Upload
nicholas-lee
View
174
Download
1
Embed Size (px)
Citation preview
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
37
Probable Maximum Precipitation Derivation in Malaysia: Review and Comparison
*Hii Ching Poon1, Heng Hock Hwee2 1 Hydrologist in Department of Civil Engineering, Universiti Malaysia Sarawak. 2 Associate Professor in Faculty of Engineering and Science, Universiti Tunku Abdul Rahman, Malaysia *Corresponding Author Abstract The importance of PMP is always highlighted and emphasized in terms of public safety and hazard downstream of any major river regulating structures especially if it is located in the upland catchment of the populated town or city centers. As such the PMP convention is always a requirement as primary design dam/reservoir criteria when public safety is of concern. The objective of this review is to compare the Probable Maximum Precipitation (PMP) convention of SMHB/B&P vis-à-vis other consultants’ studies that have been carried out in Malaysia. The review primarily addresses the issues on the PMP derivation in Peninsular Malaysia and with minimum coverage of PMP issues in the Borneo states of Sarawak and Sabah. The short- and long-duration PMP values were applied in Peninsular Malaysia and Borneo states. The PMPs adopted by SMHB/B&P are further classified into two series, i.e. Coastal and Inland. Fourteen (14) reports and studies related to the derivation of PMP in Peninsular Malaysia by other consultants were discussed in detailed. Both PMPs adopted by SMHB/B&P and studies by other consultants are presented systematically in tandem in this review. It should be emphasized a priori that there is no single unified methodology or procedure in estimating PMP values in Malaysia, specifically for the case 24-hour duration PMP adopted in various studies throughout Peninsular Malaysia. Competent professionals and experts in this specialized field may even obtain different results because most these estimations required subjective judgments and empiricisms.
Keywords: Probable Maximum Precipitation (PMP), public safety, hazard.
Submitted: 27th June 2010 Published after corrections: 11th August,2010.
INTRODUCTION
The objective of this review is to
compare the Probable Maximum
Precipitation (PMP) convention of
SMHB/B&P vis-à-vis other
consultants’ studies that have been
carried out in Malaysia. For the past
40 years of the existence of SMHB in
the dam design/engineering
consultancy practices adopts and
inherits the conventional practices of
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
its former parent company in the
UK. The review primarily addresses
the issues on the PMP derivation in
Peninsular Malaysia and with
minimum coverage of PMP issues in
the Borneo states of Sarawak and
Sabah. An example that warranted
comparison is the PMP adopted for
the recent design and construction of
Selangor dam (CA=197 km2) at the
upper Sg. Selangor basin.
In the context of this review, the
terminology, PMP is defined by the
World Meteorological Organization
(WMO; 1986) as “the greatest depth
of precipitation for a given duration
meteorologically possible for a given
basin of a particular time of year,
with no allowance made for long-
term trends”.
ADOPTED PMP CONVENTION
BY SMHB/B&P
SMHB Sdn. Bhd. (known as SMHB
hereinafter) and its predecessor,
Binnie and Partners (known as B&P
hereinafter), generally adopts both
the short- and long-durations PMP
values from their past numerous
dam design experiences and studies
in Singapore and Malaysia (Seletar,
Langat, Semenyih, etc). Specifically,
three (3) specific reports/studies
form the basis of PMP derivation at
that time. They were SSP/HH
(1979), B&P (1980), and SSP/SMEC
(1985) for project locations in
southern Johor and Singapore.
These PMP values have since being
adopted for all reservoir design
projects subsequently undertaken by
SMHB/B&P. Notable projects were
Seletar and Upper Pierce dams in
Singapore, Semenyih and Langat
and recently Tinggi dams in
Selangor, Linggiu dam in Johor,
Linggi dam in Negeri Sembilan,
Chereh dam in Pahang, Durian
Tunggal and Jus dams in Melaka,
etc.
The short- and long-duration PMP
values, by definition in this
presentation, divided arbitrarily at
the 24-hour duration. As such, PMP
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
values of duration less and more
than 24-hour are classified
accordingly as the short- and long-
duration PMP respectively.
However, a 6-hour duration is
sometimes used to demarcate the
short and long duration as being
adopted before by the Australian
Bureau of Meteorology (ABM).
The PMPs adopted by SMHB are
further classified into two series, i.e.
Coastal and Inland, while in essence
taking into consideration the vast
difference in meteorological and
geographical factors, as their names
implied at both peninsular coastal
and inland regions. For short
duration PMP series, the values
adopted as Coastal PMP are based
mostly on the Singapore rainstorm of
1978 and about 12% higher than the
inland PMP. After applying an
appropriate transposition factor, it is
transposed inland (specifically for
Semenyih reservoir design project),
this series is therefore known as
Inland PMP. Table 1 shows both
coastal and inland PMP derived and
adopted by SMHB/B&P for duration
ranges from 1- to 120-hour.
Table 1: Coastal and Inland PMP (Short- and Long-Duration) adopted by SMHB Duration (hour) Coastal PMP (mm) Inland PMP (mm) 1- 211/190.5# 188 3- 338 300 6- 440 391 12- 584 518 24- 777 692 Long Duration PMP (arbitrarily defined for this review) 48- 1356 908 72- 1593 1067 120- 2030 1360 # 19.5 mm or 7.5 in is originally quoted but 211mm is back calculated from 188 mm Short-Duration PMP The basis of the PMP derivation for
SMHB/B&P is based on actual
occurrence and records of maximum
rainfall in Malaysia and Singapore.
Some notable highest rainfall records
are (SMHB, 1992):
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Near Kuantan in late
December 1926, with the bulk of the rainfall falling between 27th and 31st of December including 631 mm (24.85 inches) within one day at the Jeram Kuantan Estate;
In Singapore on 17th July 1941 when in a very intense but relatively short storm 65.6 mm was recorded in 30 minutes, 120 mm in 60 minutes and 147 mm in 2 hours;
In Singapore on 9th and 10th December 1969 when 478 mm was recorded in 24 hours;
Near Mersing between 29th December and 4th January 1971 when 541 mm occurred in a 24 hour period and a total of 1453 mm (1600 mm and1800 mm are being reported elsewhere) was measured in 120 hours; and
In southern Johor and Singapore on 2nd and 3rd of December 1978 when 537 mm was recorded in a 24-hour period at Serangoon Sewage Disposal Works with values of 533 mm being recorded concurrently at two other stations on Singapore.
The December 1978 storm was
primarily selected as basis for short
duration PMP derivation because it
was the most severe recorded storm
in the southern region of the
Peninsula Malaysia other than the
highest recorded storm in Jeram,
Pahang. These short duration PMPs
are derived by maximizing the 24-
hour rainstorm during 2nd and 3rd
December, 1978 in both southern
Johor and Singapore. A 24-hour
record of rainfall (536.5 mm) was
recorded at the Serangoon Sewage
Disposal Works (SDW) station. In
addition, rainfalls of about 533 mm
were also recorded concurrently at
both Kim Chuan Road Sewerage
Works and Sembawang Agricultural
Research Station in Singapore.
Storm Maximization The storm depth was maximized
based on the ratio/index of
maximum precipitable water in the
air column to the actual precipitable
water during the storm (as a function
of maximum and persistent dew
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
point temperature for 12-hour at
1000 mb).
Based on an average of the recorded
values at Paya Lebar Airport and
Changi Airfield the 24-hour
persisting 1000 mb dew point
temperature at the beginning of
December 1978 storm was 23.8 C. At
this dew point temperature the
precipitable water in the atmosphere
prior to the storm was estimated at
73.5 mm.
The period of dew point temperature
was searched based on hourly
records from 1955 to 1978
presumably from the historical
database of the Paya Lebar Airport
station and Changing Airfield.
Coupled with the consideration of
the limiting influence of the
maximum sea temperature, it was
deduced that the estimated
maximum 24-hour persisting dew
point temperature could not be
possibly more than 28oC (as
originally presented in PUB, 1980).
At this dew point temperature, the
corresponding precipitable water
was 106.8 mm.
The storm-maximizing factor is then
calculated simply as an index of the
ratio of the maximum precipitable
water to the prevailing precipitable
water content prior to the storm, i.e.
