Upload
trantram
View
218
Download
1
Embed Size (px)
Citation preview
PROCUREMENT & IMPLEMENTATION
OF
URBAN TRANSPORT PROJECTS
S. SIVAMATHAN
GM/DMRC
GLIMPSES OF UT MODES
Structure of Presentation
Objectives of Module
Preparation of Feasibility Report (FR) and Detailed Project
Report (DPR)
Procurement Process
Contracting Options and Case Studies
Procurement Strategies
Preparation of RFQ/RFP
Bid Process Management
Contract Management including condition for „Make in India‟
Case Example/Case Studies
3
Objective of Module The objective is to make the users mainly understand the following:
Components of project life cycle
Preparation of Feasibility Report and DPR, and their appraisal
Preparation of Terms of Reference (TORs) and Request for
Proposals(RFP)
Procurement and contracting strategy for urban transport projects
Preparation of bid documents, contract documents and Agreements
Project implementation options and models
Preparation of various types of procurement documents and
contract documents
Bid process, evaluation and award of contracts
Supervise/ monitor/ manage projects
4
Project Life Cycle
Project Identifica
tion Project Scoping
Planning
Project
Preparation
Appraisal Public
Consultation
Project Structurin
g
Contracting
Implementation
Monitoring &
Evaluation
Project Life
Cycle
PROCUREMENT & IMPLEMENTATION OF UT PROJECTS
PROCUREMENT & IMPLEMENTATION OF UT PROJECTS
UT PROJECT DEVELOPMENT STAGES
A: Conceptual
Macro Planning Study
Pre-Feasibiliy Study
B: Project Formulation
Feasibility Study
Detailed Project Report
Detailed Engineering
C: Contracting Phase
Bid Process Management
D: Project Implementation
Project Implementation
Operation & Maintenance
How to select a Consultant for Preparing
DPR? Procedures and steps for hiring consultants
Preparation of cost estimate and budget
Preparation and issue of:
Request for Proposal (RFP);
Letter of Invitation (LOI)
Information to Consultants (ITC)
Proposed Contract
Receipt of proposals
Evaluation of technical proposals: consideration of quality
Evaluation of financial proposal
Final evaluation of quality and cost
Negotiations and award of the contract to the selected firm
8
SCOPE OF STUDIES - 1 COMPREHENSIVE MOBILITY PLAN(CMP)
(Macro-Planning)
CMP to form the basis of subsequent Studies. Multimodal Transit System based on Vision, Policies, Objectives,
Regulatory Requirements
TYPICAL MULTIMODAL TRANSIT NETWORK
PROCUREMENT & IMPLEMENTATION OF UT PROJECTS
SCOPE OF STUDIES – 2
PRE-FEASIBILITY STUDY
(for Project Identification)
Traffic Estimation on identified corridor(s)
Reconnaissance/Investigation Survey
Preliminary Design of suggested Transit Mode &
Infrastructure
Project Cost
O&M Cost
Technical Feasibility Report
PROCUREMENT & IMPLEMENTATION OF UT PROJECTS
SCOPE OF STUDIES - 3
TECHNO-ECONOMIC FEASIBILITY STUDY
(for Administrative Approval)
Economic Profile Survey & Traffic Survey Leading to Traffic Analysis & Traffic Projection on identified corridor(s)
Preliminary Topographic Survey including limited Geotechnical Investigations, Preliminary Structural Designs for suggested Transit Mode
System Design for selected mode
Assess Equipment Required viz., Buses, Metro/LRT Coaches etc.,
EIA (Environmental Impact Assessment) & R&R (Rehabilitaiton and Resettlement)
Project Cost
O&M Cost
EIRR & FIRR
Techno-economic Feasibility Study Report
PROCUREMENT OF CONSULTANCY & IMPLEMENTATION
SCOPE OF STUDIES - 4
DETAILED PROJECT REPORT (DPR) (for technical approval & Financial Sanction)
Detailed Traffic Forecast Study
Topographic Survey including Geotechnical Investigations, Preliminary Structural Designs for suggested Transit Mode
System Design for selected mode
Issues with Local Authorities for traffic regulation, Shifting of Utilities, land requirements etc.
