/16 in the amount of $93,881.00 and recommend signature by M. Moore. No
discussion, motion passed unanimous.
62.5 Record J. Seeley distributed and reviewed PFA Budget Revision Request No. 8, dated 3/16/16
corresponding to Change Order No. 7.
A motion was made by P. Mahoney and seconded by F. White to approve PFA Budget
Revision Request No. 8, dated 3/16/16. No discussion, motion passed unanimous.
62.6 J. Seeley Vouchers for reimbursement to Eric Kinsherf for $332.50 for CPA services, National Grid
for $2,658.07 for Pole Installation, FAI for $85,750.00 for Construction Administration
services, Consigli for $1,866,127.14 for Construction, SMMA for $54,080.97 for OPM
services, were reviewed including the MSBA Payment Tracking Log, attached.
Committee Discussion:
1. P. Mahoney asked why Eric Kinsherf CPA was charging time for calls to MSBA to
resolve a ProPay error message?
J. Seeley will contact Eric Kinsherf CPA and inform them the Committee will not
pay for such in the future.
A motion was made by P. Mahoney and seconded by J. Day to approve the Vouchers. No
discussion, motion passed unanimous.
62.7 T. Gordon
J. Seeley contacted Town Counsel to provide direction on who has the authority and what
is the process and timing to classify some of the adjacent town-owned land as Protected
Habitat to obtain an additional LEED point.
Town Counsel requested formal direction from a Town authority before proceeding. T.
Gordon will contact Town Counsel.
62.8 V. Dube
T. Vautour
V. Dube and T. Vautour will provide a rough order of magnitude budget for the parking lot
at JFK Elementary School and the elevated pedestrian/golf cart walkway from the JFK
Elementary School to the project site including railing and lighting at the next Committee
meeting.
New Holbrook Pre-K – 12 School
3/16/2016
62
3
Item # Action Discussion
62.9 V. Dube
T. Vautour
D. Moriarty
T. Vautour and V. Dube distributed and reviewed the pricing for VE items 0911, 3303,
3307, 3330, 3340 and 3302, attached.
Committee Discussion:
1. J. Day asked why is there more concrete drive s.f. being added than asphalt drive
s.f. being credited in VE 3303?
T. Vautour indicated there was a slight discrepancy in the original asphalt VE take
off from the Design Development phase, the concrete take-off is from the final
construction documents. T. Vautour to provide a drawing indicating the extent of
paving for both VE 3303 and 3307 for the next Committee meeting.
2. J. Day asked if the existing temporary classroom modular building can be
relocated and used for Maintenance Storage in lieu of one of the VE 3302 items?
D. Moriarty to contact the company that originally placed the modular to review the
viability and cost of relocating.
3. M. Bolger asked where will landscaping be added to account for the additional
40% in VE 3340?
V. Dube will provide a drawing showing the extent of the 40%, which is made up of
additional plantings and larger caliper specimens for next Committee meeting.
4. S. Towne asked what is the 10% Design Cost figure for?
J. Seeley indicated it is a place holder so the Committee can understand the full
cost of the added work. Once the Committee decides on what, if any, VE items
are to be added, FAI will be asked to submit a design fee thru the standard
Amendment approval process for review and approval.
62.10 T. Gordon
J. Day
T. Vautour
Irrigation Well – Status of Four Options
1. T. Gordon indicated the Tri-Town Water Board hearing for March has not been
scheduled yet and that he will notify the Committee once scheduled.
2. J. Seeley indicated the test on the existing Sumner Fields well was performed and
the well yields 30 gpm, sufficient for the baseball and softball outfields. J. Day will
follow-up with St. Joseph Parish about an easement should tapping off the
Sumner field be the final direction.
3. J Seeley reviewed that the Well Driller has indicated a Hydro-Frac test could be
performed on one of the three test wells, which might be able to open a vein to
increase the water flow. The cost is approximately $3,000 for each test.
A Motion was made by P. Mahoney and seconded by F. Day to approve up to
$10,000 for Hydro-Frac tests on the three test wells. No discussion, voted
unanimously. T. Vautour to submit formal CR for signature.
4. Performing a fourth test well – on hold pending results of Options 1, 2 and 3.
V. Dube indicated the outside date for seeding the fields is 6/1/16 for this upcoming
planting season. T. Vautour indicated CCC will need direction by mid-April to meet the
planting date.
New Holbrook Pre-K – 12 School
3/16/2016
62
4
Item # Action Discussion
62.11 Record B. Davis and B. Tolson distributed and reviewed the draft Topping Off Ceremony invitation
and reviewed the preliminary agenda. The sub-committee will be meeting on 3/21/16 to
finalize the agenda.
Committee Discussion:
1. B. Davis asked if CCC could provide a tent for the event?
T. Vautour indicated yes.
2. The Committee approves the invitation.
62.12 Record T. Gordon distributed and reviewed the following documents relative to the role of the
PSBC and the School Committee Maintenance Committee:
1. History of the PSBC via Town Meeting article (1961-present)
2. Statutory overview and opinion from Holbrook School Committee Counsel
(Stoneham, Chandler and Miller)
3. Legal opinion from Town Counsel (Murphy, Hesse, Toomey)
The Committee discussed the documents and voiced opinions and concerns relative to
successfully maintaining and operating the project well into the future, which all agreed to
be a common goal. M. Moore indicated the PSBC and the School Committee should
continue to dialogue to reach a mutually agreeable process which maximizes the strengths
of both the PSBC and the School Committee Maintenance Committee.
62.13 Record T. Vautour distributed and reviewed the updated OAL log, attached. Consigli has awarded
approximately 92% of the trade work, with a buy-out savings of $75,222 to date.
62.14 Record T. Vautour distributed and reviewed the Construction Progress Update, dated 3/16/16
attached. Structural steel is complete in Area A and is underway in Area C. Elevated
bearing wall masonry is underway in area B. Roof edge blocking, roof drain piping and
exterior metal stud work will commence in Area A within the next two weeks.
T. Vautour indicated the project is tracking on schedule.
62.15 Record Next PSBC Meeting: April 20, 2016 at 7:00 pm at the H-Cam Studios.
62.16 Record A Motion was made by P. Mahoney and seconded by F. White to adjourn the meeting. No
discussion, voted unanimously.
Attachments: Agenda, Budget Tracking Form, Change Order No. 7, Change Order Description Form, Change
Order/GMP Contingency/Allowance Budget Summary Form, Pricing for VE items 0911, 3303, 3307, 3330, 3340 and
3302, draft Topping Off Ceremony invitation, Role of the PSBC and the School Committee Maintenance Committee
Documents, OAL Log, Construction Progress Update
The information herein reflects the understanding reached. Please contact the author if you have any questions or are not in agreement with these
Project Minutes.
