Upload
uri
View
47
Download
1
Embed Size (px)
DESCRIPTION
Progress of BEPCII Storage Ring Construction. Ma Li May 10, 2007. Design goal of BEPCII. The BEPCII serves the purposes of both high energy physics experiments and synchrotron radiation applications. Main Parameters of BEPCII. N. Layout of BEPCII. SC cavities. SC IR magnets. BESIII. - PowerPoint PPT Presentation
Citation preview
5th BEPCII IMAC Meeting - 1 - May 10 - 12, 2007
Progress of BEPCII Storage Ring Construction
Ma Li
May 10, 2007
5th BEPCII IMAC Meeting - 2 - May 10 - 12, 2007
The BEPCII serves the purposes of both high energy physics experiments and synchrotron radiation applications.
Design goal of BEPCII
5th BEPCII IMAC Meeting - 3 - May 10 - 12, 2007
Main Parameters of BEPCII
5th BEPCII IMAC Meeting - 4 - May 10 - 12, 2007
Layout of BEPCII
N
SC cavities
e+ inj. point e inj. point
SC IR magnets BESIII
5th BEPCII IMAC Meeting - 5 - May 10 - 12, 2007
Goal and schedule of ring in 2006/2007 Goal of 2006
– Complete the installation of all equipments (except superconducting IR magnets)
– Try to start the SR user operation
Scheduleplan achieved
2006/03/02 start installation of storage ring
2006/10/10 2006/11/12 start outer ring commissioning (backup scheme)
2006/11/09 2006/11/25 start SR beam line commissioning and user operation
2006/12/29 2007/02/06 start commissioning e ring
2007/01/26 2007/03/03 start commissioning e ring
2007/03/25 first beam collision (backup scheme)
2007/06/15 start SR user operation (backup scheme)
2007/02/23 2007/08/01 SCQs move into the IR (about 5-month delay)
2007/04/01 start commissioning e ring with SCQ
2007/04/21 start commissioning e ring with SCQ
2007/05/11 start commissioning for collision mode
5th BEPCII IMAC Meeting - 6 - May 10 - 12, 2007
Main tasks of the ring systems
Magnet 300-plus dipoles, quads, sextupols, correctors
Vacuum 200-plus chambers, 175 photon absorbers, 150 bellows …
Align & Install 84 pre-assembly magnet rafts, survey and align, install …
RF 2 SC cavities and PS, LLRF
IR 2 SC IR magnets, 10 special magnets, IR chamber …
AP lattice design, high-level software, beam instability study …
PS 300-plus PS, magnet coil temperature monitor …
Injection 4 injection kickers and PS
Control PSC/PSI, network, timing, database, software develop …
Instrumentation 138 BPM, DCCT, BCM, BLM, tune meter, TBF …
Pay more attention to critical paths
5th BEPCII IMAC Meeting - 7 - May 10 - 12, 2007
Critical path 1: Pre-assembly and installation
2006/02/end Complete all 80 arc chambers, including correction of 20 distorted chambers.2006/03/02 Start installation of the first magnet raft in the ring tunnel. Only 31 of 84 rafts (37%) had been completed at the time. According to schedule, 2 rafts have to be completed in 5 days. No weekend and holidays.2006/07/18 Start PS test and combined commissioning with magnets and control, in parallel with installation.2006/08/21 Complete TiN coating of 70 positron beam pipes
2006/09/10 Complete installation of last magnet raft in the ring tunnel
2006/10/29 Complete installation of all chambers and vacuum components
2006/11/09 Complete fine alignment of the ring magnets
2006/11/12 Start ring commissioning
5th BEPCII IMAC Meeting - 8 - May 10 - 12, 2007
Pre-assembly and pre-alignment
5th BEPCII IMAC Meeting - 9 - May 10 - 12, 2007
Alignment in the tunnel
5th BEPCII IMAC Meeting - 10 - May 10 - 12, 2007
Installation of vacuum components
5th BEPCII IMAC Meeting - 11 - May 10 - 12, 2007
5th BEPCII IMAC Meeting - 12 - May 10 - 12, 2007
Installation of magnet rafts
5th BEPCII IMAC Meeting - 13 - May 10 - 12, 2007
2006/03/26 East SC cavity assembly completed
2006/04/28 West SC cavity assembly completed
2006/06/30 Q0 of east SC cavity reached to 5.5×108 @2MV (design goal is 5×108)
2006/07/31 East SC cavity positioned and aligned in the ring tunnel
2006/08/26 Q0 of west SC cavity reached to 9.9×108 @2MV
2006/09/07 West SC cavity positioned and aligned in the ring tunnel
2006/10/29 East SC cavity conditioned to 1.5MV, in parallel with installation
2006/10/31 West SC cavity conditioned to 1.5MV, in parallel with installation
2006/11/04 Commissioning of east SC RF system completed and ready for beam
2006/11/12 Start ring commissioning
2007/02/26 West SC cavity put into operation with beam
S.Kurokawa, K.Hosoyama, T.Furuya, K.Akai, S.Mitsunobu of KEK came here many times during test and commissioning of SC cavities. Thanks a lot.
