Presented By:Bill Winslow
Program Manager, Bernards
Presented to the
Citizens’ Oversight CommitteeNovember 29, 2011
Presented by Bill Winslow
Program Manager, Bernards
The ‘Measure L’Construction Program
Summary
Completed Projects 2002-2011
Chino Campus Fontana Campus Rancho Cucamonga Campus Schedule Financials Questions
An estimated 350,000 square feet of new facilities and a multitude of completed site improvement
projects have made a significant contribution towards improving the physical learning
environment.2
November 29, 2011
COC Presentation
Completed Projects 2002-2011 Renovate/Paint Auto Tech Lab Infrastructure/Campus Theme Environmental Impact Report Renovate Athletics Office Scoreboards Snack Bar Track & Field Timer Stadium Flag Pole Rad Tech Retrofit San Antonio Comm. Hosp./CNA Master Plan (Chino) Vocational Education – Phase I Wargin Hall – Phase I Visitor’s Restroom/ADA Access Science Complex Site work Theater Fire Alarm Bookstore Loading Dock North Parking Lot Irrigation North Parking Lot Landscaping ATL Landscaping Nature Preserve Fence Central Plant Phase IA Central Plant Phase IB
College Drive Softball Field Ralph M. Lewis Center
(Fontana) Wilson/College Dr.ive
Intersection Marie Kane Center for
Student Services/ Administration
Theatre – Phase I North Parking Lot Science Complex Don Berz Excellence Building College Drive Landscaping Maintenance Yard Drainage Agricultural Demonstration
Area Skills Road Extension Fire Lane/Science Site
Lighting New Marquee Physical, Health, and Life
Science Health and Life Science Re-
Roof Main Instructional Building
(Chino) New Elevator Tower Parking Lot 12 Health Sciences Bldg.
(Chino) Community Center Bldg.
(Chino)
Library Lawn Landscaping (Fontana) Physical Science Complex
RoofReplacement
Language Arts/Social ScienceEnergy Project
Parking Lot Upgrades (Fontana)
Chino Health Science Parking Lot
Data and Telecom Cabling Sports Center Visual and Performing Arts
Complex Visual and Performing Arts
Complex Landscape Addition
Math Success Center & Physical Science Renovations
Physical Education Facility Gymnasium Renovation
Aviary Landscape Central Plant Build Out –
Phase 1C – Hot Water Upgrades
Student Services/Administration East Doors
Fire Alarm Upgrades
3
COC Presentation November 29, 2011
(Partial Listing)
District Campuses
4
COC Presentation November 29, 2011
Chino CampusProjects in Planning
Library/Learning Resource Center
5
COC Presentation November 29, 2011
Future Location
Fontana Campus
6
COC Presentation November 29, 2011
Aerial View September 2011
Fontana Campus
7
COC Presentation November 29, 2011
Academic BuildingProjects Completed in
2011
• New 30,400 sq. ft. building includes:
laboratories, lecture rooms, dance/yoga room, art studio, library, and bookstore
Fontana Campus
8
COC Presentation November 29, 2011
Academic BuildingProjects Completed in
2011
Rancho Cucamonga Campus
Aerial View September 2011
9
COC Presentation November 29, 2011
Rancho Cucamonga Campus
Projects Under Construction
10
COC Presentation November 29, 2011
GreenhouseEstimated Completion: December
2011
Installation of a prefabricated greenhouse structure at the
Science Complex
Rancho Cucamonga Campus
Projects Completed in 2011
11
COC Presentation November 29, 2011
Business Education Renovation
Interior and exterior renovation of the existing Business Education building
includes energy and accessibility upgrades
Rancho Cucamonga Campus
Projects Completed in 2011
12
COC Presentation November 29, 2011
Michael Alexander Campus Center
New 16,454 sq. ft. two-story building includes: staff and student dining rooms,
coffee bar, kitchen and server, health services, student government, Extended
Opportunity Programs & Services, and career services
Rancho Cucamonga Campus
Projects Completed in 2011
13
COC Presentation November 29, 2011
Michael Alexander Campus Center
Rancho Cucamonga Campus
Projects in Pre-BidCentral Plant Build Out – Phase 1C – TES Tank
Installation of thermal energy storage tank and six new boilers at Central Plant
Health Science PathwayAddition of a concrete pathway from Health Sciences to the Michael
Alexander Campus Center
North Parking Lot DrainageAddition of drainage systems at Parking Lot 4
14
COC Presentation November 29, 2011
Projects in DesignPhysical Education Athletics – Parking Lot and Flagpole
Parking lot resurfacing and striping with new flagpole
Community Trail LandscapingLandscaping and irrigation
Rancho Cucamonga Campus
Projects in PlanningLanguage/Liberal Arts and Letters
Library Remodel/Expansion
Wargin Hall Remodel
Vocational and Student Service Support Remodel
15
COC Presentation November 29, 2011
Construction Cost Summary
Completed Projects 2009-2011
Project (valued over $1.0 Million)%
Comp.