JGS/sat/P:\2013\13006\04-MEETINGS\4.3 Mtg_Notes\3-PSBC Meetings\2016\62_2016_16marchpsbcmeeting\Permanentschoolbuildingcommitteemeeting_16March2016-
FINAL.Docx
AGENDA
Project: New Holbrook PreK-12 School, Holbrook, MA Project No.: 13006
Re: Permanent School Building Committee Meeting Meeting Date: 3/16/2016
Prepared by: Joel G. Seeley Meeting Time: 7:00 PM
Distribution: Attendees (MF)
1. Call to Order
2. Approval of Minutes
3. Approval of Invoices and Commitments
4. Protected Habitat for LEED Update
5. Past VE Items Review
6. Irrigation Well Update
7. Elevated Walkway to JFK Site Budget Update
8. Topping-Off Ceremony Update
9. School Department’s Maintenance Plan and the role of the PSBC
10. Procurement Update
11. Construction Update
12. Committee Questions
13. Public Comments
14. Next Meeting: April 20, 2016
15. Adjourn
JGS/sat/P:\2013\13006\04-MEETINGS\4.2 Agendas\3-PSBC Meetings\2016\63_2016_March16\Agenda_16March2016.Doc
Symmes Maini & McKee Associates, Inc. (SMMA)
Holbrook School District
New Holbrook PreK-12 School
BUDGET SUMMARY
BUDGET TRACKING FORM as of: 2/29/2016 Budget Revisions
Propay Name A B C D E
code # Feasibility Study Agreement
1 0001-0000 OPM Feasibility Study 160,000.00 160,000.00 159,250.00 159,250.00 - - 750.00
2 0002-0000 A&E Feasibility Study 450,000.00 450,000.00 450,000.00 450,000.00 - - -
3 0003-0000 Environmental and Site 100,000.00 100,000.00 63,706.00 63,039.69 666.31 - 36,294.00
4 0004-0000 Other 86,272.00 86,272.00 8,416.38 8,416.38 - - 77,855.62
Feasibility Study Agreement Subtotal 796,272.00$ -$ 796,272.00$ 681,372.38$ 680,706.07$ 666.31$ -$ 114,899.62$
Administration
6 0101-0000 Legal Fees 120,000.00 120,000.00 97,515.66 27,857.26 69,658.40 - 22,484.34
Owner's Project Manager
7 0102-0400 > Design Development 254,666.00 254,666.00 254,666.00 254,666.00 0.00 - -
8 0102-0500 > Construction Contract Documents 382,226.00 382,226.00 382,226.00 382,226.00 0.00 - -
9 0102-0600 > Bidding 138,889.00 138,889.00 138,889.00 138,889.00 - - -
10 0102-0700 > Construction Contract Administration 1,802,699.00 1,802,699.00 1,802,699.00 54,080.97 1,748,618.03 - -
11 0102-0800 > Closeout 61,004.00 61,004.00 61,004.00 - 61,004.00 - -
12 0102-0900 > Extra Services 100,000.00 100,000.00 - - - - 100,000.00
13 0102-1000 > Reimbursable & Other Services 40,000.00 40,000.00 3,960.00 3,960.00 - - 36,040.00
14 0102-1100 > Cost Estimates 100,000.00 100,000.00 52,250.00 52,250.00 - - 47,750.00
15 0103-0000 Advertising 20,000.00 20,000.00 820.38 820.38 - - 19,179.62
16 0104-0000 Permitting 50,000.00 50,000.00 1,757.94 1,757.94 - - 48,242.06
17 0105-0000 Owner's Insurance 80,000.00 80,000.00 - - - - 80,000.00
18 0199-0000 Other Administrative Costs 60,000.00 60,000.00 20,686.64 13,130.32 7,556.32 - 39,313.36
Administration Subtotal 3,209,484.00$ -$ 3,209,484.00$ 2,816,474.62$ 929,637.87$ 1,886,836.75$ -$ 393,009.38$ Architecture and Engineering
Basic Services
21 0201-0400 > Design Development 1,730,000.00 1,730,000.00 1,730,000.00 1,730,000.00 - - -
22 0201-0500 > Construction Contract Documents 2,550,000.00 2,550,000.00 2,550,000.00 2,550,000.00 - - -
23 0201-0600 > Bidding 330,000.00 330,000.00 330,000.00 330,000.00 - - -
24 0201-0700 > Construction Contract Administration 2,450,000.00 2,450,000.00 2,450,000.00 85,750.00 2,364,250.00 - -
25 0201-0800 > Closeout 200,000.00 200,000.00 200,000.00 - 200,000.00 - -
26 0201-9900 > Other Basic Services 300,000.00 300,000.00 300,000.00 - 300,000.00 - -
27 BASIC SERVICES SUBTOTAL 7,560,000.00$ -$ 7,560,000.00$ 7,560,000.00$ 4,695,750.00$ 2,864,250.00$ -$ -$
Reimbursable Services
28 0203-0100 > Construction Testing 25,000.00 25,000.00 - - - - 25,000.00
29 0203-0200 > Printing (over minimum) 120,000.00 120,000.00 - - - - 120,000.00
30 0203-9900 > Other Reimbursable Costs 180,000.00 180,000.00 12,078.98 1,320.00 10,758.98 - 167,921.02
31 0204-0200 > Hazardous Materials 240,000.00 240,000.00 - - - - 240,000.00
32 0204-0300 > Geotech & Geo-Env. 200,000.00 200,000.00 32,230.00 10,703.00 21,527.00 - 167,770.00
33 0204-0400 > Site Survey 80,000.00 80,000.00 57,475.00 57,475.00 - - 22,525.00
34 0204-0500 > Wetlands 80,000.00 80,000.00 2,970.00 2,970.00 - - 77,030.00
35 0204-1200 > Traffic Studies 100,000.00 100,000.00 - - - - 100,000.00
Architectural and Engineering Subtotal 8,585,000.00$ -$ 8,585,000.00$ 7,664,753.98$ 4,768,218.00$ 2,896,535.98$ -$ 920,246.02$
(A - B - E)
Budget
Balance
Original
PS&B Budget
7/23/14
Current
Budget
Contract
Amount Expended
(B - C)
Remaining
Contract Amount
Additional Projected
Amount
Symmes Maini & McKee Associates, Inc. (SMMA)
Holbrook School District
New Holbrook PreK-12 School
BUDGET SUMMARY
BUDGET TRACKING FORM as of: 2/29/2016 Budget Revisions
(A - B - E)
Budget
Balance
Original
PS&B Budget
7/23/14
Current
Budget
Contract
Amount Expended
(B - C)
Remaining
Contract Amount
Additional Projected
Amount
CM @ Risk Preconstruction Services
