PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS ON THE STATE OF READINESS FOR THE 2010 FIFA WORLD CUP 18 – 19 MAY 2010

PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

  • Upload
    gene

  • View
    41

  • Download
    0

Embed Size (px)

DESCRIPTION

PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS ON THE STATE OF READINESS FOR THE 2010 FIFA WORLD CUP 18 – 19 MAY 2010. OUTLINE OF PRESENTATION INTRODUCTION THE CHALLENGES AND ROLE OF TRANSNET PIPELINES THE CHALLENGES AND ROLE OF TRANSNET FREIGHT RAIL - PowerPoint PPT Presentation

Citation preview

Page 1: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

ON THE STATE OF READINESS FOR THE 2010 FIFA WORLD CUP

18 – 19 MAY 2010

Page 2: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

OUTLINE OF PRESENTATION

INTRODUCTION

THE CHALLENGES AND ROLE OF TRANSNET PIPELINES

THE CHALLENGES AND ROLE OF TRANSNET FREIGHT RAIL

THE COMMITMENT OF TRANSNET NATIONAL PORTS AUTHORITY

CONCLUDING REMARKS

2

Page 3: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

THE CHALLENGES AND ROLE OF TRANSNET PIPELINES

(“TPL”)

3

Page 4: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

THE ROLE OF TRANSNET IN JET FUEL LOGISTICS IN SOUTH AFRICA

Transnet Limited (Transnet”) through its divisions Transnet Freight Rail (“TFR”) and

Transnet Pipelines (“TPL”)) is primarily involved, in respect of the Fifa World Cup 2010 (“WC2010”)

process with the supply of jet fuel to the O R Tambo International Airport (“ORTIA”), - all other airports are supplied by road, except Port Elizabeth Airport and the former Durban International Airport which

are supplied by pipelines owned and operated by members of the oil industry.

The supply of jet fuel to ORTIA is complex and involves many role players:

SA oil industry (as producers or importers of the fuel);

Transnet as transporter of fuel from two different points of supply, as required by the

International Association of Travel Agency (“IATA”), for security of supply reasons;

OR Tambo Airport Fuel Supply (“ORTAFS”), agent of the oil industry, which is currently

managed by Chevron; and

The Airports Company of South Africa (“ACSA”).

The total requirement for ORTIA jet fuel supply are as follows:

The current demand is 4,5 million litres per day (“Ml/day”), thus the supply system is required

to deliver 33 million litres per week (“Ml/w”);

This demand is anticipated to rise to over 10Ml/day on peak days during the FIFA World Cup 2010 (“WC2010”); and

At present and also for the WC2010 period, stock levels of the jet fuel can not go below a 3 days requirement (ACSA stipulation).

4

Page 5: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

2010/11 Demand Forecast

Refined Products 5.1 bl/a

C-Zone

Total RequirementNATREF REFINERY

Sasol, Total

COP

RefinedProducts

4.9 + 0.3 bl/a

15.9 bl/a

DJPRail &Road

SECUNDAREFINERY

Sasol

Diesel in Crude(DIC) 0.3 bl/a

Crude Oil

RefinedProducts 4.4

bl/a

Rail & Road Slippage1.2 bl/a

5.4 bl/a

DURBAN COMPLEX

ENREF Rail & RoadENREF

REFINERYEngen

SAPREFREFINERY

BP, ShellSAPREF

Loading

BERTHS (5,6,7,8,9) IMPORTS

DJP – Durban Johannesburg Pipeline

COP – Crude Oil Pipeline

Pipeline feed

Pipeline feed

FUEL SUPPLY CHAIN LOGISTIC AND MARKET ANALYSIS WITH VOLUME

TARGETS : C-ZONE

5

Page 6: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

ORTIA Complex (ACSA)1

ORTAFS2

NATREF REFINERYSasol, Total

Requirement22 Ml/w

Swing supply to ensure Transnet meets average

requirements – currently10 Ml/month

DURBAN COMPLEX

DJP3

ENREF

Total Requirement33 Ml/w

Rail Loading

Requirement11 Ml/w

Rail Off Loading

ENREF

REFINERYEngen

SAPREF

REFINERYBP, Shell

SAPREF

BERTHS (5,6,7,8,9)1 Airports Company of SA IMPORTS

2 OR Tambo Airport Fuel Supply3 DJP – Durban Johannesburg Pipeline (12")

DIAGRAMMATIC LAYOUT OF COMPLEX SUPPLY CHAIN FOR JET FUEL TO OR

TAMBO INTERNATIONAL AIRPORT

6

Page 7: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

POTENTIAL JET FUEL LOGISTICS CHALLENGES DURING THE FIFA WORLD

CUP 2010

Typical issues that can, in general, cause disruptions in the supply chain include:

Production problems (availability of product) at the 4 refineries involved;

Product quality at points of entry into transport/logistics system (local production and imports);

Loading challenges at points of entry for TFR;

Challenges of transportation by rail and pipelines;

Off-loading challenges at ORTIA; and

Available storage capacity at ORTIA.