106.8/73.5= 1.45. Therefore the
maximum rainfall that could
possibly occur in 24 hours is 1.45
*536.5 mm = 777 mm. For PMP of
less than 24-hour duration, similar
methodology was applied to derive
1-, 3-, 6-, 12-hour duration PMPs.
Transposition Transposition is another major step
to be undertaken in any PMP
studies. Transposition of storms
from one location to others is
subjected to various important
contributing factors such as,
presence of topographic barrier,
elevation adjustment, distances from
the storm center, and etc. However
in SMHB/B&P practices, primarily
due to scarcity of the meteorological
data and uncertainties in the chosen
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
transposition technique, PMP values
at the coastal region (assuming that
Singapore is located in the coastal
region) might not be able to carry
out after all. As such, SMHB/B&P
adopts both short- and long-duration
PMP values without taking into
account the transposition factor for
PMP derivation in mostly coastal
region. It is though a conservative
measure, lest it should be acceptable
in the absence of both concrete
authoritative recommendations and
limitations in understandings and
knowledge of PMP derivation in
Malaysia.
Nevertheless, for interior region, the
consensus amongst the SMHB/B&P
hydrological groups opined that by
adopting coastal PMP without
taking into account the transposition
effect was “unduly conservative”.
Therefore, some forms of technique
should be devised for such purpose.
An example of the application of
transposition technique was
demonstrated in the derivation of
PMP values for Semenyih dam. In
this particular study, the PMP
derived from 1978 storm in
Singapore was transposed to the
Semenyih dam site. By taking into
consideration the highest persistent
dew point temperature in the State
of Selangor (assuming PKM Petaling
Jaya station is representative of the
whole state of Selangor, at 26.7 oC;
precipitable water 95 mm), the
transposing factor was estimated as
0.89 (95/106.8 = 0.89). This
amounting to some 11% reduction
was primarily considered justifiable
due to relatively lower historical
persistent dew point temperature in
the state of Selangor. By making the
same assumption that the PMP at the
Semenyih dam site is having the
same probability of occurrence in the
northern catchment, the PMP series
was also been adopted for the
detailed design studies of both
Tinggi (formerly known as Buloh)
and Selangor dam in the Sg.
Selangor basin respectively. Table 2
shows the adopted PMP values by
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
40
SMHB for various durations, i.e. 1- to 24-hour.
Table 2: Comparison of PMP of Coastal and Inland PMP Values Duration (hour) Coastal PMP (mm) * Inland PMP (mm) # 1- 211 (190.5 mm or 7.5 in) & 188 3- 337 300 6- 439 391 12- 582 518 24- 777 692 Col3 *transposition factor, 0.89; * based on Singapore 1978 storm; # Semenyih dam design; & in original text It should be reiterated that the
adopted PMP values by SMHB
though not strictly are based on
WMO (1986) guideline per se, for
which incorporating rather complex
maximization and transposition
approaches, nevertheless the general
principles on maximization and
transposition techniques are duly
and consistently obeyed. In addition,
the WMO approaches require some
detailed meteorological as well as
topographic information for which
most of the times are unavailable.
This essentially precludes an
elaborate and thorough PMP studies
in line with the WMO (1986). This is
particularly true for the case in
Malaysia, as most of these
meteorological parameters and data
are difficult to come by in the earlier
years of 1960’s and 1970’s. These
two series of PMP are adopted for
designs and studies undertaken by
SMHB subsequently.
Other transposition approaches for
subsequent dam design assignment
was also undertaken, such as those
adopted in the recent Kelantan River
Flood Mitigation Plan (SSP/SMHB,
1999), based mostly on the
assumptions of reducing storm
intensity and volumes when a storm
travels in land from the coast to the
dam catchments mostly located in
the interior region of Kelantan.
Analyses of the rainfall data
immediately after the storm did
support such observation. In this
study, several transposition factors
were derived, such as based on the
ratios of annual rainfall, wet seasonal
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
rainfall, maximum 5-day rainfall,
and multiple regression approach of
5-day 100-year maximum rainfall.
These transposition factors were
estimated ranges from as high as
0.92 to as low as 0.40. After diligent
deduction, a medium value of 0.70
and 0.85 was finally selected for
Kemubu and Lebir dams
respectively (SSP/SMHB, 1999).
Long-Duration PMP Long duration PMP adopted by
SMHB/B&P is based on the
maximization of the December 1970
and January 1971 storm records of
Mersing and Air Tawar rainfall
stations near Endau. These values
have also been previously used
earlier studies by SSP/SMEC (1985;
as quoted in SMHB, 1985) flood
studies on Sg. Batu Pahat basin.
SSP/SMEC (1985) study used
maximum rainfall records at
Mersing Meteorological Station for
their works but it was reported later
by SMHB (1985) that recent
investigation indicated several other
rainfall stations recorded maximum
rainfall in excess of those reported by
SSP/SMEC (1985). Notably, the
highest totals at Air Tawau School
near Endau with maximum 5- and 7-
day totals of 1453 mm and 1632 mm
respectively. Other rainfall stations
nearby, JPT Setor in Endau, about 5
km from the Air Tawar School
station also recorded higher rainfall,
i.e. 1600 mm for 5-120 hour within a
7-day duration. This infers
unrestricted total records from
automatic station at JPS store in
Endau, 5 km away from Air Tawar
School. The 120-hour or 5-day PMP
was 2030 mm if maximization factor
(i.e. about 1.27) was taken into
consideration (SMHB, 1986).
Maximization For 120-hour storm, a maximization
factor of 1.40 has been used. It is
therefore assumed that storms
between 24- to 120-hour duration
would have adopted the same factor.
However this is yet to be confirmed
as no confirmation or cross checking
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
with other reports and studies could
be made in this regard.
Transposition For transposition, a factor of 0.67
was applied for PMP duration of
more than 24 hour. This factor was
adopted based on the USBR
recommendation in their review of
PMP estimates for the Batu,
Gombak, and Klang Gates dams (as
quoted in SMHB, 1994; USBR, 1984).
Table 3 shows the coastal and
inlands PMP adopted by
SMHB/B&P.
Table 3: Coastal and Inland PMPs (Long Duration) adopted by SMHB/B&P Duration (hour) Coastal PMP (mm) Inland PMP (mm) (1) (2) (3) 24-* 777 * 692 48-# 1356 # 908 72-# 1593 # 1067 120-# 2030 # 1360 col 2* 0.89; # col 2*0.67 REVIEW ON OTHER PMP STUDIES IN MALAYSIA Several reports and studies related to
the derivation of PMP in Peninsula
Malaysia, particularly in the State of
Selangor where seven (7) existing
dams/reservoirs are located are
relevant and they are presented as
below. The most recent study on the
issue of PMP in Selangor was a
paper presented in the 1-day
Specialty Seminar conducted by
JPS/HTC using Hershfield statistical
methodology (WMO, 1986). An
extended study on short duration
extreme rainfall is also being carried
out. The preliminary findings of this
study although without routine PMP
maximization is presented during
recent International Conference on
Urban Hydrology 2002. In addition,
a detailed hydrological study was
also carried out in the design of the
Perang Besar dam in the new
Government Administrative Center
of Putrajaya in southern Selangor.
Besides, independent reviews on the
PMP using hydro-meteorological or
traditional approach was also
undertaken in a hydrology study by
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
NK/SMHB in earlier 2000. The
results obtained by this specific
study basically confirmed the
SSP/SMHB (1996) study on PMP
derivations in Kelantan.
A paper on estimation of PMP based
on proxy (radar satellite) data is also
reviewed in this presentation. This
paper was originally presented in a
workshop on satellite weather
forecasting in South America and
made available via world-wide-web
site http\\www.unesco.org.uy.
Comparison and references on PMP
values were also made on a much
small subcatchment of Sg.
Terengganu basin in the eastern
coastal region of the Peninsula
Malaysia. Due to these relevancies,
this particular paper was reviewed
as such.
SMHB/B&P PMP estimates for
various dam design projects
undertaken in Malaysia are based
largely on the findings and opinions
of SSP/HH (1979), B&P (1980), and
SSP/SMEC (1985) for short- and
long-duration event. Statistical
approach, i.e. Hershfield technique,
which is suitable for regions with
scarce hydrometric data (dew points,
wind records, etc), is sometimes
used for checking and verification. A
collaborated effort by JPS/HTC to
estimate 24-hour PMPs using this
technique based on statistical
technique in Selangor is also
presented.
