Upload
shay-waxen
View
215
Download
0
Embed Size (px)
Citation preview
7/27/2019 Pricing Electricity in Delhi
http://slidepdf.com/reader/full/pricing-electricity-in-delhi 1/4
COMMENTARY
january 5, 2013 vol xlviIi no 1 EPW Economic & Political Weekly20
Kannan Kasturi ([email protected]
)
is an independent researcher and writes on
public interest and policy.
Pricing Electricity in Delhi
Kannan Kasturi
When Delhi’s electricity
distribution was privatised in
2002, power was allocated and its
cost set by the government. Power
purchase costs were considered
pass-throughs for the operations
of the distribution utilities.
However, with significant changes
in the electricity generation and
trading business in the interim,
Delhi’s consumers are paying notonly for the regulated guaranteed
profits of the state-owned
generation, the transmission
companies and the private
distribution companies, but also
for the unregulated profiteering
of the merchant producers and
other market players.
The price of electricity has gone up
between 51% and 63% for differ-ent classes of consumers in Delhi,
all in the space of one year.1 The highest
increase of 63% has ironically been
imposed on consumers who consume
the least – less than 200 units of electri-
city per month.2 Table 1 shows the last
three revisions of the energy tariff for
domestic consumers. In addition to
these charges, customers pay electricity
tax and a fixed connection charge.
Electricity distribution in all of Delhi,
with the exception of the New Delhi
Municipal Council (NDMC) area and the
cantonment, was privatised 10 years ago
and divided up between three distri-
bution companies (discoms) – the Tata
Po wer Delhi Distribution Limited (TPDDL)
belonging to the Tata group, and BSES
Rajdhani Power Limited (BRPL) and BSES
Yamuna Power Limited (BYPL), both
belonging to the Reliance Anil Dhirubhai
Ambani Group ( ADAG). The Delhi Electri-
city Regulatory Commission (DERC) fixesthe tariff that can be collected by these
entities. It will useful to recall the pro-
cess followed in fixing tariffs before
looking into the reasons for the large
hikes in quick succession.
The Electricity Act
2003 tasks the state
electricity regulator
with laying out the
principles for tariff fix-
ing, ensuring “safe-
guarding of consumers’
interest and at the same time, recovery
of the cost of electricity in a reasonable
manner”.4 In Delhi, these principles find
expression in DERC’s Multi-Year Tariff
(MYT) regulations for discoms.
Under these regulations, discoms
submit a multi-year plan stating their
annual revenue requirement, including
the cost of power, operation and mainte-
nance expenses, depreciation, and a
guaranteed return on capital employed. After review, and possible changes, the
DERC approves the requirement for each
utility and fixes a tariff structure that
will enable all the utilities to meet their
revenue requirements.
The actual performance of a utility may
differ from the planned performance
because of factors that are not in its
control. The MYT regulation distinguishes
between “controllable” and “uncontrol-lable” factors. Operation and maintenance
expenses, depreciation, return on capital
employed and collection efficiency are
considered “controllable” while power
purchase cost and sales are considered
“uncontrollable”. Every year, a utility is
expected to submit its audited accounts
to the regulator asking for a “true up”,
that is, recognition of the variation in
expenditure and revenue from planned
values. The true up of accounts provides
utilities an annual opportunity to argue
for tariff revision on the basis of increases
in uncontrollable costs.
Safeguarding consumer interests in such
a business model calls for a high degree
of regulatory expertise and vigilance. It
also requires that utilities be completely
transparent in their operations. Unfor-
tunately, the utilities have gone to court
against attempts to bring them under
the ambit of the Right to Information
(RTI) Act while the state governmentitself has been reluctant to recommend
a Comptroller and Auditor General
(CAG) audit of their accounts despite
recommendations from the regulator
(Ramachandran 2012).
Against this background, we can look at
the rationale for DERC’s recent tariff orders.
In the true-up exercise for 2009-10
carried out in August 2011, the discoms
argued for a price increase based on
higher than anticipated power purchase
costs. DERC revised tariffs and also
introduced a new component – a fuel
price adjustment surcharge – that would
allow the discoms to pass on a sub-
stantial part of increases in power pur-chase cost during the course of the year
to consumers.
