    Production Process:

    Every production process begins with the marketplace. Marketplace demand is an independent

    demand relies on such factor change consumer test, Different seasons in a year, ups and downs

    national economy, and political winds. Different forecasting techniques can used to make good

    demand prediction. Expected demand as an input to production and aggregate planning, all

    resources necessary to meet the demand and plans for the future. The outcome of an aggregate

    planning is master production schedule (MPS). The next stage is material requirement planning

    (MRP), where a product is disintegrated into several components, each component is determined

    with the help of bills of materials and inventory records. Next a shop floor schedule for each

    component is developed.

    Although the production planning and control system is made of these blocks, there are many

    important functional departments in plant operations, such as human resources, sales and

    marketing, operations, distribution, and finance.

    Production process flow diagram for any production process is given here

  • 8/8/2019 Production Planning and Logistic Systems 2

    2/116

    Production Planning and Logistic Systems 2010

    Page | 2

    Fig. 1: Production Process Flow Diagram

  • 8/8/2019 Production Planning and Logistic Systems 2

    3/116

    Production Planning and Logistic Systems 2010

    Page | 3

    Production Planning and Control

    Production planning and control are two important topics that serve to increase efficiency in

    manufacturing and improve effectiveness in customer service. Production planning determines

    what, when, and how much to produce to meet the customer needs, without excessive inventory

    or back order costs. Production control makes sure that resources, including physical resources

    (plant, tools and equipments, raw-materials), human resources and financial resources are being

    used efficiently and effectively.

    Scheduling on the other hand, determines how to achieve the goal set in production planning

    when the resource are limited, and if the goal cannot be realized, how best to set new goals that

    are optimum and practical with the available resources. Production planning involves forecasting

    of customer orders, determination of plant capacities, and planning for the long range such as

    one year or more. The next step is that short range or immediate planning to monthly and then to

    weekly level.

    Production planning and control has three major sections

    i. Production planningii. Production control

    iii. Inventory management

  • 8/8/2019 Production Planning and Logistic Systems 2

    4/116

    Production Planning and Logistic Systems 2010

    Page | 4

    Fig.2: Production Planning and Control

    Objectives of Production Planning and Control

    The objective of the production planning and control is to produce goods services of right

    quality and quantity at the right time and right manufacturing cost.

    1. Right QualityThe quality of product is established based upon the customers needs. The right quality is

    not necessarily best quality. It is determined by the cost of the product and the technical

    characteristics as suited to the specific requirements.

  • 8/8/2019 Production Planning and Logistic Systems 2

    5/116

    Production Planning and Logistic Systems 2010

    Page | 5

    2. Right QuantityThe manufacturing organization should produce the products in right number. If they are

    produced in excess of demand the capital will block up in the form of inventory and if the

    quantity is produced in short of demand, leads to shortage of products.

    3. Right TimeTimeliness of delivery is one of the important parameter to judge the effectiveness of

    production department. So, the production department has to make the optimal utilization

    of input resources to achieve its objective.

    4. Right Manufacturing CostManufacturing costs are established before the product is actually manufactured. Hence,

    all attempts should be made to produce the products at pre-established cost, so as to

    reduce the variation between actual and the standard (pre-established) cost.

    Production Planning and Control Stages

    Production department is backbone of every process and manufacturing company and its

    performance defines the performance of company. Production department plays a vital role in

    achieving strategic goals and objectives of the company. The functions of Production

    Management depend upon the size of the firm. In small firms the production Manager may have

    to look after production planning and control along with Personnel, Marketing, Finance and

    Purchase functions. In medium sized firms, there may be separate managers for Personnel,

    marketing and Finance functions. But the production planning & control and Purchase & stores

    may be under the control of Production management department. In large sized firms the

    activities of Production Management is confined to the management of production activities

    only. Production Planning and Control activities have three stages:

  • 8/8/2019 Production Planning and Logistic Systems 2

    6/116

    Production Planning and Logistic Systems 2010

    Page | 6

    i. Pre-Planning stageii. Planning stageiii. Control stage

    Fig. 3: Production Planning and Control Stages

    Core Functions of PPC

    1. Process Planning

    Process Planning involves making choices concerning the way an organization will

    produce its products or provide services to its customers. It has major implications for

    capacity planning, layout and work methods. Managers can select from five different

    types of processes: job shop, batch, repetitive, continuous and projects. Job shops are

    used to produce a low volume of each of a large variety of products or services.

  • 8/8/2019 Production Planning and Logistic Systems 2

    7/116

    Production Planning and Logistic Systems 2010

    Page | 7

    Equipment flexibility must be high to handle the high variety of jobs. Batch processing

    involves less variety, less need for equipment flexibility, and higher volumes of each type

    of product. Repetitive processing has even less variety, less need for equipment

    flexibility, and higher volume. Continuous processing has the lowest variety, the lowest

    need for equipment flexibility, and the highest volume.

    Job shops and batch processing are classified as intermittent systems, meaning that output

    frequently switches from one product or service to another. Repetitive and continuous

    systems are classified as continuous processing because there is little or no switching

    from one product to another. Projects are used for non-routine work that is intended to

    meet a given set of objectives in a limited time frame. Job variety is high, volume is

    usually low, and equipment flexibility needs can range from low to high. Process

    selection may lead to automation or computer-aided manufacturing. A key issue in

    process selection is the management of technology. See the discussion under the

    Operations Strategy section. Another key issue in process selection is flexibility. There

    are three fundamental types of plant layout, respectively corresponding to the three

    different types of production operations situations.

    a. A product layout implies that a single product or else a single type of product, forexample, automobiles, is manufactured on an assembly line, with the production tasks

    assigned to workstations along the line.

    b. A process layout involves the movement of batches of goods between departments viaforklift truck, moving belt, or some other type of conveyance.

  • 8/8/2019 Production Planning and Logistic Systems 2

    8/116

    Production Planning and Logistic Systems 2010

    Page | 8

    c. A fixed-position layout is appropriate for a large end item such as a house or airplane,where all material is assembled to a major structure or product at a specified site.

    2. Capacity PlanningCapacity planning is the process of determining the production capacity needed by an

    organization to meet changing demands for its products. In the context of capacity

    planning, "capacity" is the maximum amount of work that an organization is capable of

    completing in a given period of time. The phrase is also used in business computing as a

    synonym for Capacity Management

    A discrepancy between the capacity of an organization and the demands of its customers

    results in inefficiency, either in under-utilized resources or unfulfilled customers. The

    goal of capacity planning is to minimize this discrepancy. Demand for an organization's

    capacity varies based on changes in production output, such as increasing or decreasing

    the production quantity of an existing product, or producing new products. Better

    utilization of existing capacity can be accomplished through improvements in overall

    equipment effectiveness (OEE). Capacity can be increased through introducing new

    techniques, equipment and materials, increasing the number of workers or machines,

    increasing the number of shifts, or acquiring additional production facilities.

    Capacity is calculated: (number of machines or workers) (number of shifts)

    (utilization) (efficiency).

    The broad classes of capacity planning are lead strategy, lag strategy, and match strategy.

  • 8/8/2019 Production Planning and Logistic Systems 2

    9/116

    Production Planning and Logistic Systems 2010

    Page | 9

    a. Lead strategyb. Lag strategyc. Match strategy3. 4 Ms (man, machine, material, method) Planning

    Planning for resources including men, machines, materials and methods for the efficient

    running or production process is responsibility of production planning department.

    Selection of the workforce having certain skills as per requirement of the process,

    training of the workforce, selection of the materials with certain quality standards and

    developing bills of materials, selection of the machines and equipment that satisfy

    requirements of capacity as well as quality and finishing of the final product, selection of

    the methods and operations through which product will be produced and sequencing of

    those operations are all responsibilities of PPC department.

    4. Production ControlMethods and procedures employed in handling materials, parts, assemblies, and sub-

    assemblies, from their raw or initial stage to the finished product stage in

    an organized and efficient manner. It also includes activities such

    as planning, scheduling, routing, dispatching, storage, etc. Production control is a sub-set

    of MRPII (manufacturing resource planning) as it refers only to the control or scheduling

    of production rather than the wider control of all business or enterprise resources.

    5. Inventory ManagementInventory Management and Inventory Control must be designed to meet the dictates of

    the marketplace and support the company's strategic plan. The many changes in market

    demand, new opportunities due to worldwide marketing, global sourcing of materials,

  • 8/8/2019 Production Planning and Logistic Systems 2

    10/116

    Production Planning and Logistic Systems 2010

    Page | 10

    and new manufacturing technology, means many companies need to change their

    Inventory Management approach and change the process for Inventory Control. Despite

    the many changes that companies go through, the basic principles of Inventory

    Management and Inventory Control remain the same. Some of the new approaches and

    techniques are wrapped in new terminology, but the underlying principles for

    accomplishing good Inventory Management and Inventory activities have not changed.

    The Inventory Management system and the Inventory Control Process provides

    information to efficiently manage the flow of materials, effectively utilize people and

    equipment, coordinate internal activities, and communicate with customers. Inventory

    Management and the activities of Inventory Control do not make decisions or manage

    operations; they provide the information to Managers who make more accurate and

    timely decisions to manage their operations.