Assess Equipment Required viz., Buses, Metro/LRT Coaches etc.,
EIA (Environmental Impact Assessment) & R&R (Rehabilitation and Resettlement)
CMP (Comprehensive Mobility Plan)
Project Cost
O&M Cost
EIRR & FIRR
Project Implementation Strategy
PROCUREMENT OF CONSULTANCY & IMPLEMENTATION
PURPOSE
Instruct Bidders on procedure for submission of bids
Describe Goods or Works to be procured or Consultancy Required
Inform the Bidders of criteria for qualification & evaluation
Define Conditions of Contract
PROCUREMENT OF CONSULTANCY & IMPLEMENTATION
PROCUREMENT OF CONSULTANCIES
SCOPE OF STUDIES - 5 PROJECT MANAGEMENTCONSULTANCY (PMC)
Scope depends on extent of delineation/defining the role of PMC & Employer
Preferably the need of PMC should be decided prior to award of works /supply contracts as the project sub-divided into various works to be awarded separately
STRUCTURING PMC BIDDING DOCUMENTS
Specify Requirements in TOR: Project Management/Construction Management Teams
List of All Contracts to be awarded
System Interaction Controls Performance Specifications
Quality Control /Quality Assurance Systems
Procedures for Change order, Claims, Financial control Delegation of authority
Define role of Engineer vis-à-vis Project Management Consultant
Reporting Systems
PROCUREMENT OF CONSULTANCY & IMPLEMENTATION
RFP BIDDING DOCUMENTS
for consultancy projects
Notice Inviting Proposals
Instruction to Consultants (ITC)
Appendix to ITC
Evaluation & Qualification Criteria
Forms for Submission of Proposals
(a) Technical
(b) Financial
Terms of Reference Special Conditions of Contract
General Conditions of Contract
Forms of Agreement.
PROCUREMENT OF CONSULTANCY & IMPLEMENTATION
PROCUREMENT & IMPLEMENTATION
Appendix to ITC – Important Clauses
Case Example
PROCUREMENT & IMPLEMENTATION
RFP DOCUMENTATION STRUCTURE
Consultancy Assignments
RAFTING OF TOR
DRAFTING OF TERMS OF REFERENCE
KEY TOPICS
1. Objectives: To be Defined based on previous Studies, possible financing
options, lessons of previous exercises, and the purpose it will
lead for decision making.
2. Scope: Work Components - specify with clarity
Details to which consultant must address in the output
3. Counterpart Effort: What facilities, reports, equipment etc., shall be provided
including reporting and coordination
4. Program for submission of Interim &Final Reports
5. Stakeholders Meeting; Details of manner of conducting and costs
6. Training Needs of Client: Details of personnel, their qualification and period
7. Key Persons & Support Personnel: Qualification, Experience, Period of
Deployment etc.
8. Specifications: If any, required to be specified
Case Example
PROCUREMENT & IMPLEMENTATION
CONDITIONS OF CONTRACT
(Consultancy Assignments)
GCC •Contract Clauses are substantially different from Works contracts
•Standard Forms of Contract for Consultancy be used
SCC Staffing Schedule of Deployment
Insurance
Performance Securities
Manner of & Implications of change of Personnel
Payment Procedures
Price adjustment
Disputes
Conditions of Contract
Selection of Consultants
The hiring of consultants should be undertaken through competition
among qualified short-listed firms
Selection should be based on technical proposal and on the cost of the
services to be provided (Quality & Cost Based Selection [QCBS]).
Other acceptable selection procedures in addition to QCBS are as under :
Quality Based Selection (QBS)
Fixed Budget Selection (FBS)
Least Cost Selection (LCS)
Single Source Selection (SSS)
Selection of individual consultants
Selection of Consultants
19
PROCUREMENT & IMPLEMENTATION
RFP DOCUMENTATION STRUCTURE –
Prequalification)
Notice Inviting Tenders (Bids)
Instruction to Tenderers (Bidders)
Appendix to ITT (ITB) or Bid Data Sheet
Bidding Forms
Employer’s Requirements
General Conditions of Contract
Special Conditions of Contract
Forms of Agreement.