The following reports/studies are
reviewed and the results of PMP
derived and used in their respective
reservoir or dam design projects are
presented in the following
subsections accordingly.
Langat Miles 24 Dam Stage II
Design, March 1976. Dams on Sg. Bekok and Sg.
Semberong, Detailed Investigation and Design: Hydrology, SSP and Howard Humphrey, October 1979.
Modifications to the Seletar and Upper Peirce Reservoirs to Provide Additional Storage, PUB, B&P, 1980.
Klang River Basin integrated Flood Mitigation Projects, Malaysia, Final Report, Kinhill Engineer Pty Ltd in
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
association with Ranhill Bersekutu Sdn. Bhd, November 1994.
Kelantan River Flood Mitigation Plan Feasibility Study, SSP/SMHB, 1999.
Putrajaya: Padang Peras Reservoir Design Study, Angkasa-GHD, 1998.
Radar and Storm Model-based Estimation of Probable Maximum Precipitation in the Tropics, P.J. Hardaker and C.G. Collier, 1999, www.unesco.org.uy
National Water Resources Study 2000-2050, Hydrology Chapter on PMP Derivation, SMHB/RHB/ZAABA, 2000.
Pahang-Selangor Raw Water Transfer Project Engineering Services and Detailed Engineering Design: Hydrology, August 2000.
Probable Maximum Precipitation for 24 Hours Duration over Southeast Asian Monsoon Region- Selangor Malaysia, Desa, Noriah, Rakhecha. Extreme of the Extreme Rainfall in Selangor, JPS/HTC Seminar, September 2000.
Short Duration Extreme Rainfall in Selangor, Desa and Rakhecha, ICUH 2002.
Gelami Dam Design Hydrological Study, JPS, 2002.
Sg. Kelinchi Dam Water Resources Study, SSP/MM, 2001.
Feasibility Study on Water Resources Development for
Seremban and Port Dickson, SSP/SMEC, 1990.
Langat Dam Design 1976 The design storm (note: it was not
mentioned explicitly in the report
that design storm is PMP in present
day terminology but for the purpose
of reservoir design, one would
assume that PMP values were
implied in the dam design practices
in Malaysia) adopted in the design of
Langat dam was based on review of
all the maximum recorded rainfall of
both short- and long-durations in
both Singapore and Malaysia.
Notably for short duration storm of
less than 1 hour was based entirely
on an earlier B&P study on
envelopment of the highest recorded
rainfall for Singapore and east coast
Malaysia. The maximum 1-hour
rainfall by envelopment was 190.5
mm (or 7.50 in). This subsequently
is being adopted by SMHB/B&P in
most of their dam design
undertaking latter year in Malaysia.
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
40
Due to steepness of the Langat
reservoir catchement and relatively
smaller area, the shorter duration
PMP is far more important that those
of more than 24 hour. Comparison
between the available historical
storm records of both east and west
coasts indicated that the east coast
were generally higher that those of
the west coast (which come to no
surprise at all if one is familiar with
the weather and climate pattern of
Peninsular Malaysia). The highest
recorded rainfall was 754 mm at
Kota Baru JPS Store and 263 mm at
Tanjung Karang JPS Store. The
design report also included some
important historical rainfall event
experienced in Malaysia. For brevity
they are tabulated and summarized
in Table 4.
Selection of the design storm for
spillway was accomplished by
comparing the design storms
adopted in other studies such as
design of Seletar, Klang Gates, and
PMP at Batang Padang. In their
opinion, as the Langat reservoir is
less exposed to the northeast
monsoon than Seletar reservoir and
is at a higher elevation than Klang
Gates catchment, therefore, after
deliberation, the design storm of 432
mm was selected for 24-hour
duration. On the other hand, for
short intensity design storm, 190.5
mm was adopted for 1-hour
duration.
Table 4: Maximum Recorded Rainfall Prior to 1976 Station
Rainfall (mm) Remarks
Mersing 287 Segamat 260 Tangkak 267
7th January 1952 (B&P, 1959)
Sg. Sembrong 260 Mawai 437 Segamat 318 Labis 468 Pekan Nanas 257
10th December 1969 B&P (1970)
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Kuantan (east) 327/ (868) MMS Mersing (east) 430 (679) MMS Subang Airport (west) 171 (293) MMS Ulu Langat Mile 22 (west) 166 (333) B&P (1971) Kepong 283 Serendah 268
From USBR 1954 Study
( ) 120-hour Klang River Basin Flood Mitigation, Kinhill/Ranhill, 1994 PMP study carried out by the dam
designer, United States of Bureau of
Reclamation (USBR) was reviewed
systematically for the Batu and
Klang Gates dams in tandem with
comparison with other studies in
Malaysia as shown in Table 5. PMP
for both dams are derived based on
the maximization of the storm
records of Air Tawar School and
Mersing during late 1970 to earlier
1971. These two stations recorded
the highest observed rainfall for long
durations, i.e. more than 1 day in
Malaysia.
Table 5: Comparison of PMP for Batu, Klang Gates, and Inland Dams
Duration (hour)
Batu Dam PMP (mm) *
Klang Gates Dam PMP (mm)*
Inland Dam PMP (mm) ARF applicable
12 391 375 474 18 460 449 N/A 24 528 517 643 36 687 675 N/A 48 846 834 863 72 1164 1153 1067
* Data were originally obtained from USBR, 1984 and reproduced in the Kinhill/RHB (1994) report If assuming equal
opportunities/probabilities of PMP
could also be occurred in the
Semenyih or Selangor basins and
considering both dams are located in
the same interior region of the State
of Selangor, the PMP values
estimated by USBR in the design of
both Batu and Klang Gates dams
therefore can be transposed to other
dam sites within the same
geographical regions as well. As
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
shown in table above, they are
founded to be somewhat lower vis-à-
vis SMHB/B&P’s for shorter
durations, albeit are compared
reasonably well as far as the long-
duration PMP, 48- and 72-hour is
concerned.
Kelantan River Flood Study, SSP/SMHB, 1999 The derivation PMP using hydro-
meteorological technique was
required for the design of the
proposed Kemubu (on Sg. Galas)
and Lebir (on Sg. Lebir) dams on
each of the major tributaries in the
upper catchment of the southern Sg.
Kelantan basin. Due to their relative
larger sizes of the dam catchment,
only long-term duration PMP, i.e.
more than or equal to 1-day are of
importance and was subsequently
derived for this study. By leaving
the short duration PMP aside
essentially circumventing the
problems encountered on the
scarcity of pluviograph or automatic
recorder data on short-duration
rainstorm in the whole Sg. Kelantan
basin.
Extensive search of the JPS extreme
rainfall database indicated 7 major
storms (Jan, 1967; Dec 1970, 1971,
1972, 1982, 1983, and 1986) have
occurred in the east coast regions i.e.
the states of Kelantan and
Terengganu. The maximization
factors for various storms were
estimated based on precipitable
water ratio of a reference extreme
dew point temperature at 27 oC. The
12 hours persisting dew point
temperature ranges from 22.0 oC to
24.6 oC. Correspondingly, the
maximization factors range from the
lowest 1.23 (Dec 1972) to the highest
1.55 (Dec 1970).
Explanations on the rationale of
transposition factor are presented in
the preceding section 2.1 or in the
reference, SSP/SMHB (1999).
Comparison of mainly long duration
PMP is tabulated in Table 6.
Columns 2 and 3 values are obtained
after taking into consideration the
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
transposition factors, 0.70 and 0.85
for Kemubu and Lebir dams sites
respectively.
