11
Search Print this chapter Cite this chapter PROCESS ECONOMICS C. R. Deddis BP Exploration Operating Company Ltd., UK Keywords: Chemical Engineering, process plant, economic evaluation, projects, net present value, internal rate of return, payback, cost estimation, risk, uncertainty. Contents 1. Introduction 2. Economic Evaluation of Chemical Process Projects 3. Economic Evaluation Techniques 4. Economic Evaluation of a Major Project in Practice 5. Economic Evaluation of Modifications to Operating Process Plants 6. Optimization of Operating Costs 7. Challenges for the Future Related Chapters Glossary Bibliography Biographical Sketch Summary Chemical processes have been harnessed to transform resources and raw materials into more useful and hence more valuable products to improve the living standards of people. This principle is at the core of Chemical Engineering. These industries have matured in the twentieth-century and have been very successful at creating wealth. The means of establishing which products to make and how to optimize the processes required for manufacture have been based on economic principles. This chapter defines how value is attributed to the material and energy streams that make up a process and then how this information is used to determine the economic value of options to ensure that optimum designs are reached. Approaches to accounting for the risks to the economic value of projects are also considered to ensure that they deliver the expected benefits. Once a chemical process plant is in operation there is an ongoing Optimization of the profit by adjusting operating variables and modifying the process to improve production capacity or quality. There is recognition that, whilst economic evaluation techniques have served the industry well, there are growing challenges in how to define ‘value’, particularly related to the long term sustainability of the human race and the planet. Chemical Engineers and economists must respond to this challenge to ensure that chemical process which can improve the quality of life continue to be ‘economically’ viable. 1. Introduction The Chemical Process Industries have played an important part in the economic growth of nations. Humankind has been able to use its knowledge of the natural sciences to invent large scale manufacture of chemical products to enhance the quality of everyday life. The chemical processes transform raw materials into more PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3... 1 of 11 1/15/2013 6:20 PM

Process Economics

Embed Size (px)

DESCRIPTION

llll

Citation preview

Search Print this chapter Cite this chapter

PROCESS ECONOMICS

C. R. DeddisBP Exploration Operating Company Ltd., UK

Keywords: Chemical Engineering, process plant, economic evaluation, projects, netpresent value, internal rate of return, payback, cost estimation, risk, uncertainty.

Contents

1. Introduction2. Economic Evaluation of Chemical Process Projects3. Economic Evaluation Techniques4. Economic Evaluation of a Major Project in Practice5. Economic Evaluation of Modifications to Operating Process Plants6. Optimization of Operating Costs7. Challenges for the FutureRelated ChaptersGlossaryBibliographyBiographical Sketch

Summary

Chemical processes have been harnessed to transform resources and raw materialsinto more useful and hence more valuable products to improve the living standardsof people. This principle is at the core of Chemical Engineering. These industrieshave matured in the twentieth-century and have been very successful at creatingwealth. The means of establishing which products to make and how to optimize theprocesses required for manufacture have been based on economic principles. Thischapter defines how value is attributed to the material and energy streams that makeup a process and then how this information is used to determine the economic valueof options to ensure that optimum designs are reached. Approaches to accounting forthe risks to the economic value of projects are also considered to ensure that theydeliver the expected benefits. Once a chemical process plant is in operation there isan ongoing Optimization of the profit by adjusting operating variables andmodifying the process to improve production capacity or quality.

There is recognition that, whilst economic evaluation techniques have served theindustry well, there are growing challenges in how to define ‘value’, particularlyrelated to the long term sustainability of the human race and the planet. ChemicalEngineers and economists must respond to this challenge to ensure that chemicalprocess which can improve the quality of life continue to be ‘economically’ viable.

1. Introduction

The Chemical Process Industries have played an important part in the economicgrowth of nations. Humankind has been able to use its knowledge of the naturalsciences to invent large scale manufacture of chemical products to enhance thequality of everyday life. The chemical processes transform raw materials into more

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

1 of 11 1/15/2013 6:20 PM

useful and therefore, more valuable materials that provide benefits to the end users.Fertilizer manufacturer, for example, enables more productive use of land to providehigher yields of important crops. This ability to take a raw material and add valuethrough its transformation into something more useful creates economic wealth andultimately improves the living standards of people.