36 0501-0000 Pre-Construction Services 600,000.00$ (400,000.00)$ 200,000.00$ 193,500.00$ 193,500.00$ -$ -$ 6,500.00$
0502-0001 Construction Budget 79,835,240.00$ 400,000.00$ 80,235,240.00$ 77,766,936.25$ 7,979,950.10$ 69,786,986.15$ -$ 2,468,303.75$
89 CSI Code CSI Description
89 0502-0010 CM Fee 1,524,560.00 1,524,560.00 156,071.34 1,368,488.66 - -
89 0502-0020 Bonds and Insurances 2,079,305.85 2,079,305.85 780,698.60 1,298,607.25 - -
89 0502-0030 Total GMP Construction Contingency 3,251,121.35 3,251,121.35 38,627.00 3,212,494.35 - -
89 0502-0100 CM Staffing 3,264,261.75 3,264,261.75 631,275.78 2,632,985.97 - -
89 0502-0100 GC's 238,687.50 238,687.50 108,143.56 130,543.94 - -
89 0502-0100 Division 1 - General Requirements 1,780,043.50 1,780,043.50 171,230.25 1,608,813.25 - -
89 0502-0200 Division 2 - Existing Conditions 954,750.00 954,750.00 - 954,750.00 - -
89 0502-0300 Division 3 - Concrete 3,773,423.75 3,773,423.75 1,305,625.85 2,467,797.90 - -
89 0502-0400 Division 4 - Masonry 3,022,837.30 3,022,837.30 204,326.00 2,818,511.30 - -
89 0502-0500 Division 5 - Metals 4,867,562.50 4,867,562.50 142,547.50 4,725,015.00 - -
89 0502-0600 Division 6 - Wood, Plastics and Composites 1,245,492.75 1,245,492.75 - 1,245,492.75 - -
89 0502-0700 Division 7 - Thermal & Moisture Protection 5,926,130.40 5,926,130.40 - 5,926,130.40 - -
89 0502-0800 Division 8 - Openings 2,871,440.55 2,871,440.55 - 2,871,440.55 - -
89 0502-0900 Division 9 - Finishes 8,487,301.90 8,487,301.90 - 8,487,301.90 - -
89 0502-1000 Division 10 - Specialties 699,782.35 699,782.35 - 699,782.35 - -
89 0502-1100 Division 11 - Equipment 950,096.90 950,096.90 - 950,096.90 - -
89 0502-1200 Division 12 - Furnishings 1,318,548.70 1,318,548.70 - 1,318,548.70 - -
89 0502-1300 Division 13 - Special Construction 180,519.00 180,519.00 - 180,519.00 - -
89 0502-1400 Division 14 - Conveying Systems 257,450.00 257,450.00 - 257,450.00 - -
89 0502-2100 Division 21 - Fire Suppression 775,105.00 775,105.00 - 775,105.00 - -
89 0502-2200 Division 22 - Plumbing 2,323,207.90 2,323,207.90 - 2,323,207.90 - -
89 0502-2300 Division 23 - HVAC 6,403,000.00 6,403,000.00 - 6,403,000.00 - -
89 0502-2600 Division 26 - Electrical 6,677,920.50 6,677,920.50 - 6,677,920.50 - -
89 0502-2700 Division 27 - Communications - - - - - -
89 0502-2800 Division 28 - Electronic Safety & Security - - - - - -
89 0502-3100 Division 31 - Earthwork 2,884,721.55 2,884,721.55 1,978,624.85 906,096.70 - -
89 0502-3200 Division 32 - Exterior Improvements 4,356,469.15 4,356,469.15 330,873.60 4,025,595.55 - -
89 0502-3300 Division 33 - Utilities 3,668,005.10 3,668,005.10 1,654,347.10 2,013,658.00 - -
89 0502-9900 Retainage 3,883,250.00 3,883,250.00 398,997.47 3,484,252.53 - -
89 0508-0000 Change Orders 101,941.00$ 101,941.00 101,941.00 78,561.20 23,379.80 - -
89 Construction Budget Subtotal 79,835,240.00$ 101,941.00$ 77,766,936.25$ 77,766,936.25$ 7,979,950.10$ 69,786,986.15$ -$ 2,468,303.75$
Alternates
90 0506-0000 Ineligible Work (Maint Blg, Press Box, Concession and Restrooms) 404,800.00 470,648.00 470,648.00 - 470,648.00 - -
Alternates Subtotal 404,800.00$ -$ 470,648.00$ 470,648.00$ -$ 470,648.00$ -$ -$
0600-0000 Miscellaneous Project Costs
94 0601-0000 Utility Company Fees 280,000.00 280,000.00 3,009.57 3,009.57 - - 276,990.43
95 0602-0000 Testing Services 300,000.00 300,000.00 110,000.00 11,010.01 98,989.99 - 190,000.00
96 0603-0000 Swing Space / Modulars - - - - - - -
97 0699-0000 Other Project Costs (Mailing & Moving) 200,000.00 200,000.00 - - - - 200,000.00
0600-0000 Miscellaneous Project Costs Subtotal 780,000.00$ -$ 780,000.00$ 113,009.57$ 14,019.58$ 98,989.99$ -$ 666,990.43$
0700-0000 Furnishings and Equipment
99 0701-0000 Furnishings 1,971,000.00 1,971,000.00 - - - - 1,971,000.00
0702-0000 Equipment
101 0703-0000 Computer Equipment 1,971,000.00 1,971,000.00 - - - - 1,971,000.00
Furnishings and Equipment Subtotal 3,942,000.00$ -$ 3,942,000.00$ -$ -$ -$ -$ 3,942,000.00$
103 0507-0000 Owner's Construction Contingency 4,012,002.00 (101,941.00) 3,910,061.00 - - - - 3,910,061.00
104 0801-0000 Owners' (soft cost) Contingency 802,400.00 802,400.00 - - - - 802,400.00
Contingency Subtotal 4,814,402.00$ (101,941.00)$ 4,712,461.00$ -$ -$ -$ -$ 4,712,461.00$
Total Project Budget 102,967,198.00$ -$ 100,462,801.25$ 89,706,694.80$ 14,566,031.62$ 75,140,663.18$ -$ 13,224,410.20$
PROJECT MANAGEMENT
UPDATED: 3/16/2016
NEW HOLBROOK PREK-12 SCHOOL, HOLBROOK, MASSACHUSETTS
Change Order Budget Summary
Change
Order No.
Change Order
Amount
Owner's Contingency
Budget
4,012,002.00$ Original PFA Budget
1 (19,298.00)$ CR-001
2 (924.00)$ CR-003, CR-004, CR-005, CR-006
3 44,268.00$ CR-008, CR-009
4 74,261.00$ CR-002, CR-010, CR-013, CR-014, CR-015, CR-017
5 3,634.00$ CR-018
6 NA
7 93,881.00$
CR-019, CR-021, CR-022, CR-023, CR-026, CR-028,
CR-029, CR-033, CR-037
Change Order
Total
Budget
Total
Budget
Balance
TOTAL 195,822.00$ 4,012,002.00$ 3,816,180.00$
GMP Contingency Transfer Budget Summary
Change
Order No.