    The basic building blocks for the Inventory Management system and Inventory Control

    activities are:

    a. Sales Forecasting or Demand Managementb. Sales and Operations Planningc. Production Planningd. Material Requirements Planninge. Inventory Reduction

    The emphases on each area will vary depending on the company and how it operates, and

    what requirements are placed on it due to market demands. Each of the areas above

  • 8/8/2019 Production Planning and Logistic Systems 2

    11/116

    Production Planning and Logistic Systems 2010

    Page | 11

    will need to be addressed in some form or another to have a successful program of

    Inventory Management and Inventory Control.

    6. Logistics Management

    Logistics Management is that part of Supply Chain

    Management that plans, implements, and controls the efficient, effective, forward, and

    reverse flow and storage of goods, services, and related information between the point of

    origin and the point of consumption in order to meet customers requirements.

  • 8/8/2019 Production Planning and Logistic Systems 2

    12/116

    Production Planning and Logistic Systems 2010

    Page | 12

    History

    The story of Servis begins with a group of friends - young, energetic, fresh from college who

    established Service Industries more than 50 years ago.. These young men, named Ch. Nazar

    Muhammad (Late), Ch. Muhammad Hussain (Late) both from Gujrat district and Ch.

    Muhammad Saeed (Late) from Gujranwala District, started business in 1941 at a small scale in

    Lahore. At that time, they were only manufacturing handbags and some other sports goods.

    Within years their business flourished remarkably and they were supplying their products to

    every corner of India at the time of Partition.

    In 1954, they installed a shoe manufacturing plant at industrial area Gulberg, Lahore. This

    started production in the same year. The industry started manufacturing various types of shoes.

    Later management shifted the factory from Lahore to Gujrat. Service Sales Corporation (Pvt.)

    Ltd. the Groups marketing company was established in 1959. Humility, fairness, and respect

    were the values close to the heart of these founders and it were these values that led to

    phenomenal success of the Group. Today, the production side of the company has flourished

    into Service Industries Limited (SIL) which has world-class shoes, tyres, tubes, and rubber

    production facilities in Gujrat and Muridke. SIL is also the leading exporter of footwear. Service

    Sales Corporation (Pvt.) Ltd. (SSC) is today Pakistans leading footwear retailer which is also

    diversifying into other businesses. A humble venture of friends has grown into a Group that

    makes a difference in lives of millions of people every day today.

    The Group

    Servis Group is one of the most respected corporate citizens of the country and has a rich

    heritage spanning over half a century. Today the Group is Pakistan's largest footwear

  • 8/8/2019 Production Planning and Logistic Systems 2

    13/116

    Production Planning and Logistic Systems 2010

    Page | 13

    manufacturer and exporter with interests in wholesale and retail sectors. With a growing

    portfolio of brands and a nationwide network that touches millions of lives everyday, Servis is

    one of the foremost brands in the country. Setup in 1958, the Group is the largest footwear

    manufacturer, retailer, and exporter operating in the country and has overall sales of more than

    PKR 12 billion. It currently employs close to 9000 people in its following companies:

    i. Service Industries Limited (SIL)ii. Service Sales Corporation (Pvt.) Ltd. (SSC)

    iii. Servaid Pharmacy (Pvt.) Ltd.The Brand - Celebrating 50 Years ofHappiness

    Starting its journey as a single retail footwear outlet, the brand today has a 400+ stores presence

    in Pakistan, 2000+ dealer-base, and a growing international footprint in Europe, Middle East,

    and many other regions of the world. At the heart of all our endeavors lies the spirit of our

    countrymen. Servis and its roots are grounded firmly in Pakistan and its people. We understand

    their needs, their lives and their dreams. Sharing in their moments both big and small, Servis has

    been their companion in happiness for over 50 years. And with our commitment to constant

    innovation and uncompromising quality, we endeavor to delight our customers with the very best

    products and services. Three generations connected through the thread that is happiness; the

    journey continues on the road to feel good.

    Best Practices

    We continuously work on adopting strategies and methodologies that yield results and maximize

    operational efficiency. With our focus to maintain the highest standards in operations, Servis

  • 8/8/2019 Production Planning and Logistic Systems 2

    14/116

    Production Planning and Logistic Systems 2010

    Page | 14

    partners with the best for its business processes. Servis is powered by technology giants

    like Microsoft, Oracle, IBM, CISCO, DELL, HP and Agility, making the decision support

    systems automated for creating efficiency & effectives at par with globally accepted scales. Our

    team is consistently working to bridge the information flows from retails outlets in rural and

    urban centers, following the customer centric approach. In addition, EPOS (Electronic Point of

    Sale) systems have been installed in over 200 stores with a goal of EPOS in every Servis store by

    2010. Our EPOS hardware partner is JBL. With a goal to create a state-of-the-art supply chain,

    world renowned retail experts Kurt Salmon Associates were engaged for a landmark project:

    Project Giant Leap. A key initiative within the Project Giant Leap fold was partnering with

    Agility Logistics for our Central Distribution Center. Believing in bringing customer to the heart

    of our decision making, we also conduct formal consumer research in concept and product

    development, marketing structure and segmentation, and pricing areas and also undertake

    ongoing consumer research initiatives like mystery customer programs, Consumer Links, and

    brand tracking with partners like Nielsen, MEMRB, AMRB, and Startex Marketing.

    International Business

    We at Servis have been servicing customers internationally for more than 25 years. Our highly

    qualified team of professionals and technical experts translate your designs into products of your

    choice. We specialize in contract manufacturing. Manufacturing as per clients requirements, we

    also assist our global clients with sourcing of raw material for manufacturing. To keep abreast

    with the international manufacturing standards and techniques we follow the tests requirements

    as defined by our valued clients. Our technical experts regular attend formal trainings at

    internationally recognized design schools. Computer aided design and manufacturing tools

  • 8/8/2019 Production Planning and Logistic Systems 2

    15/116

    Production Planning and Logistic Systems 2010

    Page | 15

    combined with the best practices at par with global standards are used. With a major focus on

    European market we follow all the pre-requisites of EU standards. With our rich experience in

    exports, we are now moving towards retailing globally. Our team of professionals is

    continuously accumulating marketing intelligence, leading towards establishing our retail brands

    in the global arena both through our own or partner retailing initiatives as well as by establishing

    a wholesale market presence. We have started establishing our brand network in UAE, Qatar &

    KSA (Kingdom of Saudi Arabia). Our brands are available at leading hyper marts like Carrefour,

    LuLu and K.M. Stores in Dubai. Our highly motivated team is exploring international frontiers

    aiming to make Servis a globally acclaimed brand.

    Nationwide Network:

    Fig. 4: SILNationwide Network

  • 8/8/2019 Production Planning and Logistic Systems 2

    16/116

    Production Planning and Logistic Systems 2010

    Page | 16

    Service Industries Limited (SIL)

    SIL is a public limited company listed on the stock exchanges of Pakistan. It has annual

    revenues of about PKR

    6

    billion and is the largest manufacturer of footwear, tyres & tubes for

    two-wheelers, and has been the largest footwear exporter of the country for the last 10 years.

    The company employs more than 6,000 people in its facilities located in Gujrat and Muridke and

    exports its products primarily to Germany, Italy, France and the UK. With a strong emphasis on

    product quality and innovation, SIL has built both domestic and international recognition of

    companys products.

    The visionary leadership and hardworking management team has led SIL to hold this top

    position in the business arena. The board comprises:

    y Mr. Arif Saeed, Chairmany Mr. Shahid Hussain, Chief Executivey Mr. M. Ijaz Butt, Directory Mr. Muhammad Akram, Directory Mr. Hassan Javed, Directory Mr. Shahid Hafeez Kardar, Directory Mr. Riaz Ahmed, Directory Mr. Zahid Hussain, (Rep. ofNIT)y Mr. Anis Wahab Zuberi, (Rep. ofNIT)

    Brands

  • 8/8/2019 Production Planning and Logistic Systems 2

    17/116

    Production Planning and Logistic Systems 2010

    Page | 17

    Process Planning

    Process Planning and capacity planning play a key role in the ability of an organization to

    achieve its mission. Technological advances in processing provide many new options for

    competitive advantage, but they also pose numerous risks for the unwary decision maker.

    Key aspects in process selection are

    1. Make or Buy DecisionThe extent to which the organization will produce goods or provide services in house as

    opposed to relying on outside organization to produce or provide them.

    2. Capital IntensityThe mix of equipment and the labor that will be used by the organization.

    3. Process FlexibilityThe degree to which the system can be adjusted to changes in processing requirements

    due to such factors as changes in product or service design, change in volume processed,

    and changes in technology.

  • 8/8/2019 Production Planning and Logistic Systems 2

    18/116

    Production Planning and Logistic Systems 2010

    Page | 18

    Fig. 5: Process Planning

    Inputs

    i. Forecastingii. Product/Service Design

    iii. Technological ChangeOutputs

    i. Plant and Equipment Selectionii. Facilities Layout

    iii. Work designiv. Capacity Planning

    Forecasting

    Product and

    Service Design

    Technological

    change

    Capacity Planning

    Plant and

    Equipment Selection

    Facilities Layout

    Work Design

    Process

    Planning

  • 8/8/2019 Production Planning and Logistic Systems 2

    19/116

    Production Planning and Logistic Systems 2010

    Page | 19

    Production Systems

    Production function is that part of an organization, which is concerned with the transformation of

    a range of inputs into the required outputs (products) having the requisite quality level.