Table 6: Comparison of PMP of Kemubu, Lebir, and Selangor Dams
Duration (hour)
Kemubu PMP (mm)
Lebir Dam PMP (mm)
Selangor Dam PMP (mm)
ARF applicable (1) (2) (3) (4) 24 301 468 643 48 651 910 863 72 840 1190 1067 96 980 1350 N/A 120 1100 1490 1360
Col 2 and 3 values are obtained after taking into consideration the transposition factors
Putrajaya: Perang Besar Reservoir, Angkasa-GHD, 1998 The PMP used in the main dam
design in the new administrative
center of the Government of
Malaysia, Putra Jaya, was based on
procedures outlined in the Bulletin
53, 1994 of the Australian Bureau of
Meteorology (ABM), Australia. This
procedure, as quoted ad verbum,”
…is based on the Depth-Area-Duration
(DAD) method, which is used
extensively in Australia and the United
States. Its basic assumption is that
PMP is produced by large stationary
thunderstorms positioned over the
catchment. The method was developed
on the basis of data colleted principally
in the US, and assumed that the basis of
data are similar throughout the world”,
and thus it is implicitly in a way
considered applicable in Malaysia.
The results of the short- and long-
term duration PMP values adopted
in the design of Perang Besar dam
and compare with the Inland PMP of
SMHB/B&P are tabulated and
summarized in Table 7.
Table 7: Comparison of Prang Besar PMP and Inland PMP Duration (hour)
PMP (mm) Angkasa-GHD
PMP (mm) SMHB in Sg. Selangor dam
% Difference
0.5 250 N/A N/A 1 N/A 188 N/A 3 610 300 +103% 24 1100 692 +84% 72 1400 1067 +31%
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Comparing with the PMP values
adopted by SMHB in the design of
Sg. Selangor dam, it was obviously
shown that the PMP values in
Angkasa-GHD design was higher
than SMHB’s. The difference is
considerably prominent for the
shorter duration PMP, i.e. for 3-hour
and lower duration by interpolation
to a certain extent. In this regard, the
Angkasa-GHD derived PMP is
almost doubled that of SMHB.
However for longer durations, says
for both 24- and 72-hours, the
difference somewhat reduces from
+103% to +84% and +31%
respectively.
The validity of adopting ABM
(derived from adjusted storm data of
both USA and Australia) PMP
estimation in Malaysia remains
controversial as obvious differences
in meteorological condition is self-
evident in the first place. From the
past studies, many arguments were
traded with regard to the adoption
of ABM’s PMP procedure in
Peninsular Malaysia. Specifically,
SMHB (1994) pointed out that “ (it) is
in their (SMEC/ABM) judgements
and professional opinions, it is valid
to transpose generalized storm data
from similar tropical regions of the
United States and northern Australia
to Peninsular Malaysia”.
Radar and Storm Model for PMP
Estimation, Hardaker and Collier, 1999
The purpose of this paper is to
estimate the PMP in the tropics, an
example quoted in the paper was a
subcatchment of Sg. Terengganu,
Sg. Petong catchment (CA=120 km2),
using meteorological parameterized
storm model of Austin et al (as
quoted in the presentation, 1995) of
UK Meteorological Office. In
essence, most of the input data are
obtained from the Doppler weather
radar. Therefore, in a way that this
proxy and indirect methodology
offers an obvious advantage vis-à-vis
the conventional maximization and
transposition methods that requires
bulk of measured rainfall records,
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
primarily to construct a Depth-Area-
Duration (DAD) curves for the
largest storms ever recorded in the
project area or at its vicinity.
The preliminary results of the point
PMP for 3-, 6-, 24-, 72-, and 120-hour
duration were estimated. The
authors concluded that the estimated
PMP using weather data were of the
same order of magnitude with the
past studies (quoted from Mr. David
Mcdonald, Chief Hydrologist of
Binnie and Partners of UK). The
authors however in their final
remarks cautioned that the
promising results obtained in their
study were of preliminary nature so
the adoption of such methodology
was still pending and warranting a
further in-depth investigation. For
comparison purpose, the results are
compared with the SMHB PMP
values as listed in Table 8.
Table 8: Comparison of PMPs of Hardaker & Colier and SMHB Coastal PMP Duration (hour)
PMP (mm) Hardaker and Collier 1999
PMP (mm) SMHB Coastal PMP
% Difference
3 484 338 +43% 6 593 440 +35% 24 818 777 +5% 72 924 1593 -42% 120 1029 2030 -49%
The variation between these two
methodologies is rather significant,
ranging from +43% to –49% of the
PMP values adopted by SMHB.
Specifically for long duration PMP
values, the difference is significant
by almost half of SMHB’s. The
exception was the 24-hour PMP that
differed only by 5%. It should be
noted that most of the east coastal
extreme rainfall only occurred
during monsoon months of
November to Earlier January. This
tropical storm surge, as it is
preferably termed by the
meteorological experts, is the results
of a regional cold front that is
originated from the northern
hemisphere. This Siberian cold front
reaches the equator sometimes at the
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
end of the calendar year. The surge
most likely lasts for several days. On
the other hand, the storm cell model
calculated in this study is based on
localized storm mechanisms and to
somewhat resemblance of a
convective storm process. Therefore,
it might be possible that this is the
reason for which lower PMP values
were calculated for longer duration
of more than 24 hours.
National Water Resources Study, SMHB/RHB/ZAABA, 2000 Hydrometeorological technique
(maximization and transposition
approaches) was used to generate
generalized isohyetal PMP maps of
various durations (3-, 6-, 12-, 24-, 72-,
120-, and 168-hour) for Peninsula
Malaysia. In this approach the
maximum rainfall recorded for
various durations (mostly acquired
from PKM database) are maximized
in situ using index of both prevailing
dew point temperature during storm
and maximum persistent dew point
temperature. Seven (7) isopleth
maps for all durations mentioned
above are then prepared
accordingly. Cautions are taken into
account when generating the
isopleth as a differentiation should
be made on the influence of
Northeast Monsoon in the east coast.
For brevity, the following table
presents the “point” PMP values for
all durations extracted directly from
the isopleth maps at the Sg. Selangor
dam site. Comparison with the
SMHB’s PMP (both Coastal and
Inland) values is shown in Table 9.
Table 9: Comparison of PMPs of NWRS 2000-2050 and SMHB Duration (hour)
PMP (mm) NWRS 2000-2050 Approx
*
PMP (mm) SMHB Coastal
PMP (mm) SMHB Inland
% Difference
3 430 338 300 (261) +65% 6 590 440 391 (352) +68% 12 680 582 518 (474) +43% 24 820 777 692 (643) +28% 72 1300 1067 (1035) +26% 120 1500 2030 1360 (1360) +10% 168 1650 N/A N/A
* choosing/interpolating to nearest contour as point value ( ) in col 3 indicates after applying the ARF
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
37
After reviewing the long duration
rainfall records, the investigators
concluded that any storm coming
from the northeast monsoon in the
upper region of the east coast of
Peninsular Malaysia, i.e. Terengganu
and Kelantan could also affect
rainfall on the west coast as
evidenced in the 1971 storm.
Likewise, a storm closer to Johor
Bahru and Kuantan in the lower
region of the east coast can also
affect the west coast of the
Peninsular Malaysia at the other side
of the Banjaran Titiwangsa (main
range).
Desa, Noriah, & Rakhecha. 2000 The Regional Humid Tropics and
Water Resources Centre for
Southeast Asia and the Pacific (HTC)
of JPS undertook the commendable
task of deriving 24-hour PMPs for
the State of Selangor by making use
of the relatively long-term rainfall
records in the JPS TIDEDA Database
System. This study is essentially
based on Hershfield technique using
some 32 rainfall stations of varying
years of records ranging from 34 to
62 years of long-term records to
derive the 24-hour PMP for the state
of Selangor. Subsequently an
isohyetal 24-hour PMP was
presented. This study carried out by
JPS/HTC opines that that the
recommended frequency factor
(Km=15) by Hershfield (1965) was
higher for Malaysia condition
(WMO, 1986). A review of such
nature i.e. in search of a common
basis of Km frequency factor is in
line with the recommendation of
WMO (1986). Therefore an entirely
new set of frequency factors was
subsequently derived using
observed one-day highest rainfall of
various station records and vital
statistics such as mean and standard
deviation. The new Km values are
ranging from low 2.0 to as high as
8.4. Three (3) point PMP values are
of importance for comparison
purpose due to their proximities to
the dam site and the upper Sg.
Selangor basin. They are Ldg Escot,
Hospital Kuala Kubu Baru, and Ldg
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Batang Kali. The calculated 24-hour
PMP values are presented in Table
10.
