22
Process for Evaluating Logistics Process for Evaluating Logistics Readiness Levels (LRLs) for Readiness Levels (LRLs) for Acquisition Systems Acquisition Systems October 26, 2005 Aging Aircraft Integrated Product Team (AAIPT) Elizabeth Broadus Booz Allen Hamilton, Inc. Technology & Process Cost Logistics Engineering

Process for Evaluating Logistics Readiness Levels (LRLs) for ......Process for Evaluating Logistics Readiness Levels (LRLs) for Acquisition Systems October 26, 2005 Aging Aircraft

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • Process for Evaluating LogisticsProcess for Evaluating LogisticsReadiness Levels (LRLs) forReadiness Levels (LRLs) for

    Acquisition SystemsAcquisition Systems

    October 26, 2005

    Aging Aircraft Integrated Product Team (AAIPT)Elizabeth BroadusBooz Allen Hamilton, Inc.

    Technology& Process

    CostLogistics

    Engineering

  • AgendaAgenda

    • Background of Logistics Readiness Level (LRL) concept• LRL Defined• LRL Excerpts• Benefits• Next Steps• Questions• NAVAIR Aging Aircraft Points of Contact

  • BackgroundBackground

    • LRL concept initially based on the DOD 5000.2mandated Technology Readiness Levels (TRL)assessment process

    • TRLs provide:– Evaluation of critical technology maturity– Maturation plan (as needed)– Best practices/guidelines for each Milestone

    • MS B target is TRL = 6• MS C target is TRL = 7• MS C preferred is TRL = 8

  • Background: TRL DefinitionsBackground: TRL Definitions

    TRL 9----

    TRL 8----

    TRL 7----

    TRL 6----

    TRL 5----

    TRL 4----

    TRL 3----

    TRL 2----

    TRL 1

    TRL 2----

    TRL 1

    • System Completed• Flt / Mission Qual

    • System/SubsystemDevelopment

    • Tech Demo

    • TechDevelopment

    •Research to ProveFeasibility

    • Basic TechResearch

    System Validated on Representative A/C Via OT …

    System Validated on Representative A/C Via DT …

    System Demo ~ Dynamic OP Flight Environ ….

    Sys/Subsys Demo ~ Relevant Lab Environ …

    Component/Breadboard ~ Relevant Environ …….

    Component/Breadboard ~ Lab Environ ………….

    Analytical /Experimental Proof-of-Concept …….

    Technology Concept ………………………

    Basic Principles ……………………………

  • BackgroundBackground

    • TRLs provide an understanding of the technical maturitywithout consideration of the sustainment of thosetechnologies– TRLs were never intended to consider logistics– LRLs is a new concept with the intent to consider

    sustainment issues

    • Logistics benchmark system was desirable– ~10 logistics elements that are often interdependent

    and parallel are required to successfully acquire, field,and support new technology

    – Aid in understanding what sustainment is required atdifferent time phases

  • LRL DefinitionLRL Definition• LRL intent:

    – Provide a methodology for assessing LogisticElement Readiness for technology

    – Establish benchmarks for programs at differentphases in time

    – Provide a management tool to forecast logisticsworkload, manpower requirements, identify gaps,etc.

    • NAVAIR Aging Aircraft convened a working group ofengineers, logisticians, and program managers to draftan LRL concept– LRL concept is work in progress!!!– Initial phase was to focus on technology insertion

    for in-service (post MS C) aircraft platforms– LRL evaluated for project (vice platform)

  • Draft LRLDraft LRL• LRL’s considered at the project level (i.e. technology

    insertion) for an in service aircraft• LRL’s evaluated for 6 project phases:

    – Lab Test/R&D– Project Definition (Fleet Need/metrics/BCA/Decision to

    proceed)– Project Development /Implementation (Finalized

    analysis, change recommended, ECP development,Class II change development, RAMEC, LECP, other)

    – Engineering Validation– Fleet Verification– Fleet Use

    • Answers question of what has to be done at each projectphase for logistics

  • LRL ExcerptLRL Excerpt –– Design InterfaceDesign Interface

    Technicalupdatescompleted andavailable.

    Technicalupdates (such asMaintenanceRequirementCard changes)verified.