    Production is defined as the step-by-step conversion of one form of material into another form

    through chemical or mechanical process to create or enhance the utility of the product to the

    user. Thus production is a value addition process. At each stage of processing, there will be

    value addition.

    Edwood Buffa defines production as a process by which goods and services are created. Some

    examples of production are: manufacturing custom-made products like, boilers with a specific

    capacity, constructing flats, some structural fabrication works for selected customers, etc., and

    manufacturing standardized products like, car, bus, motor cycle, radio, television, etc.

    Fig. 6: Schematics Production System

    The production system of an organization is that part, which produces products of an

    organization. It is that activity whereby resources, flowing within a defined system, are

  • 8/8/2019 Production Planning and Logistic Systems 2

    20/116

    Production Planning and Logistic Systems 2010

    Page | 20

    combined and transformed in a controlled manner to add value in accordance with the policies

    communicated by management. A simplified production system is shown above.

    The production system has the following characteristics:

    1. Production is an organized activity, so every production system has an objective.2. The system transforms the various inputs to useful outputs.3. It does not operate in isolation from the other organization system.4. There exists a feedback about the activities, which is essential to control and improve

    system performance.

    Classification of Production System

    Production systems can be classified as Job Shop, Batch, Mass and Continuous Production

    systems.

    Fig. 7: Classification of Production Systems

  • 8/8/2019 Production Planning and Logistic Systems 2

    21/116

    Production Planning and Logistic Systems 2010

    Page | 21

    Batch Production: Production System at SIL

    Production system in practice at Servis Industries Ltd. is Batch Production. Batch Production

    is to manufacture of number of identical products either to meet the specific order or to satisfy

    the demand. When the production of plant and equipment is terminated, the plant and equipment

    can be used for producing similar products. This system has further three categories.

    i. A Batch Produced Only Once:Servis Industries have international clients. Customers place order with the firm for the

    product of their specifications. Industrial Engineering dept. provides time study

    information for the product. Production planning dept. generates MRPs for all the

    materials which are sent to the Materials dept. for procurement. Materials arrive as per

    requirement of quality and quantity withing required dates. Then production is scheduled.

    In case the order is large, SIL outsources the cutting process to its vendors. Cutting

    patterns and cutting requirements are provided to them by the company. Processes of

    stitching andsole fixing are carried out in the company. Record of production including

    materials, machines, labor is maintained.

    ii. A Batch Produced at Irregular Intervals as per Customer Order or When the NeedArises:

    Servis Industries Limited has a wide range of articles whose demand varies. Demand

    Forecasts or Purchase orders are generated by the Marketing dept. of the company, whose

    responsibility is to keep tracking customer behaviors, buying trends, and changing

    customer requirements. Some articles have demand in one season and some in the other.

    So, production is scheduled as per demand or as per purchase orders generated by

    marketing dept. When order is received, production planning process begins, which is

  • 8/8/2019 Production Planning and Logistic Systems 2

    22/116

    Production Planning and Logistic Systems 2010

    Page | 22

    explained in previous heading. As the frequency is irregular, the firm can maintain a file

    of its detailed plans and it can refer to its previous files and start production.

    iii. A Batch Produced Periodically at Known Intervals:This system is used in make to stock production systems or where consistent demand

    for the product exists. Here the firm either receives order from the customer at regular

    intervals or it may produce the product to satisfy the demand. It can have well designed

    file of its plans, material requirement and instructions for the ready reference. It can also

    purchase materials required in bulk in advance. As the frequency of regular orders goes

    on increasing the Batch Production system becomes Mass Production System. Here also,

    incase the demand for a particular product ceases, the plant and machinery can be used

    for producing other products with slight modification in layout or in machinery and

    equipment.

    This system is not yet being used in SIL, since demand for the articles is irregular.

    Characteristics of Batch Production

    Batch production system is used under the following circumstances:

    1. When there is shorter production runs.2. When plant and machinery are flexible.3. When plant and machinery set up is used for the production of item in a batch and

    change of set up is required for processing the next batch.

    4. When manufacturing lead time and cost are lower as compared to job order production.

  • 8/8/2019 Production Planning and Logistic Systems 2

    23/116

    Production Planning and Logistic Systems 2010

    Page | 23

    Advantages of Batch Production

    Following are the advantages of batch production:

    1. Better utilization of plant and machinery.2. Promotes functional specialization.3. Cost per unit is lower as compared to job order production.4. Lower investment in plant and machinery.5. Flexibility to accommodate and process number of products.6. Job satisfaction exists for operators.

    Limitations of Batch Production

    Following are the limitations of batch production:

    1. Material handling is complex because of irregular and longer flows.2. Production planning and control is complex.3. Work in process inventory is higher compared to continuous production.4. Higher set up costs due to frequent changes in set up.

  • 8/8/2019 Production Planning and Logistic Systems 2

    24/116

    Production Planning and Logistic Systems 2010

    Page | 24

    Facility Layout Designing

    Facility layout refers to arrangement of machines, storage areas, and/or work areas usually

    within the confines of a physical structure, such as a retail store, an office, a warehouse, or a

    manufacturing facility.

    In Servis Industries two types of layouts are being installed.

    a. Cellular Layoutb. Production Lines

    Cellular Layout

    There are 3 major processes involved in production of shoes, each of which is completed in a

    particular section or cell. These sections/cells are:

    1. Cutting Cell2. Closing or Machining Cell3. Lasting & MakingCell4. Finishing and Packing Cell

    Within each cell, machines are arranged in sequence i.e, within each cell exist production line.

    1. Cutting CellIn this department, the top part of the shoe or the "upper" is made. The cutting operative

    is given skins of leather, mostly cow leather but not restricted to this type of leather.

    Using metal strip knives, the worker cuts out pieces of various shapes that will take the

    form of "uppers". This operation needs a high level of skill as the expensive leather has to

    be wasted at the minimum level possible. Leather may also have various defects on the

  • 8/8/2019 Production Planning and Logistic Systems 2

    25/116

    Production Planning and Logistic Systems 2010

    Page | 25

    surface such as barbed wire scratches which needs to be avoided, so that they are not

    used for the uppers. Components are cut as per cutting requirements provided by the

    planning department. Various cutting machines are used in cutting section for leather

    cutting. These are:

    a. Press Cutting Machine (used to cut patterns of single leather layer using a cutting die)b. Transfer Head Cutting Machine (used to cut patterns of multiple leather layers using a

    cutting die)

    c. Splitting Machine (used to reduce thickness of leather cuttings to match designspecifications)

    d. Skiving Machine (used to reduce thickness of leather cuttings at the edges, so that whentwo leather cuttings are joined/stitched together, joint does not become too thick)

    Cutting Lines

    In cutting cell, machines are arranged in sequence so as to maximize in-sequence moves

    and avoid back-tracking.

    Fig. 8: Cutting Lines in Cutting Cell

    These processes must be completed in sequence. Splitting cant be done before cutting, and

    skiving cant be done before splitting.

    Press/Transfer Head

    Cutting Machine

    Splitting Machines Skiving Machines

  • 8/8/2019 Production Planning and Logistic Systems 2

    26/116

    Production Planning and Logistic Systems 2010

    Page | 26

    2. Closing or Machining CellHere the component pieces are sewn together by highly skilled machinists so as to

    produce the completed upper. The work is divided in stages. In early stages, the pieces

    are sewn together on the flat machine. In the later stages, when the upper is no longer flat

    and has become three-dimensional, the machine called post machine is used. The sewing

    surface of the machine is elevated on a post to enable the operative to sew the three

    dimensional upper. Various edge treatments are also done onto the leather for giving an

    attractive look to the finished upper. At this stage only, the eyelets are also inserted in

    order to accommodate the laces in the finished shoes.

    In stitching cell, leather cuttings are stitched using stitching machines. Different types of

    stitching machines are used, such as:

    a. Single Stitch Machine (such machines are conventional style but special purposestitching machines. They contain a single stitching needle, and are used for single stitch)

    b. Double Stitch Machine (these stitching machines contain two needles and are used fordouble stitch)

    c. Zigzag Stitching Machine (these are special purpose stitching machines which createzigzag stitching patterns on the upper. Their use depends on the design of the article)

    Stitching Lines

    In stitching cell, workstations are designed and arranged as per article and its

    components. At each workstation, a certain stitching operation is performed within the

    time provided bye the Industrial Engineering dept. so as to optimize the production

    system productivity and complete the customer order in-time. For each article, there is a

    different time study data, and each article has its own arrangement of machines for its

  • 8/8/2019 Production Planning and Logistic Systems 2

    27/116

    Production Planning and Logistic Systems 2010

    Page | 27

    manufacturing. So, every time when a batch is scheduled, position of machines is

    shuffled accordingly. Workstations are arranged in series to maximize in-sequence

    moves.