Table 10: Comparison of PMP (SMHB and JPS/HTC) Station Name Station No. 24-hour PMP
using Km = 8.7 (mm)
24-hour PMP using Km = 15
(mm) (1) (2) (3) (4) Ldg Escot 3615001 378 607 Hospital KKB 3516023 367 540 Ldg Batang Kali 3416025 347 508
It is obviously indicated that the
PMP value using Hershfield
technique is some 50% lower than
the PMP series (if choosing Km
equal 8.7) adopted by SMHB in the
Sg. Selangor dam design, i.e. 24-hour
inland PMP of 692 mm. However if
strictly following the
recommendation outlined in the
WMO (1973; 1986) manual on the
Km factor and no adjustment made
to the mean and standard deviation
of the maximum storm annual series,
the results presented in column 4 of
the table above are consistent and
comparable to the SMHB PMP value
vis-à-vis those of using a lower Km
value.
The statistical approach for any dam
design assignments is always
subjected to controversies,
uncertainties and criticisms under
the pretext that PMPs derived in this
way is only representative of a
“point” PMP value. Furthermore the
length of records that is used to
derive the statistic oftentimes is
rather short to be statistically
meaningful (Hersfield suggested a
minimum of 20-year records by
Hershield, as quoted in WMO
[1986]). As a result, some significant
rainfall event might be missed out
entirely due to non-recording or
error in instrumentation.
In addition, another important point
that is subjected to further argument
is the conversion from point PMP to
areal PMP, which is usually
accomplished by applying a
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
reduction coefficient (Areal
Reduction Factors; ARFs) based on
both the size of the catchment and
the chosen duration. For longer
durations and smaller catchment
areas, the reduction factor is
approaching unity. The ARF curves
are mainly derived by U.S. National
Weather Services (NWS) and
presumably using mostly storm
information in the continental USA.
Thus the validity and subsequently
suitability of such ARF factors
application in Malaysia is again
doubtful. Although there was a
study undertaken by the JPS in the
mid 1980’s, however the results were
inconclusive as “the ARFs derived in
this study were based on very short
records and therefore should be used
with caution” (Ong and Liam, 1986).
Furthermore, the author also
explained the fact that the ARF is
considered rather low for tropical
climatic condition such as in
Malaysia where the storms are
mostly of Blitz type thunderstorm
and short duration nature. This
probably explained low ARF factors
vis-à-vis the US NWS’s.
Interstate Raw Water Transfer, NK/SMHB 2000 This recent study is basically an
independent review and appraisal
on the substantial bulk of works
carried out previously in the
Kelantan Flood Mitigation Study
(SSP/SMHB, 1999) before adopting
PMP values in the design of both
Kelau (Catchment Area =331 km2)
and Telemong (Catchment Area
=360 km2) dams in the interior State
of Pahang. Eight major storms
mostly in the east coast regions of
Kelantan and Terengganu during
Northeast monsoon were identified
for the preparation of Depth-Area-
Duration curves (DAD). Each
individual DAD curve was prepared
using about 20 to 30 station records
in the vicinity of the storm epicenter.
Both auto and manual recorded
rainfall values were utilized though
in general, the auto-record data is
scarce in the regions
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
notwithstanding with only relatively
short period of records.
Long-duration PMP i.e.24- to 48 hour
was then derived after appropriate
adjustment for ‘unrestricted’ values.
The PMP values were then
enveloped, maximized and
transposed to the inland dam sites
that are closer to each other.
Similarly, short-term PMP for less
than 24-hour was also derived albeit
using different approach for reason
explained earlier on the scarcity of
auto-recording rainfall stations in the
east coast region as a whole.
Therefore it was not being able to
develop the DAD curves for shorter
duration from the amount of data
available.
In such case, recourses are then
made to adopt the short duration
PMP derivation based on procedure
developed by Australian Bureau of
Meteorology (ABM, 1985). This
technique is in turn, a procedure
based on the method of ‘adjusted
United States data’ as explained in
earlier subsection. Studies on the
maximum enveloping values
between these two continents
(although of relatively different
climatological characteristics
nevertheless lend support on the
adoption of the vast USA database in
Australia continent, (ABM, 1985)). It
was concluded that pattern and
nature of occurrence of short
duration storm are the same between
these two continents of almost the
same longitude. Based on this
similar argument, the short duration
PMP methodology developed by
joint US and Australian
meteorologists could be also used
elsewhere in the Southeast Asia
region. Essentially it assumes that
“the extreme rainfalls for short
durations and small area will be
produced by large, efficient, and
virtually stationary thunderstorms or
from part of a meso-scale or synoptic-
scale storm system with embedded
cumulus cells” (as quoted ad verbatim
from NK/SMHB, 2000; cf WMO,
1986).
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
40
As a check on the PMP values
derived from the hydro-
meteorological approach, Hersfield
technique was also used to ascertain
if the estimated PMP values are at
least in the same order of magnitude.
Nine (9) rainfall stations in the
vicinity the project site were used.
The results of 24-hour point PMP are
comparable, ranging from 410 mm to
highest 637 mm. These are
compared with the areal PMP at
both dam sites, i.e. 625 mm and 615
mm for Kelau and Telemong dam
sites respectively. Table 11 shows the
comparison of PMP values used in
the Interstate Water Transfer vis-à-
vis SSP3 projects.
Table 11: Comparison of PMP Derived from Interstate Water Transfer Project Duration (hour)
Kelau dam CA=331 km2
Telemong dam
CA=360 km2
Selangor Dam * CA=197 km2
ARF Adjusted Selangor
Dam 1 270 260 188 0.75 141 2 310 300 N/A 0.87 N/A 3 370 350 300 0.90 261 6 480 460 391 0.92 352 12 530 520 518 0.93 474 24 625 615 692 0.95 643 48 905 895 908 0.97 863 72 1050 1040 1067 N/A 1035 120 N/A N/A 1360 N/A 1360
N/A not available for duration more than 72-hour; * inland PMP
If conservatively assuming that the
PMP values for both Kelau and
Telemong dams can be transposed in
toto to the Selangor dam site without
adjustment, the PMP values for all
duration except for shorter duration,
are closely comparable. However it
should be borne in mind that, this is
nevertheless a conservative
approach by assuming that both
maximization and transposition
factors are the same for the dam
catchments at both sides of the
Banjaran Titiwangsa (main range of
the Peninsular Malaysia). This in
essence implies an equal
opportunity/probability of storm
occurrence in both the east and west
coasts notwithstanding the nature of
storm. Dominant storm in the west
coast region is often of the
convective nature, which is typified
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
by very intense and heavy
precipitation that last for a short
duration, i.e. 2 to 6 hours and
oftentimes occurs during the two
intermonsoon periods (from April to
May and October to November).
While in the east coast region of
Peninsular Malaysia and the coastal
region of Sabah and Sarawak, the
monsoon storms during November
to January are prevalent and
predominant and they are
widespread as well as could last for
a longer period, from several days to
a week. However it does not
preclude the occasional occurrence
of such long duration storm or surge
as preferably termed in the
meteorological communities in the
west coast.
Anecdotal observation of the
historical concurrent extreme storm
events in both east and west coasts
of the Peninsula Malaysia seemed to
prove otherwise (as evidenced by
less devastating flood consequences
and lesser rainfall). With the
exception of well-documented 1971
storm event in the west coast, hardly
any significant storms of the same
order of magnitude on a par with
1971 in latter years occurred in the
west coast. The consensus amount
the hydrologists within the
SMHB/B&P groups on the
transposition of east coast storm to
the sheltered inland or west coast (by
crossing the Banjaran Titiwangsa)
without appropriate transposition
factors are considered as “unduly
conservative” (SMHB, 1992). To
quote an example, the transposition
methods used in the Kelantan Flood
Mitigation Feasibility Study
(SSP/SMHB, 1999) were based on
ratios of 1-, 5-day total rainfall.
Short Duration Rainfalls in Selangor, Desa and Rakhecha, 2002 This study was undertaken by HTC
is an extended study on earlier 24-
hour PMP derivation in Selangor
and mainly focuses on the short
duration extreme rainfall. The
purpose of this study is to provide
pertinent information on the
characteristics of short duration
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
rainfalls for the design of small and
moderately sized hydraulic
structures in the urban areas. This is
implied that the study is more of
concern of low probability
occurrence of extreme rainfall, such
as in the range of return periods
from 2- to 100-year. This study in
essence, is a collation and
documentation of the highest auto
recorded rainfall event for short
duration in Selangor without further
analysis to derive PMPs. Therefore,
at this preliminary stage, it does not
take into consideration of converting
these observed rainfall records to
PMP by conventional maximization
technique using meteorological
parameters.