In order to sustain the manufacture of useful products the processes must beeconomically profitable. In other words the costs of manufacture must be less thanthe income generated through product sales. Therefore, it is vitally important toassess the economic benefits of investments in new processes to ensure that theventure is economically viable and sustainable. This is not a one-off exercise at thestart of a project but an ongoing process throughout the entire lifetime of thechemical plant as it is adapted and modified to improve the manufacturing process,change product characteristics, replace obsolete equipment, respond to changes inenvironmental and safety legislation and so forth.

Process economics is an important element of the Chemical Engineering disciplineand is concerned with the Optimization of profit which is determined by the processengineering design and ultimately operation. The Optimization, therefore, requiresan ability to determine the influence of processing techniques and sequencing, andequipment design and operating parameters on the economic performance.

Despite the Chemical Process Industries covering a diverse range of products theprinciples in determining the value of these processes are the same and are drawnfrom economics. This paper will discuss the main methods employed to evaluateprojects and optimize operations in the Chemical Process Industries.

1.1. The Economic Nature of Chemical Processes

Chemical processes fundamentally transform raw materials into more usefulproducts that are consequently of higher value. In its simplest form a chemicalprocess consists of a series of material and heat flows which can be represented by asimple model as shown in Figure 1:

Figure 1. Chemical Process Schematic

Each of these material or energy flows has an economic value either as a cost or asource of income. For instance, energy consumed in a process will have a cost whichreflects its generation and transmission but it may also be possible that a processgenerates a source of energy that can be utilised and sold to a third party therebygenerating income.

At the heart of most chemical processes is a chemical reaction. The stoichiometry ofthe chosen transformation process will set the material and heat flows for the processand ultimately the economics for that process.

This can be expressed in a general sense as:

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

2 of 11 1/15/2013 6:20 PM

The stoichiometry and thermodynamics of a chemical reaction determines the degreeto which the feed materials are converted to products as well as the overall heatrequirements. The effluent from the reactor will contain unconverted feed, productsand contaminants. Unconverted feed material is separated and recycled or re-used toimprove the product yield. Products will have to be separated from the wasteproducts and waste products will need to be treated such that they can be re-used,recycled or disposed of in an environmentally sound manner.

All of this processing requires additional unit operations which have energyrequirements in the form of electricity, steam, cooling water, refrigeration etc. Thesedemands will have to be met by generating on site or importing from third parties.Therefore, from the choice of reaction route the process flowsheet containing all thenecessary unit operations can be defined with associated costs and revenue streams.The influence that each of the material and energy streams have on the economicsare considered in turn below.

1.1.1. Feedstock

The cost associated with feedstock is determined by both its quantity and quality.The quantity required is a function of the reaction yield to produce the desiredamount of product. The quality of the feedstock defined by its purity of reactant isan important factor in reducing the quantity of unwanted by-products and/or wasteproducts from the reaction. The presence of impurities can also reduce catalystactivity and increase corrosion leading to the introduction of further processingsteps, higher operating costs to replace catalysts and the use of more expensivecorrosion resistant materials for equipment fabrication.

1.1.2. Catalyst

Catalyst selection is usually made on the basis of product yield and selectivity.Optimization of the catalyst can reduce investment and operating costs. Forinstance, a reduction in residence time will therefore reduce the equipment size for agiven capacity and allowing the reaction to occur at lower operating temperaturesand pressures leads to thinner walled vessels potentially made of cheaper materials.

1.1.3. Energy

A major cost for most chemical processes is energy. Energy streams are required ina variety of forms both as sources of heat and also as heat sinks e.g. steam forheating, electricity for pump and compressor motors, water for cooling. It is alwaysdesirable to use energy efficiently. The choice of reaction route is often one of themost important factors in determining the overall energy requirements of a processand once set can be difficult to subsequently optimize throughout the life cycle of theprocess. There are also opportunities to produce useful forms of energy that can beoptimized. For example, the heat generated by exothermic reactions can be used togenerate steam for use in the process thereby minimizing heat import requirementswith the balance exported to be used by a third party thus attracting a value.

1.1.4. Products

The major source of revenue that determines the economic performance is theproduct streams. Like the feedstock, the two important parameters are the quantityand quality. The quantity is determined by the reaction route, quality of the feedstockand catalyst selection. This parameter often sets the primary processing objective of

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

3 of 11 1/15/2013 6:20 PM

a chemical process. The value of a product is set by its quality measured in terms ofpurity of the chemical species or desired function. Quality influences not only thevalue of a product but it will determine the investment and operating costs bydictating the downstream (of reactor) separation steps required to meet a qualityobjective.

