85
© 2013 Navigant Consulting, Inc. Evolution of the Electric Industry Structure in the U.S. and Resulting Issues Prepared for: Electric Markets Research Foundation Navigant Consulting, Inc. 1200 19 th Street NW Suite 700 Washington, DC 20036 202.973.2400 www.navigant.com October 8, 2013

Prepared for: Electric Markets Research Foundationemrf.net/uploads/3/4/4/6/34469793/evolution_of_the...Prepared for: Electric Markets Research Foundation Navigant Consulting, Inc

Embed Size (px)

Citation preview

 

© 2013 Navigant Consulting, Inc.

 

 

 

 

 

 

 

 

 

Evolution of the Electric Industry 

Structure in the U.S. and  

Resulting Issues  

 

Prepared for: 

Electric Markets Research Foundation  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Navigant Consulting, Inc. 

1200 19th Street NW 

Suite 700 

Washington, DC 20036 

 

202.973.2400 

www.navigant.com 

 

 

October 8, 2013 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc.

Copyright This report is protected by copyright. Any copying, reproduction, performance or publication in 

any form without the express written consent of Navigant Consulting, Inc. is prohibited. 

 No Warranties or Representations, Limitation of Liability This report (The “Report”) was prepared for Electric Markets Research Foundation on terms 

specifically limiting the liability of Navigant Consulting, Inc. (“Navigant”).  Navigant’s conclusions 

are the results of the exercise of its reasonable professional judgment based upon information 

believed to be reliable.  This Report is provided for informational purposes only.  Navigant accepts 

no duty of care or liability of any kind whatsoever to the reader or any other third party, and all 

parties waive and release Navigant for all claims, liabilities and damages, if any, suffered as a result 

of decisions made, or not made, or actions taken, or not taken, based on this report.  Use of this 

Report by reader for whatever purpose should not, and does not, absolve reader from using due 

diligence in verifying the Report’s contents. 

 

Electric Markets Research Foundation 

Navigant conducted this study for the Electric Markets Research Foundation (EMRF).  EMRF was 

established in 2012 as a mechanism to fund credible expert research on the experience in the United 

States with alternative electric utility market structures – those broadly characterized as the 

traditional regulated model where utilities have an obligation to serve all customers in a defined 

service area and in return receive the opportunity to earn a fair return on investments, and the 

centralized market model where generation is bid in to a central market to set prices and customers 

generally have a choice of electric supplier.   

 

During the first few years of restructured markets, numerous studies were done looking at how 

these two types of electric markets were operating and the results were mixed.  But since those early 

studies, limited research has been done regarding how centralized markets and traditionally 

regulated utilities have fared.  The Electric Markets Research Foundation has been formed to fund 

studies by academics and other experts on electric market issues of critical importance. 

 

 

 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page i October 8, 2013

Table of Contents 

1. Executive Summary ................................................................................................................ i 

History and Development of Traditional Regulation and Competitive Markets .................................. i Today’s Two Broad Models ......................................................................................................................... iii System Reliability ......................................................................................................................................... iv Environmental Issues .................................................................................................................................... v Relative Allocation of Risks over Time ...................................................................................................... vi Responsibilities for Planning and the Types of Planning Performed .................................................... vi Innovation and the Levels of Research and Development Pursued ..................................................... vii State and Federal Government ................................................................................................................. viii 

2. Introduction ............................................................................................................................ 1 

3. History and Development of Traditional Regulation and Competitive Markets ..... 2 

3.1 Development of Traditionally Regulated Markets .............................................................................. 3 3.2 Period of Growth and Declining Costs, 1945‐1970 .............................................................................. 6 3.3 Slowed Growth and Inflation, Seeds of Competition, 1970‐1990 ...................................................... 7 3.4 The Advent of Centralized Markets, 1990‐1999 ................................................................................... 9 3.5 Traditional Regulation and Centralized Markets Today .................................................................. 13 

4. Today’s Two Broad Models ............................................................................................... 20 

4.1 Current Status of Centralized Wholesale Generating Markets ....................................................... 20 4.1.1 Todays’ Centralized Wholesale Generating Markets .......................................................... 20 4.1.2 Energy Markets ........................................................................................................................ 21 

4.2 Bilateral Wholesale Generation ............................................................................................................. 23 4.3 Today’s Retail Choice Status ................................................................................................................ 23 4.4 Cost‐Based Rates and Traditional Utility Regulation ....................................................................... 24 4.5 The Retail Choice Model ....................................................................................................................... 24 4.6 Differences Between the Traditional and Retail Choice Models ..................................................... 26 

4.6.1 Retail Choice Markets .............................................................................................................. 26 4.6.2 Pricing for Generation Services .............................................................................................. 27 

5. System Reliability ................................................................................................................ 28 

5.1 Development of the Mandatory Reliability Standards ..................................................................... 28 5.2 Transmission Reliability ....................................................................................................................... 31 

5.2.1 The NERC Standards and Who Must Comply .................................................................... 31 5.2.2 Role of the Registered Entities and States ............................................................................. 33 5.2.3 Compliance Monitoring and Enforcement ........................................................................... 34 

5.3 Resource Adequacy ............................................................................................................................... 34 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page ii October 8, 2013

6. Environmental Issues .......................................................................................................... 39 

6.1 Impacts of Environmental Regulation ................................................................................................ 39 6.2 Differing Impacts for Different Structures ......................................................................................... 39 

6.2.1 Greenhouse Gas Initiatives ..................................................................................................... 40 6.2.2 Renewable Portfolio and Energy Efficiency Resource Standards ..................................... 42 6.2.3 Mercury and Air Toxics Standards ........................................................................................ 44 6.2.4 National Ambient Air Quality Standards ............................................................................. 44 6.2.5 Clean Air Interstate Rule/Cross‐State Air Pollution Rule ................................................... 44 6.2.6 Regional Haze ........................................................................................................................... 44 6.2.7 Cooling Water Intake Structures ............................................................................................ 45 6.2.8 Coal Combustion Residuals .................................................................................................... 45 

7. Relative Allocation of Risks over Time ........................................................................... 46 

7.1 Traditionally Regulated Model ............................................................................................................ 46 7.2 Centralized Market Model .................................................................................................................... 47 

8. Responsibilities for Planning and the Types of Planning Performed ...................... 51 

8.1 The Transmission Planning Framework ............................................................................................. 51 8.1.1 Regional Planning and the Inclusion of Non‐Incumbent Transmission Developers ..... 51 8.1.2 Interregional Planning Coordination .................................................................................... 53 8.1.3 Cost Allocation ......................................................................................................................... 54 8.1.4 Planning for Public Policy Requirements ............................................................................. 56 

8.2 Transmission Siting and Transmission Grid Expansion .................................................................. 59 8.3 Adequacy Planning and Integrated Resource Planning ................................................................... 60 

8.3.1 Integrated Resource Planning and Procurement Plans ...................................................... 60 

9. Innovation and the Levels of Research and Development Pursued .......................... 63 

9.1 Declining Costs and Increasing Flexibility of Generation Technologies ........................................ 63 9.2 Emergence of Demand Side Alternatives ........................................................................................... 65 9.3 Smart Grid ............................................................................................................................................... 66 9.4 Research and Development Investment ............................................................................................. 67 

10. State and Federal Government ........................................................................................ 70 

 

   

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page iii October 8, 2013

List of Figures and Tables 

Figures: 

Figure 1. Historical Timeline 1920‐1945 ................................................................................................................ 3 Figure 2. Historical Timeline 1945‐1970 ................................................................................................................ 6 Figure 3. Historical Timeline 1970‐1990 ................................................................................................................ 7 Figure 4. Historical Timeline 1990‐1999 ................................................................................................................ 9 Figure 5. Historical Timeline 1999‐Present ......................................................................................................... 13 Figure 6. Regional Transmission Organizations ................................................................................................ 18 Figure 7. Status of Electricity Restructuring (Retail Choice) by State .............................................................. 19 Figure 8. NERC Regions ........................................................................................................................................ 31 Figure 9. State RPS Policies ................................................................................................................................... 42 Figure 10. State EERS Policies ............................................................................................................................... 43 Figure 11. Forecasted Energy Sales from Alternative Suppliers ...................................................................... 49 Figure 12. States with Integrated Resource Planning (or similar planning process) ..................................... 62  

Tables: 

Table 1. Wholesale and Retail Market Structure by State ................................................................................. 20 Table 2. Centralized Markets and their Attributes ............................................................................................. 22 Table 3. Examples of Market‐Based Resource Adequacy Mechanisms .......................................................... 37 Table 4. Examples of Cost Allocation Approaches Used by Planning Region ............................................... 55 Table 5. Estimated National Average Levelized Cost of New Generation Resources in 2018 ..................... 64 Table 6. EPRI Planned R&D Funding for 2013 and 2014 .................................................................................. 69 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page i October 8, 2013

1.  Executive Summary 

This paper explores the key policy questions surrounding two broad regulatory/market structures that 

currently exist in the United States (U.S.) in varying degrees: traditional utility regulation without 

centralized markets on the one hand, and centralized electricity markets, often involving restructured 

regulation, on the other.1  The paper is intended as an educational piece for non‐industry experts on how 

and why electric utility regulation has evolved and one model has developed in some areas of the 

country while not in others.  This paper does not provide a critique of the market structures nor a 

quantitative comparison between the two models.  This paper may also serve as a foundation for 

identifying the issues that characterize the key differences between the approaches and help guide 

decisions on future research projects for the Electric Markets Research Foundation. 

History and Development of Traditional Regulation and Competitive Markets  

The evolution of the U.S. electric industry is a history of adaptation to changes in the operating and 

regulatory environment.  The first chapter traces the history of the two regulatory/market structures.  It 

begins from the early structure of the electric utility industry as it developed around the concept of a 

central source of power with vertically integrated utilities and regulation of these entities by municipal 

and state governmental entities.   

 

During the early twentieth century, electric systems grew rapidly.  Under the Rural Electrification Act 

service was extended to unserved, or underserved, rural areas, which also gave rise to rural electric 

cooperatives in many areas of the U.S.  Disenchantment with privately owned power spurred the 

development of government‐owned utilities, particularly hydroelectric power facilities.  During the 

presidency of Franklin D. Roosevelt (1933 to 1945), a number of these facilities were built, ushering in the 

beginning of publicly owned power. 

 

In 1920, the Federal Water Power Act was passed to coordinate the development of these hydroelectric 

projects. This act created the Federal Power Commission (FPC), now the Federal Energy Regulatory 

Commission (FERC).  In 1935 the law was renamed the Federal Power Act and the FPC’s regulatory 

jurisdiction was expanded to include all interstate electricity transmission and sales of power for resale 

                                                           1 Within the two different general models there are further distinctions.  The traditionally regulated model is often 

characterized at the wholesale level by bilateral resource transactions while at the retail level the traditional 

vertically integrated utility provides / purchases all functions required to provide service to the end users.  The 

centralized market model generally involves the existence of a Regional Transmission Organization (RTO) or 

Independent System Operator (ISO) that administer centralized, bid‐based markets at the wholesale level with some 

degree of retail competition where the customer has the right to procure power competitively with transmission and 

distribution service provided by a regulated utility.  Transmission and distribution under both models remains 

governed by a cost of service regulatory approach.  Further, the reader should be aware that there may be instances 

where regions or entities generally characterized as functioning under a certain broad model may not exhibit all 

features of that model.  For example, there are regions that have centralized wholesale energy markets that may not 

have implemented retail choice in all states within that region.  Similarly, there are regions that remain traditionally 

regulated but have elements of centralized markets and retail choice. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page ii October 8, 2013

and formed the basis for federal jurisdiction over the electric and natural gas industries, and the 

responsibilities of the FERC.  In that same year, after several large holding company systems collapsed, 

the Public Utility Holding Company Act of 1935 (PUHCA) was passed, giving the Securities and 

Exchange Commission responsibility for regulating utility holding companies. Under Title II, PUHCA 

charged the FPC with regulating utilities involved in interstate wholesale marketing or transmission of 

electric power.  Regulatory administration of the rate case established base rates based on the actual 

normal costs of providing service determined by the utility’s revenue requirement. 

 

A number of damaging events occurred in the 1960s and 1970s that interrupted the growth that had 

occurred in the prior several decades.  First, the Northeast Blackout of 1965 raised concerns about 

reliability; then, the passage of the Clean Air Act of 1970 and its amendments in 1977 increased utility 

costs to reduce polluting emissions.  And, most significantly, the Oil Embargo of 1973‐1974 resulted in 

increases in fossil‐fuel prices.  In 1978, Congress pursued legislation to address these pressures by 

reducing U.S. dependence on foreign oil and developing renewable and alternative energy sources.  The 

Public Utility Regulatory Policies Act of 1978 ushered in a greater reliance on market forces to set 

wholesale energy prices, while requiring utilities to buy power at their “avoided cost” from unaffiliated 

alternative energy resources meeting a number of qualifications.  Throughout the late 1980s, utility 

interest in wholesale transactions grew, prompted by a number of factors.  Some utilities found 

themselves with excess generation because expected demand growth did not meet projected levels.  In 

addition, in the wake of aggressive utility construction programs, regulators determined that some costs 

were imprudent and refused to allow the utilities to recover them in rates.  Utilities sought to sell 

electricity in wholesale transactions at market‐based rates, and FERC would grant these requests upon a 

showing that the utility could not exercise market power to set prices. 