    3. Lasting & MakingCellThe completed uppers are molded into a shape of foot with the help of a "Last". Last is a

    plastic shape that simulates the foot shape. It is later removed from the finished shoe to

    be used further in making other shoes. Firstly, an insole to the bottom of the last is

    attached. It is only a temporary attachment. Sometimes, mostly when welted shoes are

    manufactured, the insole has a rib attached to its under edge. The upper is stretched and

    molded over the last and attached to the insole rib. After the procedure completes, a

    "lasted shoe" is obtained. Now, the welt- a strip of leather or plastic- is sewn onto the

    shoe through the rib. The upper and all the surplus material is trimmed off the seam. The

    sole is then attached to the welt and both are stitched together. The heel is then attached

    which completes the "making" of the shoe. That was the process for heeled shoes. When

    a flat shoe is in the making, there are considerably fewer operations. The insole in this

    case is flat and when the uppers are 'lasted', they are glued down to the surface of the

    inner side of the insole. The part of the upper that is glued down is then roughed with a

    wire brush to take off the smooth finish of the leather. This is done because rough surface

    absorbs glue to give a stronger bond. The soles are usually cut, finished and prepared as a

    separate component so that when they are glued to the lasted upper, the result is a

    complete and finished shoe. Soles can also be pre-molded as a separate component out of

    various synthetic materials and again glued to the lasted upper to complete the shoe.

    Two methods for sole joining are:

  • 8/8/2019 Production Planning and Logistic Systems 2

    28/116

    Production Planning and Logistic Systems 2010

    Page | 28

    a. Direct Injection method (sole in joined with the upper using an injectionmolding machine. This method is used for articles such as Cheetah n other trainer

    shoes for which upper is not stitched with the sole)

    b. Stuck-on method (method explained above. Sole is joined with the upper usingan adhesive material, and then stitched. Soles are manufactured separately)

    4. Finishing and Packing CellThe finishing of a shoe depends on the material used for making it. If made of leather, the

    sole edge and heel are trimmed and buffed to give a smooth finish. To give them an

    attractive finish and to ensure that the edge is waterproof, they are stained, polished and

    waxed. The bottom of the sole is often lightly buffed, stained and polished and different

    types of patterns are marked on the surface to give it a craft finished look. A "finished

    shoe" has now been made. For shoe room operation, an internal sock is fitted into shoe

    which can be of any length- full, half or quarter. They usually have the manufacturers

    details or a brand name wherever applicable. Depending on the materials used for the

    uppers, they are then cleaned, polished and sprayed. Laces and any tags that might have

    to be attached to the shoes, such as shoe care instructions, are also attached. The shoes, at

    last, get packaged in boxes.

  • 8/8/2019 Production Planning and Logistic Systems 2

    29/116

    Production Planning and Logistic Systems 2010

    Page | 29

    Capacity Planning

    "Capacity" is the maximum amount of work that an organization is capable of completing in a

    given period of time.

    The basic questions in capacity planning of any sort are the following

    1) How much is needed?2) When is it needed?

    The fundamental decisions in any organization concern the choice of product or services it

    offers. All other decisions pertaining to capacity, facilities, location are governed by the choice

    of product.

    Fig. 9: Capacity Planning

    Forecast

    Demand

    Compute

    NeededCapacity

    Compute

    Rated

    Capacity

    Evaluate

    Capacity

    Plans

    ImplementBest Plan

    QualitativeFactors

    e. . Skills

    Select Best

    CapacityPlan

    Develop

    Alternative

    Plans uantitative

    Factorse. . Cost

  • 8/8/2019 Production Planning and Logistic Systems 2

    30/116

    Production Planning and Logistic Systems 2010

    Page | 30

    Importance of Capacity Decisions

    Capacity decision have a real impact on the ability of an organization to meet futuredemands for product and services

    Capacity decisions affect operating costs. A decision might be made to balance the costof over and under capacity.

    Capacity is usually a major determinant of initial cost. Although larger units tend to costproportionately less than smaller units.

    Capacity decisions often involve long-term commitment of resources, and it is difficultand closely to modify those.

    Capacity decision can affect competitiveness.Definition and Measuring Capacity

    It is difficult to assign single measure of capacity, for different products and variety of services.

    The measure of capacity must be tailored to the situation.

    The above definition of capacity is functional. It can be refined into three useful definitions.

    Design capacity: the maximum that can be achieved under ideal conditions.

    Effective capacity: The percent of design capacity actually expected.

    Rated Capacity:Maximum usable capacity of a particular facility

    RC = (Capacity)(Utilization)(Efficiency)

    Utilization Measure of planned or actual capacity usage of a facility, work center, or machine

    Utilization = Actual Output / Design capacity

  • 8/8/2019 Production Planning and Logistic Systems 2

    31/116

    Production Planning and Logistic Systems 2010

    Page | 31

    Efficiency: is the ratio of actual output to effective capacity

    Efficiency = Actual Output / Effective capacity

    Make or Buy Decision and Capacity Planning

    A manufacture has to consider whether to make or buy some for all the parts or to subcontract

    some or all of a service.

    In make or buy decisions, a number of factors are usually consider.

    y Available capacity: If the organization has available equipment and skill, it will producein house.

    y Expertise: Buying might be a reasonable choice, if the organization lacks the expertise todo the job.

    y Quality considerations: Firms that specialize can usually offer higher quality than anorganization can attain itself. Special quality requirements or the ability to closely

    monitor quality may cause an organization to perform a job itself.

    y Nature of demand: When the demand for item that is high and steady the organization isbetter off doing the work itself.

    y Cost: Any cost savings achieved from buying or making must be weighed against thepreceding factors. Cost saving might come from itself or from transportation, fixed cost

    saving.

  • 8/8/2019 Production Planning and Logistic Systems 2

    32/116

    Production Planning and Logistic Systems 2010

    Page | 32

    Strategies for Capacity Planning

    The broad classes of capacity planning are lead strategy, lag strategy, and match strategy.

    I. Lead strategyis adding capacity in anticipation of an increase in demand. Lead strategy is an aggressive

    strategy with the goal of luring customers away from the company's competitors. The

    possible disadvantage to this strategy is that it often results in excess inventory, which is

    costly and often wasteful.

    II. Lag strategy refers to adding capacity only after the organization is running at fullcapacity or beyond due to increase in demand. This is a more conservative strategy. It

    decreases the risk of waste, but it may result in the loss of possible customers.

    III. Match strategy is adding capacity in small amounts in response to changing demand inthe market. This is a more moderate strategy.

    Fig. 10: Strategies for Capacity Planning

    Expected Demand Expected Demand

    Expected Demand Expected Demand

    Time in Years Time in Years

    Time in YearsTime in Years

    De

    ma

    nd

    De

    ma

    nd

    De

    ma

    nd

    De

    ma

    nd

    New Capacity

    New CapacityNew Capacity

    New Capacity

    Capacity leads demand with an incremental expansion Capacity leads demand with a one-step expansion

    Capacity lags demand with an incremental expansionAttempts to have an average capacity, with an

    incremental expansion

  • 8/8/2019 Production Planning and Logistic Systems 2

    33/116

    Production Planning and Logistic Systems 2010

    Page | 33

    Machine Utilization Improvement Work at SIL:

    The measure of machine hours recorded against production vs. the hours available or scheduled

    for a given period. The machine utilization is a measure of the fraction of time that the machine

    is busy. The symbol r (rho) is often used to represent this quantity. Note that r is unit-less, and

    that it's values must be in the range from 0 to 1.

    Causes of poor Equipment / Machine Utilization and/or Efficiency

    1. Failure to plan work so that effective and efficient utlization is made of all availablemachinery

    2. Failure to inspect machinery to keep it in good condition and to prevent breakdown3. Foreman's lack of knowledge on possible use and capacity of machines4. Failure to make regular examination of wire ropes, belts, chain drives, gear drives,

    conveyors, lubrication systems, valves etc

    5. Using unnecessary large and powerful machine for small work6. Lack of cooperation with maintenance department; upkeep, repairs, painting etc.7. Not protecting idle machinery from weather, dust, dirt, rust, fumes etc8. Allowing machinery to stay dirty by lack of periodic cleaning9. Failure to inspect for proper lubrication of all moving parts10. Failure to make needed repairs promptly11. Lack of instruction to employees on the proper operation of machinery12. Lack of proper discipline to prevent abuse of machinery and equipment13. Allowing employees to make "shoestring" repairs14. Failure by the foreman to keep informed on the latest technology

  • 8/8/2019 Production Planning and Logistic Systems 2

    34/116

    Production Planning and Logistic Systems 2010

    Page | 34

    15. Failure to pay attention to workers opinions on value and condition of machinery.16. Abusing small machines on large work17. Repairing machinery that should be scrapped; may cost more than replacing

    During our research work at Servis Industries, we collected data on machine utilization for 5

    days. And we found that if we reduce change over times and could overcome break downs, we

    may enhance our production up to 29 percent. Here is the study we did in Servis Industries:

  • 8/8/2019 Production Planning and Logistic Systems 2

    35/116

    Production Planning and Logistic Systems 2010

    Page | 35

    Day 1

    Actual Production 467 Pairs

    Loss 188 Pairs

    Machine Productivity 72 %

    Production Loss 28 %

    Hourly Production of Desma Machine # 3

    Time Production (Pairs)