Short duration of auto-recording
rainfall data (from 1971 to 1999) of 13
recording rainfall stations in the state
of Selangor are compiled in the
respectively tables. The severity of
the extreme rainfall event is
quantified as percent chance of
occurrence (or represented by return
period in standard and conventional
hydrological practices).
In the records, the stations in the
state of Selangor received heavy falls
of rain of the order of 42 to 106 mm
in 0.25 hour, 60-183 mm in 0.50 hour,
73 to 365 mm in 1 hour, 114 to 522
mm in 6 hour, and 132 to 523 mm in
a 12-hour duration. In terms of
duration, the maximum rainfall
converged to about 6 hour, which is
evidently represented by some 90%
of the rainfall in the previous time
periods. In the opinion of the
authors, the prevailing extreme
rainfall events were mostly of short
duration nature.
In addition, it is also found out that a
majority of top 20 highest storm
events were mainly occurred during
the inter monsoon season from April
to May and October to November.
Table 12 shown below summarizes
the highest recorded rainfall for
different durations.
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
40
When comparing the highest rainfall
records vis-à-vis adopted PMP value
at Selangor dam, it should be in
mind highest recorded point
rainfalls in table above do not take
into account of conventional PMP
derivation technique of storm
maximization (irrelevant for
transposition in the context). The
implication of these findings is far
reaching in such a way that a
reassessment of the short duration
PMP rainfall in Selangor is most
likely warranted.
From Table 12, it could be seen
clearly that the first, second, and fifth
highest recorded rainfalls for 12-
hour duration are located some
distances from upland catchment
except for Sek Men Kg. Lui and Kg.
Kalong Tengah station. Comparison
of these observed upland basin
highest rainfall records vis-à-vis the
Selangor PMP is imperative to
ensure that the PMP convention of
SMHB/B&P is indeed adequate.
Table 12: Highest Records Extreme Rainfalls for Various Durations in Selangor Duration (hour) No Name of the rainfall station ¼- ½- 1- 6- 12-
1 Pejabat Pos Manggis 42 60 73 119 154 2 Ibu Bekalan Enam Kaki 96 96 96 114 169 3 Pintu Kawalan P/S Teluk Gong (1) 91 183 365 522 523 4 Setor JPS Kajang 54 71 89 165 171 5 Puchong Drop (2) 55 61 91 126 316 6 Pusat Penyelidikan JPS Ampang 54 68 96 125 136 7 Sek Keb Kg Lui (4) 99 99 142 197 197 8 Rumah Pam JPS Paya Setia 64 68 112 163 169 9 Setor JPS Tanjung Karang (5) 74 74 87 174 175 10 Kg Kalong Tengah (3) 68 68 76 226 227 11 Loji Air Kuala Kubu Baru 106 106 106 154 154 12 Ibu Bekalan Sg. Bernam 62 85 104 147 165 13 Rumah Pam JPS Bagan Terap 101 102 102 132 132 Excerpt from Desa and Rakhecha (2002); ( ): ranking in terms of highest rainfall Table 13 shown below summarizes
highest records of rainfall stations in
the upper catchment in Selangor.
Setor JPS Kajang and Sek Keb Kg.
Lui are located in the Sg. Langat
basin, while the other two, Kg
Kalong Tengah and Loji Air Kuala
Kubu Baru stations are within the
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
upper Sg. Selangor catchment downstream of the Selangor dam.
Table 13: Comparison of Higher Rainfall Records in Upper Catchment in Selangor Duration (hour)
Setor JPS Kajang
Sek Keb Kg Lui
Kg Kalong Tengah
Loji Air Kuala Kubu
Baru
Selangor Dam CA=197 km2
¼ 54 99 68 106 ½ 71 99 68 106 1 89 142 76 106 188 2 N/A 3 300 6 165 197 226 154 391 12 171 197 227 154 518
The comparison in Table 13
apparently is not in anyway
unreasonable and indicative of
underestimation of the Selangor
PMP by SMHB. If the observed
highest values are maximized by
some coefficients, say, 50% higher
due to moisture saturation in the
upper planetary boundary (by
measuring the maximum persistent
dew point temperature and storm
dew point temperature) do not
exceed the PMP values except 1-hour
duration rainfall of Sek Keb. Kg. Lui
station. Only the highest rainfalls
recorded for almost all durations in
the downstream and near the coastal
region, such as Puchong Drop and
Tanjung Karang, are exceeding the
Selangor PMP. It is not known at
present the reasons of such highest
PMP values due to limitation on the
knowledge in the area of expertise of
meteorology. However, this is not in
anyway to ignore such highest
records in the lower catchment
where no major water detention
structures are most likely to be
located especially in the state of
Selangor. Nevertheless,
counterchecking with neighboring
stations is imperative to ascertain if
these values are not isolated event in
the vicinity.
Sg. Kelinchi Dam, SSP/MM, 2001 The PMP derivation was part of the
Kelinchi dam design study by
SSP/MM (2001). The Kelinchi
reservoir is located within the upper
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
catchment of Upper Muar reservoir.
The purpose of the reservoir is to
facilitate water transfer across the
mountain range (via tunnel) to the
Sg. Terip WTP. Besides, it is also
served as extra holding for raw
water via pumping from upper
Muar reservoir downstream. Table
14 is extracted from the design
report on PMP.
Table 14: Comparison of PMP at Upper Muar Dam and Kelinchi Dam Upper Muar Dam Duration (hour)
PMP (mm) Kelinchi Dam Duration (hour)
PMP (mm)
3.5 315 3 337 6.5 400 6 394 12.5 525 12 521 24.5 689 24 692 120 1800 Excerpt from SSP/MM 2001 Upon checking, the results of PMP
analysis are agreeable to SMHB,
although Hershfield’s methodology
was used by SSP/MM in their
assignments. In line with the
recommendation by Hershfield on
the derivation of Km factor,
SSP/MM (2001) slightly modified
the Km values in their computations.
This is accomplished mostly by the
reduction of Km with increased
annual maximum rainfall in the 2600
stations that were used in the
original derivation of the Hershfield
equation. The Km factor is lower for
short duration, i.e. 13 is adopted for
3- and 6-hour duration respectively.
It is however, a blanket adoption of
such adjustment might not be
warranted in the tropic region, such
as in Malaysia. This is due to the fact
almost 90% of the data selected by
Hershfield in the derivation of
statistically based equation were
from USA. As such, if no reduction is
made on the Km factors, the
calculated PMP could be higher than
those tabulated and summarized in
Table 14 (see column 4).
Unfortunately, at the time of this
writing, the mean and standard
deviation of the rainfall records are
not available for calculation using a
constant Km value, i.e. 15.
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Gelami Dam Design JPS, 2002 The proposed Gelemi reservoir/dam
is a small scheme water supply for
the aquacultural research station in
the upper teriang basin in Negeri
Sembilan. The proposed dam site is
located on one of the tributary of Sg.
Teriang basin. The hydrology
division of the JPS carried out the
detailed PMP study as part of the
assignment for engineering
(spillway) design. The methodology
adopted in this study is of statistical
approach (Hershfield, 1965) but with
modification to the derivation of the
frequency factor, Km. This
modification is based on a research
note published in the Water
Resources Research (Koutsoyannis,
1999). Other than Km modification,
the estimation by JPS also made
appropriate conventional
adjustments for mean and standard
deviation of the maximum rainfall
annual series for individual
duration. For information, the Km
factor for most of the standard
derivation is 15 as this is the highest
enveloped value in the original
Hershfield analysis (WMO, 1986).
The modification is achieved by
recalculating the Km factors for each
duration. As a result, Km factors are
lower to as low as 10.4 for 0.25-hour
duration to as high as 17 for longer
duration, i.e. 120 hour. For
comparison, for a 24-hour duration
PMP, Km is adjusted slightly
upward to about 16 vis-à-vis 15, that
is normally in statistically based
PMP studies.
