13
Innovation in Procurement Presentation to Construction Clients’ Group Wednesday 28 May 2014

Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

Innovation in ProcurementPresentation to Construction Clients’ Group

Wednesday 28 May 2014

Page 2: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Intro to Meridian Energy Ltd

•New Zealand’s largest electricity

generator

•Generates electricity from only

renewable resources

•Retails electricity to homes, farms,

businesses and industry throughout NZ

•Recently partly privatized ~51%

ownership held by the Crown

•Own, operate and maintain 7 Hydro

sites (2,368 MW installed capacity), 5

Wind sites in NZ (356 MW installed

capacity) and 1 wind site under

construction (59.8 MW capacity).

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 3: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Procurement Innovation?

“Being the customer of choice”

1. Building long-lasting industry relationships

2. Selecting a fit-for-purpose contracting method

3. Using these relationships and contracts to drive improved performance

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 4: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Customer of Choice

•Why does it matter?

• Critical infrastructure -> Response times

• Limited industry -> Contractor availability

• Specialised skills -> Forward planning of projects

• Relationships -> Better understanding of risks

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 5: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Types of procurement undertaken

•New generation asset builds (Mill Creek ~NZ$169M)

•Asset Management Capital Programme (~NZ$27M per annum)

• Waitaki Refurbishment

• Manapouri Ventilation Upgrade

• Benmore Final Configuration

•Asset Maintenance & BaU (~NZ$22M per annum)

• ~70% is locked up just keeping the lights on

• Facilities Maintenance

• Lakeshore erosion protection

• Revenue Metering certification

• Hydrometric Services

• Dam Safety Review / Data Monitoring

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 6: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Building long-lasting industry relationships

•SRM Framework with key parties

• Relationship managers within each Party to discuss performance, problems,

opportunities & resourcing.

•Constructability workshops

• Opportunity to get Contractors who perform well to provide professional advice

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 7: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Project – Manapouri Powerhouse Ventilation Upgrade

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Cost: ~$10M

Time: 2012 – 2015

Scope:

•Replace coolers

•Replace corroded

ducting

•New control

systems

Procurement:

•2 NEC3 PSC

•2 NEC3 ECC

Page 8: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Selecting a fit-for-purpose contracting method

•NEC3 Contract Suite

• “Relational contracting”

• Process contract

• Best for project outcomes through Early Warnings

•Contract training sessions

• For staff, contractors / consultants etc

•Standardised tendering

• Online tendering ~ reduced timeframes

•Panel / master agreements

• 5 year commitment -> reduced rates

• Easier to engage (mini-tenders)

• Better risk coverage

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 9: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Project – Waitaki Refurbishment

Cost: ~$45M

Time: 2013 – 2016

Scope:

•Refurbish cranes

•Replace CO2

•Refurbish lift

•Replace intake

screens

•Recommission G3

•Repair river bank

erosion

•Replace unit

protection systems

Procurement:

•Approx 40 NEC3

contracts

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 10: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Driving performance

•In-house project management capability

• Better relationships with contractors/suppliers

• Significant savings compared to main contractors / project management body

shops

•Contract management system

• Standardised process for managing contracts

• Easier identification of contractual timeframes

• Portfolio reporting on contractual performance

•Collaborative solutions to problems

• Using relationships and contractual processes to get real best-for-project

outcomes

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

Page 11: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Project – Benmore Final Configuration

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

G1

522

523

521

7

36

T2

11

1

T1

VG1

G2

2

G3

3

12

VG2

8

G4

4

9

462

37

T5

G5

5

G6

6

465

463

T3

Bus A

Bus B

Bus C

16kV

220kV

220kV

220kV

Bus ABus B

n/o

SLD Benmore (pole 1B removed)

From this...

To this...

Page 12: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Or alternatively

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group

From this...

To this...

Cost: ~$22M

Time: 2010 – 2014

Scope:

•Replace 16kV

switchgear

•Replace

transformers

•Electrical

Reconfiguration

Procurement:

•NEC3 PSC

•2 NEC3 SC

•3 MF/2

•NEC3 ECC

Page 13: Presentation to Construction Clients’ Group in... · Building long-lasting industry relationships •SRM Framework with key parties • Relationship managers within each Party to

MERIDIAN ENERGY LIMITED

Questions?

28 May 2014 | Innovation in Procurement & Delivery | Construction Clients’ Group