    07:30 to 08:30 50

    08:30 to 09:30 00

    09:30 to 10:30 51

    10:30 to 011:30 80

    11:30 to 12:45 101

    12:45 to 13:15 Break

    13:15 to 14:15 78

    14:15 to 15:15 80

    15:15 to 15:30

    Total

    27

    467

  • 8/8/2019 Production Planning and Logistic Systems 2

    36/116

    Production Planning and Logistic Systems 2010

    Page | 36

    Breakdown Losses

    Problem Frequency Time Lost Pairs Lost

    Mould Problem /

    Change / Adjust

    1 16 24

    Injection Miss 1 10 15

    Incomplete Sole 1 6.67 10

    Repair Work 1 14.67 22

    Spray Problem 1 2.67 04

    Upper not Lasted 1 2.6768 04

    Cleaning & Reamer 1 68 102

    Mould Adjustment 1 4.67 07

    Table 1: Breakdown Losses: Day 1

  • 8/8/2019 Production Planning and Logistic Systems 2

    37/116

    Production Planning and Logistic Systems 2010

    Page | 37

    Graph 1: Problems vs Pairs Lost: Day 1

    Ideal Condition Pairs = (Shift Time / Mold Turn Time) * No of pairs on mold machine

    = (450 / 10.3) * 15

    = 655 Pairs

    Time Wasted due to Breakdowns = 125.33 mins

    Pairs Wasted = 125.33 * 1.5 = 188 Pairs

    Total Pairs = 655 188 = 467

    Productivity = (Pairs Produced / Ideal Condition Production) * 100

    = (467 / 655)100

    = 72 %

    Production Loss = 28 %

    0 20 40 60 80 100 120

    Mould Problem / Change / Adjust

    Injection Miss

    Incomplete Sole

    Repair work

    Spray Problem

    Upper not Lasted

    Cleaning & Reamer

    Mould Adjustment

    Pairs Lost

  • 8/8/2019 Production Planning and Logistic Systems 2

    38/116

    Production Planning and Logistic Systems 2010

    Page | 38

    Day 2

    Actual Production 549 Pairs

    Loss 106 Pairs

    Machine Productivity 84 %

    Production Loss 16 %

    Hourly Production of Desma Machine # 3

    Time Production (Pairs)

    07:30 to 08:30 60

    08:30 to 09:30 65

    09:30 to 10:30 74

    10:30 to 011:30 77

    11:30 to 12:45 90

    12:45 to 13:15 Break

    13:15 to 14:15 68

    14:15 to 15:15 79

    15:15 to 15:30

    Total

    36

    549

  • 8/8/2019 Production Planning and Logistic Systems 2

    39/116

    Production Planning and Logistic Systems 2010

    Page | 39

    Breakdown Losses

    Problem Frequency Time Lost Pairs Lost

    Mould Problem /

    Change / Adjust

    1 3.33 05

    Injection Miss 1 4 06

    Incomplete Sole 1 7.33 11

    Upper not available 1 32.67 49

    Spray Problem 1 1.33 02

    Discolor 1 4.67 07

    Reamer 1 12 18

    Tip Cleaning 1 5 8

    Table 2: Breakdown Losses: Day 2

  • 8/8/2019 Production Planning and Logistic Systems 2

    40/116

    Production Planning and Logistic Systems 2010

    Page | 40

    Graph 2: Problems vs Pairs Lost: Day 2

    Ideal Condition Pairs = (Shift Time / Mold Turn Time) * No of pairs on mold machine

    = (450 / 10.3) * 15 = 655 Pairs

    Time Wasted due to Breakdowns = 70.33 mins

    Pairs Wasted = 70.33 * 1.5 = 106 Pairs

    Total Pairs = 655 106 = 549 PairsProductivity = (Pairs Produced / Ideal Condition Production) * 100

    = (549 / 655)100

    = 84 %

    Production Loss = 16 %

    0 10 20 30 40 50 60

    Mould Problem / Change / Adjust

    Injection Miss

    Incomplete Sole

    Upper not available

    Spray Problem

    Discolor

    Reamer

    Tip Cleaning

    Pairs Lost

  • 8/8/2019 Production Planning and Logistic Systems 2

    41/116

    Production Planning and Logistic Systems 2010

    Page | 41

    Day 3

    Actual Production 412 Pairs

    Loss 243 Pairs

    Machine Productivity 64 %

    Production Loss 36 %

    Hourly Production of Desma Machine # 3

    Time Production (Pairs)

    07:30 to 08:30 32

    08:30 to 09:30 22

    09:30 to 10:30 54

    10:30 to 011:30 52

    11:30 to 12:45 78

    12:45 to 13:15 Break

    13:15 to 14:15 73

    14:15 to 15:15 77

    15:15 to 15:30

    Total

    28

    412

  • 8/8/2019 Production Planning and Logistic Systems 2

    42/116

    Production Planning and Logistic Systems 2010

    Page | 42

    Breakdown Losses

    Problem Frequency Time Lost Pairs Lost

    Mould Problem /

    Change / Adjust

    1

    18.67

    28

    Injection Miss 1 1.33 02

    Incomplete Sole 1 0.67 01

    Repair Work 1 16.67 25

    Spray Problem 1 2.67 04

    Upper not Lasted 1 3.33 05

    Cleaning & Reamer 1 10 15

    Mould Adjustment 1 4 06

    Upper not Available 1 36 54

    Injection M/t

    Shortage

    1

    45.33

    68

    Maintenance

    Problem

    1

    23.33

    35

    Table 3: Breakdown Losses: Day 3

  • 8/8/2019 Production Planning and Logistic Systems 2

    43/116

    Production Planning and Logistic Systems 2010

    Page | 43

    Graph 3: Problems vs Pairs Lost: Day 3

    Ideal Condition Pairs = (Shift Time / Mold Turn Time) * No of pairs on moldmachine

    = (450 / 10.3) * 15 = 655 Pairs

    Time Wasted due to Breakdowns = 162 mins

    Pairs Wasted = 162 * 1.5 = 243 Pairs

    Total Pairs = 655 243 = 412

    Productivity = (Pairs Produced / Ideal Condition Production) * 100

    = (412 / 655)100

    = 64 %

    Production Loss = 36 %

    0 10 20 30 40 50 60 70 80

    Mould Problem / Change / Adjust

    Injection Miss

    Incomplete Sole

    Repair Work

    Spray Problem

    Upper not Lasted

    Cleaning & Reamer

    Mould Adjustment

    Upper not Available

    Injection M/t Shortage

    Maintenance Problem

    Pairs Lost

  • 8/8/2019 Production Planning and Logistic Systems 2

    44/116

    Production Planning and Logistic Systems 2010

    Page | 44

    Day 4

    Actual Production 483 Pairs

    Loss 172 Pairs

    Machine Productivity 73.7 %

    Production Loss 26.3 %

    Hourly Production of Desma Machine # 3

    Time Production (Pairs)

    07:30 to 08:30 00

    08:30 to 09:30 31

    09:30 to 10:30 68

    10:30 to 011:30 88

    11:30 to 12:45 99

    12:45 to 13:15 Break

    13:15 to 14:15 82

    14:15 to 15:15 87

    15:15 to 15:30

    Total

    28

    483

  • 8/8/2019 Production Planning and Logistic Systems 2

    45/116

    Production Planning and Logistic Systems 2010

    Page | 45

    Breakdown Losses

    Problem Frequency Time Lost Pairs Lost

    Mould Problem /

    Change / Adjust

    1

    13.33

    20

    Repair Work 1 16.67 25

    Mould Adjustment 1 6 09

    Upper not Available 1 6.67 10

    Maintenance

    Problem

    1

    58

    87

    Injection Miss +

    Incomplete Sole

    (Scrapper Problem)

    1

    12.67

    19

    Table 4: Breakdown Losses: Day 4

  • 8/8/2019 Production Planning and Logistic Systems 2

    46/116

    Production Planning and Logistic Systems 2010

    Page | 46

    Graph 4: Problems vs Pairs Lost: Day 4

    Ideal Condition Pairs = (Shift Time / Mold Turn Time) * No of pairs on mold machine

    = (450 / 10.3) * 15 = 655 Pairs

    Time Wasted due to Breakdowns = 114 mins

    Pairs Wasted = 114 * 1.5 = 172 Pairs

    Total Pairs = 655 172 = 483

    Productivity = (Pairs Produced / Ideal Condition Production) * 100

    = (483 / 655)100

    = 73.7%

    Production Loss = 26.3 %

    0 10 20 30 40 50 60 70 80 90 100

    Mould Problem / Change / Adjust

    Repair Work

    Mould Adjustment

    Upper not Available

    Maintenance Problem

    Injection Miss + Incomplete Sole

    Pairs Lost

  • 8/8/2019 Production Planning and Logistic Systems 2

    47/116

    Production Planning and Logistic Systems 2010

    Page | 47

    Day 5

    Actual Production 392 Pairs

    Loss 263 Pairs

    Machine Productivity 59.85 %

    Production Loss 40.15 %

    Hourly Production of Desma Machine # 3

    Time Production (Pairs)

