Upload
vitapur1
View
218
Download
0
Embed Size (px)
Citation preview
8/4/2019 Production of Rigid PU and PIR Slabstock
1/9
Page 1 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
Production of rigid foam slabstockfrom polyurethane or polyisocyanurateat low investment cost
Siegfried Buschkamp
8/4/2019 Production of Rigid PU and PIR Slabstock
2/9
Page 2 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
Production of rigid foamslabstock from polyurethaneor polyisocyanurate at low
investment cost
Summary
This technical information sheet describes the
minimal resources and equipment required to start
and run polyurethane rigid foam slabstock produc-
tion, for example in developing countries.
Contents
Page
1. General introduction 2
2. Equipment and resources 3
required for operating a slabstock
foaming plant
2.1 Buildings
2.2 Personnel
2.3 Slabstock molds
2.4 Technical equipment and apparatus
2.5 Containers
2.6 Accessories
2.7 Raw materials
3. Procedure 4
4. Example of slab production 5
5. Observations on personnel 7
6. Shed plan 8
7. Suppliers' addresses 9
1. General introduction
This information sheet is intended to show the
minimal expenditure on buildings, equipment and
personnel required for polyurethane rigid foam
slabstock production.
Polyurethane also includes polyisocyanurate rigid
foam, as this is merely a specific variant.
Slabstock manufacture by stirrer mixing offers the
following advantages in addition to the low cost of
investment:
High-viscosity products can be mixed
Formulations can easily be varied
Pastes and colorants can be added
Working by this method does, however, mean cer-
tain disadvantages:
Increased costs through greater losses of
material (residues of about 2 kg in the mix-
ing vessel)
Costs of a polyethylene bag to line the mix-
ing vessel
A considerable amount of air is taken in.
This is generally beneficial as it leads to afine cell structure due to nucleation. Increa-
sed viscosity of raw materials and/or short
cream times can lead to large individual
pores (entrapped air) and lower thermal in-
sulation.
Products with short reaction times are diffi-
cult to process. However, this applies only
very rarely as the reaction times can usually
be adjusted by varying the catalyst content.
8/4/2019 Production of Rigid PU and PIR Slabstock
3/9
Page 3 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
2. Equipment and resources requiredfor operating a slabstock foamingplant
2.1. Buildings2.1.1 Space for production, approx. 100 - 200 m
2.1.2 Space for storage of raw materials and
foam slabstock
2.1.3 Space for cutting and packaging equipment
2.1.4 Extractor on mixing unit Extractor on cutting
machines Extractor on production units,
possibly in storage area
2.1.5 System for keeping raw materials at tem-
peratures as near as possible to 20 - 22 C
2.1.6 Wash basin and eye-rinse water at work-
place
2.2 Personnel (see observations on personnel
under Item 5)
2.3 Slabstock molds (approx. 2 - 3),
e.g. 1 x 1 x 0.8 m, costs of wood + 50 man-
hours + costs for small components
2.4 Technical apparatus
2.4.1 Balance, range up to 200 kg for mixing and
production
2.4.2 Balance, range up to 10 kg for addition of
small amounts (table balance)
2.4.3 Stirrer2.4.3.1 Powerful hand drill (sufficient for blocks up
to 1/2 m3
with low-viscosity raw materials)
2.4.3.2 Fixed stirrer (output approx. 2 - 7 kW)
2.4.3.3 Stirrer discs
2.4.4 Drum lifting truck
2.4.5 Band-saw for trimming and cutting
2.4.6 Paper cutting device
2.5 Containers
2.5.1 Mixing vessel (size: the vessel should be
about half full when it contains the batch)
2.5.2 PE round-bottom sacks to fit mixing vessel2.5.3 Plastic container for rinsing liquid
2.5.4 Measuring beaker for weighing or measur-
ing out additives If the density of the raw
materials is taken into account, balances
can often be dispensed with when using
measuring beakers
2.5.5 Rubbish bags and bins
2.5.6 If 2.5.2 is unobtainable, 2.5.1 should be a
plastic container with which it is possible to
knock out the residues
2.6 Accessories
2.6.1 Protective goggles
2.6.2 Dust filters for sawing
2.6.3 Stopwatch
2.6.4 Rubber gloves
2.6.5 Packaging paper for covering the floor andfor making molds for control pours
2.6.6 Staplers with staples
2.6.7 Scissors/shears
2.6.8 Knives
2.6.9 Felt pens for writing on the foam
2.6.10 Adhesive tape for sticking paper to the floor
2.6.11 Work table approx. 1 x 1m, 80 cm high, for
putting down the accessories and the
measuring beakers for the foam additives
(catalysts, etc.)