Other more specific issues that play a role in disruptions or delays in such a chain are:

ESKOM power interruptions and reliable power supply;

Weather conditions (cannot load Rail Tank Cars (“RTCs”) in the rain in Durban;

Cable theft challenges for TFR and TPL;

Faulty equipment and system failures;

Commercial arrangements (contracts of supply) between SA Oil Industry members; and

Personnel issues throughout the chain (skills, availability, etc).

Absolute requirements for such a complex system are:

Excellent communication and reporting;

Co-ordinated team-effort by all role players; and

Strong leadership through the Department of Energy (“DOE”).

7

Page 8: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

• Present expectations of demand for period of WC2010:

• Total additional volumes of jet-fuel required at ORTIA : Range between 46 and 107 million litres.

• Combined petrol and diesel additional demand in Zone C : 23 Million litres.• Petrol and diesel volumes displaced by jet-fuel in the DJP, which require additional logistics

capacity from the coast, range between 138 and 45 million litres.

• Transnet’s high level actions to meet requirements for jet fuel to ORTIA and additional petrol and diesel capacity from the coast are:

• Ensure 24 Ml/week transported by TPL from Natref to ORTIA by the dedicated pipeline every week during WC2010.

• Ensure 14Ml/week transported by TFR between Durban and ORTIA by rail every week during WC2010.

• Transport 10Ml/week of jet fuel through the DJP from Durban every week during WC2010 (presently 5Ml/month on average).

• The above actions will ensure more than sufficient capacity for jet fuel in the low level case and will leave only 9Ml/w short over the whole period for the high level case (one extra slug of 10Ml in the DJP over the 8 week period).

• For additional capacity needed for petrol and diesel from coast, 2 slugs of diesel or petrol in the crude oil pipeline (1 per month) are proposed, which will be sufficient for the requirements of a low level case (DIC/PIC initiative).

• For the volumes required for the high level case, attempts to be made by TFR, TPL (ex Secunda; Natref) as well as all round stock-piling initiatives (TFR spare RTCs; TPL tankage as well as stock piling with all other roleplayers) to achieve required capacity. As final fall-back only: to increase present road transportation. 8

SUMMARY OF WC2010 CHALLENGES AND WAY FORWARD

Page 9: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

THE CHALLENGES AND ROLE OF TRANSNET FREIGHT

RAIL (“TFR”)

9

Page 10: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

TRANSNET FREIGHT RAIL CAPACITY BREAKDOWN:

DURBAN/ORTIA

Installed capacity = 18 Ml/w

Being tested till end May 2010

Operational capacity = 16 Ml/w

Realistic supply = 14 Ml/w

Simulation model assumes this performance

10

Page 11: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

TRANSNET FREIGHT RAIL JET FUEL FLOWS AT TIME OF WC2010

Possible Supply1.8 Ml/w Matola (Mozambique)

IsandoRequirement

14 Ml/w

BloemfonteinRequirement

0.58 Ml/w

Durban

Loading site Off-loading site

11

Page 12: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

BUT TRANSNET FREIGHT RAIL’S CURRENT SUPPLY CHAIN CAPABILITY HAS

CONSTRAINTS

ORTIA – can offload at best 40 RTCs per day

(DAY shift only)BOTTLENECK

RAIL – can move 2 x blocks of 39 RTCs per day

SAPREF/ENREF – can load 64 per

day (32/32 split)NO CANOPIES

12

Page 13: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

www.transnet.net

ORTIA JET FUEL PERFORMANCE (Week 50-06)

10,707

10,699

10,538

12,110

3,886

8,666

9,455

6,039

9,881

RTC offloaded

Act Lt on Rtc

Average days stock

117 RTCs on hand – ISO

227 RTCs on hand

87 RTCs on hand

High stock level at ORTIA ;changing filters, 28 RTCs on hand at Isando, 32 en route

To decant 32 today (14th). High stock level

48 RTCs on average under load on hand.

Wk 5 264 16356 6.4

Wk 4 170 11177 4.6

Wk 3 160 9743 5.2

Wk 2 114 6800 6.3

Wk 1 242 14951 5.9

Wk 52 160 9881 6.4

Wk 51 173 10707 7.1

Wk 50 176 10699 7

Wk 6 8.214286184

RTC offloaded

Act Lt on Rtc

Average days stock

T1518 arrived 10h50am with 28 RTC in Isando

Shortage of product at loading end caused shortage of loaded RTCs at ORTIA

T1518 Delayed due to cable theft along the Natcor

Customer did not operate on 18 April. As of the morning of 19 April 10, 82 Loaded RTCs on hand with 59 loaded RTCs en-route to Isando

26 April only one shift was working. 29 April 64 RTCs could not be shunted by TFR due to diesel failure

1 May – tanks are full so only 16 RTCs were offloaded

2 May – ORTIA did not work

13

Page 14: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

ACTIONS PLANS

Standby crew slots were increased from 25 February 2010 to ensure crew

delays are eliminated.

