Course Overview Prescience Technology is an Oracle Platinum Partner and specialist provider of Primavera Services. This Prescience course introduces the user to Oracle Primavera P6 Professional Client. It explores P6 navigation and core functionality and demonstrates how to build a project from start to finish. Course content incorporates the ‘best practice’ principles for project execution and management and is highly recommended to get you up and running with P6.
Course Structure & Certification This is a two-day Instructor Led Training (ILT) training course facilitated by P6 experts with wide industry experience.
It includes a number of learner activities and formal assessment along with easy-to-use learner materials designed to support during and beyond training.
Course Objectives
This course aims to:
1) Provide an introduction to Oracle Primavera P6 Professional as an Enterprise Portfolio Project Management (EPPM) tool
2) Demonstrate how to build a project in P6
3) Explore how to execute and optimise the project
4) Introduce and explore the Visualizer reporting tool
5) Equip the learner with a level of competency that enables them to use P6 in the workplace
Target Audience This course is aligned to the competency requirements of the new Primavera P6 Professional user.
PrerequisitesWhile there are no formal prerequisites, an understanding of project management and controls practices and terminology is expected.
Assessment The assessment of knowledge and skill development is based on the following:
• Progressive Interactive Learner Activities
• Formal Assessment at end of course
Primavera P6 Professional Fundamentals
Course Outline
Prescience Technology Primavera P6 Professional Fundamentals Course Outline 1
Module 1: Introduction to Primavera P6 Professional
Key Topics
• P6 as a Project Portfolio Management (PPM) tool
• Enterprise Project Structure (EPS) and Organisational Breakdown Structure (OBS)
• Enterprise Project Structure (EPS) and Organisational Breakdown Structure (OBS)
• Navigation of Main Menu and accessing P6 Help
• Enterprise vs Project Data
• Navigation of the Projects Window
• Open a Project
Learning Outcomes
1) Describe P6 as a Project Portfolio Management (PPM) tool
2) Understand the purpose of the Enterprise Project Structure (EPS) and the Organisational Breakdown Structure (OBS)
3) Login to P6 and navigate the Main Menu
4) Differentiate between Enterprise and Project data
5) Navigate the Projects Window
6) Open a Project
Learner Activity
• Login & navigate the Primavera Professional Homepage
• Open a project and review toolbars
Module 2: Building a Project
Key Topics
• Creating a Project
• Creating a Work Breakdown Structure
• Describe Activity Attributes and explain the use of the different Activity Types
• Add Activity Relationships
• Link Projects
Learning Outcomes
1) Creating a Project
2) Creating a Work Breakdown Structure
3) Understanding Activities
4) Creating Activity Relationships
5) Linking Projects
Learner Activities
• Create a new Project and Build the WBS
• Add Activities to a project
• Creating Activity Relationships
Module 3: P6 Calendars
Key Topics
• View and Create Calendars
• Assign Calendars to Activities
Learning Outcomes
1) View calendars using the Enterprise file option
2) Create Calendars
3) Assign Calendars to Activities
4) Assign a Project Default Calendar
Learner Activities
• Create and assign a calendar to an activity
Module 4: Resources
Key Topics
• Understand the Resource Breakdown Structure (RBS)
• Create New Resources
• Assign Resources
• View Resource Allocation
Learning Outcomes
1) Understand Resource Breakdown Structure (RBS)
2) Describe Resource classification in P6
3) Navigate the Resources page and explore detail tabs
4) Create and Assign a Resource to an activity
5) View Resource profile and assignments
Learner Activity
• Create and Assign a Resource
Primavera P6 Professional Fundamentals
Course Outline
Prescience Technology Primavera P6 Professional Fundamentals Course Outline 2
Module 5: Schedule a Project
Key Topics
• Critical Path Method Scheduling and the Impact of Float
a. Forward and Backward passes
b. Out of Sequence activities
• Schedule a Project
a. Schedule Settings
b. Viewing the schedule log
c. Viewing the Critical Path
• Assign a constraint
Learning Outcomes
1) Describe Critical Path Method scheduling and the impact of Float
2) Schedule a Project
3) Assign a constraint
4) Interpret the scheduling log
5) View the Critical Path
Learner Activities
• Scheduling a project
Module 6: Baseline a Project
Key Topics
• Perform schedule analysis and optimise
• Undertake resource analysis
• Create and assign a project baseline
Learning Outcomes
1) Perform schedule analysis and optimise schedule
2) Undertake resource analysis
3) Create and assign a project baseline
Learner Activities
• Create and Assign Baseline
Module 7: Progress the Project
Key Topics
• Methods of applying progress
• Update individual activities
• Assessing Project Performance
Learning Outcomes
1) Methods of applying progress
2) Understand how P6 calculation settings affect progress updates
3) Assess Project Performance
4) Update individual activities
Learner Activities
• Update and reschedule a project in P6
Module 8: Layouts Filters, Group and Sort
Key Topics
• Using Layouts, Reporting Layouts
• Filtering, Grouping and Sorting
• Customising Columns and Gantt Chart bars
Learning Outcomes
1) Create and Save a Layout
2) Prepare data for printing
3) Format Project Data
4) Utilise Filters to constrain data displayed
5) Utilise Group and Sort options to arrange data
6) Customising Columns
7) Customise data using the Bars dialogue box
Learner Activities
• Creating a Layout
Primavera P6 Professional Fundamentals
Course Outline
Prescience Technology Primavera P6 Professional Fundamentals Course Outline 3
Module 9: Data Movement
Key Topics
• Importing & Exporting Data
• Publish Project Web Site
• Claim Digger / Schedule Comparison
• Using P6 Documents Function
Learning Outcomes
1) Export and Import XER format Files
2) Export and Import Data in XLS format
3) Generate and set up a Project Web Site
4) Launch and use Claim Digger / Schedule Comparison
5) Assign a Document to an Activity, WBS or Project
6) Create links to P6 Document Categories in a Project
7) Launch a Document from within P6
Learner Activities
• Use XLS Format to Create Activities
Module 10: Reporting on a Project
Key Topics
• Generate Standard Reports
• Generate Time Distributed Reports
Learning Outcomes
1) Generate a Report using the Report Wizard
2) Generate a Report from a Layout
3) Generate a Time Distributed Report
4) Set print Options for Reports
5) Run Reports in the Report window
6) View Reports in the Report window
Learner Activities
• Report on a project
Module 11: Using P6 Visualizer
Key Topics
• Visualizer basic operations
• Using the Options and Imports functions
• Create New Timescaled Logic Diagram
• Create New Gantt Chart
Learning Outcomes
1) Launch Visualizer Stand Alone and from within P6
2) Use the Visualizer Options settings when modifying or creating Timescaled Logic Diagrams and Gantt Charts
3) Open an existing Timescaled Logic template
4) Create Timescaled Logic diagrams
5) Open an existing Gantt Chart template
6) Create Gantt Chart Diagrams
7) Import Primavera P6 Layout ‘.PLF’ files into Visualizer to create Gantt Chart views
Learner Activities
• Create New TSLD
• Create New Gantt Chart
Contactcall: 1300 086 816 email: [email protected] online: www.prescience.com.au address: Level 1, 5 Cribb Street, Milton Q 4064
Primavera P6 Professional Fundamentals
Course Outline
Prescience Technology Primavera P6 Professional Fundamentals Course Outline 4