 

Two significant policy decisions occurred in the 1990s that provided a foundation for energy market 

development.  The first was the passage of the federal Energy Policy Act of 1992 (EPACT), which created 

a number of incentives for market development.  The second was the cornerstone in the creation of 

competitive wholesale power markets, FERC’s Order No. 888.  Order No. 888 strove to eliminate anti‐

competitive practices and undue discrimination in transmission services through a universally applied 

open‐access transmission tariff.  At the same time these changes were occurring in the wholesale 

electricity markets, a growing number of states were also pursuing a reliance on competitive markets for 

the retail supply of electric power.  This typically required the incumbent utility to divest some or all of 

its generation and become a wires‐only distribution utility.   

 

By 2000, FERC was calling for the voluntary formation of regional transmission organizations (RTOs) 

through its Order No. 2000.  The basis of Order No. 2000 was FERC’s belief that RTOs would facilitate 

the continued development of competitive wholesale power markets and would lead to improvements 

in reliability and management of the transmission system, eliminating any remaining discriminatory 

practices.  However, concurrent with FERC’s efforts under Order No. 2000, challenges were arising in 

the California markets.  In 2001, California suffered from flaws in its power market structure leading to 

the insolvency of one of the largest utilities in the state.  Following the California energy market crisis 

and a blackout that affected a large portion of the northeastern U.S. and Canada in 2003, Congress 

enacted the Energy Policy Act of 2005 (EPAct 2005) on August 8, 2005.  This legislation provided FERC 

greater authority to oversee wholesale electricity markets.  FERC subsequently issued Order No. 890 in 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page iii October 8, 2013

early 2007 to correct flaws in its pro forma Open Access Transmission Tariff (OATT) that had been 

uncovered during the ten years since Order No. 888 was issued. 

 

During the autumn of 2008, large disruptions in the financial markets also uncovered vulnerabilities in 

the electricity markets.  In response, FERC issued Order No. 741 proposing extensive revisions to its 

policy on RTO/Independent System Operator (ISO) credit practices.  Congress took additional actions in 

response to the 2008 financial crisis, including enacting the Dodd‐Frank Act, which had the potential to 

affect energy trading companies and wholesale energy markets. 

Today’s Two Broad Models 

At the wholesale level, bilateral transactions prevail in the Southeast, most of the Southwest, parts of the 

Midwest and the West, excluding California.  Under this regime, utilities engage in wholesale physical 

power transactions through bilateral arrangements ranging from standardized contract packages, to 

customized, complex contracts known as structured transactions.  This is characterized as a component 

of the traditionally regulated model.  A centralized market model is the norm in the Northeast, Mid‐

Atlantic, much of the Midwest, the Electric Reliability Council of Texas (ERCOT), and California.  In 

these markets participants bid/offer resources into a centralized market and are paid a uniform clearing 

price. 

 

Similarly, two models are currently employed in the United States to deliver electric power to retail 

consumers.  The traditional model is the Vertically Integrated Utility, where various services are 

“bundled,” meaning that all energy and energy delivery (transmission and distribution) services, as well 

as ancillary and retail services, are provided by one entity.2  Customers do not have the option of 

selecting another provider for any of these services, and the utility’s charges are set entirely by the 

regulatory authority or governing body in the case of public power.  In contrast, under the retail choice 

model, customer choice has been partially or fully implemented.  In this model, customers may often 

select their energy provider, and the utility will deliver the power.  Non‐utility energy providers can set 

their own pricing for power, but the utility’s charges for delivery and related services are set by the 

regulatory authority.  Traditional “bundled” pricing may also be available from the utility, for some or 

all types of customers.3 

 

In the United States, traditional utility pricing (or ratemaking) is cost‐based, meaning that the utility is 

allowed to charge prices that will recover prudent operating costs and provide an opportunity to earn a 

reasonable rate of return on the property devoted to the business.  Among the historical criticisms of 

cost‐based ratemaking are that it creates an incentive to over‐invest in capital‐intensive projects and fails 

to provide utilities proper incentives to operate efficiently. 

 

 

                                                           2 Although in the case of Public Power, generation and transmission may be provided by joint authorities and 

bundled by the local distribution utility. 3 It is worth noting that the “Retail Choice” model encompasses a spectrum of features that may vary from state to 

state.  The key features, such as the existence of retail choice for at least some customers and the availability of 

organized wholesale energy markets are the same, although there may be differences in the manner and degree to 

which these features are implemented.   

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page iv October 8, 2013

The customer choice aspect of the Retail Choice model was introduced in the United States in the 1990s 

in response to high regulated prices in some regions relative to the cost of wholesale markets.  Many 

consumer groups found retail competition attractive because the prices in emerging wholesale markets 

were significantly below the regulated retail prices charged by utilities. 

 

In contrast to the traditional regulated model, the customer choice feature of the retail choice model 

limits the operation of the regulated utility to the transmission and distribution functions, where 

traditional cost‐based pricing is implemented and approved by regulators.  Generation services are 

provided either by competitive service providers or through a default “provider of last resort.”  Retail 

choice also has its criticisms; among them are that residential participation in some retail markets has 

been slow to materialize, in part because retail suppliers have not pursued residential customers as 

aggressively as commercial customers due to their relatively small size.  Other factors may include a lack 

of incentives (i.e., lower prices) or information. 

System Reliability 

Reliability standards or criteria used for planning and operations are an integral part of the electric 

power industry and have been since the very first systems were developed in the late nineteenth 

century.  There are two principal components to bulk power system (BPS) reliability—resource adequacy 

and transmission security.4  The area of transmission security is governed by FERC, the North American 

Electric Reliability Corporation (NERC), and the Regional Entities (REs).  The states still retain a role in 

resource adequacy and in regulating the reliability of local distribution systems. 

 

Over the years, a series of blackouts (the 1965 Northeast Blackout, the blackout on the East Coast in July 

1977, the West Coast blackouts in July and August of 1996, and the blackout on August 14, 2003 affecting 

the northeastern U.S. and Canada) led to the creation of NERC and its REs.  Prior to 2005, compliance 

with reliability standards was voluntary.  The enactment of EPAct 2005 eliminated the voluntary nature 

of the NERC reliability standards.  FERC was charged with the ultimate oversight of electric reliability of 

the Bulk Power System (BPS).  NERC, as the independent Electric Reliability Organization (ERO), along 

with its REs develop mandatory reliability standards subject to FERC approval, monitor industry 

participants’ compliance with these standards, and can levy penalties for noncompliance up to one 

million dollars per day per violation for the most serious violations.  

Currently, there are 102 standards with more than 1,300 requirements applicable and mandatory in the 

U.S.  Within the United States, other than Alaska and Hawaii, all users, owners, and operators of the BPS 

must comply with the reliability standards developed by the ERO and regional reliability standards 

developed by the REs.  This responsibility extends FERC jurisdiction not only to the government‐owned 

and other so‐called non‐jurisdictional utilities, but also to utilities in Texas as well as to a wide range of 

non‐utility entities that use the transmission grid. 

 

The ERO’s compliance registry process is used to identify the set of entities that are responsible for 

compliance with a particular reliability standard and the applicability section of a particular reliability 

standard determines the applicability of each reliability standard.  The NERC Functional Model provides 

                                                           4 Reliability is also dependent at the local level on the reliability of the local distribution system. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page v October 8, 2013

guidance concerning the type of function for which an entity is registered and, therefore, their role in 

maintaining reliability. 

 

Regardless of whether entities are located in regions that have centralized markets and RTOs/ISOs or a 

traditional regulation structure, the REs and NERC will identify who must be registered and as what 

type of functional entity.  The primary difference between functional responsibilities of entities that exist 

in RTOs/ISOs and those that do not is that RTOs/ISOs often perform the functional roles of balancing 

authority, reliability coordinator, transmission operator, and transmission planner.  In regions that do 

not have RTOs/ISOs, the electric utility often performs all the functions and is registered as multiple 

functional entity types.  The states and other governmental entities that have regulatory oversight 

functions may participate as non‐voting members in NERC and RE activities, under the government 

sector, and may also provide comments in FERC proceedings. 

 

Two approaches have been applied to achieving the resource adequacy goals—market‐based and an 

administrative approach.  With a capacity market, suppliers receive periodic (i.e., annual or monthly) 

payments for providing “reliable” capacity to a system and Load‐Serving Entities (LSEs) are required by 

the regulatory standard to purchase the capacity.  Examples of capacity markets are PJM, NYISO, and 

ISO‐NE.  There are also other variations to the market‐based approach; these are energy‐only markets (in 

ERCOT) and markets with administrative resource adequacy requirements for LSEs (CAISO and MISO).  

One key concern for consumers is price volatility and uncertainty.  Questions also remain as to how 

current market design will work to ensure capacity adequacy in the long term at economically efficient 

levels.  Under the administrative approach, resource adequacy is achieved through traditional Integrated 

Resource Planning (IRP) and competitive resource solicitation.  One key concern with the administrative 

approach is increased consumer cost due to uneconomic long‐term investment decisions.  Examples of 

administrative approaches are the Southwest Power Pool, most of the Western Electricity Coordinating 

Council outside the CAISO, and the southeast U.S. 

Environmental Issues 

Market/regulatory structure plays an important role in whether and how environmental requirements 

and policies affect electric entities.  Where the traditionally regulated model prevails, the impacts—

whatever they are—fall on the utility and the associated costs flow to its customers through cost‐based 

rates.  In contrast, where there has been a restructuring of utility regulation and the development of 

centralized electricity markets, impacts vary widely.  A utility that owns no generation would not incur 

the direct expense of complying with environmental rules relating to emissions, although generators 

would try to raise prices to recover costs.  Similarly, generation‐only entities would not normally be 

subject to renewable portfolio standards (RPS) or policies favoring the use of renewable energy 

resources.   

 

Independent generators in centralized markets are particularly sensitive to the costs of environmental 

regulation, since these generators rely on market pricing rather than cost of service rates.  Uneconomic 

generation in competitive markets may be retired rather than operated at a loss for any extended period 

of time.  Under the traditional regulated model, vertically integrated utilities are also sensitive to 

environmental regulation, including policies or regulations favoring renewables, since compliance 

would increase or decrease its costs. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page vi October 8, 2013

 

The costs and risks from proposed environmental regulations will differ by region, largely affecting 

those regions of the country with significant amounts of existing coal‐fired generation.  Whether 

environmental costs end up being passed through in cost‐based rates or result in higher market‐based 

rates, the impact on electricity consumers in those regions will be considerable. 

Relative Allocation of Risks over Time 

Under the traditional regulated model, the allocation of risks is well established.  The utility has a 

monopoly right to provide electric service to retail customers, who in turn are entitled to electricity at a 

“reasonable” cost.  The utility’s risk in the traditional model is that its rates will not recover its actual 

investment and operating costs or meet the rate of return required for its investors to risk their money.  

The utility also risks that its costs will be determined to have been prudently incurred and that it will 

receive timely recovery through the regulatory process.  The customers face much of the risk of utility 

over‐investment or under‐investment (either through bad decision making or out of concern that it will 

not recover its costs), and unreliable service and high costs as a result of ineffective operations or bad 

decision making; to the extent the regulators allow utilities to recover their costs. 

 

In a centralized market model, the risks for customers and the mechanisms for addressing them are the 

same with respect to the transmission and distribution system.  Rate cases and regulation are the 

principal tools to protect customers from monopoly abuses and to set the utility’s pricing for the delivery 

of electricity.  However, with respect to generation, the market sets wholesale energy prices.  In these 

markets, many generators in a region compete with one another to supply electricity.  These regions also 

rely on market forces to cause needed generation to be added when and where it is needed but some 

markets have found that these forces may not be enough incentive.  A further complexity in some 

centralized markets is customer choice where a utility must be prepared to procure power for a changing 

customer base.  

Responsibilities for Planning and the Types of Planning Performed 

Planning functions encompass adequacy and transmission security planning.  State and federal 

governments have overlapping responsibilities for these two aspects of planning.  The oversight of 

resource adequacy planning has traditionally been a state function while transmission security planning, 

with the important exception of transmission siting, has now become governed by federal law and 

regulation overseen by FERC. 

 

In recent years, two key FERC Orders have encompassed the field of transmission planning.  They are 

Order No. 890 and Order No. 1000, which apply to entities whether in RTO/ISO regions with centralized 

markets or not.  Order No. 890 promoted increased open, transparent and coordinated transmission 

planning on sub‐regional (local) and regional levels.  Order No. 1000 built upon and extended many of 

the ideas initially introduced under Order No. 890.  Among the changes introduced in Order No. 1000 

are requirements for regional and interregional planning, cost allocation, consideration of public policy 

requirements, and elimination of the Right of First Refusal in wholesale tariffs to construct new facilities.  

In areas where RTO/ISOs have formed, transmission planning often encompasses a larger region than 

previously existed and is coordinated around a centralized processes administered by the RTO/ISO.  In 

areas where traditional regulation remains, planning is coordinated by the vertically integrated utilities 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page vii October 8, 2013

or public power entities within their territory.  These territories may also encompass large areas due to 

mergers and holding company consolidation.  Both traditionally regulated and competitive market 

(RTO/ISO) regions have in place processes to coordinate planning with their neighboring entities. 