Due to its close proximity to Sg.
Semenyih basin, i.e. neighboring
basin, comparison of PMP vis-à-vis
those adopted in the Semenyih dam
design is considered reasonable.
Except for 3-hour duration, the
estimated PMP by JPS using
modified version of Hersfield
methodology is mostly lower than
SMHB, i.e. from 9% to as high as
30%. As mentioned above, the
designer adopted adjusted mean and
standard deviation in the calculation.
This adjustment essentially lowers
both the mean and standard
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
deviation of the maximum rainfall
annual series for reason of shorter
length of records vis-à-vis
recommendation in WMO (1986). If
assuming that no adjustments are
made, the estimated PMP for each
duration will then be slightly higher
than before. For such purpose, the
recalculated PMP values without
adjustments are shown in column 6
in Table 15.
Table 15: Comparison of PMPs of JPS (2002) and SMHB Inland Series Duration (hour)
Modified Km factor
(JPS, 2002)
PMP (mm) JPS (2002)
PMP (mm) SMHB Inland
% Difference PMP (mm) without Xn and
Sn adjustment JPS (2002)
((1) (2) (3) (4) (5) (6) 3 12.394 315 300 (261) 5.00% 412 6 13.645 356 391 (352) -8.95% 461 12 14.958 460 518 (474) -11.20% 540 24 15.947 598 692 (643) -13.58% 664 72 16.679 774 1067 (1035) -27.46% 1069 120 16.974 941 1360 (1360) -30.81% 1312
( ) in col 3 indicates after applying the ARF Kelinchi Dam Feasibility Study, SSP/SMEC, 1990 Short duration PMPs are calculated
at each dam site using the Australia
Bureau of Meteorology (ABM)
generalized approach. As
previously compared with other
studies, the ABM estimates are
seemed to be rather high PMPs
value. The estimated PMPs are also
adjusted by the elevation/moisture
inflow barrier and dew
point/maximum atmospheric
moisture factors. The adjustment
procedures could be further referred
in the ABM bulletin for short
duration PMP estimation (recent
amendment of PMP was made in
1996 and issued as Bulletin 53). The
estimated PMPs by ABM are also
tabulated in the Table 16. For
comparison, the Selangor PMP for
similar duration periods is also
written.
Table 16: Short Duration PMP for Various Dam Sites in Negeri Sembilan Duration (Hour)
Kelinchi dam
Sikamat dam
Teriang dam
Gelami dam 1 (mm)
Gelami dam 2
Selangor (mm)
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
(mm) (mm) (mm) (mm) 1 349 352 342 342 352 188 2 627 634 611 611 634 3 836 848 816 816 848 300 Calculation based on ABM short duration methodology
Jemelan Reservoir, JPZ, 1998 The project encompasses a small
reservoir/dam and appurtenances
on Sg. Jemelan, Jerebu, Negeri
Sembilan. The reservoir drains about
7.2 km2 of Teriang Forested Reserve.
The PMP is estimated using
statistical approach, presummedly
Hershfield’s methodology. Table 17
shows the PMP calculated up to 24
hour.
Table 17: PMP in Jelebu, Negeri Sembilan. Relationship of PMP Selangor Dam Rainfall duration
(hour) PMP (%) (mm) (mm) 3 67% 322.40 300 6 83% 399.39 391 12 94% 452.32 518 1-day 100% 481.19 692 Excerpted from JPZ (1998) CONCLUSIONS Both PMPs adopted by SMHB/B&P
and studies by other consultants are
presented systematically in tandem in
this review.
It should be emphasized a priori that
there is no single unified
methodology or procedure in
estimating PMP values in Malaysia
as can be evidently seen in Table 18,
specifically for the case 24-hour
duration PMP adopted in various
studies throughout Peninsular
Malaysia. Competent professionals
and experts in this specialized field
may even obtain different results
because most these estimations
required subjective judgments and
empiricisms. This is further
concurred by WMO (1986),
“Procedure for estimating PMP cannot
be standardized as they vary with
amount and quality of data available,
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
basin size, and location, basin and
regional topography, storm type and
climate…”.
Two series of PMP values, namely
Coastal and Inland PMPs are
basically adopted by B&P/SMHB in
their dam design projects
undertaken throughout the year.
The Inland PMP values were
adopted in several dam design
studies, such as Linggi, Semenyih,
Tinggi, and Selangor dams, as it is
most suitable to represent the
prevailing weather pattern in the
interior west coastal basin.
The long duration PMP, which
derived based on several recorded
extreme events (about 8 of them) in
the Northeast Monsoon in the east
coast are basically consistent in the
same order of magnitude for 3
independent studies, i.e. SSP/HH
(1979), SSP/SMHB (1999), and
NK/SMHB (2000).
Table 18: Selected PMP Estimate for Dams in Peninsular Malaysia PMP Duration Dam Catchment
area (km2) 3-hour (mm) 6-hour (mm) 24-hour(mm) 72-hour(mm) Sources/Remarks
Ayer Hitam 5.8 230 259 366 (B&P, 1976) Langat 41 191 (1-h) 432 && (B&P, 1976) Kenyir 1600 470 1280 (ABM and SMEC, 1976) Layang 31 490 840 (T&T, 1977) Semberong 130 312 541 817 (SSP and HH, 1979) Semberong 130 203 352 531 (Grout, 1980) Semberong 130/123 297 697 1412 (ABM and SMEC, 1984) Bekok 350 291 524 791 (SSP and HH, 1979) Bekok 350 207 372 562 (Grout, 1980)) Bekok 350/349 297 687 1412 (ABM and SMEC, 1984) MacRitchie 7.7 675 (PUB, 1979) Seletar 10.8 338 440 777 (B&P, 1980) Semenyih 58 300 390 692 (B&P (1983) Tinggi (Buluh) 40 300 390 692 (SMHB, 1990) Selangor 192 300 390 692 (SMHB, 1999) Ahning 120 244 348 436 (JK and SMEC, 1982) Ahning 120 740 1160 1720 (ABM, 1984) Ahning 120 323 634 806 (B&P, 1986) Machap 30 234 396 577 (SSP and HH, 1979) Malut 3.4 440 (1-h) 600 (2-h) 740 (3-h) (JK et. at., 1984) Malut 3.4 N/A N/A N/A N/A **(SMHB, 1994) Batu 50 337 470 820 (USBR, 1984) Klang Gates 77 330 460 812 (USBR, 1984) Gombak 88 329 458 806 (USBR, 1984) Tembat 101 510 660 1010 1660 (SMEC, 1985) Linggiu 208 723 1541 (SMHB, 1985)
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
Terengganu 2 44 640 840 1140 1330 (ABM and SMEC, 1988) Kuala Yong 91 600 780 1080 1270 (ABM and SMEC, 1988) Paya Peda 77 610 850 1655 (ACE, 1995) Noak 15.8 250 350 560 720 (SMHB, 1984) Puah 410 420 560 470 ? 1150 (SMEC, 1983) Upper Muar 148 295 390 685 1412 (SMHB, 1993) Beris 116 204 385 536 1015 (ACE, 1994) Timah Tasoh 191 402 560 1090 (ACE, 1996) Padang Saga 12 330 577 695 (ACE, 1987) Padang Saga 12 466 577 695 (JPZ, 1997) Aur 98.3 542 756 1428 (JPZ, 1998) Bukit Merah 480 525 630 (MACE, 1987) Bukit Merah 480 707 1408 (JPZ, 1997) Congok 17.6 777 2030 * (SMHB, 1988) Lebam 18.9 777 2030 * (SMHB, 1991) Telemong 360 350 460 615 1040 # (NK and SMHB, 2000) Kelau 331 370 480 625 1050 # (NK and SMHB, 2000) Lebir 1465 * (SSP and SMHB, 1999) Kemubu 1090 * (SSP and SMHB, 1999) Babagon 30 320 575 (7-h) 700 (KKPK and SMHB, 1992) Gelami Lami 22.2 315 356 598 774 (JPS, 2002) Kelinchi (SSP and MM, 2001) Kelinchi 836 (SSP and SMEC, 1990) Sikamat 848 (SSP and SMEC, 1990) Gelami 1&2 816/848 (SSP and SMEC, 1990) Jemalan 322 399 481 (1-d) (JPZ, 1998) * 120-hourduration; # 72 hour; && not equated to PMP in B&P (1976) report; PMP values without areal adjustment: Excerpted from SMHB, 1992; SMHB, 1994; checked with SMHB/RHB/ZAABA, 2000.