Table 1: Electricity Tariff in Delhi for Domestic ConsumptionEffective from Slab-wise Energy Charges (Rs/unit) Power Price Deficit
Adjustment Surcharge0-200 Units 201-400 Units > 400 UnitsSurcharge (%) (%)
March 2008 2.45 3.95 4.65
September 2011 3.95 4.80 5.50 Variable
July 2012 4.65 5.70 6.50 Variable 8
Source: DERC tariff orders.3
7/27/2019 Pricing Electricity in Delhi
http://slidepdf.com/reader/full/pricing-electricity-in-delhi 2/4
COMMENTARY
Economic & Political Weekly EPW january 5, 2013 vol xlviIi no 1 21
In the next true-up exercise, this time
for 2010-11, carried out in July 2012,
DERC accepted that the revenue shortfall
of the discoms had cumulated to high
levels till the end of 2011, despite the
tariff increase of September 2011. It
revised tariffs upwards, after estimating
the power purchase costs for 2012-13 andsucceeding years and also added another
component to the tariff, a special sur-
charge to recover past shortfalls in reve-
nue, besides modifying the fuel price
adjustment surcharge to a power pur-
chase price adjustment surcharge.
It appears that DERC raised tariffs
both times in response to a single factor
deemed to be outside the control of the
discoms – the increase in the cost of
power purchased by them.
Operational Costs
The costs of discoms primarily engaged
in retail supply may be broken up into
the cost of power delivered to the distri-
bution network and the distribution cost
(including the discoms’ return on capital
employed). These are presented as aver-
age cost per unit (kWh) of power. The
quantum of power billed to customers is
less than the quantum of power pro-
cured by the utility because of distribu-tion losses.5 The cost of the lost power is
borne by the billed customers.
Table 2 indicates the build up of costs
for TPDDL. The figures till 2010-11 are
trued-up costs while the ones for 2012-13
are the projections that were used by
DERC for changing tariffs.
In 2008-09, the average cost of power
available with TPDDL for distribution to
its customers was Rs 2.83/unit. After
accounting for a 19% distribution loss,
the cost of power increased to Rs 3.50/
billed unit. Together with a distribution
cost of Rs 0.95/billed unit, the total cost
of power supplied to the customer
became Rs 4.45/billed unit. This was
also indicative of the average revenue
per billed unit that had to be recovered
from customers.7
As Table 2 indicates, the reduction in
distribution losses reached a plateau for
TPDDL and the benefits for customers
from loss reduction – a major argument
advanced for privatisation – have largely
run their course. Distribution costs haveremained largely under control except for
a blip in 2009-10, caused by staff salary
increases from the Sixth Pay Commission.
Without accepting that distribution costs
are at reasonable levels, it can still be seen
that increases in the cost of electricity
delivered to the customer is almost
entirely driven by increases in the cost of
purchased power.
The other discoms differ in their cost
details, but the above conclusion holds
for them, too.8
Adding Up the Cost of Power
The bulk of the power needed for Delhi
is procured through standing long-term
power purchase agreements (PPAs) with
central and state sector generation plants.9
If the power supplied from these plants
is inadequate, the discoms must make
their own arrangements to source power
from elsewhere. They must also make
arrangements to sell surplus power.
Selling power in the short-term is
pretty much unavoid-
able for Delhi’s discoms.
With consumption being
mainly domestic and
commercial, there is a
large variation in de-mand over the course of
a day. Thanks to Delhi’s
extreme climate, demand also varies by
season. The ratio of the same day peak
load to minimum load in 2011 moved
from 1.4 in summer to as high as 2.1 in
winter and the ratio of summer peak
load to winter minimum load was 3.1.10
Catering to peak loads through long-
term contracts will entail selling power when the load decreases.