 

The authority over transmission siting is a patchwork quilt of overlapping and sometimes unclear 

divisions of authority.  While the majority of siting authority currently lies with the states, there are 

instances where federal approvals are required.  The Energy Policy Act of 2005 established a limited role 

for the U.S. Department of Energy (DOE) and the FERC in transmission siting.  The act directed DOE to 

create “transmission corridors” in locations with adequate transmission capacity that had “national 

interest” implications.  The act also granted FERC secondary authority over transmission siting in these 

corridors, which may not be exercised by FERC unless the state where the facility would be sited lacks 

the authority to issue the permit, the applicant does not qualify for the permit in the state, or the state 

has “withheld approval” of the permit for more than one year. 

 

While some regions have moved to develop capacity markets, discussed earlier, to ensure generation 

adequacy, many states, particularly in areas where the traditionally regulated model remains, have 

retained the IRP approach, which began in the late 1980s.  Steps taken in an IRP include forecasting 

future loads, identifying potential supply‐side and demand‐side resource options to meet those future 

loads and their associated costs, determining the optimal mix of resources taking into account 

transmission and other costs, receiving and responding to public participation (where applicable), and 

creating and implementing a resource plan. 

Innovation and the Levels of Research and Development Pursued 

Innovations in the electric industry, technical and economic, have come about through the application of 

research and development (R&D) of projects by the electric sector, governments, and other industrial, 

communications, and technology sectors. 

 

The expansion of combined heat and power and natural gas‐fired combined cycle plants in the late 1970s 

into the 1990s was a strong contributing factor to growth in the class of non‐utility generation.  The cost‐

effectiveness of smaller increments of generation has reduced the need for utilities to periodically have 

large, “lumpy”, capital‐intensive investments and corresponding large additions to their rate base.  

Moreover, since generation can be added in smaller increments and with lead times closer to the time of 

anticipated need, the investment cycle has become smoother.  This benefits both traditional and 

competitive market entities. 

 

Demand‐side management (DSM)‐induced reductions in load growth reduce or defer the need for new 

generation plant investment and the costs of the DSM alternatives may be less than the cost of new 

generation.  Centralized market regions are gradually implementing market rules that seek to place 

supply‐ and demand‐side options on equal footing with respect to bidding into capacity and energy 

markets.  Traditionally regulated regions seek to maintain equal footing for these two types of options 

through integrated resource plans vetted by state regulators.   

 

In the last decade, or less, the Smart Grid has become a hot topic in political and academic circles as well 

as other groups not traditionally involved in the regular processes of the electric sector.  The expectation 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page viii October 8, 2013

is that Smart Grid implementation will generate potential savings to customers by providing them the 

tools to manage their energy consumption habits and costs, as well as providing potential savings to 

utilities and their customers through operating efficiencies. Utilities in both models would benefit from 

savings.  Similarly, customers can benefit from smart meters and usage information under both models. 

 

R&D investment by electric utilities (including their contributions to the Electric Power Research 

Institute) is small when compared to other industrial sectors and when observed in the context of the 

role electricity plays in our national economy and society.  However, historically, electric equipment 

manufacturers have provided the majority of the R&D in the sector; this is primarily because utilities 

cannot necessarily internalize the benefits of the innovations developed through R&D.  No study has 

definitively assessed the impact of restructuring efforts on R&D investment in the electricity industry.  

However, several studies have noted a decline in R&D investment in some areas and concluded that 

utility restructuring is the likely cause.  However, there are also studies that have concluded that the 

centralized market model encourages more innovation than the traditionally regulated model.5 

State and Federal Government 

The electric utility industry in the United States is regulated at the state and federal levels.  State 

regulation extends to most areas of utility operations, rates, and end‐user issues.  Federal regulation, 

founded on interstate commerce impacts, generally relates to the wholesale side of the utility business, 

including interstate transmission and sales of electricity for resale.  State and Federal jurisdiction over 

transmission siting, resource adequacy and transmission security planning, and electric reliability have 

been discussed above. 

 

Investor‐owned utilities are subject to state regulation as to their duties to customers, system 

requirements, financing arrangements, and retail rates.  Government‐owned utilities and rural electric 

cooperatives are not generally subject to regulation under state utility laws, but must follow the 

requirements of the ordinance or law establishing them and have governing boards that provide 

oversight. 

 

Under both the traditionally regulated model and the centralized market model, interstate transmission 

rates are approved by FERC and FERC regulates the interstate transmission and generation activities of 

“public utilities.”  FERC does not regulate government‐owned utilities or most cooperatives, which are 

often referred to as “non‐jurisdictional” entities.  In addition, because most of the Texas transmission 

grid is not interconnected with the rest of the interstate transmission grid, Texas is not subject to FERC 

rate regulation.  In Texas, the state regulator is responsible for approving transmission rates (because 

Texas transmission is intrastate) as well as regulating all other aspects of the electric utility business in 

Texas.       

 

While FERC’s regulatory reach is not absolute, FERC has effectively extended many of its regulations to 

non‐jurisdictional utilities through reciprocity.  For example, if a non‐jurisdictional utility wants to take 

advantage of the terms of a public utility’s Open Access Transmission Tariff (OATT), then it must itself 

have an OATT where the terms of service other than rates must comply with FERC requirements.  

                                                           5 These studies are discussed in greater detail in section 9.4. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page ix October 8, 2013

Similarly, in order to be part of the regional planning process and to take advantage of proposed cost 

allocation mechanisms, FERC has said that non‐jurisdictional entities have to agree to participate in the 

FERC‐regulated planning processes and be subject to the outcome of these processes. 

 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 1 October 8, 2013

2.  Introduction 

This paper explores the key policy questions surrounding two broad regulatory/market structures that 

currently exist in the United States in varying degrees: traditional utility regulation without centralized 

markets on the one hand, and centralized electricity markets, often involving restructured regulation, on 

the other.  The latter structure also generally involves the existence of a Regional Transmission 

Organization (RTO) or Independent System Operator (ISO).    

 

This paper provides a brief history of regulation and competition in the electric industry and identifies 

the issues that characterize the key differences between the two major regulatory/market structures, 

which for ease of reference are being called a “traditionally regulated” model and a “centralized market” 

model.6  The paper is intended as an educational piece for non‐industry experts on how and why electric 

utility regulation has evolved and centralized energy markets have developed in some areas of the 

country and not in others.  It focuses on consumer impacts and discusses how various issues are 

addressed under the two broad models as well as identifying ongoing issues and challenges.  This paper 

does not provide a critique of the models nor a quantitative comparison between the two models. 

 

A secondary purpose of the paper is to serve as a foundation for identifying the issues that characterize 

the key differences between the two regulatory/market structures that will help guide decisions on 

future research projects for the Electric Market Research Foundation (EMRF) to meet its goal of 

informing the public policy debate on the pros and cons of the major market structures. 

 

                                                           6 Within the two different general models there are further distinctions.  The traditionally regulated model is often 

characterized at the wholesale level by bilateral resource transactions while at the retail level the traditional 

vertically integrated utility provides / purchases all functions required to provide service to the end users.  The 

centralized market model generally involves the existence of a Regional Transmission Organization (RTO) or 

Independent System Operator (ISO) that administer centralized, bid‐based markets at the wholesale level with some 

degree of retail competition where the customer has the right to procure power competitively with transmission and 

distribution service provided by a regulated utility.  Transmission and distribution under both models remains 

governed by a cost of service regulatory approach.  Further, the reader should be aware that there may be instances 

where regions or entities generally characterized as functioning under a certain broad model may not exhibit all 

features of that model.  For example, there are regions that have centralized wholesale energy markets that may not 

have implemented retail choice in all states within the region.  Similarly, there are regions that remain traditionally 

regulated but have elements of centralized markets and retail choice. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 2 October 8, 2013

3.  History and Development of Traditional Regulation and Competitive Markets 

The evolution of the U.S. electric industry is a history of adaptation to changes in the operating and 

regulatory environment.  During times of significant economic and technological change, policymakers 

adapted regulatory policy to ensure the public interest continued to be served, economic principles of 

efficiency and competition were advanced, and the reliable and efficient delivery of electric service to 

consumers was maintained.  The decisions made by regulators and policymakers shaped the two 

regulatory paths that have emerged—traditional rate making based on cost of service regulation and 

centralized market development.  Today, both of these approaches co‐exist and continue to evolve to 

meet changing economic and technological challenges. 

 

The allocation of regulatory authority between the federal government and the states is distinguished by 

what constitutes interstate commerce and what constitutes intrastate commerce.7  Furthermore, there is 

the preemptive effect of federal wholesale rate orders on state retail rate authority.8  This dichotomy has 

resulted in a number of distinctions among industry participants as to whether they are subject to 

federal, state or both federal and state regulation by virtue of how they are organized and whether they 

operate within a single state.  Further, distinctions as to the applicability of federal vs. state regulation 

turn on which specific physical and functional components of the electric system (e.g., generation, 

transmission, distribution, and customer service) are in question.  

 

The sections that follow describe, from the early beginning to present day, the key events that 

transformed approaches in electric regulation policy and the evolving approaches designed by 

regulators and policymakers on both the federal and state levels to meet those challenges. 

                                                           7 See also, New York v. FERC, 535 U.S. 1 (2002).  The court acknowledged that FERC correctly could choose not to 

regulate the transmission component of bundled retail sales.  Bundled sales are sales that combine energy and 

transmission service as a single unit. 8 Under the Narragansett line of cases, Narragansett Elec. Co. v. Burke, 381 A.2d 1358 (1977), cert. denied, 435 U.S. 972 

(1978), comprising what is now called the ʺfiled rate doctrine,ʺ state regulators must treat a utilityʹs FERC‐approved 

wholesale power costs as reasonable operating expenses in the companyʹs retail cost of service.  In other words, the 

retail regulator cannot, in its retail rate hearing, question the reasonableness of the wholesale rate that the FERC has 

fixed. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 3 October 8, 2013

3.1  Development of Traditionally Regulated Markets 

Figure 1. Historical Timeline 1920‐19459 

  

The early structure of the electric utility industry developed around the concept of a central source of 

power supplied by efficient, low‐cost utility generation, transmission, and distribution.  Regulation of 

utilities began in the late nineteenth century, with municipalities issuing franchises, often overlapping, 

as a method of regulation, promoting competition between utilities.  This regulatory oversight derived 

from a series of nineteenth century court decisions in the U.S. that held industries such as grain 

elevators, warehouses, and canals were “monopoly” providers of service “affected with the public 

interest”7 and that their rates and terms of service could therefore be regulated.10  Municipal regulation 

gave way to state regulation following the passage of laws in New York and Wisconsin developing 

powerful state commissions.11 

 

In the early part of the twentieth century, the electric industry evolved quickly through the creation, 

growth, and consolidation of vertically integrated utilities.  A rapid increase in electricity generation 

encouraged growth and consolidation of the industry to achieve economies of scale, which resulted in an 

expansion into more and more cities across wider geographic areas.12  During this period, vertically 

integrated electric utilities produced approximately two‐fifths of the nationʹs electricity.13  Over time, 

states granted these consolidated utilities monopoly franchises with exclusive service territories in 

exchange for an obligation to serve customers within that territory at rates for service based on state‐

regulated, cost‐of‐service ratemaking.14  As utility service territories grew throughout the 1900s, state 

                                                           9 Source:  Navigant Consulting, Inc. 10 See Munn v. Illinois, 94 U.S. 113, 126 (1877). 11 There are alternative views of why the municipal regulation ended.  The natural monopoly view is that state 

regulation was necessary to distance the regulator from the local level and to enforce uniform regulation throughout 

the jurisdiction. This view assumes that one firm can serve the market more cheaply than two or more firms and can 

keep out rival firms by expanding output and lowering price when threatened.  The alternative view was that the 

move from municipal to state regulation was in the public interest. See R. Richard Geddes, A Historical Perspective 

on Electric Utility Regulation,  CATO REVIEW OF BUSINESS, 

http://www.cato.org/sites/cato.org/files/serials/files/regulation/1992/1/v15n1‐8.pdf, at pp. 75‐77. 12 See U.S. Electric Power Industry ‐ Context and Structure, Analysis Group for Advanced Energy Economy 

(November 2011) (“AEE Context and Structure”). 13 Energy Information Administration, The Changing Structure of the Electric Power Industry 2000: An Update  

(October 2000) Part I, Chapter 2, pg. 5 (“EIA Changing Structure”). 14 See AEE Context and Structure. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 4 October 8, 2013

regulation of privately owned electric utilities increased.  Among the first states to regulate electric 

utilities were Georgia, New York, and Wisconsin, which established state public service commissions in 

1907.15  These states were soon followed by more than 20 other states.  Part of the justification for 

exclusive service territories was that a single distribution system in an area was more efficient due to 

economies of scope; competing distribution facilities on thoroughfares and in communities would 

require redundant capital investment and expenditures.  

 

Despite the lure of exclusive franchises, some areas were inevitably less attractive than others.  This was 

particularly true with respect to rural areas, where the progress of electrification was much slower than 

in urban areas.  The Rural Electrification Act was enacted to provide power to unserved, or underserved, 

rural areas and gave rise to the advent of rural electric cooperatives in many areas of the U.S.   