    Results of RCMand FMECA usedto develop ormodify existingcondition basedand schedulebasedmaintenancetasks. Results ofRCM and FMECAalso used toupdate the CriticalItems list asapplicable.Technical dataupdates draftedand validated.

    For new designs,ReliabilityCenteredMaintenance(RCM) andFailure Modesand EffectsAnalysis(FMECA)completed toidentify failuremodes, failurefrequency, effecton performance,and criticality.For modificationsto existing design,RCM and FMECAreviewed forimpacts. Designinterface issuesresolved.

    ExistingReliability andMaintainability(RAM) metricsreviewed. Initialimprovementpredictionsdetermined.Design interfaceissue resolution inwork.

    Review andidentifysignificantdesigninterfaceimpacts ofproject toexistingsystem orplatform (ex.availablepower,weightconstraints,etc.) CreatePOAM toresolve anydesigninterfaceissues.

    DesignInterface

    Fleet UseFleet

    VerificationEngineeringValidation

    ProjectDevelopment/Implementat

    ionProject

    Definition)

    LabTest/R&D

    phase

    Phase

  • LRL ExcerptLRL Excerpt –– Training and FacilitiesTraining and Facilities

    Fleet Use

    FleetVerificati

    on

    EngineeringValidati

    on

    ProjectDevelopment/Implementati

    on

    ProjectDefinit

    ion

    Lab TestR&D

    phase

    Phase

    New or modifiedFacilitiescompleted .

    Facilities projectcompletedand approved.

    As needed withfundingavailable,Facilitiesmodifications or newfacilitiesprojects inwork.

    Current Facilities reviewedand impacts

    identified. Whenapplicable, facilitiesmodifications or new

    requirements aredocumented and

    analysis completedfor (in) adequacy ofexisting facilities,trade studies for

    optimal new facility,funding requested.

    Facilities

    Traininingcurriculaupdated.NTSPupdated.

    Training curriculachangesupdated postvalidation/verification withchanges asnecessary.NTSPchangesfinalized.Changessubmitted forapproval.

    Trainingcurriculachangesdrafted. Asrequiredchanges toNavalTrainingSystemsPlan(NTSP)drafted.

    Impacts to Trainingidentified

    Existing trainingprocedures/curricula andtrainingplanidentifiedandreviewed.

    Training

  • LRL ExcerptLRL Excerpt –– DMSMSDMSMS

    Fleet UseFleet

    VerificationEngineering

    Validation

    ProjectDevelopment/Implementation

    ProjectDefinition

    Lab TestR&Dphase

    Phase

    Metrics andusagemonitored asrequired.

    DMSMSmanagementplan updated.Technical datapackage thatsupportsDMSMSmitigationstrategyavailable.

    DMSMSforecastingcompletedfor newtechnology.Updates toDMSMSmanagementplan drafted.Technicaldatapackagerequirementsdrafted.

    New technologyevaluatedtodeterminecriticality asit relates toDMSMS.Assesscomponents againstthe techrefreshstrategy.Impacts toDMSMSplan ormetricsidentified.

    ExistingDMSMSprogrammanagement planreviewed.Determinethetechnicalrefreshstrategy(2 yr, 4 yr,spiral, etc.)

    DMSMS

  • Draft LRLDraft LRL

    • Evaluated percentage of total effort required at eachphase

    • Graphed percentage effort as a function of phase of theproject

    • Percent effort is subjective number based on effortsoutlined in the LRL for each element at each phase

    • Many other ways to depict data– 3 examples follow

  • Percent Effort by Project Phase

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    Lab Test/R&D Phase Project Definition Project Development Engineering Validation Fleet Verification Fleet Use

    Project Phase

    Perc

    ent E

    ffort

    Maintenance PlanningSupply SupportTechnical DataTrainingFacilitiesManpowerPHS&TSupport EquipmentComputer ResourcesDesign InterfaceDMSMS

  • Percent Effort During Each Phase

    0

    10

    20

    30

    40

    50

    60

    Lab Test/R&D Phase Project Definition Project Development EngineeringValidation

    Fleet Verification Fleet Use

    Phase of Project

    Perc

    ent E

    ffort

    Technical DataMaintenance PlanningTrainingFacilitiesSupply SupportManpowerPHS&TSupport EquipmentComputer ResourcesDesign InterfaceDMSMS