For Works
Case Example
PROCUREMENT & IMPLEMENTATION
RFP DOCUMENTATION STRUCTURE
For
Procurement of Works
PART 1- Bidding Procedures
Notice Inviting Bids (Tender)
Instruction to Bidders (Tenders)
Appendix to ITB (ITC)
Forms for Submission of Proposals
Part 2 – Employer’s Requirements
Price Bid Document
Terms of Reference
Specifications
General Conditions of Contract
Special Conditions of Contract
Forms of Agreement.
Appraisal of DPR – JnNURM
PROCUREMENT & IMPLEMENTATION
Compliance of NUTP & TOR
Covers coordination issues with local authorities. Viz.., Traffic Management ,
Utilities Shifting , Land acquisition, Legal & Regulatory
Economic & Financial Viability
Financing options
Procurement Strategy
Procurement Process
Identify Project Implementation
Option
Type of Procurement
Method
Finalise Type of Contract
Qualification and Bidding
Criteria EoI/ RFQ
Queries/ Response
Short listing
Issue of RFP Pre bid
meeting
Amend bid document
Two cover bid submission
Technical Shortlisting
Financial Opening
Financial Evaluation
Issue of LoI
Negotiation and Contract
Signing
PROCUREMENT & IMPLEMENTATION
EVALUATION OF KEY PERSONNEL QUALIFICATIONS
3. General Qualifications
1 Professional Qualifications 10 (i) Length of Experience and Positions held 5 (ii) Time with the consulting firm 5 (iii) Overseas Experience 10
Sub Total 30 b) Adequacy for the project
i) Project Management Experience 20 ii) Professional Experience specific to the Assignment 25
(i) Specialization/skills useful for project 15 Sub Total 60 c) Experience in Region and Language 2. Experience of working in similar area/region 7 2. Knowledge of local language in addition to English 3
Sub Total 10 Grand Total 100
Contracting Options
Public Private Partnerships (PPP) vs. Engineering
Procurement Construction (EPC) Contracts
26
EPC PPP
Project is implemented by a public/
Government agency. Herein, private
goods/ services can be procured by the
public agency by competitive bidding
process. Though, private sector won‟t be
allowed entailed as a revenue share
stakeholder.
NEED FOR EPC
• Guaranteed Price
• Guaranteed Timeline for Completion
• Specified Level of Performance
• Single Point of Responsibility
• Post-Commissioning Services
• Flexibility and Certainty
• Higher Supervision and Control
An arrangement between the public and
private sectors with clear agreement for
delivery of public infrastructure and/or
public services, revenue and risk sharing.
BENEFITS
• Speedy, Efficient and Cost-effective
delivery of Projects
• Higher Performance Incentives
• Better Value of Money
• Competition and Greater Construction
Capacity
• Higher Accountability
• Better Risk Allocation
• Government Support
Source: http://ecurrentaffairs.in/blog/special-article-on-epc-mode-vs-ppp-mode-for-national-highways/
Contracting Options Types of works contract
Lumsum / Measurement Contracts
PROCUREMENT & IMPLEMENTATION
Lumpsum Contracts : As the name indicates, the contractor undertakes to carry out the
work to completion for a lump sum price.
The complete, full detail and exact scope of work required to be done under the
lumpsum contract is laid down by way of drawing and specification incorporated into the
tender documents. Recording of detailed measurement at site is not necessary.
Interim payments are made on the basis of assessment of the progress of work actually
done i.e., mile stones achieved.
Type of Lumpsum Contracts:
Design & Built contract
Part Design & Built and
Built only contracts
Contracting Options Types of works contract
Lumsum / Measurement Contracts
PROCUREMENT & IMPLEMENTATION
Measurement Contracts: In measurement contracts, quantities of
various items involved in the scope of work are stated approximately in
the BOQ contracts. The exact amount payable to contract for running
account bill/final bill is decided only after measurement of each item of
work done at site priced at rates quoted for each item of work.
Types of Measurement contracts:
Item Rate Contract (BOQ): In this type of contract the tenderer is
supplied with BOQ which contains item with approximate quantities.
Percentage rate contract on pre-priced BOQ:
• Who is Financing ?
• Who does most of the Design?
• How complex is the project?
• What are the Performance Requirements?
• Constraints of Cost & Time.
Criteria for Choosing the Form Of Contract ?