Contingency Transfer
Amount
GMP Contingency
Budget
273,972.00$ Amendment No. 1
1 NA
2 (56,915.00)$ CT-003; CT-004
3 19,569.00$ CT-001; CT-002
4 27,240.00$ CT-009; CT-010; CT-012
231,210.00$ Amendment No. 2
154,304.00$ Amendment No. 3
5 NA
1,788,807.00$ Amendment No. 4A
6 77,812.00$ CT-006, CT-008, CT-016, CT-017, CT-019
7 4,317.00$ CT-020
Contingency Transfer
Total
GMP Contingency
Total
Contingency
Balance
TOTAL 72,023.00$ 2,448,293.00$ 2,376,270.00$
Allowance Transfer Budget Summary
Change
Order No.
Allowance Transfer
Amount
Allowance Transfer
Budget
376,500.00$ Amendment Nos. 1 through 3
1 NA
2 NA
3 NA
4 NA
5 17,674.00$ AT-001, AT-002, AT-003, AT-004
597,440.00$ Amendment No. 4A
6 75,337.00$
AT-005, AT-007, AT-008, AT-009, AT-010, AT-011, AT-
014, AT-015, AT-016, AT-017
7 NA
Allowance Transfer
Total
Allowance Transfer
Budget
Allowance Transfer
Balance
TOTAL 93,011.00$ 973,940.00$ 880,929.00$
1 OF 1
Change Order
Date:
Project:
Consigli Construction Co., Inc.72 Sumner StreetMilford, MA 01757
1484 Holbrook - New PreK-12 School
7
3/15/2016
To Contractor:
Holbrook, MA 02343245 South Franklin Street
Change Order:
The Contract is changed as follows:
Owner Change Order #7
BT002-P1 Temp. Parking Lot Striping $0.00
CR019-P4 PR#006 - Lintels at South Side Gym Wall $0.00
CR021-P4 PR#008.3 - Door Schedule Clarification $14,926.00
CR022-P4 PR#009 - GWB Location Clarifications $14,224.00
CR023-P4 PR#011 - Curtainwall Dimension Revisions $7,750.00
CR026-P4 PR#014 - Fixed Louver and Precast Sill $179.00
CR028-P4 PR#016.1 - Additional Spray Fireproofing $12,585.00
CR029-P4 PR#017 - Modifications to Mechanical Doghouse at West Wall Gym $2,063.00
CR033-P4 PR#021 - Change to Cast Iron Closers - Entire Project $5,946.00
CR037-P4 OAL16r1 - Change in Accepted Bid for Tile Work $36,208.00
CT020-P1 Temp. Drainage Connection $0.00
$93,881.00 Total:
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
Town of Holbrook
OWNERARCHITECT CONTRACTOR
Consigli Construction Co., Inc.
The Contract Time will be unchanged.
$78,135,643.00
$78,331,465.00
The original Contract Amount was
Net change by previously authorized Change Orders
The Contract Amount prior to this Change Order was
The Contract will be increased by this Change Order in the amount of
The new Contract Amount including this Change Order will be
$101,941.00
$78,237,584.00
77 North Washington Street
Holbrook, MA 02343
50 North Franklin Street
Boston, MA 02114
72 Sumner Street
Milford, MA 01757
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
$93,881.00
Page 1 of 1
Consigli Construction Co., Inc.
Construction Managers and General Contractors
72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Change Order #7 3/16/2016 BT002-P1 Temp Parking Lot Striping CR019-P4 PR006 Lintels at South Side Gym Wall CR021-P4 PR008.3 Door Schedule Clarifications CR022-P4 PR009 GWB Location Clarifications CR023-P4 PR11 Curtainwall Dimension Revisions CR026-P4 PR14 Fixed Louver and Precast Sill CR028-P4 PR16.1 Additional Spray Fireproofing CR029-P4 PR17 Modifications to Mechanical Doghouse at West Wall Gym CR033-P4 PR21 Change Cast Iron Closers – Entire Project CR037-P4 OAL16r1 Change Accepted Bid for Tile Work CT020-P1 Temp Drainage Connection BT002-P1 Temp Parking Lot Striping Additional striping and numbers for the temp parking lot related to the additional signage and traffic flow clarifications requested by the owner. CR019-P4 PR006 Lintels at South Side Gym Wall This was due to coordination of early structural steel design package to the final architectural openings at the CMU bearing wall at the north side of the cafeteria area. CR021-P4 PR008.3 Door Schedule Clarifications The final bid door schedule had inconsistencies related to door finishes, sizes, hardware and ratings. The changes were necessary to provide consistency of door finishes (wood finishes rather than painted steel doors), and to provide wider corridor openings at cross corridor doors to coordinate with the structural concrete openings. Some rated stair doors clarified that their glass transoms needed to be rated which resulted in glass changes. Hardware was revised where doors were changed. This a very small percentage of changes per the number of doors. CR022-P4 PR009 GWB Location Clarifications This clarifies the intent of the south wall of the STEAM area and minor exposed walls in the Cafeteria in order to provide a consistent finished appearance. CR023-P4 PR11 Curtainwall Dimension Revisions Additional mullions were added at some curtainwalls to align with ceiling heights. Curtainwall submittals have been returned. CR026-P4 PR14 Fixed Louver and Precast Sill The louver is required to finish an exhaust duct shown on the mechanical drawings and the precast sill replaces a brick sill in order to be consistent with other windows in similar locations. CR028-P4 PR16.1 Additional Spray Fireproofing This is a required coordination of the early structural drawings package with the final architectural plans, which resulted in additional beams needing fireproofing than anticipated at the time of the structural bids.
CR029-P4 PR17 Modifications to Mechanical Doghouse at West Wall Gym These modifications are necessary due to coordination of the early structural drawings and the final mechanical and architectural plans. CR033-P4 PR21 Change Cast Iron Closers – Entire Project The project specified heavy duty cast aluminum closers The school had requested heavy duty closers, but intended that request to be the heaviest duty closer available. Cast iron is considered more heavy duty and the closers are being changed to reflect the request of the school. CR037-P4 OAL16r1 Change Accepted Bid for Tile Work The original tile filed-sub bidder made a mathematical error and withdrew their bid. The second lowest bidder has agreed to accept the project. This change reflects the cost difference from the lowest to the second lowest bidder’s pricing. CT020-P1 Temp Drainage Connection This change was required to provide drainage of site water during the construction phase from new work until the final detention structure connection can be completed.
Budget Transfer Request
Phone:
Job: 1484 Holbrook - New PreK-12 School
Number:
Date:
BT002-P1
1/28/16
To: Joel G. Seeley AIA
Symmes Maini & Mckee
Ph: (617)520-9403 Fax: (800)648-4920
Description: Temp. Parking Lot Striping
We offer the following specifications and pricing to make the changes as described below:
This budget transfer is being submitted for the cost of temp. striping 110 parking stalls with one coat of paint.