  • Percent Effort vs. Project Phase

    0

    20

    40

    60

    80

    100

    120

    Tech

    nical

    Data

    Maint

    enan

    cePla

    nning

    Train

    ing

    Facil

    ities

    Supp

    lySu

    pport

    Manp

    ower

    PHS&

    TSu

    pport

    Equip

    ment

    Comp

    uter R

    esou

    rces

    Desig

    n Inte

    rface

    DMSM

    S

    Logistic Element

    Perc

    ent E

    ffort

    Fleet UseFleet VerificationEngineering ValidationProject DevelopmentProject DefinitionLab Test/R&D Phase

  • • Benefits include:– LRLs will be a template/benchmark to measure readiness

    by logistic element on a project level basis– Template can be utilized to train/mentor new logistics

    personnel (and engineering personnel) in sustainmentrequirements for tech insertion projects

    – LRLs will aid in planning manpower/funding/schedulerequirements for projects as they mature from projectconcept to implementation

    – LRLs will dovetail with logistics risk assessments foranother perspective

    LRL BenefitsLRL Benefits

  • • Continue to collect input on Draft LRL concept• Brief Draft LRL concept to solicit further input• Update/change draft as needed• Establish a working group to expand the scope to

    encompass aircraft in the entire lifecycle vice limiting to in-service aircraft

    • Apply and test the process at NAVAIR AAIPT

    Next StepsNext Steps

  • Questions?

  • • AAIPT Lead, Bob Ernst, 301-342-2203,[email protected]

    • AAIPT Assistant Program Manager for Logistics, HarryProffitt, 301-757-0868, [email protected]

    • AAIPT Air Vehicle IPT lead, Don Sheehan, 301-342-0131,[email protected]

    • AAIPT Consultant, Elizabeth Broadus, 301-862-7049,[email protected]

    AAIPT Points of ContactAAIPT Points of Contact

  • Backup SlidesBackup Slides

  • AAIPT OrganizationAAIPT Organization

    0

    5

    10

    15

    20

    25

    30

    1992

    1994

    1996

    1998

    2000

    2002

    2004

    2006

    2008

    2010

    Ave

    rage

    Age

    (Yea

    rs)

    Army

    Commercial

    Navy

    USAF

    Average Age > 20 Years

    Problem: Aging Aircraft

    - Identify Problems - Quantify Risk- Provide Information to Program teams- Advocate for Enabling Technologies- Provide Standard Risk & Cost EvaluationTools

    - Focus Attention to Aging Aircraft problems- Leveraged Funding to reduce cost

    AAIPT Vision:AAIPT Vision:

    Why is an AAIPT needed?

  • H-46

    AV-8H-1

    H53

    AIR 1.0 AIR 3.0 / 6.0 AIR 4.0 / 5.0

    AAIPT LEAD

    STAFFFUNCTIONS

    WIRING &POW ER

    LOGISTICS

    AIR VEHICLE AVIONICS OBSOLESCENCEFASTRACK

    SUSTAINMENT(S.E.T.)

    COST

    FINANCES

    CONTRACTS

    JCAA

    On BoardDiagonstics

    Off BoardDiagonstics

    C ircuitProtection

    Batteries

    ProcessImprovement

    Fire Extinguisher

    Corrosion

    Hydraulics

    Transparencies

    Aeromachanics

    NDI / NDE

    Bearings

    Repair / Bonding

    S & T

    Legacy

    Process

    Policy

    Process /Tools

    “Hot Line”

    PMA Support

    Policy

    Process

    StructureAnalysis

    Products

    ENVIRONMENT

    AAIPT OrganizationAAIPT Organization

    • Command Support ThroughoutNAVAIR

    • Technical Expertise

    • Adequately staffed to meetemergent needs (Triage)

    • Command Support ThroughoutNAVAIR

    • Technical Expertise

    • Adequately staffed to meetemergent needs (Triage)

    Fleet Focus Teams

  • Fleet Focus TeamFleet Focus Team

    • Fleet Focus Teams (FFTs) identify, communicate, and leverageengineering solutions across Type Model Series and/or ServiceBoundaries

    • Fleet Focus Teams (FFTs) identify, communicate, and leverageengineering solutions across Type Model Series and/or ServiceBoundaries

    Simply Stated:

    Common FleetIssue

    Fleet FocusTeam

    (Engineering,Logistics,

    Cost)

    Common Solution