PROCUREMENT & IMPLEMENTATION
BRT & Bus Operations
• Buses
• Infrastructure
• Bus Q Shelters with Passenger Information
System and lighting
• Operation & Maintenance
Typical Projects for UT Systems
PROCUREMENT & IMPLEMENTATION
Parking Areas
A: Multilevel Parking Projects • Land
• Infrastructure
• Operations and Maintenance
B: On-street & Off-street Parking • Land
• Infrastructure
• Operations and Maintenance
Typical Projects for UT Systems
PROCUREMENT & IMPLEMENTATION
URBAN RAIL TRANSIT
Metro/Mono Rail • Civil Engineering Infrastructure – Underground Tunnel,
Viaducts & Associated Buildings • Station Buildings with all Services • Track Infrastructure • Traction Infrastructure • Signaling & telecommunications • Air conditioning and Ventilation –(Generally for
Underground Systems.)
Typical Projects for UT Systems
PROCUREMENT & IMPLEMENTATION
Procurement of Goods
PROCUREMENT & IMPLEMENTATION
SYSTEMS OF PROCUREMENT
International Competitive Bidding (ICB)
Open Tender (without Pre-qualification)
Open Tender (with Pre-qualification)
Limited Tender
Single Tender
Cash Purchase
Registration of Suppliers
Procurement of Goods
PROCUREMENT & IMPLEMENTATION
SYSTEMS OF PROCUREMENT
Single Tender
Adopted for Proprietary Items
To avoid delays in an emergency
Cash Purchase/Petty Purchase
Suitable for Small Value
Standard Specifications
Off the Shelf availability
Cash Purchase Procedures
• Market Survey
• Selection of Firms
• Quotation/Performa Invoice –At least three
GLOBAL PROCUREMENT (ICB)
FUNDING AGENCIES REQUIREMENTS
INADEQUATE DOMESTIC PARTIES
HIGHER TECHNOLOGY IMPORT
CONTRACT ADMINISTRATION
Objectives Ensure Project Completion
On Time, Quality, Minimum cost Without any Disputes Manage Changes in Scope
by
S. K. Manglik
PROCUREMENT & IMPLEMENTATION
CONTRACT ADMINISTRATION
Elements to Control & Plan
Project Planning
Time Control
Change control
Cost control
Compliance of laws, Regulations, Policies
Enforcement of Terms of Contract
by
S. K. Manglik
PROCUREMENT & IMPLEMENTATION
CONTRACT ADMINISTRATION
Establish Employer’s Organization (Within the framework of the Employer’s Delegation & Requirements)
Employer (Employer)
The Engineer
Specialists
Supervisors
Engineer’s Role
Supervision & Administering the Contract
Quasi Judicial Role
by
S. K. Manglik
PROCUREMENT & IMPLEMENTATION
CONTRACT ADMINISTRATION
SYSTEMS & PROCEDURES
Monitoring
Ordering procedure
Payment procedure
Resource management
MIS
Change
Variations
Deviations
by
S. K. Manglik
PROCUREMENT & IMPLEMENTATION
Case Example
Background
In a Standing Committee Meeting of an urban local
body held on 25th January 2015, based on advise of a
city engineer, a decision was taken to develop 2 urban
roads.
The City Engineer is advised to implement the project
immediately and accordingly a Notice Inviting Tender
(NIT) is to be issued by him on 30th January 2015
41
• What are the issues in this entire process ?
Problems and Issues
42
• The Standing Committee took a decision on implementation of
the project without conducting a Feasibility Study/ DPR and
neither advised the City Engineer to get a DPR/ Feasibility Study
conducted
• The Project Implementation Options were not deliberated upon.
The project could be implemented on a PPP basis or through
funding support from other Government agencies
• If the city does not have internal resources/ capacity to
conceptualize/ structure the project, external assistance from
advisors/ consultants should have been taken before issuing
the NIT.
Notice Inviting Tender Given below is a tender notice that appeared in the newspapers. Read the tender
notice and list out all the lacunae that you find
Government of ………………/
Government of ……………..Urban Development Trust
…………………………Municipality
Tender Notice No:8/ ____________/__________/12-13
Dated:30-1-2012
The Municipal Commissioner,………………… Municipality, invitees sealed tenders
from interested bidders for “Providing Street lighting in the unserved areas in
Package-A: Road No ……to……. Of Sector …… and
Package-B: Road No ……to……. Of Sector ……”
Estimated Contract value of work is (a) Rs 255.55 lakhs (b) Rs 154.85 lakhs. Last
Date for receipt of tenders including EMD is before 3.00Pm on (a) 21-01-2013 (b)
21-01-2013.