Table 3 shows how sourcing of power,
transmission costs and losses and the
sale of surplus power build up to the
price of power available for distribution
to the customer.11
In 2008-09, TPDDL procured 89.7% of
its power through long-term PPAs at a
cost of Rs 2.59/unit and the rest through
short-term power purchases at Rs 4.35/
unit. After adding transmission costs,
the average cost of power was Rs 2.97/
unit. Transmission losses accounted for
4.1% of the power purchased and 10.8%
was sold to other utilities. Surplus power
could be sold at Rs 5/unit, much above
the cost of power procured. This kept the
cost of power available for distribution to
TPDDL customers at Rs 2.87/unit, only
10% above the cost of long-term power.
The situation changed dramatically
for the worse in 2009-10. Expensive
short-term power purchases were used
to a much larger extent and surplus
power was sold at rates below the short-
term purchase rates. These transactions
drove up the cost of power available for
distribution to Rs 3.68/unit, a 30% mark
up over the cost of long-term power.
Similar factors played out in 2010-11. Intwo years, TPDDL’s cost of power for dis-
tribution went up by a whopping 49%.
Table 2: Operational Costs of TPDDL2008- 09 2009-10 2010-11 2012-13 (P)
Power cost per input unit (A) 2.83 3.70 4.20 4.27
Distribution loss (B) (%) 19.00 16.51 12.39 12.06
Power cost per billed unit [C]=(A/(1-B)) 3.50 4.43 4.80 4.86
Distribution cost per billed unit (D) 0.95 1.21 0.95 1.03
Total cost per billed unit (C+D) 4.45 5.64 5.75 5.89
All costs in Rs/unit; (P) indicates DERC projections.
Source: DERC true-up orders.6
Table 3: Power Cost Build-up for TPDDL and BRPL2008- 09 2009-10 2010-11 2012-13 (P)
Amount (%) Rate Amount (%) Rate Amount (%) Rate Amount (%) Rate
TPDDL12 Long-term purchase 89.7 2.59 80.2 2.81 82.4 3.20 100.0 3.71
Short-term purchase 10.3 4.35 19.8 5.25 17.6 5.56 0.0 0.00
Transmission costs 0.20 0.22 0.28 0.26
Net purchase 100.0 2.97 100.0 3.52 100.0 3.90 100.0 3.97
Transmission losses 4.1 5.4 4.8 4.9
Excess sales 10.8 5.00 8.9 4.11 12.1 2.96 35.5 4.00
Net for customers 85.1 2.86 85.7 3.68 83.2 4.25 59.6 4.27
BRPL Long-term purchase 91.1 2.57 81.5 2.81 80.9 3.20 100.0 3.74
Short-term purchase 8.9 4.54 18.5 5.36 19.1 5.12 0.0 0.00
Transmission costs 0.22 0.23 0.31 0.32
Net purchase 100.0 2.96 100.0 3.51 100.0 3.88 100.0 4.06
Transmission losses 4.4 4.1 5.7 4.7
Excess sales 8.8 5.17 13.2 3.66 16.9 3.21 30.2 4.00
Net for customers 86.8 2.89 82.7 3.66 77.4 4.31 65.1 4.39Rates are in Rs/unit; amounts represent the percentage of total power procured; (P) indicates DERC projections.
Source: Discom true-up petitions13 and DERC true-up orders.
7/27/2019 Pricing Electricity in Delhi
http://slidepdf.com/reader/full/pricing-electricity-in-delhi 3/4
COMMENTARY
january 5, 2013 vol xlviIi no 1 EPW Economic & Political Weekly22
The poor realisations on sale of sur-
plus power have negative implications
for the cost of power in coming years.
DERC’s projections for 2012-13 show that
with the availability of power from newly
commissioned plants, Delhi’s utilities will
have a large surplus on hand.14 TPDDL,
for example, will have to dispose off over35% of the power it purchases. DERC has
optimistically assumed that this power
can be sold at Rs 4/unit when the reali-
sation was only Rs 2.96/unit for much
smaller amounts of power in 2010-11,
without giving any reasons for its opti-
mism.15 If these assumptions turn out
incorrect, Delhi’s consumers are in for
further sharp increases in tariff.