 

During the 1920s and the early years of the Depression, the public became disenchanted with privately 

owned power and began to support the idea of government ownership of utilities, particularly 

hydroelectric power facilities.  This disenchantment resulted primarily from abuses imposed by holding 

companies on utilities, and ultimately on their customers, causing the price of electricity to increase.  A 

fierce debate at the time was whether government‐owned hydroelectric power facilities could produce 

power cheaply and sell it to publicly owned utilities for distribution.  During the presidency of Franklin 

D. Roosevelt (1933 to 1945), a number of these facilities were built, ushering in the beginning of publicly 

owned power.16 

The development of hydroelectric projects in the United States was coordinated under the Federal Water 

Power Act in 1920.  The act created the Federal Power Commission (FPC), now the Federal Energy 

Regulatory Commission (FERC), as the licensing authority for these plants.  The FPC also regulated the 

interstate activities of the electric power and natural gas industries.  The responsibility of the FPC was to 

maintain just, reasonable, and nondiscriminatory rates to the consumer.  In 1935 the law was renamed 

the Federal Power Act (FPA), and the FPC’s regulatory jurisdiction was expanded to include all 

interstate electricity transmission.  The FPC was also given authority to regulate nonfederal hydropower 

projects.  The Federal Power Act is the core legislation providing federal jurisdiction over the electric and 

natural gas industries and defining the responsibilities of the FERC.17  However, the FPA exempts 

                                                           15 Energy Information Administration, Annual Outlook for U.S. Electric Power 1985, DOE/EIA‐0474(85) (August 1985), 

pg. 3. 16 EIA Changing Structure, Part I, Chapter 2, pg. 6.  As part of the program, President Roosevelt proposed that the 

government build four hydropower projects and, within a year after his proposal, his administration began to 

implement the projects.  

Hoover Dam began generation in 1936, followed by other large projects. 

Grand Coulee, the nation’s largest hydroelectric dam, began operation in 1941. 

Under the Tennessee Valley Authority Act of 1933, the federal government supplied electric power to 

states, counties, municipalities, and nonprofit cooperatives.  

The Bonneville Project Act of 1937 pioneered the federal power marketing administrations.  

From 1933 to 1941, one‐half of all new capacity was provided by federal and other public power installations.  Public 

power contributed 12 percent of total utility generation, with federal power alone contributing almost 7 percent.  See 

Id.  It should be noted that the federal power generating entities were not subject to regulation by States. 17 See AEE Context and Structure. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 5 October 8, 2013

certain entities from many provisions of the Act, including entities in the state of Texas, which is a 

single‐state Interconnection with no interstate transactions, as well as certain non‐public utilities (i.e., 

Municipal Utilities, Cooperatives, Power Marketing Administrations, and state authorities).18 

 

After several large holding company systems collapsed, an investigation by the Federal Trade 

Commission was ordered, leading eventually to the passage of the Public Utility Holding Company Act 

of 1935 (PUHCA).  PUHCA was aimed at breaking up the unconstrained and excessively large trusts 

that then controlled the nationʹs electric and gas distribution networks.19 

 

PUHCA gave the Securities and Exchange Commission (SEC) responsibility for regulating utility 

holding companies.  Under Title II of PUHCA, the FPC also regulated utilities involved in interstate 

wholesale marketing or transmission of electric power.20  One of the most important features of the Act 

was that the SEC was given the power to break up the large interstate holding companies by requiring 

them to divest their holdings until each became a single consolidated system serving a circumscribed 

geographic area.  Another important feature of the law permitted holding companies to engage only in 

business that was essential and appropriate for the operation of a single integrated utility.21 

 

In the Supreme Court case of FPC v. Hope, the Court stated: “[t]he rate‐making process … i.e., the fixing 

of ― just and reasonable rates, involves a balancing of the investor and the consumer interest.”22  This 

balancing of consumer and investor interests evolved into what has become known as the regulatory 

compact.23  In addition, Hope gave rise to an End Results Doctrine relating to rates.  Under this doctrine, 

only the end result – not the methodology – matters in determining whether rates are just and 

reasonable.24 

 

The regulatory compact is premised on the existence of a set of rights, obligations, and benefits that are 

shared between utilities and their customers.25  In return for the grant of a franchise and the right to 

recover its costs plus a market‐determined profit equal to the cost of debt and equity capital, the 

                                                           18 Section 201(f) of the FPA generally exempts the United States, a state or any political subdivision of a state, an 

electric cooperative that receives financing under the Rural Electrification Act of 1936 (7 U.S.C. 901 et seq.) or that 

sells less than 4,000,000 megawatt‐hours of electricity per year from Part II of the FPA.  However, it should be noted 

that the reliability section of the FPA added under EPACT 2005 extends to entities that were described under 201(f) 

of the FPA.  See Federal Power Act § 215(b), 16 U.S.C §844o(b). 19 EIA Changing Structure, Part I, Chapter 4, pg. 29. 20 Ibid., Part I, Chapter 2, pg. 5. 21 Ibid., Part I, Chapter 4, pg. 29. 22 Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 603 (1944). 23 The concept of a regulatory compact is not that there is a formal agreement between the utility and government 

but rather that  the legal obligations of regulators and utilities have evolved through a long series of court decisions,  

See RAP Publications, Electricity Regulation in the US: A Guide (March 2011) , 

www.raponline.org/document/download/id/645 , pp. 4-5. 24 Dr. Karl McDermott, Cost of Service Regulation In the Investor‐Owned Electric Utility Industry  (June 2012), pg. 3 

(“Cost of Service Regulation”). 25 Cost of Service Regulation, pg. vii. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 6 October 8, 2013

investor‐owned utility must submit to rate regulation and provide service efficiently.26  “The regulatory 

compact has a two‐fold focus: (1) establish prices based on the actual prudent costs (i.e., avoid monopoly 

pricing); and (2) provide incentives to maintain a reasonable level of efficiency in serving the 

customers.”27 

 

Under traditional utility regulation, this determination of the appropriate cost of service that can be 

charged by the utility is determined through what developed as the rate case process, which examines 

the prudency of costs after they are incurred.28  This form of regulation serves as an administrative 

replacement for market mechanisms in determining what costs were efficient.29 

3.2  Period of Growth and Declining Costs, 1945‐1970 

Figure 2. Historical Timeline 1945‐197030 

  

From the 1940s through the 1960s the industry saw extensive growth and increasing electricity 

consumption.  Economies of scale increased as new, larger generating units were built which drove 

down costs, and stimulated an increased demand for electricity.31 

 

Regulatory administration of the rate case process described above became routine during this period 

and established the normal course of utility operations and funding.  Utilities would provide service to 

all customers in their franchise area and in return were guaranteed a reasonable return on their 

investments determined through the rate case process.  Both utilities and customers have benefited from 

this relationship; utilities received a guaranteed service territory with a return on investment (ROI) and 

customers received protection from monopoly pricing. 

 

The rate case would establish rates based on the normal costs of providing service determined by the 

revenue requirement.  The utility had to work within a framework of regulatory lag, demand growth, 

and cost instability in real‐time operations.  Exposure to real‐time operations provided both a risk and 

                                                           26 See Ibid.  “The utility was obligated to supply service efficiently, but had the right to recover its costs, including an 

opportunity to earn a return/profit equal to its market‐determined cost of debt and equity capital.” Ibid. 27 Ibid., pg. vii. 28 A rate case is a formal administrative process in which the utility provides support for its proposed cost of service 

and the public, including the regulatory body, is provided the opportunity to scrutinize the data, policy arguments, 

and any other relevant information.  Ibid., pg. 12. 29 Ibid., pg. viii. 30 Source:  Navigant Consulting, Inc. 31 Cost of Service Regulation, pg. ix. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 7 October 8, 2013

incentive.  If the original assumptions remained fairly accurate, utilities would be able to operate fairly 

successfully; however, if the assumptions proved to be incorrect, either the utility or the regulator would 

seek adjustments.32 

 

This worked well for most of this period, although the Northeast Blackout of 1965 raised pressing 

concerns about reliability. 

3.3  Slowed Growth and Inflation, Seeds of Competition, 1970‐1990 

Figure 3. Historical Timeline 1970‐199033 

 

A number of damaging events occurred in the 1970s that interrupted the growth that occurred in the 

prior several decades.  After the Northeast Blackout of 1965, state and regional power pools were created 

or took on expanded roles.  Many of these are the predecessors to today’s Regional Transmission 

Organizations.  In addition, regional, voluntary reliability councils were formed by the utilities in an 

effort to enhance reliability and stave off regulation.   

The passage of the Clean Air Act of 1970 and its amendments in 1977 required utilities to reduce their 

emission of pollutants, raising their operating costs, particularly for utilities operating coal‐fired 

generation.  Probably the most significant event was the Oil Embargo of 1973‐1974, which resulted in 

burdensome increases in fossil‐fuel prices due to transportation costs.  Although the embargo lasted only 

until March 1974, its effects increased public awareness of energy issues, resulted in higher energy 

prices, and contributed to inflation.   

The accident at Three Mile Island in 1979 led to higher costs, regulatory delays, and greater uncertainty 

for companies pursuing nuclear generation.  In general, inflation caused interest rates to more than 

triple.  The escalating fuel costs, reduction in demand growth, and accompanying unprecedented 

inflation in labor, capital costs, and construction materials meant that utilities were not realizing the 

incremental cash flows that had helped finance new construction in the past.34 

 

In 1978, Congress pursued legislation intended to reduce U.S. dependence on foreign oil, develop 

renewable and alternative energy sources, sustain economic growth, and encourage the efficient use of 

                                                           32 Ibid., pg. 16. 33 Source:  Navigant Consulting, Inc. 34 Cost of Service Regulation, pg. ix. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 8 October 8, 2013

fossil fuels.35  A greater reliance on market forces to set wholesale power costs was introduced through 

the Public Utility Regulatory Policies Act of 1978 (PURPA), which adopted avoided cost pricing for 

energy purchased by utilities from certain types of third‐party suppliers.36  PURPA became a catalyst for 

competition in the electricity supply industry, because it allowed nonutility facilities that met certain 

ownership, operating, and energy efficiency criteria established by FERC (referred to as  “qualifying 

facilities” or  “QFs”), to enter the wholesale market.37  Utilities did not initially welcome this forced 

competition.38  The QFs themselves are not subject to cost‐of‐service regulation, and the prices paid to 

them are not based on their cost of producing the electricity.39  Instead, the prices they are paid reflect 

the avoided cost of the purchasing utility (generally determined by the utility’s regulatory authority), 

that is, the cost the utility avoided by not producing the electricity received from the QF or purchasing it 

from another source.40  In some cases utility regulatory authorities set an avoided cost that was very high 

leading to financial problems for utilities that were forced to pay these high prices. 

 

The economic challenges of the 1970s fed directly into the 1980s.  Demand growth continued to be slow.  

The beginning of the decade saw high inflation in the cost of construction materials and labor along with 

double‐digit financing rates.  This led to dramatic cost overruns in coal and nuclear plants under 

construction.  In the wake of the Three Mile Island accident in 1979, the cost to complete nuclear plants 

under construction soared as new safety requirements came into play.   Some plants (nuclear and non‐

nuclear) were cancelled before completion.   These factors led to increased utility costs for plants that 

were ultimately cancelled and substantial rate shocks for plants that were completed and entered the 

rate base.  Regulators responded to the challenge of construction cost overruns by expanding their 

oversight of the prudence of project costs.  The number of rate cases expanded dramatically from the few 

dozen major prudence cases between 1945 and 1975 to over 50 during the 1975 through 1985 period.41 

 

In addition, regulators, public interest groups, and utilities began to recognize in the late 1970s and early 

1980s that actions taken to promote conservation and demand‐side management (DSM) could be less 

costly under some conditions than construction of new power plants.  While the economic conditions 

that supported the premise that incremental costs of DSM could be less than the incremental costs of 

new generation were reversed during an era of lowered natural gas prices later, new state and federal 

                                                           35 EIA Changing Structure, Part I, Chapter 2, pg. 8. 36 Cost of Service Regulation, pg. 24. 37 EIA Changing Structure at Part I, Chapter 2, pg. 8. 38 Ibid., Part I, Chapter 2, pg. 8.  PURPA defined a new class of energy producers called qualifying facilities. These 

producers are either small‐scale producers of commercial energy who normally self‐generate energy for their own 

needs but may have surplus energy, or incidental producers who happen to generate usable electric energy as a by‐

product of other activities. When a facility of this type meets the requirements for ownership, size and efficiency, 

utility companies are obliged to purchase their energy based on a pricing structure referred to as avoided cost rates. 

These rates tend to be highly favorable to the producer, and are intended to encourage more production of this type 

of energy as a means of reducing emissions and dependence on other sources of energy. See AEE Context and 

Structure. 39 EIA Changing Structure, Part I, Chapter 4, pg. 32. 40 Ibid. at Part I, Chapter 4, pg. 32. 41 Cost of Service Regulation, pg. 25. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 9 October 8, 2013

regulations or conservation programs introduced the retail customer class to much greater involvement 

in utility planning than had existed before. 