1.1.5. Waste Products

Waste products are those materials that have no utility and therefore no value. Mostwaste products attract a disposal cost and should therefore be minimized. Wasteproducts come in a variety of forms products of side reactions involving feedstockimpurities, combustion products, solvents used in separation processes e.g. water,purges, fugitive emissions etc. The waste streams are hence defined in large part bythe choice of process route. The costs associated with waste streams are incurred bythe requirement to treat waste streams to make them suitable for disposal into theenvironment e.g. water effluent treatment and disposal tariffs or taxes imposed bynational or local government. Current economic systems do not always allow a costto be assigned to a waste stream e.g. combustion products. However, engineers havea responsibility to take into account the deleterious effects on human health or theenvironment and factor this into the decision making process.

1.1.6. Interactions

The setting of the overall heat and material balance is therefore a critical step in anyproject to develop a process for manufacturing a particular chemical. The abovediscussion illustrates that the Optimization of a process from an economicperspective is complex and requires trade-offs to be made between competingfactors. For example, the selection of reaction route may require the choice betweena process that requires more expensive feedstock but is less energy intensive and aprocess, that although the feedstock is inexpensive, could require a high pressure andtemperature for the reaction and involve more downstream processing steps toseparate the final products.

There are usually a large number of technically feasible options available to meet aparticular process objective for a new plant. Methods to evaluate the economics in astandardized format to facilitate decision-making and Optimization of designs havebeen developed. Employing these methods allows organizations to decide on whichprojects to pursue and also how to optimize the design in order to maximize thebenefits. The next section discusses these methods in more detail.

2. Economic Evaluation of Chemical Process Projects

The preceding section considered the influence of the process engineering design onthe economics of a process plant. However, the net profit from the operation of aprocess plant equals the total income minus all the costs associated with its operationincluding the administrative functions. For new process plants or modifications toexisting process plants the cash flow across the entire lifecycle of the project must beconsidered to determine the economic performance. A typical project lifecycle cashflow is represented below in Figure 2. The numerical values are for illustrationpurposes only.

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

4 of 11 1/15/2013 6:20 PM

Figure 2. Project Cash Flow Curve

Year 0 represents the point at which the project to construct the process plant hasfinished and the plant is put into operation. For the three years prior to the plantstart-up capital investment is required to design, build and install the process plant.During this phase of the project the cash flow is negative. The total capitalinvestment at time zero includes the land cost, fixed capital investment and workingcapital. From Year 0 onwards the income on an annual basis (after tax) becomespositive and the cumulative cash flow increases with time. At the end of Year 4(beginning of Year 5), the cash flow becomes positive indicating that the capitalinvestment is completely repaid. This time period is known as the payback time. Atthe end of the project life (Year 10) when the operation ceases and the plant isshutdown, the working capital and land value are recovered. The working capitalrecovery comes from sales of feedstock, stored product and equipment. At the end ofthe project the overall net cash flow is positive meaning that wealth has been createdby the project which can then be distributed to shareholders or used for futureinvestments.

Any project for a new process or modification to an existing process must be able toestimate and then optimize the cumulative cash flow curve. It is important to ensurethat there is sufficient confidence in the project outcome prior to investing largesums of money. Figure 2 demonstrates that the actual income from a project couldtake several years to materialize; therefore, these cash flows must be estimated aheadof time prior to any major expenditure. As the project progresses they must berefined and re-evaluated to ensure that the capital investment remains worthwhile.

Because projects constitute cash flows over relatively long timescales it is importantfactor that the time value of money is taken into consideration. The value of moneyinvested in a bank must be conserved over time, which is achieved through thepayment of compound interest. Money not invested in a bank will therefore decreasein value with time. This means that projected future cash flows must be discounted atan appropriate rate of compound interest, , for comparison purposes to the presentday value of money. The present value, , of a future cash flow, in year is thus:

(1)

The cumulative cash flow curve can then be constructed by summing the presentvalues of all income and expenditure for each year. The cumulative value over theentire lifecycle of the project is called the Net Present Value (NPV) and representsthe net wealth in today’s money that has been created (or destroyed). In order for aproject to be economically viable the NPV must be positive and this is often one ofthe measurements used for comparing capital projects as discussed in Section 3below.