BRPL procurement costs display be-
haviour similar to TPDDL’s. In complete
contrast to these two, the state-owned
distribution arm of NDMC was able to
keep the cost of power available for dis-
tribution as low as Re 0.62/unit and
Rs 2.87/unit in 2008-09 and 2009-10 re-
spectively!16 The secret of this amazing
feat was that NDMC was allocated
enough “cheap” long-term power, obvi-
ating the need for short-term purchases.
Further, it was also able to sell its sur-
plus – 43% of its allocated power in
2008-09 and 39% in 2009-10 – at aprofit to other utilities.
Short-term power purchase and sales
were not the only reason for escalating
power costs of the discoms. An
examination of Table 3 shows
that the cost of long-term pow-
er went up by about 24% over
two years. Transmission costs
went up inordinately and trans-
mission losses too showed an
upward trend.17
The cost of power from the
central sector and state power
generators is regulated by the
Central Electricity Regulatory
Commission (CERC) and the
DERC respectively. It is a cost-
plus model, with assured re-
turns for the power producers. The for-
mula for the rate at which power is sold
has two components – a “fixed” part
and a part that varies with the cost of
fuel. Fuel cost increases are automati-cally passed on to the power purchasers
while fixed costs are revisited in tariff
orders by the regulators. The long-term
state-owned power producers have
been effectively inflation proofed!
Discretion in Power Trades
Since short-term trades have played a
huge role in escalating the cost of power
sold by the discoms, it will be useful toexamine them in greater detail.
Delhi’s discoms have several options to
meet their short-term power requirements.
They can procure power from each oth-
er (intra-state) or make power banking
arrangements with other utilities who
have complimentary needs, “depositing”
power with their partners when they
have it in excess and “withdrawing” the
power at a different point in time when
they are in deficit. These two are the
most cost-effective options.
Power can also be bought a day ahead
in power exchanges or based on bilateral
term agreements with private producers
at market prices. Finally, unscheduled
interchange (UI) – by deficit or excess
withdrawal of power – has the same cost
implications as a sale or purchase of
power but at rates that are related to the
instantaneous demand-supply balance
on the grid.
Table 4 shows how BRPL and TPDDL managed their short-term power require-
ments in 2010-11. The dominant form of
procurement was based on bilateral
agreements. These purchases were made
at rates far above the long-term contract
rate of Rs 3.20/unit prevailing in 2010-11.
A similar pattern is evident in the short-
term power purchases of 2009-10.Delhi’s discoms entered into bilateral
contracts mostly mediated by power
trading companies, and sometimes di-
rectly with the generation companies.
Their parent groups – Tata and Reliance
ADAG – have companies engaged in pow-
er trading and contracts were often
made through these companies. Compa-
nies in the “merchant power” market are
power companies that have not tied up apart or the whole of their output in long-
term contracts, or companies in other
industries that have captive power gen-
eration at their disposal.
A prominent supplier of merchant
power for Delhi has been Jindal Power
Limited (JPL), carrying a reputation as
the first company to operate a power
plant entirely on a merchant basis (Shar-
ma 2012). JPL’s high cost power is, ironi-
cally, fuelled by low-cost coal from captive
coal blocks that were allocated to it by
the government (Mohammad 2012).
Delhi has other merchant suppliers like
Lanco Infratech and GMR who have had
access to gas at government-controlled
prices from the Krishna Godavari basin
for their power plants (Narayan and
Mohammad 2012).
In several cases, the discoms show
purchases from power trading companies
and the actual supplier’s name is not
made public. There is also a wide variationin power purchase rates (in TPDDL’s case
for example, prices varied from Rs 5.48/
unit to Rs 7.59/unit in 2010-11).19 As
DERC observed in July 2012,20 contracts
were largely made by the utilities with-
out following any competitive process
and often many months in advance of
the power requirements.
All this points to the complete lack of
transparency in short-term power pro-
curement contracts and raises the suspicion
that the distribution utilities may not be
putting in their best efforts towards
reducing the cost of power procured.