Description Material Subcontract Other PriceLabor Equipment
J. Derenzo COR#22, dated 11/13/15 $1,298.00$1,298.00
Temporary walkway - J. DerenzoCOR#22, dated 11/13/15
$-1,298.00$-1,298.00
$0.00Subtotal:
$0.00Fee (5%)
$0.00SDI (1.4%)
$0.00GL (1.2%)
$0.00Builders Risk (.1%)
$0.00P&P Bond (.75%)
$0.00Total:
SCHEDULE IMPACT
We have proceeded with this change to achieve schedule.
As directed, we will not proceed with this change until formal direction from OWNER is received.
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
OWNERARCHITECT CONTRACTOR
Milford, MA 01757
72 Sumner Street
Consigli Construction Co., Inc.
Boston, MA 02114
77 North Washington Street
Flansburgh Associates, Inc
Holbrook, MA 02343
50 North Franklin Street
Timothy Vautour
Page 1 of 1Consigli Construction Co., Inc.
Construction Managers and General Contractors72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Change Request
Phone:
Job: 1484 Holbrook - New PreK-12 School
Number:
Date:
CR021-P4
3/7/16
To: Joel G. Seeley AIA
Symmes Maini & Mckee
Ph: (617)520-9403 Fax: (800)648-4920
Description: PR#008.3 - Door Schedule Clarification
We offer the following specifications and pricing to make the changes as described below:
Change Request CR021-P4 is being submitted for the following worked added and altered in the Proposal Requests up to and
including the lastest revision, PR#008.3 – “Door Schedule Clarifications”:
References: A10.00, A10.01A-C
1. Kelley Brother's will furnish the inventory for the revised hardware schedule. The changes up to and included in PR#008.2 were
captured as an Credit Alternate of -($6,900) per OAL#09. The changes made to the hardware schedule from PR#008.2 to
PR#008.3, which included:
a) Deleting Openings A102A and C102A,
b) Increasing the door size of C119 and C200 from 6' to 6'-6" and
c) changing doors S2-01, S2-02, S3-01, S3-02, S7-01 and S7-02 from MTL to WD
resulted in a change ammount of $14,092, per Kelley Brother's CP#3 . The net changes listed above resulted in a net change of
$7,192 from Kelley Brother's.
2. Kapiloff's Glass will provide and furnish glazing for the revised hardware schedule.The revised hardware scheudle changed the
folowing square footage for glazing:
a) Glazing was increased or added to A209, B114, B136, B220, B22c, B222d, B223, 2xS5-02, S6-01, S6-02, and S6-04.
b) Glazing reduced or removed in B175a, B232, C212, C212a, and S6-03.
c) Glazing in C119, C200, S7-01 and S7-02 changed from annealed glass to Fire Resistant.
These changes resulted in a cost change of $6,554, per Kapiloff's Glass's COR#02.
Rev1 - 3/16/16 - Reduced price from Kapiloff's COR#02 to $6,554 from $6,609. Additional backup detailing the change in cost for
Kelley Brother's in CP#3.
Description Material Subcontract Other PriceLabor Equipment
Kelley Brothers, OAL#09, 1/5/16 $-6,900.00$-6,900.00
Kelley Brothers, CP#3, 2/26/16 $14,092.00$14,092.00
Kapiloff's Glass, COR#02, 3/7/16 $6,554.00$6,554.00
$13,746.00Subtotal:
$687.30Fee (5%) $13,746.00
$192.44SDI (1.4%) $13,746.00
$175.51GL (1.2%) $14,625.74
$13.75Builders Risk (.1%) $13,746.00
$111.11P&P Bond (.75%) $14,815.00
$-0.11$13,746.00
$14,926.00Total:
SCHEDULE IMPACT
We have proceeded with this change to achieve schedule.
As directed, we will not proceed with this change until formal direction from OWNER is received.
OWNERARCHITECT CONTRACTOR
Milford, MA 01757
72 Sumner Street
Consigli Construction Co., Inc.
Boston, MA 02114
77 North Washington Street
Holbrook, MA 02343
50 North Franklin Street
X
Page 1 of 2
Consigli Construction Co., Inc.
Construction Managers and General Contractors
72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Change Request
Phone:
Job: 1484 Holbrook - New PreK-12 School
Number:
Date:
CR021-P4
3/7/16
To: Joel G. Seeley AIA
Symmes Maini & Mckee
Ph: (617)520-9403 Fax: (800)648-4920
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
Flansburgh Associates, Inc Timothy Vautour
Page 2 of 2
Consigli Construction Co., Inc.
Construction Managers and General Contractors
72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Contingency Change Request
Phone:
Job: 1484 Holbrook - New PreK-12 School
Number:
Date:
CT020-P1
1/28/16
To: Joel G. Seeley AIA
Symmes Maini & Mckee
Ph: (617)520-9403 Fax: (800)648-4920
Description: Temp. Drainage Connection
In accordance with the contract terms, this Contingency Change Request will be funded from the construction manager's projectcontingency. Please consider this Contingency Change Request as formal notification of contingency use.
This contingency transfer is being issued for installing 66 lf of temporary 10" drain piping from the proposed drainage structure ICS#630 to the existing drain manhole located behind the existing school. This temporary drainage measure was approved by NitschEngineering.
Description Material Subcontract Other PriceLabor Equipment
J. Derenzo COR#29, dated 1/4/16 $4,317.00$4,317.00
Contingency - J. Derenzo COR#29,dated 1/4/16
$-4,317.00$-4,317.00
$0.00Subtotal:
$0.00Fee (5%)
$0.00SDI (1.4%)
$0.00GL (1.2%)
$0.00Builders Risk (.1%)
$0.00P&P Bond (.75%)
$0.00Total:
SCHEDULE IMPACT
We have proceeded with this change and use of contingency to achieve schedule.
As directed, we will not proceed with this change and use of contingency until formal direction from OWNER is received.
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
OWNERARCHITECT CONTRACTOR
Milford, MA 01757
72 Sumner Street
Consigli Construction Co., Inc.
Boston, MA 02114
77 North Washington Street
Flansburgh Associates, Inc
Holbrook, MA 02343
50 North Franklin Street
Timothy Vautour
Page 1 of 1Consigli Construction Co., Inc.
Construction Managers and General Contractors72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Page 1 of 3
TO: Director of Capital Planning
FROM: Superintendent Patricia Lally
Holbrook Public Schools
New Holbrook PreK-12 School
MSBA Project ID Number: 200801330505
DATE: March 16, 2016
RE: Project Funding Agreement Budget Revision Request, NUMBER: 8
Pursuant to Section 3.6 of the Project Funding Agreement between the TOWN OF HOLBROOK, MASSACHUSETTS (the “District”) and the MASSACHUSETTS SCHOOL BUILDING AUTHORITY (the “Authority”), the District hereby requests a revision to the Total Project Budget, Exhibit A, dated October 23, 2014, for the New Holbrook PreK-12 School. As required, the District has provided the information outlined in the table below to indicate the Total Project Budget categories (line items) affected, the amounts needed and the reasons for the proposed revision.