Shunts at Loading and Offloading ends for jet fuel have been enhanced to

ensure no shunt delays are experienced.

Jet fuel RTCs are being increased from the current fleet of 313 to as follows: -

Target date: 14 April 2010 = 321 RTCs

Target date: 30 April 2010 = 381 RTCs

Target date: 28 May 2010 = 433 RTCs

CHALLENGES

Security incidents and network unavailability remain a major threat to the service we

provide. This leads to reductions in orders.

Product availability at the loading end.

14

Page 15: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

THE COMMITMENT OF TRANSNET NATIONAL PORTS

AUTHORITY (“TNPA”)

15

Page 16: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

TRANSNET NATIONAL PORTS AUTHORITY MARINE SERVICES TO

VESSELS

• Vessels entering the port require ISPS (“International Ship and Port Security Code”) clearance before

TNPA will allow them vessel to enter a port;

• Vessels must also request a pilot, tug assistance and berthing assistance before entering a port;

• The normal procedure is:

• Vessels submit an arrival notice 72 hours prior to arrival;

• TNPA generates a 72-hour planning list;

• Vessels confirm arrival 24 hours prior to arrival;

• TNPA generates a 24-hour planning list; and

• Vessel movement is confirmed 4 hours prior to service when scheduling commences to

provide marine services to the vessel.

• Vessel service priority is determined based on first come first served requests;

• When multiple service requests are received for the same time, priority is determined as

follows:

• Navy and Passenger vessels;

• Container Vessels and Car Carriers; and

• All other vessels.

16

Page 17: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

TRANSNET NATIONAL PORTS AUTHORITY MARINE SERVICES TO

VESSELS DURING THE FIFA 2010 SOCCER WORLD CUP

• Vessels will be expected to adhere to the same ISPS and Marine Service request procedures which

facilitate proper and controlled planning of movements in/out of the port;

• No special prioritisation procedures will be applied;

• The Harbour Master has the final authority over vessel movements in the port and must be

approached in all events where vessels may require urgent service;

• The Harbour Master will assess the situation at the port and make the final decision – this is the

normal process followed to deal with urgent vessel calls; and

• The 72-hour and 24-hour planning lists provide a mechanism to assess the situation at the port and

inform the Harbour Master’s decision-making.

17

Page 18: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

CONCLUDING REMARKS

18

Page 19: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

• Transnet has made additional investment by increasing its fleet of jet fuel RTCs from the current

266 to 400 by mid-May 2010, to ensure that South Africa hosts a successful event.

• Transnet has committed 32 RTCs to be used as backup storage during the FIFA World Cup 2010.

• One load of 32 RTCs will run once a week from Durban to Hamilton to feed Bloemfontein and Kimberley

airports only during the World Cup.

Jet fuel, including Diesel displacements in the pipeline and block trains from sourcing points will

enjoy absolute freight priority second only to passenger trains on the Durban Johannesburg Corridor.

• Fuel vessel prioritisation at the Port of Durban will be dealt with without compromising other

economic activity in the country during this period.

• Transnet as a key fuel logistics supplier for South Africa remains committed to obligation to safeguard

the security of supply of petroleum products to ensure South Africa’s

successful hosting Fifa World Cup 2010.

19

CONCLUSION

Page 20: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

• General suggestions for the FIFA World Cup 2010 risk mitigation in respect of stock-outs include:

• DOE minimising adjustments (increases or decreases) in fuel prices in South Africa

during the 3 month period (May, June, July).

• Commercial issues:

All available tank-space should be declared by all role players (TPL included) and used for

stocking-up purposes before the FIFA World Cup 2010. National Energy Regulator of

South Africa could play a critical role in this regard.

• Stock management:

Managing stock at ORTIA should be improved with the use of a computer-based

simulation model. Transnet has funded the development of this

computer-based simulation model, which will improve the management of

stock at ORTIA during the FIFA World Cup 2010.

20

CONCLUSION

Page 21: PRESENTATION TO JOINT PARLIAMENTARY PUBLIC HEARINGS

THANK YOU