    07:30 to 08:30 28

    08:30 to 09:30 24

    09:30 to 10:30 45

    10:30 to 011:30 49

    11:30 to 12:45 77

    12:45 to 13:15 Break

    13:15 to 14:15 74

    14:15 to 15:15 69

    15:15 to 15:30

    Total

    26

    392

  • 8/8/2019 Production Planning and Logistic Systems 2

    48/116

    Production Planning and Logistic Systems 2010

    Page | 48

    Breakdown Losses

    Problem Frequency Time Lost Pairs Lost

    Mould Problem /

    Change / Adjust

    1

    24

    36

    Injection Miss 1 1.33 2

    Incomplete Sole 1 0.67 1

    Repair Work 1 16.67 25

    Spray Problem 1 2.67 4

    Upper not Lasted 1 2.67 4

    Cleaning & Reamer 1 10 15

    Mould Adjustment 1 4 6

    Upper not Available 1 38 57

    Injection M/t

    Shortage

    1

    50

    75

    Maintenance

    Problem

    1

    25.33

    38

    Table 5: Breakdown Losses: Day 5

  • 8/8/2019 Production Planning and Logistic Systems 2

    49/116

    Production Planning and Logistic Systems 2010

    Page | 49

    Graph 5: Problems vs Pairs Lost: Day 5

    Ideal Condition Pairs = (Shift Time / Mold Turn Time) * No of pairs on mold machine

    = (450 / 10.3) * 15 = 655 Pairs

    Time Wasted due to Breakdowns = 176 mins

    Pairs Wasted = 176 * 1.5 = 263 Pairs

    Total Pairs = 655 263 = 392

    Productivity = (Pairs Produced / Ideal Condition Production) * 100

    = (392 / 655)100 = 59.85 %

    Production Loss = 41.15 %

    0 10 20 30 40 50 60 70 80

    Mould Problem / Change / Adjust

    Injection Miss

    Incomplete Sole

    Repair Work

    Spray Problem

    Upper not Lasted

    Cleaning & Reamer

    Mould Adjustment

    Upper not Available

    Injection M/t Shortage

    Maintenance Problem

    Pairs Lost

  • 8/8/2019 Production Planning and Logistic Systems 2

    50/116

    Production Planning and Logistic Systems 2010

    Page | 50

    Machine Efficiencies

    Overall efficiencies of these five days is as follows;

    Day Machine Efficiency

    Day # 1 72

    Day # 2 84

    Day # 3 64

    Day # 4 73.7

    Day # 5 59.85

    Average Efficiency 70.1 %

    Table 6: Efficiency per Day

    Graph 6: Efficiency per Day

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    Day # 1 Day # 2 Day # 3 Day # 4 Day # 5

    Machine Efficiency

    Machine Efficiency

    Avg. Efficiency

  • 8/8/2019 Production Planning and Logistic Systems 2

    51/116

    Production Planning and Logistic Systems 2010

    Page | 51

    Why Too Low Efficiency?

    Pairs Lost

    Problem Day 1 Day 2 Day 3 Day 4 Day 5 Total Share %

    Mould Problem / Change /

    Adjust

    24 5 28 20 36 113 11.63

    Repair Work 22 0 25 25 25 97 9.98

    Spray Problem 4 2 4 0 4 14 1.44

    Upper not Lasted 4 0 4 0 4 12 1.23

    Cleaning & Reamer 102 18 15 0 15 150 15.43

    Mould Adjustment 7 0 6 9 6 28 2.88

    Upper not available0 49 54 10 57 170

    17.49

    Discolor 0 7 0 0 0 7 0.72

    Tip Cleaning 0 8 0 0 0 8 0.82

    Injection M/t Shortage 0 0 68 0 75 143 14.71

    Maintenance Problem 0 0 35 87 38 160 16.46

    Scrapper Problem 25 17 3 19 3 67 6.89

    Total 188 106 243 172 263 972 100 %

  • 8/8/2019 Production Planning and Logistic Systems 2

    52/116

    Production Planning and Logistic Systems 2010

    Page | 52

    Now for applying Pareto Rule, 1st

    of all we sort out these breakdowns on basis of their

    percentage share. So

    Problems Percentage Share Cumulative Percentage Share

    Upper not available 17.49 17.49

    Maintenance Problem 16.46 33.95

    Cleaning & Reamer 15.43 49.38

    Injection M/t Shortage 14.71 64.09

    Mould Problem / Change / Adjust 11.63 75.72

    Repair Work 9.98 85.70

    Injection Miss + Incomplete Sole

    (Scrapper Problem)

    6.89 92.59

    Mould Adjustment 2.88 95.47

    Spray Problem 1.44 96.91

    Upper not Lasted 1.23 98.14

    Tip Cleaning 0.82 99.28

    Discolor 0.72 100

  • 8/8/2019 Production Planning and Logistic Systems 2

    53/116

    Production Planning and Logistic Systems 2010

    Page | 53

    Graph 7: Pareto Chart for Breakdowns

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

  • 8/8/2019 Production Planning and Logistic Systems 2

    54/116

    Production Planning and Logistic Systems 2010

    Page | 54

    The graph shows that if we overcome these types of breakdowns we may avoid almost 85.70 %

    breakdowns. These breakdown cause are as follows:

    1. Upper not available .17.492. Maintenance Problem..16.463. Cleaning & Reamer.15.434. Injection M/t Shortage14.715. Mould Problem / Change / Adjust..11.636. Repair Work.9.98

    Total 85.70

    We may categorize our breakdowns into two types

    y Production Breakdownsy Mechanical Breakdowns

    Production breakdowns are usually because of worker carelessness regarding production. Good

    production planning may help to avioid these types of breakdowns. For example if materail

    shortage occurs then this is a production breakdown and proper production planning may help to

    avoid such types of breakdowns. According to our research study, Repair Work, Spray Problem,

    Upper not Lasted, Upper not available, Discolor, Injection M/t Shortage, Mould Adjustment, if

    we add all these causes of breakdown, these result 48.45 % of all breakdowns. So if we

    overcome this type of breakdown, we may improve our machine utilization up to 84 %.

  • 8/8/2019 Production Planning and Logistic Systems 2

    55/116

    Production Planning and Logistic Systems 2010

    Page | 55

    Mechanical Breakdowns are related to machines. For example, maintenance is a major issue in

    mechanical breakdowns. By adopting total productive maintenance(TPM), a hell of breakdown

    causes may be avoided. According to our research study, Cleaning & Reamer, Mould Problem,

    Tip Cleaning, Maintenance Problem, Injection Miss + Incomplete Sole (Scrapper Problem)

    If we add all these causes of breakdown, these result 51.55 % of all breakdowns. So if we

    overcome this type of breakdown, we may improve our machine utilization up to 86 %.

    Because of both of these breakdowns, our time loss is (0.289*450) 130 minutes. Hence our

    production loss is (130 * 1.5) 195 pairs. This is the production loss per day per machine. There

    are 15 such machines with the same breakdowns and with the same results. So if we overcome

    these breakdowns; production breakdowns and mechanical breakdowns; we may have dramatic

    improvement in our production and we will realize that our outsourced work will be reduced and

    list of our subcontractors will be shortened that is currently 19 subcontractors.

  • 8/8/2019 Production Planning and Logistic Systems 2

    56/116

    Production Planning and Logistic Systems 2010

    Page | 56

    Resource Planning: 4 Ms Approach

    1. Selection of Materials:Selection of materials for the product is a major role of production planning department.

    Production manager must have sound Knowledge of materials and their properties, so

    that he can select appropriate materials for his product. Research on materials is

    necessary to find alternatives to satisfy the changing needs of the design in the product

    and availability of material resumes. In selection of the materials, safety requirements,

    legal and regulatory requirements are taken into considerations. Selection of the materials

    becomes even more important when there are certain quality considerations. Better is the

    quality of the raw material, better will be the quality of the products, more satisfied will

    be the customers and higher will be the market share.

  • 8/8/2019 Production Planning and Logistic Systems 2

    57/116

    Production Planning and Logistic Systems 2010

    Page | 57

    Fig. 11: Materials Used in Shoe Manufacturing

  • 8/8/2019 Production Planning and Logistic Systems 2

    58/116

    Production Planning and Logistic Systems 2010

    Page | 58

    2. Selection of Methods:A product can be manufactured in a number of ways, using a number of methods.

    Finding the best method for the process that is consistent with the available resources of

    the organization including plant, machines and equipment is first priority of the

    production planning department. By doing this, organization will not have to invest much

    and install a separate plant for the process, they can only increase capacity of their

    running plant and achieve their goals. For products which require separate production

    setup, selection of production methods and identification of sequence of operations

    becomes an important job for PPC department. In selection of the methods and

    operations, safety consideration is of high importance. Methods and processes which are

    considered dangerous and have high injury rates, cause environmental problems are of

    least priority because safety and health of not only employees but of people living in

    vicinities of the organization is responsibility of the organization.

    3. Selection of Machines and Equipment:An operation can be performed on various types of machines which may differ in terms

    of their capacity, quality of finished good, power consumption and efficiency and

    effectiveness. So, production planning department has to choose from these available

    choices that best suit their requirements of capacity, quality, durability and performance.

    Equipment for Shoe Production at SIL:

    I. Cutting Machinesi. Pattern Cutting Machines

    Press Cutting Machine used for cutting of single layer

    Transfer Head Cutting Machine used for cutting of multiple layers

  • 8/8/2019 Production Planning and Logistic Systems 2

    59/116

    Production Planning and Logistic Systems 2010

    Page | 59

    ii. Splitting MachinesUsed to reduce the thickness of leather as per requirement

    iii. Skiving MachinesThey are used to reduce thickness of leather at the edges so that thickness

    remains according to standards even at the joints.