Documents can be purchased from the Municipal Commissioner ,
…………….Municipality Ph.No……………..,Fax No…………..by remitting a D.D. or
Municipal Challan for Rs 22,000/- before 5.00pm on (a) 16-01-2013 (b) 16-01-2013.
Other details regarding eligibility etc. are in the tender documents.
Sd/-
(City Engineer,……….)
43
Lacunae in the NIT
Following are the lacunae for the above Tender Notice
Reference of website for downloading the detailed tender notice not given
Eligibility/Qualification of bidders not mentioned
Bidders are eligible to apply for individual packages or not
Eligibility in terms of joint venture and consortium details not mentioned
EMD amount not mentioned
Pre-bid meeting and contact person to be contacted
Application sale start dates
Qualification Criteria in terms of technical and finance
Is the Cost of tender document of Rs 22,000/- is for Package (A) or both
packages
44
Case Studies
Case Studies
Concessionaire : L&T
Cumulative Length: 71.16 km
Project Cost: Rs 12132 Cr.
Govt. Grant: Rs 1458 Cr.
Concession Period: 35 years (with extension for 25 years)
Govt. owns “Golden Share” in SPV- one representative on Board with
affirmative powers
Real Estate Development at:
3 Depots : Total cumulative area- 11.61 Lakhs sqm.
25 Stations: Total cumulative area- 5.57 Lakhs sqm.
Automatic Annual Fare Revision linked with WPI
Revenue Share with Govt: (Ceiling 10%)
Period Revenue Share (% of realized revenue-net of any tax)
1st to 21st year 0.5%
22nd to 23rd year 1%
23rd onward 1.5%
Hyderabad Metro
Shareholders in Concessionaire
Company:
IL&FS Rail- 48%
ITNL- 26%
DLF- 26%
Based on DBFO model
Total Concession Period: 99 years
Schedule and fare integrated with DMRC
Modalities of Implementation of Gurgaon Metro
Bus Terminus Developed on PPP
No Name of
Project
Project
Area Components
Mode of
Development Remarks
1
Ludhiana
Bus
Terminal,
Punjabi
8 acre
(Rs 15
Cr- 2001)
35 bus bays, 100
ideal parking's
Passenger amenities
Limited
Commercial
Adda Fee to PSP
BOT Mode
• Concession Period was
bidding parameter
• BOQ was fixed
• Sources of Revenue were
limited.
2
Manali Bus
Terminal,
Himachal
Pradesh
4 acre
(Rs 100
Cr-2012)
• 35 bus bays
• 30 idle paring
• Local bus bays
• 426 MLCP
• passenger
concourse
• STU office space
DBFOT
Mode
• ACF was the bidding
parameter
• Difficult terrain for work
• Enormous potential for
commercial development
• MLCP & New Bus Stand
was the need of the town.
3
Zirakpur
Bus Stand ,
Punjab
1 acre
(Rs 4 Cr)
• Transit bus stand
• Bus Lay bus &
Parking
(EPC/ Cash
Contract)
• Scale is small
• Limited Revenue Sources
• Further to be Converted
in O & M contract
Case Study – Ahmedabad, BRTS
SPV contracts and monitors
Buses procured by operator and operating on gross cost +
incentives basis
Minimum guaranteed kms committed by SPV
SPV has financial as well as manpower support from MC
Fare revision linked with change in fuel price & WPI, periodic revision
on 1st April of every year
Cost/km revision wrt change in fuel & WPI
Incentives/penalties linked with pre-defined performance parameters
Change in schedule, fleet size at the discretion of SPV
System sustainability: breaking even
Case Study – Ahmedabad, BRTS
Intelligent Transit Management System (ITMS) –
Conceptual Overview of AJL ITMS
MAKE IN INDIA
DMRC’S CONTRACT CONDITIONS
52
Rolling Stock Procurement by Delhi Metro- an apt
example of ‘Make in India’
Tender for procurement of 486 Standard Gauge cars (RS 10) for Line 7 & Line 8 of Phase-III of Delhi Metro.
