19
© 2017 USACE & City of Arvada, all rights reserved. Study developed by the U.S. Army Corps of Engineers, the Urban Drainage and Flood Control District, the City of Arvada and other participating agencies PRESENTATION STARTS AT 6:30 P.M. SECTION 205 FLOOD RISK MANAGEMENT FEASIBILITY STUDY FOR THE RALSTON CREEK WATERSHED

PRESENTATION STARTS AT 6:30 P.M

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRESENTATION STARTS AT 6:30 P.M

© 2017 USACE & City of Arvada, all rights reserved.

Study developed by the U.S. Army Corps of Engineers, the Urban Drainage and Flood Control District, the City of Arvada and other participating agencies

PRESENTATION STARTS AT 6:30 P.M.

SECTION 205 FLOOD RISK MANAGEMENT FEASIBILITY STUDY FOR THE RALSTON CREEK WATERSHED

Page 2: PRESENTATION STARTS AT 6:30 P.M

SECTION 205 FLOOD RISK MANAGEMENT FEASIBILITY STUDY FOR THE RALSTON CREEK WATERSHED

WELCOMEPreliminary Alternatives Informational Meeting

This study is authorized under Section 205 of the Flood Control Act of 1948, as amended, which allows the U.S. Army Corps of Engineers to assess the feasibility of and construct projects that reduce flooding-related damages

About the Flood Risk

Management Feasibility Study

About f looding problems and Preliminary Alternatives

to manage flood risks along Ralston CreekLearn More Provide Your Input

1

Page 3: PRESENTATION STARTS AT 6:30 P.M

History of flooding in Arvada

Infrastructure and safety risks

Study OverviewWHY ARE WE CONDUCTING THIS STUDY?

Examine the feasibility and environmental effects of implementing flood risk management

solutions along Ralston Creek in the City of Arvada

WHAT WILL THIS STUDY DO?

WHAT IS SECTION 205?

Authorizes the Corps to construct projects to reduce flooding-related damages

STUDY DURATION:

Fall 2016 – Summer 2018

The City of Arvada submitted a letter of

request to USACE for a study in May 2009

STUDY SPONSORS:

2

Page 4: PRESENTATION STARTS AT 6:30 P.M

Study Process & Schedule

FALL

2016

WINTER

2016

SPRING

2017

SUMMER

2017

FALL

2017

WINTER

2017

SPRING

2018

SUMMER

2018

FALL

2018

WINTER

2018

Compare Plans

Draft Report

Select Recommended Plan

Finalize Feasibility Report and Environmental Assessment

Public Comment on Draft Report

Public Comment on Alternative Plans

P Public Comment on Existing Conditions

P Identify Existing and Future Conditions

WE ARE

HERE

* Based on anticipated project schedule, dates are subject to change.

This study began in fall 2016 and is expected to last through summer 2018

3

P Formulate Alternative Plans

Page 5: PRESENTATION STARTS AT 6:30 P.M

STUDY LOCATION

The study area includes 3.5 miles of Ralston Creek from Beech Street downstream to the confluence with Van Bibber Creek just west of Garrison Street.

STUDY DETAILSThis study will seek to develop feasible flood risk management solutions by evaluating existing and future flood risk, economic costs and benefits, as well as environmental impacts.

Study Location & Details

4

Page 6: PRESENTATION STARTS AT 6:30 P.M

Flooding in Ralston Creek

1985 1990 1995 2000 2005 2010 2015

July 22, 1991*

* Listed as significant per Ralston Creek Flood Warning Plan (2009)

The following are documented flood events on Ralston Creek:

July 20, 1986

May 18, 1995 & June 4, 1995*

August 4, 1997*

August 4, 1999*

September 11-13, 2013

July 10, 2009*

June 8, 2004* & June 27, 2004*

5

Page 7: PRESENTATION STARTS AT 6:30 P.M

Damage to two water supply reservoirs

Turbid water caused problems at water treatment plants

Roadway overtopping

Damages to residential properties

Breaching of canal embankments

September 2013 Flood

SIGNIFICANT DAMAGES INCLUDED:

A

B

A: Ward Road at Ralston Creek

B: Ralston Creek near Memorial Park

6

Page 8: PRESENTATION STARTS AT 6:30 P.M

More than 70% of the expected annual damages occur between the Arvada Tennis Center and Brooks Drive

Flood Damage Risks to Property

Flood Damage

Category

Within 500-Year Floodplain Expected Annual

DamagesStructure Count Value

Residential (Homes) 688 $122,960,000 $2,858,400

Commercial (Businesses) 3 $590,000 $1,720,00

Other Associated Damage

Categories (e.g. vehicles,

emergency response, etc.)

N/A N/A $596,570,00

Totals 691 $123,550,000 $3,456.70

7

Page 9: PRESENTATION STARTS AT 6:30 P.M

IDENTIFY ALTERNATIVES THAT REDUCE FLOOD RISK

A potential project could lead to updated, FEMA-approved

floodplain maps and possibly reduce flood insurance requirements

in the 100-year floodplain.