2.6.12 Release agent, wax or grease and sponge
2.6.13 Drum-cocks
2.7 Raw materials
2.7.1 Polyol with drum-cock and drum lifting truck
2.7.2 Isocyanate with drum-cock and drum lifting
truck
2.7.3 Blowing agent
2.7.4 Catalyst
2.7.5 Solvents
8/4/2019 Production of Rigid PU and PIR Slabstock
4/9
Page 4 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
3. Procedure
3.1 Prepare and assemble the mold 3 minutes
Apply release wax 2 minutes
3.2 Place polythene bag into mixing vessel 1/2 minute
put in polyol 2 - 5 minutes
(depending on quantity and viscosity)
put in blowing agent 1/2 minute
put in catalyst 1/2 minute
Premix products 1 minute
During the pre-mixing time, fill a separate container
with isocyanate and then, with the stirrer running, pour
it into the polyol and mix 1/2 minute
Carefully pour the reaction mixture into the mold 1/2 minute
Put on lid and secure with wedges 1 minute
Clean stirrer with solvent 1/2 minute
Remove polythene bag with residue (loss from mixing) 1/2 minute
3.3 Mold residence time 10 - 15 minutes
With densities over 60 kg/m3, the slabstock mold should be
opened soon after the fiber time, and at the latest before the
rise time, so the slab can relax without cracking.
Rule of thumb: Slab height in cm = 100 - density
3.4 Demolding the slab 2 minutes
3.5 Take the demolded slab (preferably in batches of
4 blocks per hour) to an external store where they
should remain for at least 5 days 2 minutes
3.6 Cutting: About 40 s are needed for one cut through a
1 m long slab. This gives 28 cuts, each of 40 s, when
cutting up a 70 cm thick slab into 30 mm sheets = 18 2/3 minutes
3.7 Packaging: By the saw there should be a device in
which the sawn sheets can be stacked. This allowssimple packaging.
8/4/2019 Production of Rigid PU and PIR Slabstock
5/9
Page 5 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
4. Example of slab production
The total quantity MA of the batch is obtained from
the volume V of the mold to be filled, the desired
average density RD, the quantity MV of reaction
mix remaining in the mixing vessel and the differ-
ence in buoyancy A between the liquid reaction mix
and the finished foam (= weight of displaced air,
approx. 1.2 kg/m at 20 C) and from the loss MG of
blowing agent occurring during mixing and expan-
sion of the reaction mix.
GVA MMAxVRDxVM +++=
The quantities MK of components are calculated as
follows:
nformulatioperweightbypartsof
MquantityTotalM AK =
Parts by weight of component per formulation
Here is an example:
Volume of molding V = 2.05 x 1.05 x 0.7 = 1.5 m
Desired average density RD = 35 kg/m
Buoyancy difference A = 1.2 kg/m
Quantity remaining in mixing vessel MV 2.5 kg
(determined experimentally)
Loss of blowing agent MG = approx. 0.5 kg
(determined experimentally)
From the foregoing equation, the batch quantity
is:
MA = 1.5 m 35 kg/m + 1.5 m 1.2 kg/m +
2.5 kg + 0.5 kg= 52.5 kg + 1.8 kg + 2.5 kg + 0.5 kg
= 57. 3 kg
Formulation:
100 parts by weight polyol
20 parts by weight blowing agent
2 parts by weight catalyst
120 parts by weight polyisocyanate
242 parts by weight Total
The individual quantities are therefore:
Baymer polyol MPolyol = kg23.68100x242
57.3=
Blowing agent MTM = kg34.7420x242
57.3=
Catalyst MDesmorapid = kg0.4742x24257.3 =
Polyisocyanate MDesmodur = kg28.4120x242
57.3=
The mold in which the foam is formed and cures
can be a wooden box in the simplest case. To sim-
plify demolding, the internal surfaces should be
smooth. Release papers (for example polyethylene-
coated kraft paper or soda kraft paper) may be laid
or stuck in the mold prior to foaming or release
agents (for example release wax) may be used. In
the latter case, the mold walls may be lined with
sheet metal (for example aluminum sheet) or
melamine resin-coated sheets. Release agent sup-
pliers can be found under "Suppliers' addresses".