Tender was finalized based on International Competitive Bidding (ICB) and awarded to Hyundai Rotem (a Korean Firm).
Maximum no of cars (6 cars in 1 train set) that can be manufactured in off-shore factory outside India is 120.
The balance 366 cars shall have to be manufactured in India.
To achieve the above condition, the contractor is required to establish facilities either independently or with an Indian partner.
Rolling Stock Procurement by Delhi Metro-
an apt example of ‘Make in India’
DMRC has also identified the spares that shall be indigenized and sourced only from India. In case of any deviations in this regard, there are stiff conditions/ penalties.
Conditions similar to the above were incorporated while procuring the Rolling Stock for Phase-I & Phase-II of Delhi Metro and for other metros like Chennai, Cochin etc.
Overall, 1,134 cars out of 1,234 cars procured by DMRC for Phase-I & Phase-II of DMRC have been manufactured indigenously.
For Phase-III of DMRC, more than 85% of the rolling stock required would be manufactured indigenously.
Rolling Stock Procurement by Delhi Metro-
an apt example of ‘Make in India’
As a result of the above steps taken by DMRC, the following rolling stock manufacturing facilities have come up in India:
BEML .
Bombardier India.
Alstom India.
A number of ancillary units have also been set up.
This results not only in competitive price for future procurements for metros in India, but also leads to generation of jobs and taxes - a true accomplishment of MAKE IN INDIA.
COMPREHENSIVE MOBILITY PLANNING
CMP is a transport sector master plan-cum-
investment program document to meet the mobility
concerns arising from the population and business growth of the study area.
Topographical & Geotechnical Survey
Topographical survey: Investigation about the ground
details including type of buildings, river, utilities, trees
etc
Geo-Technical Survey:
Soil Investigation – to design the type of foundation i.e.,
pile or open foundation?
Water level measurement – do-
Rock investigation, &
Instruction to Tenders (ITC) It provides information about the following:
Project,
Scope of Work
Source of Funding
Conditions if any for manufacturing in India,
Quality Outline, Safety Outline,
Milestone payment schedule,
Sub-Contracting
Tender validity, Guarantee, Insurance,
Tender Opening, Evaluation, Award, Signing of contract agreement etc
Employer’s Requirements
General :
Design Submission programme, Design process,
Preliminary Design, Final Design,
Availability of source code, Tests,
Unit Exchange spares, Consumables, Training,
Access to Site, Transportation to site, Operations manual, progress photographs etc
Technical: Design and performance requirements, Bogies, Train
control Management system, Heating, Ventilation and air-conditioning, Communication systems, Inspection, Tests & Trials, Interface between RS and S&T contractors etc
Detailed Engineering Layout planning, Inventory taking on site
Design of pipe layout and instrumentation
Calculation of material requirements and technical specifications
Definition of interfaces
Technical description of the processes
Quality assurance and quality control
Monitoring of time schedules
Cost control
Supervision of construction and installation work
Commissioning of plant components
Supervision of commissioning
Technical support for production / Commissioning, Trial runs etc
Process optimization
Documentation
Types of Contract Item Rate Contract (BOQ):
In this type of contract the tenderer is supplied with BOQ which
contains item with approximate quantities.
The tenderer quotes rates for each item of work, to be measured
in detail before payment.
The quantities given in the BOQ are stated to be approximate
and variation is to be handled as per contract condition.
Percentage rate contract on pre-priced BOQ:
The tenderer quotes a % above/below against the total amount in the
price priced BOQ containing items with approximate quantities and rates
as per DSR.
For NDSR items, estimates are prepared based on the LAR.
Amounts payable under RA bills and final bills are decided on the basis
of measurement of work done priced at rates given in pre-priced BOQ,
adjusted by the quoted percentage.