 

An immediate impact on regulators‘ thinking was that there was a need to plan to avoid these situations 

and to search for smaller increments of supply or demand reductions.  The least cost utility planning and 

Integrated Resource Planning (IRP) processes were part of the response to this need.42 

 

These processes were designed to take into account a broad range of information and alternatives, 

produce demand forecasts in a public process, and attempt to evaluate supply and demand options on 

an equal footing.  Much of the late 1980s saw efforts to establish more effective formal planning 

frameworks in an attempt to avoid the mistakes that occurred in the 1970s.  Regulators embraced this 

process to varying degrees, attempting to integrate the planning and rate case sequences together in a 

way that reinforced both from an information and implementation perspective.  

 

Another significant development in the late 1980s was an increased utility interest in selling their 

generation in wholesale transactions.  This was prompted by excess capacity in the early 90s that 

occurred because load growth did not meet projected levels.  FERC began allowing utilities to sell power 

at market based rates (as compared to cost‐based)  if the utility could show it had no power to set prices 

in the market, would cap the rates at avoided cost, or would provide non‐discriminatory transmission 

access to competitive generators.43  This form of regulatory rate treatment was viewed by many in the 

industry as superior to the risk of building a new unit under traditional regulation at the state level.44  By 

1991, FERC had received 40 of these market‐based pricing requests.45 

3.4  The Advent of Centralized Markets, 1990‐1999 

Figure 4. Historical Timeline 1990‐199946  

  

                                                           42 Ibid., pg. 26. 43 Ibid., pg. 30‐31. 44 Cost of Service Regulation, pg. 31. “The move to greater reliance on markets was accelerated by FERC‘s 1988 pre‐

construction rate approval in Ocean States Power as well as the notice of proposed rulemakings on market based 

pricing of electricity.  All of these factors were layered on top of the incentive provided for non‐utility generation by 

PURPA.” Ibid., pg. 30. 45 Ibid., pg. 31.  46 Source:  Navigant Consulting, Inc. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 10 October 8, 2013

Passage of the federal Energy Policy Act of 1992 (EPACT) was a significant enabler of market 

development.  First, it created a new class of electric suppliers, the exempt wholesale generator (EWG), 

extending the trend started by FERC with the market‐based rate policy and open access to the 

transmission system.47 

 

Like QFs, EWGs were wholesale producers that did not sell electricity in the retail market and did not 

own transmission facilities.48  Unlike the non‐utilities that qualified under PURPA, EWGs were not 

regulated and could charge market‐based rates.49  The growth of EWGs marked another step toward 

increasing the level of competition in the wholesale electricity market.   

 

Marketing of EWG power was facilitated by transmission provisions in EPACT 1992 that gave FERC the 

authority to order utilities to provide access to their transmission systems to utilities and non‐utilities.50  

In addition, EPACT 1992 required states to conduct an IRP process and evaluate the impact of purchased 

power contracts on the local distribution company.51  Some states took this even further, taking steps to 

break up the vertical integration of utilities within those states, to introduce retail competition.52 

 

The second cornerstone in the creation of competitive wholesale power markets came in 1996 through 

FERC’s Order No. 888.53  At that time, Order No. 888 was considered the most far‐reaching and 

ambitious project undertaken by FERC to eliminate impediments to wholesale competition in the electric 

power industry.54  Order No. 888 had two basic goals: (1) to eliminate anti‐competitive practices and 

undue discrimination in transmission services through a universally applied, open‐access transmission 

                                                           47 Cost of Service Regulation, pg. 32. 48 EIA Changing Structure, Part I, Chapter 2, pg. 8. The Commission ceased making case‐by‐case determinations of 

exempt wholesale generator status following the enactment of EPACT 2005 calling for the repeal of PUHCA.  See 

Repeal of the Public Utility Holding Company Act of 1935 and Enactment of the Public Utility Holding Company 

Act of 2005, Docket No. RM05‐32‐000, (Sept. 2005) at P 21. 49 49 EIA Changing Structure at Part I, Chapter 2, pg. 8. 50 Ibid., Part I, Chapter 4, pg. 33. 51 Cost of Service Regulation, pg. 32. 52 See AEE Context and Structure. 53 The actions taken by the Commission in Order No. 888 paralleled and in many instances were guided by Gas 

Restructuring, Order No. 636, open‐access transport in gas. 54 EIA Changing Structure,  Part II, Chapter 7, pg. 64. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 11 October 8, 2013

tariff, and (2) to ensure the recovery of stranded costs55 a utility might accrue in the transition to 

competitive markets.56 

Another equally important component of Order No. 888 was the requirement for transmission owners to 

functionally unbundle their services.  Functional unbundling required the transmission owner to take 

transmission service under the same tariff as other transmission users under a comparability standard.  

They were required to separate rates for wholesale generation, transmission, and ancillary services and 

to rely on the same electronic information network that its transmission customers relied on to obtain 

information about prices and available capacity of the transmission system.  The concept of unbundling 

was to preclude the appearance of possible favoritism and discriminatory practices within a vertically 

integrated utility by separating its transmission services functions from other business activities in the 

company and by requiring utilities to provide transmission service to others for wholesale transactions 

in the same manner as they provide it to themselves.57 

 

Accompanying the requirement for non‐discriminatory access to the transmission system, timely and 

accurate day‐to‐day information about transmission was also made available to all transmission users.58  

Order No. 889 required all investor‐owned utilities (IOUs) to participate in the Open Access Same‐Time 

Information System (OASIS), which facilitated the functioning of competitive power markets.59  At the same time these changes were occurring in the wholesale electricity markets, a growing number 

of states were also pursuing a reliance on competitive markets for the retail supply of electric power.  

Retail choice was introduced in the United States in the 1990s in response to high regulated prices in 

some regions.  As noted, excess generation capacity was triggered by the generation construction cycle 

that began in the 1960s and continued into the 1970s.  Consumer groups in some regions found retail 

                                                           55 Stranded costs refer to an investment made under regulation whose value will not be recovered under prices 

determined in a deregulated environment.  Recognizing that FERC only had jurisdiction over a part of the stranded 

costs issue, FERC sought to permit public utilities to seek recovery at FERC as the primary forum for a limited set of 

existing wholesale requirements contracts, those executed on or before July 11, 1994, termed retail‐turned‐wholesale 

transmission customers.  Recovery is only permitted where there is a direct nexus between the availability and use 

of a Commission‐required transmission tariff and the stranding of the costs.  Furthermore, recovery at FERC for 

stranded costs caused by unbundled retail wheeling would only be for those stranded costs caused by retail 

wheeling where the state regulatory authority did not have authority to address retail stranded costs at the time the 

retail wheeling is required.  Order No. 888 at pg. 8.  As the primary vehicle for recovery, FERC concluded that direct 

assignment of stranded costs to the departing wholesale generation customer through either an exit fee or a 

surcharge on transmission is the appropriate recovery method.  Promoting Wholesale Competition Through Open 

Access Non‐discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities 

and Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996), order on rehʹg, Order No. 888‐A, 

FERC Stats. & Regs. ¶ 31,048 (1997), order on rehʹg, Order No. 888‐B, 81 FERC ¶ 61,248 (1997), order on rehʹg, Order 

No. 888‐C, 82 FERC ¶ 61,046 (1998), affʹd in relevant part sub nom. Transmission Access Policy Study Group v. FERC, 

225 F.3d 667 (D.C. Cir. 2000), affʹd sub nom. New York v. FERC, 535 U.S. 1 (2002), pg. 477. (“Order No. 888”) 56 Ibid.  57 EIA Changing Structure, Part II, Chapter 7, pg. 64. 58 Ibid., Part II, Chapter 7, pg. 66. 59 The OASIS is an interactive, Internet‐based database containing information on available transmission capacity, 

capacity reservations, ancillary services, and transmission prices. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 12 October 8, 2013

competition attractive because the prices in emerging wholesale markets were significantly below the 

regulated retail price of utilities, reflecting both excess generation capacity (depressing wholesale energy 

prices) and the large number and cost of new generating assets recently placed in service (increasing 

regulated retail rates).  In addition, these factors also raised concerns that the generation planning as 

implemented by utilities and reviewed by regulators in these regions was flawed. 

 

In contrast to the traditionally regulated model, retail choice limits the operation of the regulated utility 

to the transmission and distribution functions, where traditional cost‐based pricing is implemented and 

approved by state‐level regulators.  Generation services are provided either by competitive service 

providers or through a default “provider of last resort” (POLR). 

 

Ultimately, 15 states, plus the District of Columbia, implemented retail choice.60  This typically required 

the incumbent utility to divest its generation and become a wires‐only transmission and distribution 

utility.  Some states forced their utilities to divest utility‐owned generation to unaffiliated non‐regulated 

entities; other states simply permitted them to create affiliated generation subsidiaries; still other states 

required only operational and management separation (i.e., functional separation) from the utilities’ 

transmission and/or distribution functions.  In the restructured states, policymakers were presented with 

a host of new issues requiring significant policy responses.  Challenges included stranded costs, 

development of market rules, the designation of a provider of last resort where retail choice was not 

exercised, and level of cost for wires‐only companies.61  Some states that adopted competition faced 

market conditions that resulted in the abandonment of restructuring and a return to traditional 

regulation.62 

                                                           60 See http://www.eia.gov/electricity/policies/restructuring/restructure_elect.html. 61 Cost of Service Regulation, pg. 31. 62 Ibid., pg. 34.  In December 1998, 23 State public utility commissions sent Congress a letter expressing concerns that 

issues affecting them may not be given adequate consideration in the debate about restructuring. Kentucky, whose 

electricity prices are the lowest east of the Rocky Mountains, is one of these states. Recently, Kentucky’s Special Task 

Force on Electricity Restructuring concluded that there are no compelling reasons to restructure their electric power 

industry.  EIA Changing Structure, Part II, Chapter 8, pg. 81.  Furthermore, not all commissions may be endowed 

with the necessary legal authority to manage an evolving competitive market structure. Accordingly, legislation 

may be necessary in some states to grant the utility regulatory agency the authority to address the restructuring 

issues or to consider alternative rate‐making processes (incentive‐ or performance‐based regulation).  In some cases, 

legislative actions may become necessary to adopt decisions recommended by the commission(s) for 

implementation.  Ibid., Part II, Chapter 8, pg. 82. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 13 October 8, 2013

3.5  Traditional Regulation and Centralized Markets Today 

Figure 5. Historical Timeline 1999‐Present63  

  

In December 1999, FERC released Order No. 200064 calling for the voluntary formation of RTOs.  FERC 

believed that RTOs would facilitate the continued development of competitive wholesale power markets 

and would lead to improvements in reliability and management of the transmission system, eliminating 

any remaining discriminatory practices.65  Order No. 2000 asked all transmission‐owning utilities, 

including non‐public utilities, to voluntarily place their transmission facilities under the control of an 

appropriate regional transmission organization.  So that utilities could comply with this request, the 

characteristics and minimum functions of an appropriate RTO were defined in the Order. 

 

Order No. 2000 envisioned the creation of independent RTOs that would operate the transmission 

systems of its members, engage in regional transmission planning and operate wholesale energy 

markets.  The RTOs would provide tariffed transmission service and eliminate rate “pancaking” to the 

greatest extent possible.  Order No. 2000 resulted in the creation of several RTOs, as well as adoption of 

various RTO characteristics by the then‐existing ISOs.      

Concurrent with FERC’s efforts under Order No. 2000, challenges were arising in the California markets.  

In 2001, California, which led the nation toward competitive retail electric markets, suffered from, 

among other things, an over‐reliance on spot markets.66  Utilities were required to sell all of their power 

into, and buy all of their load‐serving power out of, the California Power Exchange (PX), which operated 

a day‐ahead hourly spot market, holding auctions and matching bids for purchase and sale.  As a result, 

California utilities incurred high costs of which they were only allowed to pass through a portion to 

                                                           63 Source:  Navigant Consulting, Inc. 64 Regional Transmission Organizations, Order No. 2000, 1996‐2000 FERC Stats. & Regs., Regs. Preambles ¶ 31,089 

(1999), order on reh’g, Order No. 2000‐A, 1996‐2000 FERC Stats. & Regs., Regs. Preambles ¶ 31,092 (2000), petitions for 

review dismissed sub nom. Pub. Util. Dist. No. 1 v. FERC, 272 F.3d 607 (D.C. Cir. 2001). 65 EIA Changing Structure, Part II, Chapter 6, pg. 49. 66 There were additional exacerbating factors identified including increased power production costs combined with 

increased demand due to unusually high temperatures and a scarcity of available generation resources throughout 

the West and California in particular and flawed market rules, including restrictions on the ability to forward 

contract , and retail regulatory policies. See Investigation of Practices of the California Independent System Operator 

and the California Power Exchange, 93 FERC ¶61,121 at ¶¶61,354‐355 (2000). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 14 October 8, 2013

retail customers,67 leading to a bankruptcy filing by one of largest utilities in the state.  The state was 

forced to step in and procure the utilities‘ residual power requirements that could not be met by utility‐

retained generation.68 

 

At the wholesale level, the divestiture of rate‐based generating assets made restructured utilities more 

dependent on wholesale purchases.  Even utilities that remained vertically integrated faced uncertainties 

about future state restructuring policy.  This led many to rely on wholesale purchases rather than 

commit new capital to build rate‐based facilities.  At the same time, the development of competitive 

wholesale markets69 brought energy price volatility, leading to uncertainties about the optimal timing of 

purchases.70 

 In the aftermath of the California energy market crisis, FERC took steps to investigate the causes and 

introduce corrective policies.  FERC’s report on the investigation into the California Bulk Power market 

concluded that “the electric market structure and market rules for wholesale sales of electric energy in 

California are seriously flawed” and that these structures led to unjust and unreasonable rates.71  Among 

the remedies ordered by FERC was the elimination of the requirement that Californiaʹs investor‐owned 

utilities sell all of their generation into, and buy all of their energy needs from, the PX.  FERC concluded 

that the buy/sell requirement led to over‐reliance on spot markets and over‐exposure.  The Commission 

also urged buyers to enter into long‐term contracts and not rely only on spot markets.  Furthermore, 

FERC staff was directed to develop a market monitoring and mitigation program to be applied to the 

California wholesale markets. 