2.1. Costs of Chemical Process Projects

The costs that must be taken into account during the economic evaluation of aproject to build or modify a process plant can be broken down into two main

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

5 of 11 1/15/2013 6:20 PM

categories capital investment and operating costs. The capital investment is theinitial outlay to fund the purchase and installation of the process plant. The operatingcosts are those ongoing charges required to continue the operation.

2.1.1. Capital Investment

The capital investment consists of two elements fixed capital and working capital.

The fixed capital is the money necessary to purchase and install all the equipmentrequired for the complete operation of the process. It is sub-divided into direct andindirect costs.

The direct costs include the following items:

Purchased equipment all equipment on the process flowsheet, spares, surplus, inflation allowances,freight charges, taxes, import duty, insurance.Purchased equipment installation installation, structural supports, insulation and painting.Instrumentation and controlsPiping pipes, supports, fittings, valves etc.Electrical systems switchgear, motors, cable, lighting and installation etc.Buildings platforms, stairways, ladders, cranes, lifting equipment, control rooms,maintenance workshops, administrative buildings, laboratories, heating andventilation, communications etc.Site preparation roads, civil works etc.Utility systems steam, water, power, refrigeration, instrument air, fuel, waste treatment anddisposalNon-process equipment office furniture, fire fighting equipment,Distribution systems raw material receipt and storage, product storage, loading stations etc.Land property, surveys and fees.

The indirect costs include the following items:

Engineering and supervision costs process design, administrative, disciplineengineering design, consultants, travel, supervision, inspection etc.Legal fees national and local regulations, regulatory permits and approvals,contract negotiations etc.Construction construction, operation and maintenance of temporaryfacilities, offices, roads, construction equipment, material handling, safety andsecurity etc. Contractors’ fees.Contingency.

The working capital for a process plant consists of the funds (cash) required to

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

6 of 11 1/15/2013 6:20 PM

operate the plant. These funds are replaced on a monthly basis from productrevenues but they must be invested up-front to establish operations and are only fullyrecovered when the production ceases and the project lifecycle is completed. Theworking capital includes the cost of stored raw materials and supplies, product instock and semi-finished in the process, cash required to pay monthly operationalexpenses such as salaries, accounts payable, accounts receivable and taxes payable.

2.1.2. Operating Costs

The operating cost or total product cost is the sum of the manufacturing costs and thegeneral administrative expenses. The manufacturing costs consist of the followingitems:

Direct production costs raw materials, utilities, maintenance, operating supplies, operating labor,direct supervision, laboratory charges, patents and royalties. These are alsoreferred to as variable costs as they depend on the plant operating and to someextent on the production volume. Some items will have an element of fixedcost which is the minimum that would be incurred if the process wasshutdown for a period of time.Fixed costs depreciation, local taxes, insurance, rent and interest payments. These costsare independent of production volumes.Plant overheads general plant upkeep, payroll overhead, health, safety and security

The general administrative charges are generally made up of management salaries,legal fees, communications, distribution and marketing costs, and research anddevelopment costs.

2.2. Revenue and Profits of Chemical Processes

In order for a process plant to be profitable it must generate products that are of ahigher value than the ongoing operating costs. This revenue is generated throughproduct sales. In most competitive chemical markets the product prices are fixed bysupply and demand and these can be difficult to forecast. In order to overcome thisproblem, most organizations will set a standard product price used to test theeconomics of projects. This price is usually set by considering the long term demandoutlook and the current and future supply capacity. A lot of bulk chemicals aresubject to cyclical prices depending on season of the year and global product demandcycles. In order to ensure a project is economically robust the assumed price foreconomic appraisal usually reflects the perceived financial risks and varies inchemical sectors and across organizations.

It is important when estimating revenues to take into account the expectedavailability of the plant. Whilst a plant may have a design capacity for a particularproduct expressed in tonnes per annum, it is unlikely that it will be able to achievethis rate continuously. Planned and unplanned maintenance of equipment will reducethe production capability and there will often be longer periods of no productionduring which time major maintenance occurs. These factors must all be taken intoaccount when projecting future revenue.

The operating profit (pre-tax) is calculated on an annual basis by subtracting the total

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

7 of 11 1/15/2013 6:20 PM

operating costs from the total revenues for each year. Before any tax is calculated,the depreciation charges must then be subtracted from the pre-tax profit.Depreciation is an allowance made for the fact that process plant and equipment willwear out over time due to use.

