Upload
thomasine-woods
View
214
Download
1
Embed Size (px)
Citation preview
Presented to: NDIA PMSC
By: Keith A. Kratzert
Date: August 17, 2005
Federal AviationAdministrationEVM at the FAA
2 2Federal AviationAdministration
EVM at the FAAAugust 17, 2005
FAA Acquisition Management System (AMS)
http://fast.faa.gov
3 3Federal AviationAdministration
EVM at the FAAAugust 17, 2005
Recent activity
• December 2004 – included ANSI/EIA-748 compliance and IBR in FAA AMS policy
• January 2005 – created EVM Focal Point
• February 2005 – initiated EVM assessment of all OMB Exhibit 300 programs
• March 2005 – developed EVM training
• August 2005 – incorporated additional AMS policy and developed detailed guidance
4 4Federal AviationAdministration
EVM at the FAAAugust 17, 2005
AMS Policy revisions
• Provides for program and contract level EVM
• Assigns responsibilities for EVM, including the FAA EVM Focal Point
• Outlines certification requirements for program and contract level
• Outlines surveillance requirements for program and contract level
5 5Federal AviationAdministration
EVM at the FAAAugust 17, 2005
EVM assessments• Programs fall into one of 5 EVM improvement categories
– Planning
– Programs with >2 years remaining in development/ implementation/ deployment
– Programs with <2 years remaining in development/ implementation/ deployment
– Programs with performing Implementations only
– Full O&M/Steady State or dropped off the list
• Effective sustained EVM requires a complete program management system architecture (estimating through scheduling & EVM analysis up to portfolio management)
• Most program level EVM remedies lie in the project management and integrated project management domains – tie together related and supporting PM disciplines through the formation and work of a Cross-functional EVM Working Group
6 6Federal AviationAdministration
EVM at the FAAAugust 17, 2005
Assessment Themes - Issues• PM Commitment
• Cross Cutting Themes– Multiple Baselines– Government FTE’s & Effort– Program Support LOE– Choosing the Correct Contract Type– Including Sufficient EVM Language in Contracts– Comprehensive Program-Level WBS
• FAA Best Practices– Performance-based Payments– Mature Estimating Techniques– Alignment of Program WBS with Contract CLINS and OMB 300 Useful
Segments– GCAMS & CCAMS– Program Level EVM Tools Application– Risk Adjusted Schedule & Cost Applications
7 7Federal AviationAdministration
EVM at the FAAAugust 17, 2005
EVM assessment results
• Average Rating of all FAA Exhibit 300 programs is “Yellow” using ANSI/EIA-748 as benchmark
– RED – 8 Programs
– YELLOW – 4 Program
– GREEN – 7 Programs
– Planning and Steady state programs were assessed but received no R/Y/G rating
8 8Federal AviationAdministration
EVM at the FAAAugust 17, 2005
Recommendations• Form Working Group including at least:
– Systems Engineering
– Cost Estimating
– Procurement
– Risk Management
– Program Management
• Empower members to represent disciplines and to elevate to executive level any needed decisions
• Invite OMB to attend a meeting as appropriate
• Identify program office people to present “lessons learned” to group
9 9Federal AviationAdministration
EVM at the FAAAugust 17, 2005
Assistance Needed
• Most of our contracts are with the same companies that DoD deals with
• Some of the non-DoD divisions do not appear to have the EVM expertise that the DoD divisions have
• We need your help to ensure a standard EVM capability and expertise within your companies, both DoD and non-DoD applications