The disposal of surplus power by the
distribution utilities confirms this suspi-
cion. A large fraction of this power is
not even actively sold, but simply not
withdrawn from the grid to realise UI
(under-draw) rates, which are lower
than any category of sale and far below
the average rates at which the power
has been purchased.DERC has been content with gently
chiding the utilities, stating that “there
Table 4: Short-term Power Purchase and Sales in 2010-11TPDDL BRPL
Amount Rate Amount Rate(%) (%)
Purchase Bilateral agreements 59.6 6.20 66.1 5.67
Banking 24.7 4.27 27.3 4.02
Intra-state 7.1 4.44 4.3 3.84
UI 5.9 5.26 1.5 3.33
Exchange 2.8 6.65 0.8 7.58
Sale UI 71.1 2.66 25.7 2.71
Exchange 10.5 3.67 44.1 3.16
Banking 15.1 3.76 9.0 3.50
Bilateral agreement 3.2 3.53 20.6 3.78
Intra-state 0.2 3.91 0.7 3.98
Rates are in Rs/unit; amounts represent the percentage of total purchases
or sales.
Source: TPDDL true-up petition18 and DERC true-up orders.
7/27/2019 Pricing Electricity in Delhi
http://slidepdf.com/reader/full/pricing-electricity-in-delhi 4/4
COMMENTARY
Economic & Political Weekly EPW january 5, 2013 vol xlviIi no 1 23
Permission for Reproduction of Articles Published in EPW
No article published in EPW or part thereof should be reproduced in any form without prior
permission of the author(s).
A soft/hard copy of the author(s)’s approval should be sent to EPW.
In cases where the email address of the author has not been published along with the articles,
EPW can be contacted for help.
was scope for better management of the
process of short-term power purchase
and sale of surplus power so as to signifi-
cantly promote the interests of the con-
sumers”,21 that too in July 2012, while
this process has been working against
the interest of customers from 2009-10.
The poor management of the purchaseand sale of power by the distribution
utilities is not particularly surprising,
considering that the cost of power is a
pass-through cost as far as the utilities
are concerned and in no way affects
their profits.
Concluding Remarks
Several factors – increases in long-term
power rates, non-availability of long-
term power in adequate quantities lead-
ing to purchase of expensive short-term
power and low realisation from sales of
surplus power – have contributed to the
massive increase in the cost of power
available for distribution.
When Delhi’s electricity distribution
was privatised in 2002, the focus of the
regulators was on controlling the costs
of distribution and reducing the techni-
cal and commercial losses in the net-
work. Power was allocated and its cost
set by the government; the cost of power was considered a pass-through as far as
the operations of the distribution utilities
were concerned.
Over the years, significant changes
have occurred in the electricity genera-
tion and trading business with private
producers, traders and exchanges coming
into play with merchant power. Trading
in electricity has become an important
part of the operations of a distribution
utility, especially one servicing a metro-
politan area, and involves significant
discretionary spending and sales. The
regulator has been slow to respond
to this changed environment and its
actions to bring greater transparency
into power trades by the utilities appear
ineffective.22
The larger problem however lies in
the unregulated electricity market. Delhi’s
consumers are paying not only for the
regulated guaranteed profits of the
state-owned generation and transmis-sion companies and private distribution
companies, but also for the unregulated
profiteering of the merchant producers
and other market players.
Notes
1 These numbers represent the increase in theper unit cost of electricity including deficit sur-charge, for domestic consumers in the highestand lowest consumption categories, between
August 2011 and August 2012. The increases forcommercial and industrial users fall in-between.
2 The government provides a subsidy of Re oneper unit for consumers using less than 200units per month.
3 Available on the DERC website: http://www.derc.gov.in/
4 Section 61 (d),Electricity Act, 2003.
5 Distribution loss refers to the power input intothe distribution network that the discom can-not account for, either because it has been lostduring transmission or stolen. It is calculatedas the fraction of the power that cannot bebilled to customers.
6 See note 2.
7 The actual average rate per billed unit would
be slightly higher as it would also need to in-clude any performance incentives for whichthe discom has qualified.