Study Objectives

IDENTIFY ALTERNATIVES TO IMPROVE PUBLIC SAFETY

8

Page 10: PRESENTATION STARTS AT 6:30 P.M

Determined existing and future flood risk

Held a public scoping meeting on May 9, 2017 to gather your input

Held an Alternative Formulation workshop with the City on May 10 and 11, 2017

Identified three Structural Alternatives and one Nonstructural Alternative to reduce the

flood risk

Process & Measures

THE FOLLOWING HAS BEEN CONDUCTED TO DEVELOP THE STUDY:

9

Page 11: PRESENTATION STARTS AT 6:30 P.M

Reduces average annual damages 31% (37% from Arvada Tennis Center to Brooks Drive)

Alternative 1INITIAL PROJECT COSTS $16.3 MILLION

42 acre (520-acre-ft of storage) detention basin

Removal of grade control structure

Limited channel modifications for detention basin inlet and outlet

Vegetation thinning from Simms St. to Brooks Drive

No real estate acquisitions are anticipated

10

Page 12: PRESENTATION STARTS AT 6:30 P.M

Reduces average annual damages 53% (70% from Arvada Tennis Center to Brooks Drive)

Alternative 2INITIAL PROJECT COSTS $14 MILLION

Bridge removals W. 68th Ave. / W. 61st Ave.

New bridges at Ward Road and Rensselaer Drive

Modified channel walls from Arvada Tennis Center to Brooks Drive

Modified channel includes vegetation removal

Vegetation thinning from Beech St. to Arvada Tennis Center

Potential for select real estate acquisitions as yet to be determined

A B

A: Existing channel condition

B: After implementation channel condition11

Page 13: PRESENTATION STARTS AT 6:30 P.M

Reduces average annual damages 49% (65% from Arvada Tennis Center to Brooks Drive)

Alternative 3INITIAL PROJECT COSTS $17.4 MILLION

12-foot-tall by 12-foot-wide box culvert under Johnson Way

Limited channel modifications for box culvert inlet and outlet

Vegetation thinning from Beech St. to Brooks Drive

Potential for select real estate acquisitions as yet to be determined

High flow box culvert typical cross section

12

Page 14: PRESENTATION STARTS AT 6:30 P.M

Understand importance of existing conditions

Portions of creek are narrow and flooding occurs at a 10-year event

Balance between the following:

Reducing flood risk

Minimizing impacts to private property

Minimizing impacts to trees

Vegetation Thinning and RemovalWHY CONSIDER IT?

13

WHAT ARE THE OPTIONS?

Larger channel could be constructed

Higher cost and real estate acquisitions

May not be economically justifiable

Page 15: PRESENTATION STARTS AT 6:30 P.M

Nonstructural AlternativesWET FLOODPROOFING DRY FLOODPROOFING HOME ELEVATION BUY-OUTS OR RELOCATION

14

Structures impacted by flooding were reviewed to determine potential for nonstructural measures

Some structures are economically justified for nonstructural measures

No substantial grouping of structures

Without a substantial grouping, a stand-alone nonstructural alternative is not justified

Nonstructural measures will be considered in combination with the structural alternatives considered

Page 16: PRESENTATION STARTS AT 6:30 P.M

Improving channel and overbank capacity of Ralston Creek

Creating riparian and wetland habitat areas

Improving recreation and transportation networks through recreational trails

upstream and downstream of the study area

Opportunities

ALTERNATIVE DEVELOPMENT OPPORTUNITIES:

Increasing local awareness

Gathering input from citizens, local, state and federal entities to aid in the

identification and implementation of flood risk reduction solutions

PUBLIC INVOLVEMENT OPPORTUNITIES:

15

Page 17: PRESENTATION STARTS AT 6:30 P.M

We want your input throughout the study process. You can provide feedback by filling

out a questionnaire today or by going online, printing it out, and mailing it back.

Public Involvement

Feedback on Preliminary Alternatives

Flooding problems, impacts, or damages in the study area

Potential outcomes of the study you’d like to see avoided

Your suggested improvements to recreational trails and networks in the study area

PROVIDE YOUR FEEDBACK ON THE FOLLOWING:

16

Page 18: PRESENTATION STARTS AT 6:30 P.M

Go to the project webpage to learn more at:

nwo.usace.army.mil/Missions/Civil-Works/Planning/Planning-Projects/ArvadaCO

How Can You Help?

LEARN MORE ONLINE

Rebecca Podkowka, ATTN: CENWO-PM-AC, 1616 Capitol Avenue, Omaha, NE 68102

MAIL US ANY COMMENTS OR QUESTIONS

[email protected]

EMAIL US ANY COMMENTS OR QUESTIONS

17

Page 19: PRESENTATION STARTS AT 6:30 P.M

© 2017 USACE & City of Arvada, all rights reserved.

THANK YOU FOR ATTENDING