Critical path 2: superconducting RF system
5th BEPCII IMAC Meeting - 14 - May 10 - 12, 2007
Assembly and tunnel installation of superconducting cavity
5th BEPCII IMAC Meeting - 15 - May 10 - 12, 2007
LLRF installation and commissioning
5th BEPCII IMAC Meeting - 16 - May 10 - 12, 2007
Horizontal high power test of east superconducting cavity
5th BEPCII IMAC Meeting - 17 - May 10 - 12, 2007
2006/06/21 Q1a, Q1b, ISPB, Q2, Q3 passed acceptance test
2006/08/18 Two superconducting IR magnets cooled-down
2006/08/end Two superconducting IR magnets and PS, quench protection system tested.
The magnets are powered with 20-50% rated current.
PS and quench protection system showed a good performance.
Valve-box and current leads have to be modified.
2-Q and 1-B backup scheme was proposed to replace 2-B scheme.
2006/09/29 Two superconducting IR magnets moved out off the ring
2006/10/begin BPM welding on the OFHC IR chambers had some troubles.
Decide to fabricate substitutions of stainless steel chambers
for OFHC chambers.
2006/10/26 Complete fabrication of stainless steel IR chambers
2006/10/29 Complete installation of IR chambers and vacuum pumps
2006/11/05 Complete cable connections and chamber baking
2006/11/10 Complete combined commissioning of IR magnets, PS and control systems
2006/11/12 Start ring commissioning
Critical path 3: IR magnets and chambers
5th BEPCII IMAC Meeting - 18 - May 10 - 12, 2007
Installation superconducting IR magnets and valve-box
5th BEPCII IMAC Meeting - 19 - May 10 - 12, 2007
Horizontal test of superconducting IR magnets
5th BEPCII IMAC Meeting - 20 - May 10 - 12, 2007
Backup scheme with 2 dipoles (April, 2006)
With this 2-dipole backup scheme, the collision mode cannot be commissioned.
5th BEPCII IMAC Meeting - 21 - May 10 - 12, 2007
原有
2700X970X628(支架长X宽X )高 2700X970X628(支架长X宽X )高 1800X1200(长X )宽
东
南
西
北
原有
批准
R0版本号
A0
图 幅
审核
计算机文件名
设计编号 更改单 修改 更 改 内 容 日 期
中国科学院高能物理研究所 I HEP-BEPCI I
共 张
比 例1: 15
未注公差的尺寸
重 量
第 张
数 量对撞区设备布置图
1序号
2
绘 图
批 准
审 核 校 核
审 定 会 签
设 计
13 (GB1804-79)按 级公差 制造
绘图软件名AutoCAD2004
谱仪中心轴
2. 7长 M支架中心线
图 号 名 称 数量 备 注材料 总重12345
9876
141312
1011
序号
1800X1200(长X )宽
谱仪轨道钢板 谱仪轨道钢板
2对撞区代用方案
李春华
21
-对撞区总体 lch
R4 R3
束流中心
水泥支撑台 水泥支撑台
16171819
15
202122232425
ISPBQ1aQ1b ISPB Q1a Q1b
26
单重
I P对撞点
小B铁160Q 160Q
I P对撞点
BEPC magnet supports are used to saving time and cost
Change scheme with 2 quads and 1 dipole (September, 2006)
5th BEPCII IMAC Meeting - 22 - May 10 - 12, 2007
Installation of IR components
5th BEPCII IMAC Meeting - 23 - May 10 - 12, 2007
Systems not on the critical path
AP lattice design, high-level software, beam instability study …
Power Supply 300-plus PS, magnet coil temperature monitor …
Injection 4 injection kickers and PS
Control PSC/PSI, network, timing, database, software develop …
Instrumentation 138 BPM, DCCT, BCM, BLM, tune meter, TBF …
All efforts have been made to prevent these systems from becoming a new critical path.
5th BEPCII IMAC Meeting - 24 - May 10 - 12, 2007
impedance measurement solenoid for suppressing ECI
5th BEPCII IMAC Meeting - 25 - May 10 - 12, 2007
Commissioning and test of the magnet PS
5th BEPCII IMAC Meeting - 26 - May 10 - 12, 2007
Injection kickers and PS
5th BEPCII IMAC Meeting - 27 - May 10 - 12, 2007
Installation and commissioning of PS control system
5th BEPCII IMAC Meeting - 28 - May 10 - 12, 2007
Center control room
5th BEPCII IMAC Meeting - 29 - May 10 - 12, 2007
BPM
5th BEPCII IMAC Meeting - 30 - May 10 - 12, 2007
Synchrotron light monitor
5th BEPCII IMAC Meeting - 31 - May 10 - 12, 2007
Transverse beam feedback system
5th BEPCII IMAC Meeting - 32 - May 10 - 12, 2007
Step-by-step inspection performed before the commissioning
开机后发现仍然有差错– 内、外环电源搞错– 磁铁极性接反– 部分磁铁线包有短路
经验:不同人员反复检查
5th BEPCII IMAC Meeting - 33 - May 10 - 12, 2007
Milestone of ring commissioning2006/09/22 First meeting of the Ring Commissioning Group led by Jiuqing Wang
2006/11/12 Start ring commissioning
2006/11/18 First e beam storage in outer ring (SR ring)
2006/12/25 Start SR user operation
2007/02/02 Stop SR user operation
2007/02/09 First beam storage in e ring
2007/02/18 Spring Festival (7-day holiday)
2007/03/04 First beam storage in e ring
2007/03/25 First trial of beam collision at 6mA×6mA
2007/04/10 150mA ebeam current reached
2007/04/21 100mA ebeam current reached
Jiuqing will give detailed descriptions for the ring commissioning.