The District acknowledges and agrees that it will not seek reimbursement from the Authority for any costs that exceed the already approved line item limits set forth in Exhibit A until after the Authority has accepted this Total Project Budget Revision Request, and the Authority’s ProPay system has been adjusted accordingly.
The District further acknowledges and agrees that in accordance with Sections 3.6 and 3.7 of the Project Funding Agreement, any revisions to the Total Project Budget will not result in an increase to the Total Facilities Grant amount set forth in Section 2.1 of the Project Funding Agreement.
The District further acknowledges and agrees that the need for these revisions to the Total Project Budget have been identified in the OPM monthly report as required pursuant to the Contract for Owner’s Project Management Services between the District and the OPM.
The District further acknowledges and agrees that all of the information contained in this Total Project Budget Revision Request has been reviewed and approved by Permanent School Building Committee, and it further certifies and acknowledges that the funds to pay for the costs associated with these proposed revisions are available as indicated by the signatures noted below.
Use Table 1 for identification of expenditures against the Owner’s contingency. The Total Owner’s Contingency in the Current Total Project Budget, Exhibit A of the PFA dated January 8, 2015 is $802,400.00.
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Owner’s Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
$802,400
Page 2 of 3
Use Table 2 for identification of expenditures against the Construction Contingency. The Total Construction Contingency in the Current Total Project Budget, Exhibit A of the PFA January 8, 2015 is $4,012,002.00
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Construction Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
0507-0000 Owner’s Construction Contingency
0508-0000 Change Orders $93,942.00 Change Order No. 7, dated March 16, 2016 $3,816,119.00
Use Table 3 for identification of expenditures against the Allowances.
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Construction Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
0502-0030 GMP Construction Contingency
0502-3200 Exterior Improvements
$1,298.00 BT-002 was included in Change Order No. 7
0502-0030 GMP Construction Contingency
0502-3300 Utilities $4,317.00 CT-020 was included in Change Order No. 7
Page 3 of 3
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Matthew V. Moore
Title: Chief Executive Officer
Date: March 16, 2016
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Patricia Lally
Title: Superintendent of Schools
Date: March 16, 2016
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Arthur George
Title: Chair of the School Committee
Date: March 16, 2016
MASSACHUSETTS SCHOOL BUILDING AUTHORITY
________________________________________
By:
Title: Director of Capital Planning
Date: __________________________________ P:\2013\13006\00-INFO\0.9 Budget Revisions\PFA Budget Revision Requests\PFA_BudgetRevisionRequestNo.8_16March2016\MASTER PFA Budget Revision Request Rev 8.doc
REVERSE VE ORDER OF MAGNITUDE ESTIMATE3/16/2016
Description Takeoff Qty Total Cost/Unit Total Amount Original VE Total
VM 0911 - PorcTile in lieu of Vinyl Plank at 6-12 Cafeteria (4,000 sf only)
Vinyl plank flooring -2900 7.5 /sf (21,750.00) Porcelain floor tile at lobby 2900 25 /sf 72,500.00 10 % Design Cost 10% 5,075.00
PorcTile in lieu of Vinyl Plan at 6-12 Cafeteria (4,000 sf only) 55,825.00 40,000
VM 3303 - Change Bitmuinous Bus Driveway to Concrete
Remove Existing Binder & Regrade East 3,680 sf 3.03 /sf 11,150.40 Additoinal Soil Export (Grading for Concrete) 310 cy 12 /cy 3,720.00 Driveway Binder Course -1240 sy 11 /sy (13,640.00) Driveway Top Course -1450 sy 6.65 /sf (9,642.50) Bituminous WAL -210 tn 115 /tn (24,150.00) Concrete drive (x/L12) ‐ redimix 8" +10% 362 cy 130 /cy 47,060.00 Concrete drive ‐ place and finish 13320 sf 3.10 /sf 41,292.00 Edge form ‐ 8" 240 lf 16 /lf 3,840.00 WWM of above 13320 sf 0.20 /sf 2,664.00 10% Design Cost 10% 6,229.39
Change Bituminous Bus Driveway to Concrete 68,523.29 49,450
VM 3307 - Change Portions of Walks from Bituminous to Concrete
Bituminous paving walk -1628 sy 28 /sy -45,584.00Concrete sidewalk (x/L12) ‐ redimix 4" +20% 217 cy 120 /cy 26,040.00Concrete sidewalk ‐ place and finish 14,650 sf 3.1 /sf 45,415.00Edge form ‐ 8" 2,442 lf 16 /lf 39,072.00WWM of above 14,650 sf 0.2 /sf 2,930.0010% Design Cost 10% 6,787.30
Change Portions of Walks from Bituminous to Concrete 74,660.30 28,813
VM 3330 - Add (4) Dug-outs
Split face, cmu at dugout ‐ say 9'h 828 sf 26 /sf 21,528 Dug‐out roof structure 960 sf 25 /sf 24,000 Dug‐out roof 960 sf 12 /sf 11,520 10% Design Cost 10% 5,705
62,753 57,048
VM 3340 - 40% Increase of Plantings
Increase plantings 40% 887,170.00 354,868 10% Design Cost 10% 35,486.80
40% Increase of Plantings 390,355 228,000
20' X 40' Storage Shed
20'x40' Pre-engineered Insulated Metal Building 10' High Clear - 1 access door (1) 8x8 OH door
1 EA 40,250.00 /ea 40,250.00
Concrete Slab with Haunched Perimeter 60 cy 130.00 /cy 7,800.00