 

Following the California energy market crisis and a blackout that affected a large portion of the 

northeastern U.S. and Canada in 2003,72 Congress enacted the Energy Policy Act of 2005 (EPAct 2005) on 

August 8, 2005.73  This legislation provided greater authority to the Commission’s oversight of 

jurisdictional wholesale electricity markets.  EPAct 2005 authorized the Commission to require 

transmission‐owning utilities, except for certain small entities, to provide access to their transmission 

facilities on a comparable basis.  Congress also directed the Commission to facilitate price transparency 

in markets and authorized the Commission to prescribe rules to provide for the dissemination of 

information about the availability and price of wholesale electric energy and transmission service.74  

                                                           67 Retail prices charged by the California utilities were capped at a discount per The Electric Utility Industry 

Restructuring Act Assembly Bill 1890 (AB1890).   68 Cost of Service Regulation, pg. 36. 69 Including open access transmission, market pricing authority, and the introduction of spot markets. 70 Cost of Service Regulation, pg. 36. 71 93 FERC ¶61,121 at ¶61,349.  See also, Staff Report to the Federal Energy Regulatory Commission on Western 

Markets and the Causes of the Summer 2000 Price Abnormalities (November  2000).  72  On August 14, 2003, a series of events lead to a blackout affecting much of the system in the northeastern U.S., 

Canada, and portions of the Midwest.  A team of industry experts concluded that there had been violations of the 

NERC voluntary reliability standards, which resulted in dramatic changes in reliability enforcement.  The 2003 

blackout and its effect on utility regulation are further explained in Section 5. 73 Energy Policy Act of 2005, Pub. L. No. 109‐58, 119 Stat. 594 (2005). 74 EPAct 2005 also resulted in the development of mandatory reliability standards, which is discussed in Section 5. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 15 October 8, 2013

Finally, Congress emphasized compliance with the Commission’s regulations, adopting and increasing 

the civil and criminal penalties for violations of Commission‐administered statutes and regulations. 

At the same time that the wholesale and retail markets were evolving, states were promulgating new 

mandates to improve energy efficiency and demand response.  The growing costs of environmental 

controls resulting from the Clean Air Act and other regulations placed greater pressure on utilities and 

state commissions to adopt alternative cost recovery programs for these targeted expenditures.  In 

addition, the need to replace aging infrastructure and the potential for modernization of the network 

through the use of digital and Smart Grid technology increased.75   

 

To address these challenges, regulators experimented with the use of alternative ratemaking, including 

the use of tracker mechanisms, riders, and other mechanisms to provide cost recovery in a manner that 

was timelier than traditional rate cases.  These mechanisms were useful in cases where the costs of the 

specific activity were identified and recovered as incurred.  The prudence of the associated costs was 

reviewed periodically.  These trackers allowed the timely recovery of costs and maintained the utilities’ 

financial integrity, protecting the level of service provided to customers.  In addition, these mechanisms 

often involved a true‐up process since the process of granting rate increases ahead of the completion of a 

project involves a risk that customers could overpay for the final product.  The true‐up mechanism 

represented an appropriate retroactive method for providing customers a rebate should cost overruns 

occur.76   

 

Similarly, government mandates regarding renewable portfolio standards (RPS) have resulted in new 

costs for wind, solar, and biofuels that may be above market.  These costs have also sometimes been 

treated as a separate cost category for recovery through a rider or adjustment clause mechanism.  The 

tracker mechanisms developed were an attempt by regulators to match rates with costs.  Nevertheless, 

reliance on traditional regulatory tools such as prudence reviews and rate cases continues to serve a 

fundamental role in providing a substitute for market mechanisms to induce efficient behavior or to 

further public policy objectives.77 

 

In February of 2007, FERC issued Order No. 89078 to correct flaws in its pro forma Open Access 

Transmission Tariff (OATT) that had been uncovered during the ten years since Order No. 888 was 

issued.  The Commission recognized that although Order No. 888 had been successful, the need for 

additional reform was apparent to realize its goal of remedying undue discrimination in the wholesale 

marketplace.  The changes introduced in Order No. 890 were intended to: (1) ʺstrengthen the pro forma . . 

.  OATT to ensure that it achieves its original purpose of remedying undue discrimination; (2) provide 

greater specificity to reduce opportunities for undue discrimination and facilitate the Commissionʹs 

                                                           75 Cost of Service Regulation, pg. 39. 76 Ibid., pg. 39. 77 Ibid., pg. 39. 78 Order No. 890 also introduced reforms in transmission planning that were further refined through 

Order No. 1000.  Both of these orders are discussed further in Section 8.  Preventing Undue Discrimination and Preference in Transmission Serv., Order No. 890, FERC Stats. & Regs. ¶ 31,241 (2007), on reh’g, Order No. 890‐A, FERC 

Stats. & Regs. ¶ 31,261 (2007), on reh’g, Order No. 890‐B, 123 FERC ¶ 61,299 (2008), reh’g denied, Order No. 890‐C, 126 

FERC ¶ 61,228 (2009). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 16 October 8, 2013

enforcement; and (3) increase transparency in the rules applicable to planning and use of the 

transmission system.ʺ79  However, FERC retained several core elements of Order No. 888 such as the 

existing division of federal and state jurisdiction including FERCʹs seven factor functional unbundling 

test, native load protection, firm network service, and firm and non‐firm point‐to‐point transmission 

service, and declined to require corporate or structural unbundling, opting instead to retain functional 

unbundling.80  The major reforms included: (1) consistency and transparency of methodologies and 

calculations for available transfer capability (ʺATCʺ); (2) open, transparent, and coordinated 

transmission planning on sub‐regional (local) and regional levels; (3) transmission pricing reforms; (4) 

increased efficiency of transmission grid utilization; (5) increased transparency and customer access to 

information; (6) enhanced compliance and enforcement efforts; and (7) revisions to non‐rate terms and 

conditions of transmission service.81  Complementary to the wholesale market reforms introduced in 

Order No. 890, in June of 2007, the Commission issued Order No. 697 to clarify and codify its market‐

based rate policy.82 

 

During the autumn of 2008, large disruptions in the financial markets affected the credit markets and 

reduced the availability of credit.  The electricity markets were vulnerable to the effects of this broader 

financial crisis.  Defaults in certain markets within the PJM RTO spurred a need for credit reforms as the 

threat of defaults form larger market participants raised concerns.  In Order No. 741, the Commission 

proposed extensive revisions to its policy on RTO/ISO credit practices.83   

 

                                                           79 Ibid., preamble summary. 80 Ibid. 81 Ibid. 82 See Market‐Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, Order 

No. 697, FERC Stats. & Regs. ¶ 31,252, clarified, 121 FERC ¶ 61,260 (2007), order on reh’g, Order No. 697‐A, FERC Stats. 

& Regs. ¶ 31,268, clarified, 124 FERC ¶ 61,055, order on reh’g, Order No. 697‐B, FERC Stats. & Regs. ¶ 31,285 (2008), 

order on reh’g, Order No. 697‐C, FERC Stats. & Regs. ¶ 31,291 (2009)..  The Order presented an up‐front analysis to 

determine whether market‐based rates should be granted and if a market‐based rate seller or any of its affiliates has 

market power in generation or transmission, whether that market power had been mitigated.  The order also 

established two classes of MBR sellers: Category 1 sellers (anyone below 500 MW in that market) are generally 

exempt from submitting triennial market power studies and Category 2 sellers (all others) must continue to file 

triennial studies.  The Commission also took the opportunity to clarify its interpretation of several decisions by the 

United States Court of Appeals that may have created uncertainty for sellers transacting pursuant to its market‐

based rate program.  The Commission affirmed its position that an ex ante finding of the absence of market power, 

coupled with the EQR filing and effective regulatory oversight, qualifies as sufficient prior review for market‐based 

rate contracts to satisfy the notice and filing requirements of FPA section 205. 83 The Commission proposed the following reforms related to the administration of credit in the organized markets: 

(1) implementation of a billing period of no more than seven days and a settlement period of no more than seven 

days; (2) reduction in the allocation of unsecured credit to no more than $50 million per market participant and a 

further aggregate cap per corporate family; (3) elimination of unsecured credit for FTR markets, (4) clarification of 

the ISOs’/RTOs’ status as a party to each transaction so as to eliminate any ambiguity or question as to their ability 

to net and manage defaults through the offset of market obligations; (5) establishment of minimum criteria for 

market participation; (6) clarification of when the ISO or RTO may invoke a “material adverse change” clause in 

requiring additional collateral; and (7) establishment of a standard grace period to “cure” collateral calls.  See Credit 

Reforms in Organized Wholesale Electric Markets, Order No. 741, FERC Stats. & Regs. ¶ 31,317 (2010), order on reh’g, 

Order No. 741‐A, FERC Stats. & Regs. ¶ 31,320 (2011), order denying reh’g, Order No. 741‐B, 135 FERC ¶ 61,242 (2011). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 17 October 8, 2013

In Congress, additional actions were taking place in response to the 2008 financial crisis.  While initially 

directed towards financial institutions, the Dodd‐Frank Act had the potential to affect energy trading 

companies and wholesale energy markets.  Entities categorized as swap dealers or major swap 

participants faced new capital, margin, and reporting requirements.  While entities that qualified as 

“end‐users” of physical energy like utilities and energy producers84 could apply for individual 

exemptions, trade by trade, the process could be extremely bulky and burdensome.85  One serious 

question left open was whether power purchase agreements for delivery within ISO regions that act as 

brokers for all trades, such as NYISO or PJM, would qualify as exempt transactions.  In February of 2012, 

the Commission‐approved RTO/ISOs86 filed a petition with the Commodity Futures Trading 

Commission (CFTC) for an exemption for certain transactions in their organized markets regulated by 

FERC or the Public Utility Commission of Texas (PUCT).  The CFTC issued its final RTO/ISO Order on 

March 28, 2013, which would exempt from CFTC regulation Specific Electric‐Related Product 

transactions in the following markets: Financial Transmission Rights (FTRs); Energy Transactions in 

Day‐Ahead and Real‐Time Markets; Forward Capacity Transactions; and Reserve or Regulation 

Transactions.87  This exemption applies when the purchase or sale of the above‐listed Specific Electric‐

Related Products is executed in an RTO/ISO market pursuant to a FERC or PUCT‐approved tariff.88 

 

                                                           84 A company that can prove it uses swaps solely for the purpose of hedging against price fluctuations may qualify 

as an end user, exempting it from some of the actʹs requirements. 85 Qualifying will depend, among other things, on the number of swaps traded, who the counterparties are, and the 

aggregate amount traded in a given period. 86 California Independent Service Operator Corporation (CAISO), PJM Interconnection (PJM), Midwest Independent 

Transmission System Operator (MISO), ISO‐New England (ISO‐NE), New York Independent System Operator 

(NYISO) and ERCOT. 87 Final Order in Response to a Petition From Certain Independent System Operators and Regional Transmission 

Organizations To Exempt Specified Transactions Authorized by a Tariff or Protocol Approved by the Federal 

Energy Regulatory Commission or the Public Utility Commission of Texas From Certain Provisions of the 

Commodity Exchange Act Pursuant to the Authority Provided in the Act, 78 Fed. Reg. 19880 (Apr. 2, 2013) (“CFTC 

RTO/ISO Final Order”). 88 The CFTC declined to delineate specific transactions that qualify for the RTO/ISO exemption and also declined 

requests to expand the exemption to cover transactions that are “outgrowths of,” or “economically comparable to,” 

the specific Electric‐related Products. The CFTC clarified that virtual and convergence bids and offers in Day‐Ahead 

Markets are exempt “energy transactions,” and that exempt energy transactions may be cash settled.  CFTC 

RTO/ISO Final Order, 19886. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 18 October 8, 2013

Today, the centralized wholesale markets that have been approved by FERC are California ISO, ISO 

New England, New York ISO, Pennsylvania, New Jersey, Maryland (PJM) (official name is PJM 

Interconnection), Southwest Power Pool, and the Midwest ISO.  In addition, the ERCOT (Texas) market 

runs under the authority of the Texas PUC.  The current state of the centralized wholesale market 

development across the U.S. is shown in the diagram below. 