5th BEPCII IMAC Meeting - 34 - May 10 - 12, 2007
Equipment failures and problems 2007/1/2, 2007/4/26 and 2007/5/9, three primary windings of 10kV rectifier tran
sformer of ring main dipole magnet PS had broke down, respectively. There are 8 transformers, with 3 such windings each. It is quality problem.
2007/1/6, compressor of cryogenic system shut down due to power line failure, causing superconducting RF cavity warmed up to 40K. It was recovered 26 hours after.
2007/1/7, compressor of cryogenic system shut down due to water-cooling problem. It was recovered 20 hours after.
2007/2/11, cryogenic system failure, causing superconducting RF cavity warm up to 20K. It was recovered 17 hours after.
2007/2/13, compressor of cryogenic system shut down due to a misoperation. It was recovered 8 hours after.
2007/1/30, a quench happened during conditioning of east cavity. Pressure in cryostat up to 1.26bara threshold due to quench protection system was not functioned in 10ms, causing the safety valve opened. It was recovered 21 hours after.
During commissioning, RF trip frequently occurred by vacuum, arc, quench, klystron pump PS, and sometimes noise, 2-3 times per day on average.
Sometimes beam loss happened during the energy ramping from 1.89GeV to 2.5GeV.
5th BEPCII IMAC Meeting - 35 - May 10 - 12, 2007
Main tasks of ring in 2007 Hardware
– IR chambers (3 types of SCQ, Y-shape and ISPB chambers)
– Superconducting IR magnets (high power test, field measurement, installation)
– 14 fixed and 2 movable masks
Commissioning and operation
– Collision mode (backup scheme)
– One-month SR operation, beam lifetime 8-10 hours @150mA/2.5GeV
– Collision mode with superconducting IR magnets
5th BEPCII IMAC Meeting - 36 - May 10 - 12, 2007
Schedule of IR
2007/04/30-2007/05/10 SCQ and SSM cool-down2007/05/11-2007/06/03 cryogenic system commissioning and SCQ high power test2007/06/04-2007/07/31 SCQ field measurement with SSM2007/08/01-2007/08/22 move SCQ into IR2007/08/23-2007/09/21 SCQ field measurement in IR without detector2007/09/22-2007/10/10 install IR components
2007/10/11-2008/02/09 commissioning (4 months)2008/02/10-2008/03/20 SR user operation2008/03/21-2008/05/07 move BESIII detector into IR2008/05/08-2008/06/22 BESIII tuning2008/06/23-2008/12/31 BESIII physics operation
5th BEPCII IMAC Meeting - 37 - May 10 - 12, 2007
Modification of SC IR magnet valve-box and current leads
5th BEPCII IMAC Meeting - 38 - May 10 - 12, 2007
Superconducting IR magnets are ready for field measurement
5th BEPCII IMAC Meeting - 39 - May 10 - 12, 2007
SCQ chamber Y-shape
ISPB chamber
5th BEPCII IMAC Meeting - 40 - May 10 - 12, 2007
Open questions
When is the suitable time for installation of background masks?
The east superconducting cavity shows a different performance during commissioning of e ring. What is the reason?
Whether the phase-lock loop between master oscillators of the injector linac and the rings is necessary?
5th BEPCII IMAC Meeting - 41 - May 10 - 12, 2007
Summary
A big progress for the construction and commissioning of the BEPCII storage rings has been made since last IMAC meeting.
It took about 16 months to complete the installation of BEPCII rings (except the superconducting IR magnets and IR chambers) after the BEPC ring shut-down in July 4, 2005.
Commissioning of the BEPCII (with backup scheme) started in mid November 2006. It is useful for us to gain experience for the future commissioning with superconducting IR magnets.
Although there are some problems, basic equipments and devices of ring systems show a good performance during the half-year commissioning and operation.
The final test of the superconducting IR magnets with modified valve-box and current leads is in progress. Success of the test is very important to reach the goal of the BEPCII project in time.
5th BEPCII IMAC Meeting - 42 - May 10 - 12, 2007
Thank you for attentions !