Place & Finish Slab 800 sf 3.10 /sf 2,480.00
Add (4) Dug-outs
REVERSE VE ORDER OF MAGNITUDE ESTIMATEEdge Form Haunch 120 lf 25.00 /lf 3,000.00
Reinforcing of Slab 800 sf 1.50 /sf 1,200.00
Excavate & Backfill SOG 924 sy 16.26 /sy 15,027.28
Dense Grade 64 tn 12.25 /tn 784.00
3/4" Crushed Stone 15 tn 13.00 /tn 195.00
Additional Soil Export 100 cy 12.00 /cy 1,200.00
Underground Electrical Service (Assumed Distance) 100 lf 29.00 /lf 2,900.00
Lighting & Receptacles (Allowance) 800 sf 10.00 /sf 8,000.00
Excavation & Backfill for Electrical Service (Assumed Distance)
100 lf 53.00 /lf 5,300.00
Area Restoration 1 ls 5,000.00 /ls 5,000.00
Sitework/Grading (Allowance) 1 ls 10,000.00 ls 10,000.00
10 % Design Cost 1 ls 10% 9,313.63
20' X 40' Storage Shed 1 112,449.91 235,144
20' X 40' Storage Shed
20'x40' Pre-engineered Insulated Metal Building 10' High Clear - 1 access door (1) 8x8 OH door
1 EA 40,250.00 /ea 40,250.00
Concrete Slab with Haunched Perimeter 60 cy 130.00 /cy 7,800.00
Place & Finish Slab 800 sf 3.10 /sf 2,480.00
Edge Form Haunch 120 lf 25.00 /lf 3,000.00
Reinforcing of Slab 800 sf 1.50 /sf 1,200.00
Excavate & Backfill SOG 924 sy 16.26 /sy 15,027.28
Dense Grade 64 tn 12.25 /tn 784.00
3/4" Crushed Stone 15 tn 13.00 /tn 195.00
Additional Soil Export 100 cy 12.00 /cy 1,200.00
Underground Elecrtical Service (Assumed Distance) 100 lf 29.00 /lf 2,900.00
Lighting & Receptacles (Allowance) 800 sf 10.00 /lf 8,000.00
Excavation & Backfill for Electrical Service (Assumed Distance)
100 lf 53.00 /lf 5,300.00
Area Restoration (Allowance) 1 ls 5,000.00 ls 5,000.00
Sitework/Grading (Allowance) 1 ls 10,000.00 ls 10,000.00
10% Design Cost 1 ls 10% ls 9,313.63
20' X 40' Storage Shed 2 112,449.91 0
REVERSE VE TOTAL 877,016.01 638,455.00
From: Traniello, SarahTo: "Barbara Davis ([email protected])"; "Beth Tolson ([email protected])"; Christian Riordan -
Consigli; Daniel F. Moriarty ([email protected]); David Curry - Consigli; "Fred White ([email protected])"; "James Day ([email protected])"; John Laperle - Consigli; Kent Kovacs - Flansburgh; Marjorie Godfrey ([email protected]); Matthew Moore ([email protected]); Mike Bolger - HPS; Patricia Lally; "Peter Mahoney ([email protected])"; Phil Brault - Consigli; Scott R. Towne; Seeley, Joel ([email protected]); "Tom Taylor ([email protected])"; Vince Dube - Flansburgh; "[email protected]"; "Vautour, Timothy"; "Tim Gordon"; "[email protected]"
Subject: FW: PSBC Role Documents PNUM: 13006 - HOLBROOK: NEW PREK-12 SCHOOLDate: Wednesday, March 16, 2016 12:26:00 PMAttachments: 20160307182701340.pdf
All, The role of the PSBC, relative to the new school facility, has been a topic of discussion at the PSBC meetings. The attachment contains the following three documents: -History of the PSBC via Town Meeting article (1961-present) (pages 1-4)-Statutory overview and opinion from Holbrook School Committee Counsel (Stoneham, Chandler and Miller) (pages 5-6)-Legal opinion from Town Counsel (Murphy, Hesse, Toomey) (pages 7-10) Bottom-line: The PSBC Town Meeting votes (over the years) do not address on-going maintenance. We could bring an article to TM for a consolidated facilities maintenance function, however, this would need to be voted favorably by the School Committee in order to implement it. This will be discussed at Wednesday’s PSBC meeting. Tim Timothy GordonTown Administrator Town of Holbrook50 North Franklin StreetHolbrook, MA 02343Telephone: 781-767-4312 Fax: [email protected]
Holbrook…moving forward
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:/o=SMMA/ou=First Administrative Group/cn=Recipients/cn=JoelSmailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]://www.holbrookma.gov/Consigli Construction Co., Inc.72 Sumner StreetMilford, MA 01757
OAL # Trade Vendor
Date Submitted Status
Date Approved
DaysOut
GMPBudget Hold Amount
SubAmount
Buy / (Bust) $
Buy / (Bust) %
1 Early Site Electrical Systems Approved #VALUE! 54,600$ -$ 54,600$ -$ 0.00%
2 Site Work Subcontractor J Derenzo Approved #VALUE! 8,340,000$ -$ 8,340,000$ -$ 0.00%
3 Temp Fencing Steelco Approved #VALUE! 118,459$ -$ 118,459$ -$ 0.00%
4 Structural Steel Subcontractor Trimax Approved #VALUE! 3,683,750$ -$ 3,683,750$ -$ 0.00%
5 Concrete Subcontractor JL Marshall Approved #VALUE! 3,143,600$ -$ 3,143,600$ -$ 0.00%
6 Early Site Landscaping Greenscape Approved #VALUE! 131,000$ -$ 131,000$ -$ 0.00%
7 Masonry (TC) Lighthouse Approved #VALUE! 3,377,000$ -$ 3,377,000$ -$ 0.00%
8 Spray Fireproofing RicMor 12/22/15 Approved 01/07/16 16 35,700$ -$ 37,000$ (1,300)$ -3.64%
9 DFH Riggs/Kelley Brothers 01/06/16 Approved 01/07/16 1 593,610$ -$ 592,664$ 946$ 0.16%
10 Kitchen Equipment Kittredge 01/26/16 Approved 01/29/16 3 521,778$ -$ 528,000$ (6,222)$ -1.19%
11 Misc. Metals Heritage Iron 01/21/16 Approved 01/21/16 0 1,540,000$ -$ 1,540,000$ -$ 0.00%
12 Waterproofing Chapman 12/23/15 Approved 01/07/16 15 676,100$ -$ 676,100$ -$ 0.00%
13 Roofing Greenwood 12/23/15 Approved 01/07/16 15 2,164,000$ -$ 2,164,000$ -$ 0.00%
14 Metal Windows Lockheed Window 12/23/15 Approved 01/07/16 15 2,297,000$ -$ 2,297,000$ -$ 0.00%
15 Glass and Glazing Kapiloff Glass 12/23/15 Approved 01/07/16 15 128,550$ -$ 128,550$ -$ 0.00%