8 BRPL and BYPL continue to have high distri-bution losses, and as a consequence, highertotal costs per billed unit compared to TPDDL.However, in their case too, cost increases weredriven by the cost of purchased power. Of the increases in total costs per billed unitbetween 2008-09 and 2010-11 of Rs 1.85 forBRPL and Rs 2.74 for BYPL, distribution costsper billed unit accounted for Re 0.22 andRe 0.31 respectively.
9 This is set to change from 2012 with TPDDLsigning a long-term PPA with Jhajjar Power, aprivate power generation firm.
10 These figures have been taken from Section
3.1, of Prayas (2012: 6-7).11 Of the three private discoms, BRPL and BYPL
have the same management. In this and subse-quent sections examining the management of power purchases and sales, the data and analy-sis has been confined to TPDDL and BRPL.
12 The cost of electricity available for distributionto TPDDL customers reported in this table mar-ginally dif fers from the figures in Table 2 as thelatter uses DERC trued-up figures while theformer is based on figures reported by TPDDLin its true-up petition.
13 TPPDL “true up” petition for 2010-11 is availa-ble at its website www.ndpl.com. All other“true up” petitions are to be found (if at all) atthe DERC website.
14 Delhi government has “Surrendered” somelong-term power allocated to it (Press Trust of India 2012).
15 See Sections 4.126, 4.127 and 4.128 of the DERCTPDDL true-up order, July 2012, available onthe DERC website.
16 See NDMC true-up petition for 2008-09 andDERC true-up order for NDMC for 2009-10available on the DERC website.
17 The higher transmission costs are due to DelhiTransco, a state utility, hiking its charges. Largertransmission losses are due to a larger proportionof power being sourced from outside the state.
18 See note 11.
19 These figures were obtained from the TPDDLtrue-up petition for 2010-11 submitted to DERC.
20 See Section 3.86 of DERC TPPDL July 2012order and Section 3.103 of DERC BRPL July 2012 order.
21 Ibid.
22 Guidelines for short-term power trades by dis-coms were issued by DERC in January 2011.While the guidelines require that discoms up-date their annual requirements/surplus of electricity at the end of every month on their
website, a visit to the BRPL website (www.bses-delhi.com) on 12 November 2012 showed thatthe “anticipated shortage/surplus” information
was last updated on 30 July 2012. This latestdata is available at: http://www.bsesdelhi.com/pdf/Revised_Anticipated_Shortage_Sur-plus_Power_BRPL_2012-13.pdf
References
Mohammad, Noor (2012): “Jindal Power IgnoresCoal Min Directive on Merchant Sale of Power”, Financial Express, 30 July, http://
www.financialexpress.com/news/jindal-power-ignores-coal-min-directive-on-merchant-sale-of-power/ 981306/2
Narayan, Subhash and Noor Mohammad (2012):“Lanco, GMR Plants Face Cut in Cas Allocation”,
Financial Express, 20 February, accessed on 12November 2012: http://www.financialexpress.com/news/lanco-gmr-plants-face-cut-in-gas-allocation/914245/0
Prayas (2012): “Electricity in Megacities”, Working
Paper, Prayas Energy Group, Pune, accessed on12 November 2012, http://www.prayaspune.org/peg/publications/item/176.html
Press Trust of India (2012): “Reallocate 1,700 MWPlanned to be Surrendered by Delhi to TN”,
Business Standard, 24 October, accessed on12 November 2012, http://www.business-stan-dard.com/generalnews/news/reallocate-1700-mw-planned-to-be-surrendered-by-delhi-to-tn/71962/
Ramachandran, Smriti Kak (2012): “RWAs WantCAG Audit of Discoms’ Accounts”, The Hindu,4 October, accessed on 12 November 2012:http://www.thehindu.com/todays-paper/tp-national/tp-newdelhi/rwas-want-cag-audit-of-discoms-accounts/article3963533.ece
Sharma, Supriya (2012): “Secret of Jindal’s Success:Cheap Coal, Costly Power”, Times of India,9 September, accessed on 12 December 2012:http://articles.timesofindia.indiatimes.com/2012-09-09/india/33713146_1_coal-blocks-power-projects-coal-india