    II. Stitching Machinesi. Single Needle Machines

    This is most common type of stitching machines. Most of stitching operations

    are performed on these machines. They contain single stitching needle.

    ii. Double Needle MachinesThey contain two stitching needles. They are used when double stitching is

    required.

    iii. Zigzag Stitching MachinesThese machines are used to create zigzag stitching patterns.

    III. Injection Molding MachinesThese machines are used to produce sole for trainer footwear and also for some

    flat shoes. Sole Making chemicals such as Polyhole, Toluene, Iso-cyanide and

    some others are mixed in certain proportion and then injected in dies. Die for

    every product is manufactured separately.

    4. Selection of Man-PowerTo perform various tasks of the production process and keep the process running in

    desired way, educated, skilled, efficient, experience and motivated labor is required. For

    this purpose, organization can hire some experienced personnel in that particular field

  • 8/8/2019 Production Planning and Logistic Systems 2

    60/116

    Production Planning and Logistic Systems 2010

    Page | 60

    such as production managers, supervisors with experience, maintenance managers and

    crew and other personnel as per requirement of the job. Organizations can also train their

    own employees in those particular fields and develop man power of their own.

    Developing man-power in house or hiring experienced personnel is a top management

    decision.

  • 8/8/2019 Production Planning and Logistic Systems 2

    61/116

    Production Planning and Logistic Systems 2010

    Page | 61

    Production Control:

    Control is the last element in implementation of cycle of planning, monitoring and controlling.

    Information is collected about system performance, compared with desired performance level,

    and actions are taken, if required, to decrease the difference. Reporting performance, comparing

    the differences between actual and desired performance levels and accounting for why such

    differences exist are all parts of the control process. In essence, control is the act of reducing the

    difference between plan and reality.

    Elements of Concern:

    Control focuses on three elements;

    1. Performance2. Cost3. Time

    Production department is constantly concerned about these three aspects.

    1. Is it delivering what it is planned to deliver or more?2. Is it delivering at or below the promised cost?3. Is it making delivery at or before the promised time?

    It is strangely easy to lose sight of these fundamental targets, especially, in large productions.

    Large projects develop their own momentum and tend to get out of hands, going their own way

    independent of wishes of the production department and the intent of the proposal.

  • 8/8/2019 Production Planning and Logistic Systems 2

    62/116

    Production Planning and Logistic Systems 2010

    Page | 62

    1. PerformanceProduction department is responsible to minimize issues relating to performance of the

    production system. Such issues can be;

    i. Arise of unexpected technical problemsii. Deficiency of resources when needed

    iii. Insurmountable technical difficulties are presentiv. Quality or reliability problemsv. Requirement of changes in system on part of clients

    vi. Arise of inter-functional complications2. Cost

    i. Technical difficulties require more resourcesii. The scope of work increases

    iii. Too low initial bids or estimatesiv. Corrective control was not exercised in timev. Changes in input price

    vi. Poor or un-timely reportingvii. In-adequate budgeting

    3. Timei. Technical difficulties take longer than expected to solve

    ii. Optimistic initial time estimatesiii. Incorrect task sequencingiv. Un-availability of required inputs of material, personnel and equipmentv. Incomplete necessary preceding tasks

  • 8/8/2019 Production Planning and Logistic Systems 2

    63/116

    Production Planning and Logistic Systems 2010

    Page | 63

    vi. Customer-generated changed orders required re-workvii. Alteration in govt. regulations

    These are only a few of the relatively mechanistic problems that can occur. Actually, there are

    no purely mechanistic problems. All problems have a human element too. For example, humans,

    by action or in-action, set a large chain of events that leads to failure to budget adequately,

    creates a quality problem, leads the production down a technically difficult path or fails to note a

    change in govt. regulations. If by chance, some of these or other things happen, as a result of

    human action or not, humans are affected by them. Frustration, pleasure, determination,

    hopelessness, anger and many other emotions arise during the course of production. They affect

    the work of individuals who feel them for better or worse. It is over this welter of confusion,

    emotion, fallibility and general cussedness that the production control department tries to control.

    Fundamental Purpose of Production Control

    There are two fundamental objectives of production control

    i. Regulation of results through the alteration of objectivesii. Stewardship of resources of organization

    Most discussions of control function are focused on regulations. Production department needs to

    b equally attentive to both regulations and conversations. Production department must guard the

    physical assets of the organization, its human resources, and its financial resources. The

    processes for conserving these three different kinds of assets are different.

  • 8/8/2019 Production Planning and Logistic Systems 2

    64/116

    Production Planning and Logistic Systems 2010

    Page | 64

    1. Physical Asset ControlPhysical asset control requires control of use of physical assets. It is concerned with asset

    maintenance, whether preventive or corrective. Timing of maintenance and quality of

    maintenance are also important issues. If the production uses considerable amount of

    physical equipment, production control has the problem of setting up maintenance

    schedules in such a way as to keep the equipment in operating condition while

    minimizing the interference with ongoing work. It is critical to accomplish preventive

    maintenance prior to the start of that final section of the production known as last minute

    panic (LMP).

    2. Human Resource ControlStewardship of the human resources requires controlling and maintaining the growth and

    development of the people. They provide particularly fertile for cultivating people

    Note:

    Timing of the LMP is not known, which makes the planning for pre-LMP preventive

    maintenance somewhat difficult.

    Physical inventory, whether equipment or material, must also be controlled. It must be

    received, inspected or certified and possibly stored prior to use. Records of all in

    coming shipments must be carefully validated so that payment to suppliers can be

    authorized. The same precautions applied to goods from external suppliers must also

    be applied to suppliers from inside the organization.

  • 8/8/2019 Production Planning and Logistic Systems 2

    65/116

    Production Planning and Logistic Systems 2010

    Page | 65

    because they are unique, differing one from another in many ways. It is possible for

    people working on them to gain a wide range of experience.

    3. Financial Resource ControlThough accountants have not succeeded in developing acceptable human resource

    accounting, their work on techniques for conservation and regulation of financial

    resources has most certainly resulted in excellent tools for financial control. It is difficult

    to separate the control mechanism aimed at conservation of financial resources from

    those focused on regulating resource use. Most financial controls do both. Capital

    investment controls work to conserve the organizations assets by insisting that certain

    conditions be met before capital can be expended, and those same conditions usually

    regulate the use of capital to achieve the organization goal of a high return on

    investments.

    Functions of PPC at Control Stage

    1. Estimating:To fix up the Production targets and delivery dates and to keep the production costs at

    minimum, production management department does a thorough estimation of Production

    times and production costs. In competitive situation this will help the management to

    decide what should be done in arresting the costs at desired level.

    A sample of estimate sheet is given here.

  • 8/8/2019 Production Planning and Logistic Systems 2

    66/116

    Production Planning and Logistic Systems 2010

    Page | 66

    Estimate Sheet

    Plan issued:

    Plan Status:

    Cutting dept: Upper Cutting + Assembly

    Closing dept: Closing/Stitching Section

    Article: plan pairs: code:

    ref# : month:

    Cutting date: Plan Id#: cartons 39 40 41 42 43 44 45 *** Total

    Raw Material Requirement U/M

    Tape Magic Soft 50 mm Black-01 Mtr

    Tape Magic Hard 50mm Black-01 Mtr

    Tape Magic Soft 30mm Black-01 Mtr

    Tape Magic Hard 30mm Black -01 Mtr

    Leather Buff Nubuck Milled Dollar Printed 1.4-1.6mm Light Brown SFT

    Fabric Non Woven Cambrella Coated (imp) 150 gm/l .yds Width 44 D/Brown Mtr

    Assembly Fabric Play Boy Black+ eva 1.5 mm + Paly Boy Black Width 50 Mtr

    Fabric Knitted Polyester Play Boy Ribbed 3.50 oz/yd sqr. Min.width 41/42 Mtr

  • 8/8/2019 Production Planning and Logistic Systems 2

    67/116

    Production Planning and Logistic Systems 2010

    Page | 67

    Packing Material Requirement

    Label Sticker Servis Price for LSF Nos

    Rubber Natural Latex 60 % Liquid Kgs

    Carton 5-ply 795*420*355 mm Nos

    80X Shoe E.Flute Breezer 335 Nos

    Bag Shopper Nos

    Tape PVC Printed Rol

    Stuffing Sheet Sht

    Stuffing Paper Poster RIM

    Tie Nylon Tag String Nos

    Tag Breezer Nos

    Special Instructions:

    _____________________________________________________________________________________

    _____________________________________________________________________________________

    _____________________________________________________________________________________

    _____________________________________________________________________________________

    _____________________________________________________________________________________

  • 8/8/2019 Production Planning and Logistic Systems 2

    68/116

    Production Planning and Logistic Systems 2010

    Page | 68

    2. Loading and Scheduling:The Production Management department draws the time table for various production

    activities, specifying when to start and when to finish the process required. It also has to

    draw the timings of materials movement and plan the activities of manpower. The

    scheduling is to be done keeping in mind the loads on hand and capacities of facilities

    available.