Depreciation is a mechanism whereby revenue is set aside in order to replace theequipment at the end of its useful life. This money can be deposited in a bankaccount or invested in another venture. This cost is recognized as a legitimateexpense by governments under the tax laws and there are therefore strict guidelinesin place to account for it. There are two main mechanisms straight linedepreciation and declining balance. Straight line depreciation takes the originalpurchase value of the equipment and divides this by the expected lifetime in years;therefore, equipment with a 10-year life would be depreciated by 10% per year.Declining balance uses an exponential decay function to reflect the fact thatequipment depreciates in value at a higher rate in the first few years of its useful life.The depreciation is thereby recalculated each year on the residual value.

The final post-tax profit is calculated by subtracting the tax from the operating profitless depreciation.

3. Economic Evaluation Techniques

There are a variety of ways to measure project profitability and the most commonare discussed here. This is not intended to be an exhaustive study of the techniquesavailable and the reader is referred to the bibliography for texts with more completeanalysis. The time value of money should always be taken into consideration whenevaluating project profitability to ensure that future cash flows are discounted;otherwise the economics will be distorted.

3.1. Net Present Value

The sum of the present values of all project cash flows (including initial capitalinvestment) throughout the entire project life is the Net Present Value (NPV)( ),

as discussed in Section 2 above. It is formally defined as:

(2)

The NPV represents the excess of present value cash inflows over the present valueof cash outflows. If the excess is positive then it means the project is worthundertaking as the value of the benefits exceeds the total cost.

The discount rate, , that is used to calculate the present value of future cash flowshas a particular economic meaning. This is the required rate of return on aninvestment also known as the ‘hurdle rate’ or the ‘cost of capital’. There are twofactors that determine what discount rate should be used for a particular industrialsector:

The level of interest rates in the economy,

The risk characteristics of the specific investment, .

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

8 of 11 1/15/2013 6:20 PM

The first interest rate can be considered ‘risk-free’ as this reflects the default returnon risk-free government bonds which are the returns paid out to postpone consumerspending.

The interest rate applied to the specific investment is a characteristic of the nature ofrisk in the specific industrial sector. Investors and firms will generally hold abalanced portfolio allowing the risk to be spread across a range of investments. Thisinterest rate reflects the compensation required by investors to bear this risk. Inutility companies such as water treatment or power generation, the risk levels aregenerally low whereas a specialized pharmaceutical company would carry a greaterrisk. Projects to build new processes in the pharmaceutical industry would have ahigher hurdle rate to make it worthwhile for investors to put up the money forinvestment.

The discount rate applied is therefore the sum of the risk-free interest rate and theappropriate risk premium. At higher discount rates, larger future cash inflows arerequired to provide a positive NPV.

(3)

It is common for projects to be evaluated at a few discount rates to gauge thesensitivity of the investment to changes in the economy over time.

Comparison between two projects or alternative designs using Net Present Valuemust be made on the same time project life basis to ensure they are comparable. NetPresent Value analysis always provides a reliable indication of project acceptabilityand it can handle both positive and negative cash flows throughout the project life.This is important for projects which incur large costs during the life of the operationor at the very end of the operation. For example, field abandonment costs whenproduction ceases from an oil or gas reservoir are incurred to make the wells safeand to destruct and dispose of the processing equipment.

3.2. Internal Rate of Return

The Internal Rate of Return, (IRR) denoted as , is a common measure that

provides the rate of interest or discount factor which when applied to a series ofproject cash flows will yield a zero Net Present Value. The Internal Rate of Return isdefined from the following relationship:

(4)

For multiple cash outflows in the first few years of a project this equation must besolved numerically to find the Internal Rate of Return.

For projects with a single cash outflow in Year 0 it can be rearranged to give:

(5)

The IRR is the maximum rate at which a loan could be raised to finance aninvestment such that the investment would just pay off the capital and interest by theend of the investment period. To evaluate whether a project is worth considering, the

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

9 of 11 1/15/2013 6:20 PM

IRR is compared to the cost of capital (hurdle rate), . If the IRR equals or exceedsthe cost of capital then the project is acceptable.

For a simple project where there is a single cash outflow at the start of theinvestment the IRR will yield the same decision as the NPV. This is also true whencomparing two alternatives over the same project timescale.