Slabs are produced as follows:
The mold is set up, and a release agent is applied
to the interior of the walls. The mixing vessel is
balanced, and polyol, blowing agents and catalysts
are poured in and mixed. The components are in-
troduced in the following order: large quantities
before small and low-viscosity products before high-
viscosity products. Finally, the polyisocyanate com-ponent is weighed in or a weighed quantity added.
The components must be mixed thoroughly and
poured into the mold within the cream time which is
sometimes very short (approx. 15 to 40 s).
8/4/2019 Production of Rigid PU and PIR Slabstock
6/9
Page 6 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
Fig. 1: Front elevation of a slabstock mold
Fig. 2: Side elevations and perspective view of a slabstock mold
It is easiest to foam in open molds. The reaction
mix is introduced into a mold (which is open at the
top) where it expands and forms a foam slabstock.
Although the pressure building up on the side walls
is relatively low, it must be allowed for when design-
ing the mold on account of the large areas. With
polyurethane slabstock, pressures of 0.1 bar have
been measured with a density of 35 kg/m and
about 0.15 bar with a density of 60 kg/m. Polyiso-
cyanurate foam develops higher pressures.
The build-up of pressure may be counteracted by
opening the mold 5 to 15 min after foaming of the
block and allowing the foam to expand freely. This
is achieved by loosening the wing nuts of the
screwed rods. The foam slab which now expands
beyond the mold dimensions should be able to
8/4/2019 Production of Rigid PU and PIR Slabstock
7/9
Page 7 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
move unimpeded over the edge of the baseplate. If
the mold is not opened after these short periods, it
is necessary to wait a few hours to prevent the slab
from tearing. The slab should be demolded when
the pressure on the mold has become sufficiently
low, and this moment should be determined ex-perimentally.
The freely rising foam forms a domed surface and
its cells are oriented predominantly vertically (ani-
sotropically). The dome formation, which may result
in a considerable quantity of scrap when cut to size,
may be reduced if the foam is allowed to rise with a
floating lid. Once the reaction mix has distributed
itself on the bottom of the mold and the foaming
process has begun, a lid is placed on top. This lid
floats on the surface of the reaction mix and is
forced up by the foam. The mold can also have a
very simple design here, but should have smooth
internal surfaces to prevent the tightly sealing lidfrom jamming. The rising lid may have to be guided
by hand. The lid normally has a weight per unit area
of about 40 kg/m2.
A completely rectangular slab may be obtained if
the lid abuts against a stop and compacts the foam
slightly.
Fig. 3: Foaming against a floating lid
In some applications, the foam must have only a
very slight cell orientation. This can be achieved by
introducing the reaction mix into a mold which can
be sealed all round and compacts the foam to a
greater extent. The pressure applied to the mold is
correspondingly higher. This foaming under pres-
sure necessitates long mold residence times as the
slabs might otherwise tear.
After production, the slabs are left to cool for at
least 3 to 5 days - usually in an open store - beforesheets or shaped parts are cut from them.
5. Observations on personnel
The number of staff needed for the foaming process
depends on the number of slabs, the size of the
slab and the amount of mix to be processed per
slab. These points, together with the production
time per slab and the quantity of raw materials that
can be processed per year, are given in the table
below.