    3. Routing:This is the most important function of Production Management department. The Routing

    consists of fixing the flow lines for various raw materials, components etc., from the

    stores to the packing of finished product, so that all concerned knows what exactly is

    happening on the shop floor.

    4. Dispatching:The Production Management department prepares various documents such as Job Cards,

    Route sheets, Move Cards, Inspection Cards for each and every component of the

    product. These are prepared in a set of five copies. These documents are to be released

    from Production Management department to give green signal for starting the production.

    The activities of the shop floor will follow the instructions given in these documents.

    Activity of releasing the document is known as dispatching.

  • 8/8/2019 Production Planning and Logistic Systems 2

    69/116

    Production Planning and Logistic Systems 2010

    Page | 69

    5. Expediting or Follow up:Once the documents are dispatched, the management wants to know whether the

    activities are being carried out as per the plans or not. Expediting engineers go round the

    production floor along with the plans, compare the actual with the plan and feed back the

    progress of the work to the management. This will help the management to evaluate the

    plans.

  • 8/8/2019 Production Planning and Logistic Systems 2

    70/116

    Production Planning and Logistic Systems 2010

    Page | 70

    Date:_______________

    Daily Production Report

    Job

    OrderNo

    Order

    Size

    Opening

    Balance

    (Quantity)

    Quantity to be

    Produced

    Issued to

    Dept

    Balance in

    Stock

    Return Wastage

    Prepared By:________________________ Approved By:_________________________

  • 8/8/2019 Production Planning and Logistic Systems 2

    71/116

    Production Planning and Logistic Systems 2010

    Page | 71

    Labor Report

    Name of

    Employee

    Working Hours

    Total Normal Over Time

    Machine Timing Report

    On Off Fault

    Machine Efficiency: __________________

  • 8/8/2019 Production Planning and Logistic Systems 2

    72/116

    Production Planning and Logistic Systems 2010

    Page | 72

    6. Inspection:Here inspection is generally concerned with the inspection activities during production,

    but a separate quality control department does the quality inspection, which is not under

    the control of Production Management. This is true because, if the quality inspection is

    given to production Management, then there is a chance of qualifying the defective

    products also. For example Teaching and examining of students is given to the same

    person, and then there is a possibility of passing all the students in the first grade. To

    avoid this situation an external person does correction of answer scripts, so that the

    quality of answers is correctly judged.

    Samples of Daily Inspection Report and Daily Rejection Sheet are given here.

  • 8/8/2019 Production Planning and Logistic Systems 2

    73/116

    Production Planning and Logistic Systems 2010

    Page | 73

    Inspection & Testing Report

    Sr No PO No Job No Operator Name Description of Material Length Weight Finishing

    Prepared By Checked By Final Inspection By Final Inspection By

    Packing Incharge Q. Controller QC Manager ProductionManager

  • 8/8/2019 Production Planning and Logistic Systems 2

    74/116

    Production Planning and Logistic Systems 2010

    Page | 74

    Daily Rejection Sheet

    Department: __________________

    Article: ______________________

    Date: ________________________

    Plan No.: _____________________

    Pairs: ________________________

    Sr No Operations TotalNon-Conformity Repairs Remarks

    1 Leather Defect

    2 Pasting/ Discolored

    3 Back Stitching4 Counter Stitching

    5 Upper Binding

    6 Upper Joining

    7 Upper Imitation

    8 Eyelet Fitting

    9 Zigzag Fault

    10 Eyeleting

    11 Side Punch/ Strip

    12 Thread Decoration

    13 Foam Collar

    14 Double Punch

    15 Damage

    Total: ______________________

    Rejection Percent: ____________

    Quality Inspector

  • 8/8/2019 Production Planning and Logistic Systems 2

    75/116

    Production Planning and Logistic Systems 2010

    Page | 75

    7. Evaluation:The Production department evaluates itself and its contribution in fulfilling the corporate

    objectives and the departmental objectives. This is necessary for setting up the standards

    for future. What ever may be the size of the firm; Production management department

    alone must do Routing, Scheduling, Loading, Dispatching and expediting. This is

    because this department knows very well regarding materials, Methods, and available

    resources etc. If the firms are small, all the above-mentioned functions ( i to x) are to be

    carried out by Production Management Department. In medium sized firms in addition to

    Routing, Scheduling and Loading, Dispatching and expediting, some more functions like

    Methods, Machines may be under the control of Production Management Department. In

    large firms, there will be Separate departments for Methods, Machines, Materials and

    others but routing, loading and scheduling are the sole functions of Production

    Management.

    Post Control

    Post control is also known as post performance control or post project control. Post control

    document contains a description of the objectives of the production. Usually the description is

    taken from the proposal and entire proposal often appears as an appendix to the post control

    report. As objectives include the effects of all change orders issued and approved during the

    execution process.

    Post control document also contains a report of performance against the planned schedule and

    budget. This can be prepared by combining and editing the various status reports made during

    the production. Significant deviations of actual schedule and budget from planned schedule and

  • 8/8/2019 Production Planning and Logistic Systems 2

    76/116

    Production Planning and Logistic Systems 2010

    Page | 76

    budget should be highlighted. Explanations of why these deviations occurred are also included in

    post control report.

    Final Report on Production Results

    When significant variations of actual performance from planned performance are indicated, no

    distinction is made between favorable and unfavorable variations. Managers focus their attention

    on the trouble, use tools like

    i. Cause and effect diagramii. Failure mode and effect analysis

    Complete documents are developed regarding reasons of the variations or failure, recommended

    actions to solve the problem and suggestions for the future so that the problem will not arise

    again.

    A specimen of Daily Production Report is given here.

  • 8/8/2019 Production Planning and Logistic Systems 2

    77/116

    Production Planning and Logistic Systems 2010

    Page | 77

    Scheduling

    Determining when an activity should start or end, depending on its

    1. Duration2. Predecessor activity (or activities)3. Predecessor relationships4. Resource availability5. Target completion date of the project.Scheduling pertains to establishing both the timing and use of resources within an

    organization. Under the operations function (both manufacturing and services), scheduling

    relates to use of equipment and facilities, the scheduling of human activities, and receipt of

    materials. Generally, scheduling objectives deals with tradeoffs among conflicting goals for

    efficient utilization of labor and equipment, lead time, inventory levels, and processing times.

    Approaches to Scheduling

    There are two general approaches to scheduling:

    1. Forward SchedulingWith forward scheduling, the scheduler selects a planned order release date and

    schedules all activities from this point forward in time.

  • 8/8/2019 Production Planning and Logistic Systems 2

    78/116

    Production Planning and Logistic Systems 2010

    Page | 78

    2. Backward Scheduling: Scheduling Approach used SILWith backward scheduling, the scheduler begins with a planned receipt date or due date

    and moves backward in time, according to the required processing times, until he or she

    reaches the point where the order will be released.

    As long as the concepts are applied properly, the choice of methods is not significant. In fact, if

    process lead times (move, queue and setup times) add to the job lead time and process time is

    assumed to occur at the end of process time, then forward scheduling and backward scheduling

    yield the same result.

    Loading

    Loading involves assigning jobs to work centers and to various machines in the work centers. If

    a job can be processed on only one machine, no difficulty is presented. However, if a job can be

    loaded on multiple work centers or machines, and there are multiple jobs to process, the

    assignment process becomes more complicated. The scheduler needs some way to assign jobs to

    the centers in such a way that processing and setups are minimized along with idle time and

    throughput time.

    Approaches to Loading

    Two approaches are used for loading work centers

    1. Infinite LoadingWith infinite loading, jobs are assigned to work centers without regard for capacity of

    the work center. Priority rules are appropriate for use under the infinite loading

  • 8/8/2019 Production Planning and Logistic Systems 2

    79/116

    Production Planning and Logistic Systems 2010

    Page | 79

    approach. Jobs are loaded at work centers according to the chosen priority rule. This

    is known as vertical loading.

    2. Finite Loading: Approach being used at SILFinite loading projects the actual start and stop times of each job at each work center.

    Capacity of each work center is taken into consideration and compared with the

    processing time so that process time does not exceed capacity. With finite loading,

    job that has the highest priority is loaded on all work centers it will require. Then the

    job with the next highest priority is loaded on all required work centers, and so on.

    This process is referred to as horizontal loading. A drawback of horizontal loading is

    that jobs may be kept waiting at a work center, even though the work center is idle.

    This happens when a higher priority job is expected to arrive shortly. The work center

    is kept idle so that it will be ready to process the higher priority job as soon as it

    arrives. This was a problem which was considered during machine utilization

    improvement work.

  • 8/8/2019 Production Planning and Logistic Systems 2

    80/116

    Production Planning and Logistic Systems 2010

    Page | 80

    Sequencing

    Sequencing is concerned with determining the order in which jobs are processed. Not only must

    the order be determined for processing jobs at work centers but also for work processed at

    individual work stations. When work centers are heavily loaded and lengthy jobs are involved,

    the situation can become complicated. The order of processing can be crucial when it comes to

    the cost of waiting to be processed and the cost of idle time at work centers.

    There are a number of priority rules or heuristics that can be used to select the order of jobs

    waiting for processing.

    y Random (R). Pick any job in the queu