Introduction and Objective of Study
Project Need and Justification, Project Area Characteristics
Existing Situation and Anticipated Demand
Options Considered and Comparison of Feasible Options - Preliminary technical & financial
assessment
Conclusions and Recommendations- Gives a GO/No GO
Introduction and other elements same as Pre-feasibility Report
Definition, Scope and, Purpose
Technical Specifications- Scope, Features of the project, location, broad alignment
Examination of the Critical Risks and Problems of the Project
Broad estimation of Financial and Economic returns from the project
Evaluation and Conclusion- Gives Recommendations - is the project technical and
financially feasible and does it warrant a DPR to be made
Introduction and other elements same as Feasibility Report
Existing Situation - Traffic and Transportation Characteristics - Issues and Policy
Project Details - Detailed Design and drawings of Project components - Technical
Specification – Detailed Project Cost and BoQ
Social and Environmental Impacts
Project Implementation Framework - Project Institutional Framework
Project Financial Structuring and Phasing - Project O&M Framework and Planning
Project Financing - Financial Viability & Sustainability -
Project Benefits Assessment (Social Cost-Benefit Assessment) - Risk Management
Framework
Conclusion - Detailed Design Drawing and Technical Specification ; Cost and Revenue
Estimates
Defining Feasibility Report and DPR
63
Pre-
Feasibility
Report
Detailed
Project Report
Feasibility
Report
Procurement
As per the Procurement Bill 2012 of Indian Government,
„„procurement‟‟ or “public procurement” means the acquisition of
works, goods or services by a procuring entity, and includes all
stages of the process of acquisition, by purchase, lease, licence or
otherwise, of works, goods or services, beginning with the process
for determining the need for such acquisition and ending with
completion and expiry of the procurement contract or framework
agreement, but does not include any acquisition without
consideration, and “procure” or “procured” shall be construed
accordingly.
64
Procurement
As per the Procurement Bill 2012:
Bill apply to Ministry or Department of the central Government,
any Central Public Sector Undertaking (50%), or authority or
society or trust or autonomous body (by whatever name called)
established or constituted under an Act of Parliament or a body
owned or controlled by the Central Government.
Bill shall not apply to procurements, which are less than INR 50
lakhs, emergency procurements made for disaster management,
and procurement for the purpose of national security.
65 States Government should follow their own acts and
regulations for procurement of good and services
PRE-QUALIFICTION CRITERIA
Working Capital should be more than AT/7
Annual Turnover = Value of work to be one in a year (Estimated
Value/Completion Time)
Turnover = Annual Turnover X 80%
Work Experience of similar works
Value of one work =>80% of the estimated value
Value of two works = 50% each of estimated value
Value of three works = 40% each of estimated value
66
MAKE IN INDIA
DMRC’S CONTRACT CONDITIONS
67
Rolling Stock Procurement by Delhi Metro- an apt
example of ‘Make in India’
Tender for procurement of 486 Standard Gauge cars (RS 10) for Line 7 & Line 8 of Phase-III of Delhi Metro.
Tender done on International Competitive Bidding and awarded to Hyundai Rotem.
Maximum no of cars (6 cars in 1 train set) that can be manufactured in off-shore factory outside India is 120.
The balance 366 cars shall have to be manufactured in India.
To achieve the above condition, the contractor is required to establish facilities either independently or with an Indian partner.
Rolling Stock Procurement by Delhi Metro-
an apt example of ‘Make in India’
DMRC has also identified the spares that shall be indigenized and sourced only from India. In case of any deviations in this regard, there are stiff conditions/ penalties.
Conditions similar to the above were incorporated while procuring the Rolling Stock for Phase-I & Phase-II of Delhi Metro and for other metros like Chennai, Cochin etc.
Overall, 1,134 cars out of 1,234 cars procured by DMRC for Phase-I & Phase-II of DMRC have been manufactured indigenously.
For Phase-III of DMRC, more than 85% of the rolling stock required would be manufactured indigenously.
Rolling Stock Procurement by Delhi Metro-
an apt example of ‘Make in India’
As a result of the above steps taken by DMRC, the following rolling stock manufacturing facilities have come up in India:
BEML .
Bombardier India.
Alstom India.
A number of ancillary units have also been set up.
This results not only in competitive price for future procurements for metros in India, but also leads to generation of jobs and taxes - a true accomplishment of MAKE IN INDIA.
Product Life Cycle
The period of time over which an item is developed, brought to market and eventually removed from the market.
First, the idea for a product undergoes research and development.
If the idea is determined to be feasible and potentially profitable, the product will be produced, marketed and rolled out.
Assuming the product becomes successful, its production will grow until the product becomes widely available.
Eventually, demand for the product will decline and it will become obsolete.