Where IRR can be used as a differentiator is when projects or alternative designshave a different capital outlay or timescale. Consider the example below in Table1where the cost of capital is assumed to be 10%.

Table 1. Project Evaluation Example

In this example both projects have different capital outlays, cash inflows andtimescales yet the NPV is identical. Despite Project B having higher financial returnsover a shorter duration, the IRR is actually greater for Project A which has a lowercapital outlay and longer timescale. This analysis does not take into account theadditional investment opportunities which would arise from investing the NPV ofProject B in Years 4 and 5.

IRR cannot be used to evaluate the performance of projects that have mixed positiveand negative cash flows throughout the lifecycle. In cases such as this there will bemore than one IRR that provides a zero NPV making it unreliable for decisionmaking.

3.3. Payback Period

A popular means of evaluating the economic value of a project is the paybackperiod. This is a calculation of the time it takes to recover the initial capital outlayfrom the project’s cash flows. In other words it is the length of time taken for aproject to pay for itself. This is shown on the cumulative cash flow curve such as inFigure 2 at the point when the cumulative cash flow turns positive. Projects with ashorter payback time are usually favored. It is often employed when consideringmodifications to existing process plants or when capital is constrained or onlyavailable for a short time period.

This method suffers from a number of disadvantages and is not recommended formajor investment decisions. The main drawback is that it doesn’t consider theproject cash flows after the initial payback time and does not reflect the time value ofmoney. Unlike NPV and IRR which can measure the value created by a project, thepayback time does not have any effective measure of profitability.

4. Economic Evaluation of a Major Project in Practice

Major projects to design, build and operate new process plants are all characterizedby elements of risk and uncertainty. At the outset of a project it may not even beknown if an economically successful outcome is possible. This is also the point in aproject when uncertainty is highest. It isn’t possible to complete all the worknecessary to provide an accurate economic appraisal at this stage as this would beprohibitively expensive in time and money. To help manage these risks, projects aretackled in a number of stages as shown in Figure 3.

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

10 of 11 1/15/2013 6:20 PM

Figure 3. Project Lifecycle

Organizations and companies use different terminology to describe these stages butessentially they follow a similar pattern. At the end of each stage an economicappraisal is conducted and progress to the next stage is only allowed if there issufficient confidence in the project achieving the economic hurdles having reviewedthe risks to delivery of the benefits. The process is characterized by one of increasingtechnical and economic definition as the project progresses through each stage withreducing uncertainty. It is also worth noting that in order to deliver successfulprojects an organization must look at a broad range of options sanctioning only thoseprojects that meet the economic hurdles.

The economic appraisal that is conducted at each stage also reflects the increasinglevel of definition and certainty. As the end goal is to provide an optimized design,defined in terms of profitability, the economic evaluation must be revisited at eachmajor decision point when authority is provided to proceed further with the processdesign until eventually the project is fully sanctioned and the plant is built. In orderto ensure a successful outcome the economic evaluation should not be regardedsolely as an output but rather it should be used to inform the design decision-making.

The stages for a process plant project and the quality of the cost estimates arebroadly defined in Table 2.

Table 2. Project Stages

In order for an economic assessment to be made there must be an estimate of all thecosts and the projected revenues at each stage of the project. The revenues tend to beeasier to estimate based on projected plant capacity and production rates taking intoaccount the plant availability and impact of maintenance on production. These arenormally presented on an annual average basis. The primary focus of projects tendsto be on the costs, both capital and operating costs.

At the end of each project stage a decision must be made on whether to continuewith the project or not. Often the commitment to fully sanction a project will occurat the end of FEED when there is sufficient confidence in the economic justification.There is always a risk that the costs could escalate through detailed design andproject execution due to changes in the project scope, price escalation or errors in theestimates (e.g. equipment omissions). In order to take care of the inherentuncertainty in an estimate, a factor is applied to the base cost estimate called reserveor unallocated provision. This takes into account the accuracy of the costs based on astatistical analysis of the estimate. The handling of risks and uncertainty in the costestimate is discussed in detail in Section 4.2.

4.1. Cost Estimation

©UNESCO-EOLSS Encyclopedia of Life Support Systems

PROCESS ECONOMICS http://greenplanet.eolss.net/EolssLogn/mss/C06/E6-34/E6-34-06/E6-3...

11 of 11 1/15/2013 6:20 PM