ABU DHABI GAS INDUSTRIES (GASCO) Habshan 5 Project Execution – Case Study PRESENTATION TITLE LOCATION DATE HABSHAN 5 Project Execution Case Study

PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

  • Upload
    vuhuong

  • View
    237

  • Download
    1

Embed Size (px)

Citation preview

Page 1: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

PRESENTATION TITLE

LOCATION DATE

HABSHAN 5 Project Execution

Case Study

Page 2: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

2

Contents • H5 Block Diagram

• H5 Location

• H5 EPC Contractors

• H5 Schedule

• H5 Achievements Highlights

• Owner’s Team Role

• EPC Phase - Engineering

• EPC Phase - Procurement

• EPC Phase - Construction

• EPC Phase – HSE

• EPC Phase – Workforce Welfare

Page 3: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

3

Habshan 5 Block Diagram

Existing Habshan

complex Offshore Gas

Th. C/D/6/7

ADCO CDS Feed Gas

Compressor 160 MMSCFD

NGL Recovery

2x650MMscfd

Acid Gas

Removal

2x650MMscfd

Sulphur Recovery

Units 4x1300TPD

Acid Gas

Removal

2x425MMscfd

Dehydration

&Recopression

Sales Gas

NGL to Ruwais

Sulphur to Ruwais

Habshan 2

Stabilization Unit

850 MMSCFD

770 MMSCFD

960 MMSCFD

900 MMSCFD

180 MMSCFD

160 MMSCFD

12,000 TPD

(3600TPD C2)

5200 TPD

770 MMSCFD

Page 4: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

4

GASCO Habshan Major Projects

Page 5: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

Al Faraá

HDEC

TCM / KN

JGC/CCC

JGC/DESCON

HDEC

HDEC

Page 6: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

H5 EPC Contractors Section Contractor Amount US$

Process Plant

NGL Trains

MP & HP Compression

Stabilization

Flare

JGC

JV Contract

4.7 Billion Process Plant

AGRU’s

SRU’s

Tecnimont

Utilities & Offsite Hyundai Engineering &

Construction 1.7 Billion

Non Process Building Al Faraa 0.1 Billion

6.5 Billion

Page 7: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

7

Page 8: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

8

Schedule

Package Award Date Duration Due Date

Process Package 29/7/2009 PAC

Phase 1 46 Months 28/5/2013

Phase 2 50 Months 28/9/2013

U&O Package 29/7/2009 PAC 46 Months 28/5/2013

Page 9: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

9

H5 Achievements Highlights

143 Million Manhours without LTI

10 weeks from Gas In to Phase 1 Commissioned

On Schedule

Cost (Process Package + U&O)

Positive variations ≈ US $ 12 Millions

Negative variations ≈ US$ 77 Millions

Final amount is US$ ≈ 65 Million less than awarded value

Page 10: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

11

Owner’s Team Role

• Location of EPC Contractors accommodation

• EPC Contractors Temporary Facilities

• Traffic Control

• Ring Road

Logistics

• CICPA Check Point

• Gates Access Control

Security

Page 11: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

12

Owner’s Team Role

Interface Management

One Team : Owner, PMC, TPI, EPC Contractors & Sub Contractors

End User : Involvement during Project Phase

FEED Quality

Heavy Equipment Transportation

Early “No Objection Certificate” - NOC

Visible Leadership in all Project Aspects

Senior Management Role

Page 12: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

13

EPC Phase - Engineering

Underground work to be treated as “Early Works” including

design, procurement, 3D Modelling and construction

Early design of structural steel

Develop as early as possible the necessary data to support

procurement

Page 13: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

14

EPC Phase - Construction Arrange equipment & material logistics

Complete underground work before starting above ground work (at

least reduce overlap)

Complete Sub stations and IES’s (Instrument Equipment Shelters)

before planned arrival of switchgears and Control panels

Assign “ Champions” for each specific areas

Produce “ Constructability Booklets” based on (a) availability of

resources : personnel and machinery, (b) material and © access.

Complete Non Process Buildings in time to support End User Team

during pre commissioning and commissioning

Establish Quality and Preservation / Cleanliness team

Page 14: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

15

EPC Phase - HSE

Adequate procedures in place

Extensive training

Firm implementation

Visible Management involvement and support

Life Saving Rules

Road safety : regulations, training and implementation

Site Construction Supervisors to be HSE qualified

Page 15: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

16

EPC Phase – Workforce Welfare

Establish “Welfare committee’s”

Ensure that Contractors / Subcontractors have the minimum

required facilities

Conduct social & sport activities to enhance the one family

spirit

Plan traffic movement

Ensure adequate security and control is implemented

Page 16: PRESENTATION TITLE - UniverSUL Consultinguniversulphur.com/mespon/2015_presentations/session_c/1. Habshan 5...PRESENTATION TITLE LOCATION DATE ... JGC/CCC JGC/DESCON HDEC HDEC . ABU

ABU DHABI GAS INDUSTRIES (GASCO)

Habshan 5 Project Execution – Case Study

19

Thank you