Original Contract
Approved Change Order
Revised Contract
% of CO
Visual and Performing Arts Complex 100%
$22,145,000
$2,211,142
$24,356,142 9.98%
Community Center/Health Science Buildings (Chino)
100%
$18,488,837 $391,120 $18,879,95
7 2.12%
Sports Center 100%
$8,560,543 $508,104 $9,068,647 5.94%
Academic Building (Fontana) 100%
$7,305,036 $404,232 $7,709,268 5.53%
Michael Alexander Campus Center 100%
$6,686,215 $122,117 $6,808,332 1.83%
Gym Renovation 100%
$4,694,000 $465,507 $5,159,507 9.92%
Business Education Renovation 100%
$3,115,168 $69,565 $3,224,733 2.23%
Physical Science and Math Success Center Renovation
100%
$2,988,289 $175,109 $3,163,398 5.86%
Language Arts/Social Science Energy Project
100%
$2,700,000 $103,828 $2,803,828 3.85%
Parking Lot Upgrades (Fontana) 100%
$1,089,000 $42,618 $1,131,618 3.91%16
COC Presentation November 29, 2011
Summary of FundsCOC Presentation
17
November 29, 2011
Original Measure L Bond ;
$229,830,000
Bond Refinance Proceeds ;
$2,300,000
Accrued Bond Interest ;
$12,291,685
Fund Source AmountPercentage
of Total
Original Measure L Bond
$229,830,000
61.29%
Bond Refinance Proceeds
$2,300,000 0.61%
Accrued Bond Interest
$14,469,233 3.86%
Other Funds $128,412,31
4 34.24%
Total Program Funds $375,011,54
7 100.00%
Fund Source AmountPercentage
of Total
Original Measure L Bond
$229,830,000
93.20%
Bond Refinance Proceeds
$2,300,000 0.93%
Accrued Bond Interest
$14,469,233 5.87%
Total Measure L Bond Funds
$246,599,233
100.00%
Original Measure L Bond ;
$229,830,000
Bond Refinance Proceeds ;
$2,300,000
Accrued Bond Interest ,
$14,469,233
Other Funds , $128,412,314
Original Measure L Bond ;
$229,830,000
Bond Refinance Proceeds ;
$2,300,000
Accrued Bond Interest ,
$14,469,233
Program Funds(Includes Rancho Cucamonga, Fontana, and Chino
Campuses)
Measure L Bond Funds(Includes Rancho Cucamonga, Fontana, and Chino
Campuses)
Remaining FundsCOC Presentation
18
November 29, 2011
Program Funds(Includes Rancho Cucamonga, Fontana, and Chino
Campuses)
Measure L Bond Funds(Includes Rancho Cucamonga, Fontana, and Chino
Campuses)
Total Program Funds $375,011,547 100.00%
Committed (Expensed or
Encumbered)
$291,221,539
77.66%
Allocated to Projects $82,106,581 21.89%
Remaining Balance $1,683,427 0.45%
Total Measure L Bond Funds
$246,599,233
100.00%
Committed
(Expensed or Encumbered)
$217,099,389
88.04%
Allocated to Projects $27,816,417 11.28%
Remaining Balance $1,683,427 0.68%
Committed (Expensed or Encumbered), $291,221,539
Allocated to Projects,
$82,106,581 Remaining Bal-
ance, $1,683,427
Committed (Ex-pensed or Encum-
bered), $217,099,389
Allocated to Projects,
$27,816,417
Remaining Bal-ance, $1,683,427
Questions?