PROCEDURES MANUAL
FOR PREPARING ENVIRONMENTAL DOCUMENTATION UNDER THE
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) OF 1969
August 2004
Tennessee Department of Transportation Environmental Planning and Permits Division
_______________________________ _______________________________
Tennessee Department of Transportation
Environmental Planning and Permits Division
Procedures Manual for
Preparing Environmental Documentation under the
National Environmental Policy Act (NEPA) of 1969
August, 2004
Effective Date: _____________
Approved by:
Director, Environmental Planning and Permits Division Chief, Environment & Planning Tennessee Department of Transportation Tennessee Department of Transportation
Table of Contents
Table of Contents
1.0 GENERAL ENVIRONMENTAL PROCEDURES .................................................................. 1-1
1.1 INTRODUCTION................................................................................................1-1
1.2 NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) ....................................1-1
1.3 REGULATIONS RELATED TO NEPA ..............................................................1-2
1.3.1 Council of Environmental Quality............................................................1-2
1.3.2 Federal Highway Administration Environmental Impact and Related
Procedures .............................................................................................1-3
1.3.3 Other Regulations Related to NEPA.......................................................1-3
1.4 NEPA PROCESS...............................................................................................1-4
1.4.1 Class of Action........................................................................................1-4
1.4.2 Significance ............................................................................................1-5
1.4.2.1 Context..................................................................................1-5
1.4.2.2 Intensity.................................................................................1-5
1.5 FITTING ENVIRONMENTAL CONSIDERATIONS INTO TDOT’S PROJECT
DEVELOPMENT PROCESS..............................................................................1-6
1.5.1 TDOT’S PROGRAM, PROJECT AND RESOURCE MANAGEMENT PLAN
(PPRM)...............................................................................................................1-8
1.5.2 ORGANIZATION OF THIS MANUAL................................................................1-9
2.0 PROJECT IDENTIFICATION AND DEVELOPMENT........................................................... 2-1
2.1 DEFINING THE PROJECT ................................................................................2-2
2.1.1 Purpose and Need..................................................................................2-2
2.1.2 Logical Termini and Independent Utility..................................................2-4
2.1.2.1 Development of Logical Termini ...........................................2-4
2.1.2.2 Demonstrating Independent Utility ........................................2-5
2.1.3 Defining the Study Area..........................................................................2-6
2.2 DEVELOPMENT AND CONSIDERATION OF ALTERNATIVES......................2-6
2.2.1 Preliminary Alternatives Development....................................................2-6
2.2.2 Development of Study Area Inventory and Base Mapping .....................2-7
3.0 NEPA PROCESS OPTIONS .................................................................................................. 3-1
3.1 DETERMINATION OF CLASS OF ACTION......................................................3-1
3.2 ADMINISTRATIVE RECORD ............................................................................3-1
N E P A P R O C E D U R E S M A N U A L
Page i
Table of Contents
3.3 ENVIRONMENTAL IMPACT STATEMENTS....................................................3-3
3.4 CATEGORICAL EXCLUSIONS.........................................................................3-4
3.4.1 “C” List CEs ............................................................................................3-4
3.4.2 ”D” List CEs ............................................................................................3-5
3.4.3 Unusual Circumstances..........................................................................3-8
3.5 ENVIRONMENTAL ASSESSMENTS................................................................3-9
4.0 EARLY COORDINATION....................................................................................................... 4-1
4.1 NOTICE OF INTENT AND SCOPING................................................................4-1
4.1.1 Notice of Intent........................................................................................4-1
4.1.2 Scoping...................................................................................................4-1
4.2 INITIAL COORDINATION PACKAGES ............................................................4-2
4.2.1 Project Data Summary Sheet .................................................................4-2
4.2.2 Exhibits ...................................................................................................4-3
4.2.3 General Transmittal Letter ......................................................................4-4
4.2.4 Special Initial Coordination Letters .........................................................4-4
4.2.4.1 Farmland Initial Coordination With NRCS.............................4-4
4.2.4.2 Section 106 Initial Coordination ............................................4-5
4.2.4.3 Cooperating Agencies Invitation ...........................................4-6
4.2.5 Initial Coordination List ...........................................................................4-6
4.3 LEAD AND COOPERATING AGENCIES .........................................................4-8
4.3.1 Lead Agencies........................................................................................4-8
4.3.2 Cooperating Agencies ............................................................................4-8
5.0 REFINE ALTERNATIVES TO ADDRESS CONCERNS ...................................................... 5-1
6.0 IMPACT ANALYSIS................................................................................................................ 6-1
6.1 OVERVIEW ........................................................................................................6-1
6.1.1 Definition of Impact .................................................................................6-2
6.1.1.1 Direct Impacts .......................................................................6-2
6.1.1.2 Secondary and Cumulative Impacts .....................................6-2
6.1.1.3 Level of Impact......................................................................6-5
6.1.2 Chapter Organization..............................................................................6-5
6.2 RECORDS CHECK IN EARLY PROJECT PLANNING PHASE.......................6-5
6.2.1 Records Check for Environmental Screening.........................................6-6
6.2.1.1 Cultural Resources ...............................................................6-6
6.2.1.2 Natural Resources ................................................................6-7
6.2.1.3 Hazardous Materials .............................................................6-8
6.2.1.4 Environmental Justice...........................................................6-8
6.2.2 Map Review............................................................................................6-9
N E P A P R O C E D U R E S M A N U A L
Page ii
Table of Contents
6.3 TECHNICAL STUDIES AND OTHER IMPACT ANALYSES ............................6-9
6.3.1 Overview.................................................................................................6-9
6.3.2 Technical Studies ...................................................................................6-9
6.3.2.1 Cultural Resources .............................................................6-10
6.3.2.2 Natural Resources ..............................................................6-16
6.3.2.3 Noise...................................................................................6-19
6.3.2.4 Air Quality ...........................................................................6-23
6.3.2.5 Hazardous Materials ...........................................................6-25
6.3.2.6 Conceptual Stage Relocation Plan .....................................6-28
6.3.2.7 Soils and Geology Analysis ................................................6-29
6.3.3 Sections 4(f) and 6(f) Analyses.............................................................6-29
6.3.3.1 Section 4(f) of the Department of Transportation Act..........6-30
6.3.