Progress of Hyderabad Metro Rail With the completion of the Hyderabad Metro Rail, the city of Hyderabad will join other elite cities of the world with its very own Mass Rapid Transport System. Once completed, it is envisaged that the Metro Rail will convert Hyderabad into a most preferred city of the country, as it will offer seamless commuting across the city. Facts about the Hyderabad Metro Rail Project The Metro Rail network will cover a distance of 72 kilometres and it is divided into 3 corridors. Corridor I: Miyapur to L.B. Nagar (29 km; 27 Stations) Corridor II: JBS, Secunderabad to Falaknuma (15 km; 16 Stations) Corridor III: Nagole to Shilparamam (28 km; 23 Stations) The Metro Rail will provide ‘seamless travel’ facility through integration with the existing rail terminals, bus depots, MMTS stations and “Merry-go-round” feeder buses to nearby colonies and business areas/offices to offer comfortable, convenient and hassle-free travel across the City of Pearls. Highlights of the Hyderabad Metro Rail The three elevated corridors throughout the city will have Metro stations along the route at a distance of approximately 1 kilometer The stations will be environment-friendly with state-of-the-art facilities like lifts, escalators and staircases As the Metro Rail will pass through major roads of the city, it will provide seamless connectivity to commercial and residential areas as well as bus stations. Along the three corridors, parking and leisure areas will be developed on the land provided by the Government of Andhra Pradesh Progress of Hyderabad Metro Rail The following table shows the Corridor number and Corridor Location. Corridor Number Corridor Details Corridor I Miyapur to LB Nag Stage 2 Miyapur to S R Nag Stage 5 S R Nagar to L B Na Corridor II JBS to Falaknuma Stage 6 JBS to Falaknuma Corridor III Nagole to Shilpara

Progress of Hyderabad Metro Rail -OCTOBER 09, 2013

Embed Size (px)

DESCRIPTION

With the completion of the Hyderabad Metro Rail, the city of Hyderabad will join other elite cities ofthe world with its very own Mass Rapid Transport System.

Citation preview

Page 1: Progress of Hyderabad Metro Rail -OCTOBER 09, 2013

Progress of Hyderabad Metro Rail

With the completion of the Hyderabad Metro Rail, the city of Hyderabad will join other elite cities of

the world with its very own Mass Rapid Transport System. Once completed, it is envisaged that the

Metro Rail will convert Hyderabad into a most preferred city of the country, as it will offer seamless

commuting across the city.

Facts about the Hyderabad Metro Rail Project

The Metro Rail network will cover a distance of 72 kilometres and it is divided into 3 corridors.

Corridor I: Miyapur to L.B. Nagar (29 km; 27 Stations)

Corridor II: JBS, Secunderabad to Falaknuma (15 km; 16 Stations)

Corridor III: Nagole to Shilparamam (28 km; 23 Stations)

The Metro Rail will provide ‘seamless travel’ facility through integration with the existing rail

terminals, bus depots, MMTS stations and “Merry-go-round” feeder buses to nearby colonies and

business areas/offices to offer comfortable, convenient and hassle-free travel across the City of

Pearls.

Highlights of the Hyderabad Metro Rail

The three elevated corridors throughout the city will have Metro stations along the route at a

distance of approximately 1 kilometer

The stations will be environment-friendly with state-of-the-art facilities like lifts, escalators and

staircases

As the Metro Rail will pass through major roads of the city, it will provide seamless connectivity

to commercial and residential areas as well as bus stations.

Along the three corridors, parking and leisure areas will be developed on the land provided by

the Government of Andhra Pradesh

Progress of Hyderabad Metro Rail

The following table shows the Corridor number and Corridor Location.

Corridor Number Corridor Details

Corridor I Miyapur to LB Nagar

Stage 2 Miyapur to S R Nagar

Stage 5 S R Nagar to L B Nagar

Corridor II JBS to Falaknuma

Stage 6 JBS to Falaknuma

Corridor III Nagole to Shilparamam

Page 2: Progress of Hyderabad Metro Rail -OCTOBER 09, 2013

Stage 1 Nagole to Mettuguda

Stage 3 Mettuguda to Begumpet

Stage 4 Begumpet to Shilparamam

In many places the, concreting work for foundations and piers for the viaduct have finished and

barricading work is in progress. This includes Nagole to Mettuguda, Miyapur to S.R. Nagar

Mettuguda to Begumpet, and S.R. Nagar to L.B. Nagar. From Begumpet to Shilparamam,

confirmatory boreholes and trial pits are being dug and the work is in progress. So far 947

foundations, 782 piers, 335 spans and 5678 viaduct segments have been completed.

With regard to the stations, at Stage 1, which is from Nagole to Mettuguda, 60 piers have been

constructed; while for Stage 2, which is from Miyapur to S.R. Nagar, 53 piers have been completed

and for stage 5, which is from S R Nagar to L B Nagar, 33 piers have been constructed. For stages 3

and 4, trial pits and confirmatory boreholes are being dug and the work is going on as per schedule.