On the other hand, for short
duration PMP, due to the primarily
scarcity of automatic recorded
information available in Malaysia,
the agreements amongst various
consultants that undertook PMP
studies in Malaysia cannot be
reached amicably. ABM who
establishes itself in Malaysia as the
principal specialist on PMPs in the
Kenyir (Terengganu) and Pergau
(Kelantan) dams design in the east
coast and several other reservoir
design in both Sabah and Sarawak
(Batang Ai, Gerugu, Kelolong, and
Babagon), derives its short duration
PMP of less than 6-hour duration
based on adjusted storm records
occurring in Australia and USA
(ABM Bulletin 51; now revised
version Bulletin 53, 1994 with
amendment issued in 1996). In their
contentions, it is valid to transpose
generalized storm data from similar
tropical regions of the USA and
Australia to Peninsular as well as
Borneo Malaysia. To start with, it
however remains doubtful if such a
generalized methodology could be
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
used in its entirety in Malaysia,
which rarely experiences such
extreme weather conditions (such as
typhoons, hurricanes, and
tornadoes) as in the USA and/or
perhaps Australia. The short
duration PMP derived by ABM is
always higher vis-à-vis
B&P/SMHB’s conventions, which is
based mostly on maximized
observed records of short duration
rainstorm in Singapore and southern
Peninsular Malaysia (mostly the1978
storm).
As a check, comparison was also
made with the statistical approach,
i.e. Hershfield technique for 24-hour
PMP in the state of Selangor. It
concludes and shows consistency in
PMP values derived by both totally
different approaches albeit the
Hershfield technique is mostly in the
lower end.
Appendix A: List of Abbreviations ABM Australia Bureau of Meteorology
Angkasa-GHD Angkasa-GHD Sdn. Bhd.
ARF Areal Reduction Factor
B&P Binnie and Partners Pty. Ltd.
CA Catchment Area
DAD Depth-Area-Duration
HH Howard Humphrey
HTC The Regional Humid Tropics and Water Resources Centre For Southeast Asian and the Pacific
JPS Jabatan Pengairan dan Saliran (Department of Irrigation and Drainage, Malaysia)
JPZ JuruPerunding Zaaba Sdn. Bhd.
Kinhill Kinhill Engineer Pty. Ltd.
km Hershfield’s Equation Frequency Factor
km2 square kilometer
MM Mott MacDonald
NK Nippon Koei
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
38
PKM Perkhidmatan Kajicuaca Malaysia (Malaysia Meteorological Service)
PMP Proable Maximum Precipitation.
PUB Public Utility Board
Ranhill Ranhill Bersekutu sdn. Bhd.
SDW Sewage Disposal Works
SMEC Snowy Mountain Engineering Consultant
SMHB Syed Mohammad, Hooi and Binnie Sdn. Bhd.
SSP Setia Sepakat Sdn. Bhd.
TIDEDA Time Dependant Data Program
USBR United States of Bureau of Reclamation
US NWS United State National Weather Services
WMO World Meteorological Organization
References Australian Bureau of Meteorology (ABM), 1985. The Estimation of Probable Maximum Precipitation in Australia for Short Durations and Small Areas. Bulletin 51, Australian Government Publishing Service, Canberra (replaced by Bulletin 53, 1994; with amendment in 1996).
Angkasa-GHD, 1998. Putrajaya: Perang Besar Reservoir Design Study, Appendix D: Flood Hydrology for Main Dam, Final Design Report.
B&P, 1980. Modifications to the Seletar and Upper Peirce Reservoirs to Provide Additional Storage, PUB, Singapore.
Desa, M,M.N., A.B. Noriah, P.R. Rakhecha, 2000. Probable Maximum Precipitation for 24 Hours Duration over Southeast Asian Monsoon Region- Selangor Malaysia, in Extreme of the Extreme Rainfall in Selangor, JPS/HTC Seminar, September 2000.
Desa M, M.N., and P.R. Rakhecha, 2002. Short Duration Extreme Rainfalls in Selangor, Malaysia. In International Conference on Urban Hydrology for the 21st Century, Kuala Lumpur, Malaysia, October 2002.
Hardaker, P.J. and C.G. Collier, 1999, Radar and Storm Model-based Estimation of Probable Maximum Precipitation in the Tropics. http\\www.unesco.org.uy
Hershfield, D.M., 1961. Estimating the Probable maximum precipitation. Proc. ASCE, Journal of Hydraulic Division, vol 87, 99-106.
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
39
Hershfield D.M., 1965. Method for Estimating Probable Maximum Precipitation. Journal of American Waterworks Association, vol 57, 965-972.
JPS, 2002. Projek Empangan dan Kolam, Gelimi Lemi, Jelebu, Negeri Sembilan, Hydrology Report, Unit Hidrologi Gunaan, Jabatan Pengairan dan Saliran (JPS) Malaysia.
Jurutera Perunding Zaaba, 1998. Detailed Design of Small Dam and Related Works at Mardi Station, Jelebu, NS. Volume 2. Draft Final Report Appendices. Jabatan Pengairan dan Saliran Malaysia.
Kinhill and Ranhill, 1994. Klang River Basin integrated Flood Mitigation Projects, Malaysia, Final Report.
Koutsoyiannis, D. 1999. Probabilistic view of Hershfield’s method for estimating probable maximum precipitation. Water Resources Research Vol 35 No. 4, pp 1313-1322.
NK and SMHB, 2000. Pahang-Selangor Raw Water Transfer Project Engineering Services and Detailed Engineering Design: Hydrology, Final Report, JBA, JKR Malaysia.
National Research Council, 1985. Safety of Dams: Flood and Earthquake Criteria, National Academic Press, Washington DC, USA.
National Research Council, 1994. Estimating Bounds on Extreme Precipitation Events: A Brief Assessment, National Academic Press, Washington DC, USA.
Ong, C.Y. and W.L. Liam. 1986. Variation of Rainfall with Area in Peninsular Malaysia. Water Resources Publication No. 17, Jabatan Pengairan dan Saliran, Kementerian Pertanian Malaysia.
SMHB, 1985. Feasibility and Preliminary Engineering Studies for the Joint Development of the Johor River Water Resources, Technical Report Vo. 4 on Hydrology, Malaysia/Singapore Joint Technical Subcommittee for the Joint Development of the Johor Water Resources, Malaysia.
SMHB, 1992. Study in Comprehensive Water Resources Planning and Development in the State of Pahang, Economic Planning Unit, Government of Malaysia.
SMHB, 1994. Study in Comprehensive Water Resources Planning and Development in the State of Johor, Government of Johor, Malaysia.
SMHB, RHB and ZAABA, 2000. National Water Resources Study 2000-2050, Hydrology Chapter, Final Report, EPU, Government of Malaysia.
SSP and HH, 1979. Dams on Sg. Bekok and Sg. Semberong, Detailed Investigation and Design: Hydrology, JPS Malaysia.
International Journal of Hydro-Climatic Engineering Assoc.Water and Enviro-Modeling Poon et.al.(pp.37 – 72) eISSN : 99990001
40
SSP and SMHB, 1999. Kelantan River Flood Mitigation Plan Feasibility Study, SSP/SMHB, Jabatan Pengairan dan Saliran, Malaysia.
SSP and MM, 2001. Sg. Kelinchi Water Resources Study. Final Report, Jabatan Bekalan Air Negeri Sembilan, Negeri Sembilan, D.K.
SSP and SMEC, 1990. Feasibility Study for Water Resources Development for Domestic and Industrial Uses for the District of Seremban and Port Dickson. Volume 1: Technical and Financial Report, Final Report, Jabatan Kerja Raya, Malaysia.
WMO, 1973. Manual for Estimation of Probable Maximum Precipitation, first edition, (WMO- No 332), World Meteorological Organization Operational Hydrology Report No. 1.
WMO, 1986. Manual for Estimation of Probable Maximum Precipitation, second edition, (WMO- No 332), World Meteorological Organization Operational Hydrology Report No. 1.