16 Tile West Flooring 02/22/16 Approved 02/25/16 3 560,000$ -$ 560,000$ -$ 0.00%
17 Acoustical Tile K&K Acoustical 12/23/15 Approved 01/07/16 15 595,442$ -$ 595,442$ -$ 0.00%
18 Resilient Flooring West Flooring 12/23/15 Approved 01/07/16 15 722,459$ -$ 722,459$ -$ 0.00%
19 Painting King Painting 12/23/15 Approved 01/07/16 15 467,000$ -$ 467,000$ -$ 0.00%
20 Elevator Delta Elevator Service Corp. 12/23/15 Approved 01/07/16 15 271,000$ -$ 271,000$ -$ 0.00%
21 Fire Protection Tyco/Simplex Grinnel 12/23/15 Approved 01/07/16 15 815,900$ -$ 815,900$ -$ 0.00%
22 Plumbing Araujo Bros. 12/23/15 Approved 01/07/16 15 2,496,000$ -$ 2,496,000$ -$ 0.00%
23 HVAC N.B. Kenney 12/23/15 Approved 01/07/16 15 6,757,000$ -$ 6,757,000$ -$ 0.00%
24 Electrical Wayne J. Griffin 12/23/15 Approved 01/07/16 15 7,059,000$ -$ 7,059,000$ -$ 0.00%
25 Wall Panels Riggs 01/19/16 Approved 01/21/16 2 3,390,720$ -$ 3,373,400$ 17,320$ 0.51%
26 OH Doors & Loading Dock Equip Baron Industries 01/21/16 Approved 01/28/16 7 23,400$ -$ 21,600$ 1,800$ 7.69%
27 Metal Lockers Manganaro Northeast 01/25/16 Approved 01/28/16 3 157,000$ -$ 137,000$ 20,000$ 12.74%
28 Resinous Flooring Kaloutas Co 01/21/16 Approved 01/28/16 7 114,038$ -$ 112,750$ 1,288$ 1.13%
29 Folding Partitions The Pappas Company 01/26/16 Approved 01/28/16 2 100,500$ -$ 101,000$ (500)$ -0.50%
30 Drywall TJ McCartney 02/02/16 Approved 02/04/16 2 4,930,344$ -$ 4,920,100$ 10,244$ 0.21%
31 Fixed Audience Seating CB Seating 02/10/16 Approved 02/17/16 7 99,000$ -$ 94,900$ 4,100$ 4.14%
32 Wood Flooring Towne & Country Wood Flooring 02/02/16 Approved 02/04/16 2 308,415$ -$ 279,705$ 28,710$ 9.31%
33 Carpet & Entrance Mats Allegheny 02/10/16 Approved 02/17/16 7 174,804$ -$ 171,815$ 2,989$ 1.71%
34 Finish Carpentry Riggs/General Wood Working 02/10/16 Approved 02/17/16 7 1,332,045$ -$ 1,384,152$ (52,107)$ -3.91%
35 Manufactured Casework Northeast Interior Systems 02/10/16 Approved 02/17/16 7 1,144,820$ -$ 1,144,820$ -$ 0.00%
36 Acoustical Wall Treatments New England Interior Specialties 02/22/16 Approved 02/25/16 3 119,200$ -$ 109,000$ 10,200$ 8.56%
37 Sound Reflective Ceiling Panels New England Interior Specialties 02/22/16 Approved 02/25/16 3 78,000$ -$ 77,000$ 1,000$ 1.28%
Owner Approval LogHolbrook K-12 School
As of: 3/11/16
1484 Holbrook - OAL Log Page 1 of 2 3/18/2016
Consigli Construction Co., Inc.72 Sumner StreetMilford, MA 01757
OAL # Trade Vendor
Date Submitted Status
Date Approved
DaysOut
GMPBudget Hold Amount
SubAmount
Buy / (Bust) $
Buy / (Bust) %
Owner Approval LogHolbrook K-12 School
As of: 3/11/16
38 Window Treatments Manganaro Northeast 144,126$ 51,200$ 92,196$ 730$ 0.51%
38 Specialties Manganaro Northeast 136,538$ 10,000$ 110,802$ 15,736$ 11.52%
38 Visual Display Boards Manganaro Northeast 113,690$ 11,900$ 87,801$ 13,989$ 12.30%
38 Projetions Screens Manganaro Northeast 33,400$ -$ 27,201$ 6,199$ 18.56%
Landscaping & Site Improvements 1,038,264$
Baseball & Softball Mix 159,390$
Athletic Equipment 191,055$
Stage Curtain and Rigging 253,869$
Signage 243,885$
Bleachers & Press Box 190,020$
Site Concrete 856,700$
Play Equipment 151,000$
Exterior Play Surfacing 287,167$
Synthetic Field Sport Surfacing 600,000$
Fencing 537,936$
Building Demo & Abatement 1,005,000$
Staging at Auditorium 80,000$
Totals to Date: 64,543,274 73,100 58,800,766 75,122 0.12%
Hard Cost of WorkNon-Procurred Hard Costs (i.e. Allowances, Amendment #3) 0.40%
Trade Support 840,000 840,000 Access Doors 10,000 10,000
Cost of Work to Buy #VALUE! 64,543,274 Cost of Work Bought 91.10%
Allowances Held 73,100 Savings 0.12%
Balance to Buy 8.67%
58,800,766
75,122 5,594,286
65,657,362 264,088
1484 Holbrook - OAL Log Page 2 of 2 3/18/2016
SOUTH FRANKLIN STREET
B 2ND FLOOR MASONRY IN PROGRESS
A 2ND FLOOR DECK PLACED
C FIRST FLOOR STEEL IN PROGRESSA
B
COURTYARD
APRIL LOOK AHEAD
TOPPING OFF - APRIL 19TH
START BUILDING A AVB
INSTALL BUILDING A ROOF DRAIN PIPING
PLACE SLAB ON DECK FOR BUILDING C
C
MAJOR CONSTRUCTION MILESTONES(NEXT 6 MONTHS)
SLAB ON DECK COMPLETE (ALL BLDGS) 05/04/16STEEL ERECTION COMPLETE (ALL BLDGS) 05/19/16C2 METAL WALL FRAMING COMPLETE 06/21/16B2 METAL WALL FRAMING COMPLETE 06/22/16ROOF TIGHT (ALL BLDGS) 07/01/16EXTERIOR SHEATHING/AVB COMPLETE (ALL BLDGS) 07/05/16A2 MEP/FP ROUGH COMPLETE 07/26/16
MARCH PROGRESS UPDATE03/16/16
A B
COURTYARD
UPCOMING PROCUREMENT
ACOUSTICAL WALL TREATMENTS
SIGNAGE
STAGE CURTAINS & RIGGING
PLAYGROUND PROTECTIVE SURFACING
FOOTBALL FIELD SURFACING
FENCING
LANDSCAPING & SITE IMPROVEMENTS
BASEBALL & SOFTBALL INFIELD MIX
SITE CONCRETE
C
MEP/FP COORDINATION
B UNDERGROUND
COORDINATIONSUBMISSION
AREA
A UNDERGROUND
ELEC & TEL/DATA PENDING SUBMITTALREVIEWMECHANICAL ROOM SUBMITTED
SUBMITTED
SUBMITTED
SUBMITTEDA SLAB SLEEVES(2ND FL)
A FIRST FLOOR (OH)A BLDG RAINLEADERS
3/11/16
3/14/16
C FIRST FLOOR (OH) 4/11/16
MARCH PROGRESS UPDATE03/16/16
Agenda_16March2016withAttachments_HANDOUT.pdfHolbrook- Holbrook Jr-Sr HS CO 1-4 + GMP Continengency Review Letter.pdfHolbrook- Holbrook Jr-Sr HS CO 1-4 + GMP Continengency Review LetterHolbrook- Holbrook Jr-Sr HS CO LogHolbrook- Holbrook Jr-Sr HS GMP Continengency Expenditure Log
Blank Page
Holbrook Logistics_March Update Rev 1.pdfSheets03D1 - March Progress03D2 - March Summary