 

Figure 6. Regional Transmission Organizations 

 Source: http://www.ferc.gov/industries/electric/indus‐act/rto.asp 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 19 October 8, 2013

The current state of retail choice in the U.S. is shown in the graphic below. 

 

Figure 7. Status of Electricity Restructuring (Retail Choice) by State 

 Source: http://www.eia.gov/cneaf/electricity/page/restructuring/restructure_elect.html. 

 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 20 October 8, 2013

4.  Today’s Two Broad Models  

At the wholesale level, there are two approaches, centralized generation markets and traditional bi‐

lateral markets.  Similarly, there are two approaches at the retail level; the traditional vertically 

integrated approach and retail choice.  While regions adopting a centralized market model often also 

provide some form of retail choice, this is not necessarily a general rule.  The variation under the two 

general approaches is shown in Table 1. 

 

Table 1. Wholesale and Retail Market Structure by State 

Centralized Wholesale Market Bilateral Wholesale Market

Vertically Integrated Utility AR*, CA, IA*, IN, KS, KY*, LA*, MN, MO, MT*, ND*, NE*, NM*, OK, SD*, VA, VT, WI, WV

AK, AL, AZ, CO, FL, GA, HI, ID, MS, NC, NV, SC, TN, UT, WA, WY

Retail Choice CT, DE, IL, MA, MD, ME, MI, NH, NJ, NY, OH, OR, PA, RI, TX

Note: Asterisked states are partially in Centralized and Bilateral Markets

4.1  Current Status of Centralized Wholesale Generating Markets 

4.1.1  Todays’ Centralized Wholesale Generating Markets  

Consumers’ energy costs include a wholesale cost component consisting of the costs of transmission and 

energy.89  As previously noted, traditional vertically integrated utilities can operate within both 

centralized wholesale energy markets and traditional bilateral markets; however, restructured utilities 

with customer choice are closely linked to organized wholesale energy markets. 

Energy markets primarily refer to wholesale markets for generation.  While transmission is necessary 

and becomes a part of the delivered cost of the energy, utility transmission is a regulated service 

provided at cost of service rates.90  A number of regions—including the Northeast, Mid‐Atlantic, much 

of the Midwest, the Electric Reliability Council of Texas (ERCOT), and California—organize their energy 

                                                           89 See Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953 (1986) (State cannot disallow a wholesale rate that the 

FERC has set as just and reasonable); see also Mississippi  Power v. MISS. Ex Rel. Moore, 487 U.S. 354 (1988).  But see, 

Pike County Light & Power Co. v. Pennsylvania Public Service Commission, 465 A.2d 735, 738 (1983) ((State can review 

prudency of a utility choosing between two choices to purchase power). 90 FERC requires that public utilities that own transmission lines used in interstate commerce offer transmission 

service on a nondiscriminatory basis to all eligible customers.  The price for the service is cost‐based and published 

in the OATT.  See Office of Enforcement, Federal Energy Regulatory Commission, Energy Primer: A Handbook of 

Energy Market Basics, A staff report of the Division of Energy Market Oversight,  (July 2012), pp. 57 and 62 (“Energy 

Primer: A Handbook of Energy Market Basics”).  Merchant transmission providers may in some cases provide 

service at negotiated rates that are not cost‐based.   

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 21 October 8, 2013

markets under an ISO or RTO.  Most states in these regions also allow retail competition.91  Other 

regions of the United States, including the Southeast and West, excluding California, have chosen to 

retain the traditional regulatory model.  Under this regime, vertically integrated utilities and certain 

public power entities retain functional control over both the transmission systems and generation 

dispatch. 

4.1.2  Energy Markets 

The centralized wholesale energy markets in the U.S. pay a uniform clearing price to all generators 

bidding in the market, which is intended to encourage generators to offer their electricity at the 

”margin,” their break‐even point for variable costs.92 

 

Most of the centralized wholesale energy markets in the U.S. have implemented what is known as 

locational marginal pricing (LMP) or nodal pricing.  Examples include the PJM Interconnection, ERCOT, 

New York, and New England markets.  The table below lists the markets and their key attributes.  In an 

LMP market, the bids/offers submitted by market participants are used to determine the prices of 

electricity at each node on the network.93  The nodal price is the highest priced bid that is dispatched to 

meet load in any hour and all successful bidders are paid this nodal or LMP price.  Where constraints 

exist on a transmission network,94 more expensive generation may be dispatched on the downstream 

side of the constraint, resulting in a price separation on either side of the constraint.  This results in what 

is termed congestion pricing or constraint rents.95  Some systems also account for marginal losses in the 

nodal price calculation.  Depending on the market, price settlements occur day‐ahead, hourly, or in real‐

time. 

 Some of the centralized wholesale energy markets have also developed capacity markets to ensure there 

is sufficient generation to meet reliability requirements.  In addition, the central markets also typically 

include ancillary service markets to meet other reliability requirements such as voltage support, and 

financial hedging devices called Financial Transmission Rights (FTRs) or Transmission Congestion 

Contracts (TCCs), which enable market participants to manage transmission congestion risks and costs. 

                                                           91 Approximately two‐thirds of the nation’s electricity load is served in RTO regions.  See Energy Primer: A 

Handbook of Energy Market Basics, pg. 42. 92 The alternative approach (not adopted in any U.S. market) is a pay‐as‐bid market, which encourages generators to 

offer their electricity at the expected market price. 93 From the bids/offers, the theoretical price of electricity at each node on the network is calculated as a ʺshadow 

price.ʺ  The shadow price reflects the hypothetical incremental cost to the system from an optimized dispatch of 

available units to meet one additional kilowatt‐hour of demand at the node in question. 94 Transmission systems are operated to allow for continuity of supply even if a contingent event, like the loss of a 

line, were to occur. This is known as a security constrained system. 95 If the lowest‐priced electricity can reach all locations, prices are the same across the entire grid. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 22 October 8, 2013

Table 2. Centralized Markets and their Attributes 

Market Key Elements

California ISO (CAISO) (established 1996)

Energy market: three-settlement (day ahead, hour ahead, and real time). Spot market with locational marginal pricing

Ancillary services, and Financial Transmission Rights market

Midcontinent ISO (MISO) (established 2002 as Midwest ISO)

Administers a two-settlement (day ahead and real-time) energy market known as the Day-2 market. It produces hourly locational marginal prices that are rolled up into 5 regional hub prices.

Also administers a monthly financial transmission rights (FTR) allocation and auction MISO bilateral trading is active on the IntercontinentalExchange (ICE) at the Cinergy

Hub and Northern Illinois Hub. Voluntary annual and monthly capacity auction

ISO New England (ISO-NE) (established 1997)

Energy market: two-settlement (day ahead and real-time) spot market with locational marginal pricing (an internal hub, eight load zones, and more than 500 nodes)

Capacity market Forward reserves market Regulation market, and financial transmission rights market

New York ISO (NYISO) (established 1999)

Energy market: two-settlement (day ahead and real-time) spot market with locational marginal pricing

Regional and locational capacity market with deliverability requirement Financial transmission rights market Market participants trade electricity bilaterally through brokers, the ICE, and the New

York Mercantile Exchange’s (NYMEX) ClearPort, using NYISO zones as pricing points but bilateral deals that go physical must be scheduled with the ISO.

PJM Interconnection (PJM) Energy market: two-settlement (day ahead and real-time) spot market with locational marginal pricing (prices are calculated at each bus every five minutes)

Capacity markets with deliverability requirement Ancillary services markets Financial transmission rights market Energy and capacity in the region are also traded bilaterally through brokers and the

ICE

Southwest Power Pool (SPP) (granted RTO status in 2004)

Market participants trade physical electricity bilaterally, either directly or through brokers, and through the energy imbalance service (EIS) market.

ERCOT Administers the Texas competitive retail market Operates wholesale markets for:

o Balancing energy o Ancillary service markets with zonal congestion management

Source: Information in this table obtained from the Federal Energy Regulatory Commission website available at: 

http://www.ferc.gov/market‐oversight/mkt‐electric/overview.asp 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 23 October 8, 2013

4.2 Bilateral Wholesale Generation

Unlike transactions in the RTO/ISO energy markets, in bilateral transactions, buyers and sellers know 

the identity of the party with whom they are doing business.96  Bilateral transactions may occur through 

direct contact and negotiation, through a broker or through an electronic brokerage platform, such as the 

Intercontinental Exchange (ICE).97 Bilateral transactions range from standardized contract packages, to 

customized, complex contracts known as structured transactions.98 

 

Traditional wholesale electric markets exist primarily in the West (other than California) and Southeast.  

In these traditional wholesale markets, utilities continue to be responsible for system operations and 

management, and, typically, for providing power to retail consumers.99  Nearly all the wholesale 

transactions in the Southeast are done bilaterally.  Long‐term energy transactions are common, and 

transaction durations for a year or more outweigh spot transactions.  Furthermore, many long‐term 

agreements involve full‐requirements contracts or long‐term purchase power agreements.100  Bilateral 

transactions also predominate among entities in the West, other than California.  Those entities also sell a 

small amount of power into the California ISO’s market.101 

4.3  Today’s Retail Choice Status 

Two models are currently employed in the United States to deliver electric power to retail consumers.  

The traditional model is the Vertically Integrated Utility where various services are “bundled”, which is 

defined by the U.S. Energy Information Administration (EIA) as “a means of operation whereby energy, 

transmission, and distribution services, as well as ancillary and retail services, are provided by one 

entity.”102  Under this model, the energy provided by the utility may be provided by its own generation 

or procured from others, generally in bilateral wholesale transactions.  Many non‐vertically integrated, 

government‐owned and cooperative entities also operate in a “vertically integrated mode” using jointly 

owned transmission and generation.  In contrast, there are regions where utility restructuring has 

occurred and retail choice103 is available for a large number of customers.  The second market model 

                                                           96 See Energy Primer: A Handbook of Energy Market Basics, pg. 64.  While bilateral transactions between two parties 

do not occur through an RTO, some bilateral activity occurs in areas where there are RTOs/ISOs. 97 Ibid., pg. 60. 98 Ibid.,  pg. 60. 99 Id., pg. 63. 100 Ibid., , pg. 73. 101 The West includes the Northwest Power Pool (NWPP), the Rocky Mountain Power Area (RMPA) and the 

Arizona, New Mexico, Southern Nevada Power Area (AZ/NM/SNV) within the Western Electricity Coordinating 

Council (WECC), a regional entity. 102 U.S. Department of Energy – Energy Information Administration, 

http://www.eia.gov/tools/glossary/?id=electricity. 103 Retail choice is a regulatory mandate to allow retail customers to use a utilityʹs transmission and distribution 

facilities to move bulk power from one point to another on a nondiscriminatory basis for a cost‐based fee.”   U.S. 

Department of Energy – Energy Information Administration, http://www.eia.gov/tools/glossary/?id=electricity. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 24 October 8, 2013

often involves centralized, bid‐based wholesale generation markets.  This paper generally refers to the 

second model as the “retail choice” model.104 

 

As of the writing of this report, 15 states and the District of Columbia have adopted electric retail choice 

programs that allow end‐use customers to buy electricity from competitive retail suppliers.105   

Overall, competitive retail suppliers provided 16% of total U.S. retail sales by volume in 2010.106  

4.4  Cost‐Based Rates and Traditional Utility Regulation 

The traditional mode of regulation in the United States is cost‐based, which permits the utility to 

establish prices that will recover prudent operating costs and provide an opportunity to earn a 

reasonable rate of return on the property devoted to the business.  The goals of cost‐based utility pricing 

are as follows:107 

1. Attracting investment capital at a reasonable cost 

2. Reasonable prices for electric service 

3. Efficiency incentive 

4. Demand control 

5. Revenue generation 

 

Cost‐based ratemaking is not without its criticisms.  The most frequent criticism of cost‐based 

ratemaking is that an incentive exists to over‐invest in capital‐intensive projects because the utility’s 

income is derived by investment (Averch‐Johnson Behavior).108  Cost‐based regulation is also sometimes 

criticized because it fails to provide utilities with an incentive to operate efficiently. 

4.5  The Retail Choice Model 

Inasmuch as the retail choice model is relatively immature (less than 15 years old in most jurisdictions), a 

number of criticisms have emerged.  First, participation in retail markets in many jurisdictions has been 

anemic due to a lack of incentives (i.e., lower prices) or information.  Second, in some jurisdictions, 

market design issues have led to price spikes which have negatively affected consumers. 

                                                           104 The descriptions of the “traditional” vs. “retail choice” reflect simplifying assumptions.  There are vertically 

integrated utilities that operate in areas with bid‐based markets.  Similarly, in some areas, limited customer choice 

has been made available to large commercial or industrial customers and no bid‐based market may exist.  The 

“Retail Choice” model generally refers to the utility and market structure that exists as a result of broad retail choice 

for the customers of a number of utilities in a given region.   105 http://www.eia.gov/electricity/policies/restructuring/restructure_elect.html 106 U.S. Energy Information Administration (“EIA”), State electric retail choice programs are popular with 

commercial and industrial customers (May 14, 2012), 

http://www.eia.gov/todayinenergy/detail.cfm?id=6250#tabs_RenewablesMaps‐1.  This website has a map of U.S. and 

identifies by region Sales for Retail choice vs. default services. 107 James Bonbright, Albert Danielsen and David Kamerschen, “Principles of Public Utility Rates, Public Utilities 

Reports, Incorporated” (1988), pg. 11‐2. 108 Harvey Averch and Leland Johnson, “Behavior of the Firm Under Regulatory Constraint”, American Economic 

Review (1962). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 25 October 8, 2013

At the height of the utility restructuring movement in the 1990s, nearly half of the states were 

considering retail choice in one form or another.  California and several northeastern states led the way, 

in many cases requiring investor‐owned utilities divest some or all of their generation, which was 

required for different reasons based upon the jurisdiction.  Common reasons for divesture of generation 

included: (1) mitigation of perceived market power; and (2) quantification of the value of these assets for 

the purposes of determining stranded investment.   