The figures are based on the assumption that one
man can handle a batch quantity of 30 kg and two
men, one of 80 kg. With larger quantities, a foaming
machine is needed. At least two persons are
needed to put on the floating lid if no crane is avail-
able. When a lid of this kind is used, the amount ofcutting waste is reduced by about 5 % to 15 - 20 %.
A lid should therefore be applied in each case.
A figure of 3 - 5 % has already been included in the
table for the amount of residue left in the mixing
vessel. An overall density of 35 kg/m3
was as-
sumed.
8/4/2019 Production of Rigid PU and PIR Slabstock
8/9
Page 8 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
On a large vertical bench band-saw, one man can
cut up about 20 m3
of foam slabstock in 6 h full
working time. This represents approx. 150 tonnes
per year. Two foaming machine operators produce
as much slab material as two men can cut up on
two bench band-saws (see table). It is thereforeessential to ensure proper investment in the cutting
machines, i.e. considerable automation and per-
haps mill saws should be provided.
6. Shed plan
Fig. 4: Slab production diagram
8/4/2019 Production of Rigid PU and PIR Slabstock
9/9
Page 9 of 9
File No.: PU21020-0409
Issue 2004-09-10
InsulationTechnical Information
7. Addresses of suppliers in Germany
7.1 Laboratory stirrer: Type LM 34
Pendraulik Maschinen und Apparate GmbH
Phillipp-Reis-Str. 3631832 Springe
Tel.: 05041 / 40 61
Fax: 05041 / 50 29
7.2 Production stirrer
Lehmann Maschinenfabrik GmbH, F. B.
Daimlerstr. 12
73431 Aalen
Tel.: 07361 / 5 62 - 0
Fax: 07361 / 5 62 - 60
E-Mail: [email protected]
7.3 Stirrer discs: e.g. Lenart rapid stirrer
Vollrath GmbH & Co., Paul
Max-Planck-Str. 13
50354 Hrth
Tel.: 02233 / 79 89 - 0
Fax: 02233 / 7 87 49
7.4 Round bottom polybags
Nittel GmbH & Co. KG
(Rau) Kelsterbacher Str. 18
65479 RaunheimTel.: 06142 / 94 67 - 0
Polymer-Synthese-Werk GmbH
Landrat-von-Laer-Str. 12
47495 Rheinberg
Tel.: 02844 / 10 - 0
7.5 Drum-cocks
Will & Hahnenstein GmbH Fasstechnik,
Wrmetechnik Anl. Fax: 0271 / 3 75 91 - 25Arnsbacher Weg 5 - 9
57072 Siegen
Tel.: 0271 / 3 75 91 - 0
7.6 Balances
Mettler-Toledo GmbH
Ockerweg 3
35396 Gieen
Fax: 0641 / 5 29 51
Tel.: 0641 / 5 07 - 0
E-Mail: [email protected]
7.7 Release wax
Acmos Chemie GmbH & Co.
Industriestr. 37 + 49
28199 Bremen
Tel.: 0421 / 51 89 - 0
Fax: 0421 / 51 14 15
IGEFA GmbH
Bonnstr. 31
50226 Frechen
Tel.: 02234 / 9 57 21 - 0
Fax: 02234 / 5 21 37
Th. Goldschmidt AG
Goldschmidtstr. 100
45127 Essen
Tel.: 0201 / 1 73 - 01
Fax: 0201 / 1 73 - 18 31
This information and our technical advice whether verbal, in writing or by way of trials are given in good faith but without warranty, andthis also applies where proprietary rights of third parties are involved. Our advice does not release you from the obligation to verify the in-
formation currently provided - especially that contained in our safety data and technical information sheets - and to test our products as to
their suitability for the intended processes and uses. The application, use and processing of our products and the products manufactured by
you on the basis of our technical advice are beyond our control and, therefore, entirely your own responsibility. Our products are sold in
accordance with the current version of our General Conditions of Sale and Delivery.
The methods described in this publication for testing the fire performance of polyurethane and the results quoted do not permit direct con-clusions to be drawn regarding every possible fire risk there may be under service conditions.
Publisher: Business Development Insulation
Bayer MaterialScience AG
D-51368 Leverkusen
www.bayermaterialscience.com