 

After the California energy crisis in 2001, however, some states, including California, abandoned these 

efforts.  There are currently only 15 states plus the District of Columbia that permit all customers to 

choose an energy supplier.109 

 

The restructuring efforts were contentious, with utilities arguing that they (and their shareholders) 

would be left with “stranded costs” (i.e., generation and other investments made in anticipation of 

needing to serve the load within their footprints that would not be recovered when exposed to market 

prices).  These issues were resolved in various ways, including by the addition of transition cost adders 

to electricity delivery charges with or without securitization arrangements.110  Residential rate freezes or 

reductions were also mandated in some cases to provide an immediate benefit to smaller consumers.  In 

some states, utilities and regulators wrestled over Provider of Last Resort (POLR)111 rates and supply to 

ensure that all customers would continue to have access to service, while at the same time fostering 

competition. 

 

Utilities that no longer own generation and retain an obligation to serve under a POLR requirement 

must procure power in wholesale transactions, either through bilateral arrangements or market 

purchases.  The cost of power, like other utility costs, is subject to review for reasonableness.  FERC rules 

require careful scrutiny of sales of power between utilities and their affiliates.112  At least one state, 

Illinois, has partially taken over the role of power procurement for the utility’s electric supply customers.  

However, more recently, municipal aggregation (where the municipality negotiates a purchase power 

agreement on behalf of the residents of the community) is increasingly replacing the state’s role as an 

electric power supplier. 

                                                           109 http://www.eia.gov/electricity/policies/restructuring/restructure_elect.html   110 Securitization arrangements allowed the issuance of binds or other similar financial instruments, which were 

secured with a property right to a non‐bypassable revenue. 111 A POLR is a default provider who provides service to customers who do not elect to secure power supply 

through a retail electric supplier. 112 Cross‐Subsidization Restrictions on Affiliate Transaction, Order No. 707, 73 FR 11013 (Feb. 29, 2008), FERC Stats. 

& Regs. ¶ 31,264 (Feb. 21, 2008) (Affiliate Transactions Final Rule), order on rehearing, Order No. 707‐A, 73 FR 43072 

(July 24, 2008), FERC Stats. & Regs. ¶ 31,272 (2008) (Affiliate Transactions Final Rule Rehearing);  Order No. 697 

(Market‐Based Rate Final Rule). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 26 October 8, 2013

4.6   Differences Between the Traditional and Retail Choice Models 

In both the Vertically Integrated and Retail Choice regulatory models the distribution and transmission 

functions are price regulated, generally using some variant of cost‐based pricing.  No jurisdiction in the 

United States has seriously entertained the notion of retail competition for distribution facilities.113  

 

The primary difference in the Vertically Integrated and Retail Choice regulatory models lies in is the 

treatment of the generation function, as discussed below. 

1. Generation Planning and Construction 

2. Vertically Integrated Utilities 

 

Traditionally, regulated utilities engage in generation system planning as part of their day‐to‐day 

business functions.  The objective of regulated generation system planning is to provide customers with 

reliable electric service at the lowest long‐run price.  Generation system planning generally considers the 

following variables in making generation decisions: (1) the cost of new generation technology or 

available wholesale market purchases; (2) what costs would be incurred to retain existing generating 

units in service; (3) expectations regarding the future costs of generator fuels (e.g., coal, natural gas, and 

petroleum products); (4) the impacts of existing and future environmental rules; (5) the delivery costs 

associated with generation siting options, and (6) expectations regarding the demand for new load.  The 

utility management performs analyses that typically rely upon complex simulations to ascertain which 

combinations of new and existing generation and transmission system improvements will provide for 

the goal of safe and reliable generation service at the lowest reasonable cost.  This process is referred to 

as integrated resource planning.  Once the decisions of the system planning are completed, the costs 

associated with those decisions are recovered from customers through regulated prices. 

4.6.1  Retail Choice Markets 

In contrast to vertically integrated utilities, the retail choice regulatory model relies solely upon 

competitive energy markets to provide customers with generation services.  Generation is constructed 

by independent power producers (IPPs) who rely upon the market to provide revenue streams in 

exchange for their investments and are therefore subjected to market risk.  Although market design 

varies from jurisdiction to jurisdiction, customers are generally served by retail electric suppliers (RESs) 

licensed to operate in that jurisdiction or through a POLR mechanism for customers who either do not 

elect to choose a retail power marketer or do not have the ability to choose a retail power marketer.  The 

latter case includes a number of jurisdictions that have abandoned the vertically integrated model but 

have not provided all customers with the ability to contract directly with a retail power marketer. 

 

Retail choice markets do not require that any organized planning process be adhered to when 

introducing new generation into the electric power system.  Developers purchase existing assets or 

develop new projects based upon expectation of future market prices.  

 

                                                           113 There are a few exceptions, including the competition which exists between First Energy and Cleveland Public 

Power in certain areas of Cleveland, Ohio. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 27 October 8, 2013

A critical difference in retail choice markets is the existence of retail power marketers.  Retail power 

marketers procure electric power either through owned assets or transactions on wholesale power 

markets to supply customers on a contractual basis.   

4.6.2  Pricing for Generation Services 

Vertically integrated utilities receive a regulated return for bundled (generation, transmission, and 

distribution) services.  Although the nuances of regulated ratemaking differ from jurisdiction to 

jurisdiction, most states have adopted some variation of rate‐of‐return ratemaking.   

 

Pricing in retail choice states is “market based” for generation or power supply service and not cost‐

based.  If the generation service is provided by a retail electric service provider, prices are determined 

competitively based upon an arm’s‐length agreement.  In most cases the retail electric supplier may not 

be accessing physical generation resources directly and instead will reply upon financial instruments 

tied to the electric power market to provide price certainty.   

 

A significant proportion of the load in many retail choice jurisdictions is served by default providers, 

who provide service to customers who do not elect to secure power supply through a retail electric 

supplier.  Default providers are generally secured through a competitive solicitation such as a request for 

proposals (RFP) or auction.  Furthermore, many states listed as retail open access jurisdictions restrict the 

competitive shopping option to certain customers (e.g., Michigan). 

 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 28 October 8, 2013

5.  System Reliability 

Reliability standards or criteria used for planning and operations are an integral part of the electric 

power industry and have been since the very first systems were developed in the late nineteenth 

century.  As power systems grew in complexity and evolved into the large synchronous interconnections 

of today, these standards have become increasingly important.114 

 

There are two components to Bulk Power System (BPS) reliability—resource adequacy and transmission 

security.  Resource adequacy ensures adequate generation or demand response to meet expected peak 

loads plus a reserve.  Transmission security ensures reliable system operation in the face of 

contingencies, loss of generation or transmission.115  Planning authorities must construct facilities to 

meet both of these identified reliability needs.   

 

FERC regulates wholesale markets in centralized market regions where markets are the source of the 

new resources to meet resource adequacy needs.  In these regions, the RTOs/ISOs and FERC are facing 

challenges of aligning transmission planning with procurement of market‐driven solutions (generation, 

demand response) to induce the most efficient outcome.  There is also the struggle between the states, 

which have historically had regulatory responsibility for assuring generation resource adequacy for 

retail electric customers.  FERC has provided oversight of resource adequacy under FERC open‐access 

tariffs and in competitive markets, and in some cases FERC oversight has conflicted with state resource 

planning objectives. 

 

FERC also oversees the North American Electric Reliability Corporation (NERC) as the Electric 

Reliability Organization (ERO) under the Federal Power Act.  In turn, NERC delegates compliance 

monitoring and enforcement oversight to its eight Regional Entities.  In states with vertically integrated 

companies, states oversee a utility’s resource planning and procurement, and the siting of jurisdictional 

power plants.  States generally must approve the siting of jurisdictional transmission lines and 

equipment. 

 

Under this shared jurisdictional framework, the states and FERC work to ensure the bulk power system 

(BPS) is designed and operated in a reliable manner.116 

5.1  Development of the Mandatory Reliability Standards 

Throughout most of the twentieth century, increased system interrelation took place.  By the early 1960s, 

power systems in most of the United States and Canada had formed into four large synchronous 

                                                           114 See Kenneth Lotterhos and Celia David, NERC and Mandatory Electric Reliability Compliance, Lexis (Apr. 2011), 

Ch2, pg. 3 (“NERC and Mandatory Electric Reliability Compliance”). 115 See NERC and Mandatory Electric Reliability Compliance, Ch2, pg. 1. 116 See Advanced Energy Economy, U.S. Electric Power Industry ‐ Context and Structure (Nov. 2011), Figure 6. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 29 October 8, 2013

interconnections or “grids.”117  During this period, individual power systems each developed and 

applied their own criteria for reliability.   

 

With the 1965 Northeast Blackout, it was plain to see that a more coordinated approach was necessary.  

Following the 1965 blackout, the North American Electric Reliability Council, which later became 

NERC,118 and Regional Reliability Councils, which later became the Regional Entities, formed.119  The 

U.S. systems also formed two new power pools: the New England Power Pool and the New York Power 

Pool.120  Across the nation systems came together to establish regional reliability councils, until 

collectively they encompassed essentially all of the continental U.S. and Canada.121 

 

Subsequent blackouts on the East Coast in July 1977 and the West Coast in July and August of 1996 

further underscored the need for greater coordination and adherence to the existing reliability standards.  

A common cause of these three major regional blackouts was violation of NERC’s voluntary Operating 

Policies and Planning Standards.122  The Northeast Power Coordinating Council (NPCC) adopted 

criteria that incorporated the NERC standards, but also established stricter requirements recognizing the 

impact on the nation’s economy and finances with the loss of New York City.  Compliance with the 

NPCC criteria was made mandatory for NPCC members by contract, while the NERC standards were 

still voluntary.123 

 

In response to the West Coast July and August 1996 cascading outages, the Secretary of Energy 

convened a task force to advise the U.S. Department of Energy (DOE) on maintaining the reliability of 

the BPS.  The task force recommended, among other things, that federal legislation should grant more 

explicit authority for the Commission to approve and oversee an organization having responsibility for 

bulk‐power reliability standards and that FERC be given jurisdiction over reliability of the BPS.124  This 

                                                           117 See NERC and Mandatory Electric Reliability Compliance, Ch2, pg. 3. 118 The systems that had been affected by the blackout formed the Northeast Power Coordinating Council (NPCC), 

the Regional Entity for the northeast portion of the U.S and Eastern Canada.  See NERC and Mandatory Electric 

Reliability Compliance, Ch2, pg. 5.  One of NERC’s roles was to establish overall reliability criteria. NERC’s original 

planning criteria were general in nature – guidelines as to what topics the regional councils should address in their 

own criteria. Another of NERC’s purposes was to provide a forum for the discussion of reliability issues. NERC 

adopted NAPSIC’s bulk‐power system protocols, including the now familiar N‐1 system contingency design, and 

operating criteria that continue to be used in operating the bulk power system.  Ibid., Ch2, pp. 5‐6. 119 The primary role of the regional reliability councils was to establish and maintain uniform reliability criteria to be 

applied in the planning and operation of their respective bulk‐power systems.  Each also developed procedures for 

assessing conformance.   Ibid., Ch2, pg. 6. 120 As deregulation proceeded in the Northeast, these evolved into Independent System Operators —New England 

(ISO‐NE) and the New York ISO. Both became constituent areas of NPCC. 121 Individual systems and power pools sometimes developed their own more detailed or more stringent criteria, but 

they were always responsible for adherence to the regional criteria as a minimum. See NERC and Mandatory Electric 

Reliability Compliance, Ch2, pg. 6. 122 Ibid., Ch2, pg. 6.  See also, http://blackout.gmu.edu/archive/a_1977.html. 123 See NERC and Mandatory Electric Reliability Compliance, Ch2, pg. 7. 124 Secretary of Energy Advisory Board, U.S. Department of Energy, Maintaining Reliability in a Competitive U.S. 

Electricity Industry, Final Report of the Task Force on Electric System Reliability (September 1998), pp. 25‐27, 65‐67. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 30 October 8, 2013

laid the groundwork for the eventual adoption of legislation that enacted the mandatory reliability 

enforcement structure that exists today.125 

 

On August 14, 2003, a series of events led to a blackout affecting much of the system in the northeastern 

U.S., Canada, and portions of the Midwest.  A team of industry experts concluded that there had been 

violations of the NERC voluntary reliability standards.  This conclusion resulted in dramatic changes in 

reliability enforcement.126  On August 8, 2005, the Electricity Modernization Act of 2005, which is Title 

XII of the Energy Policy Act of 2005, was enacted into law.127  EPACT 2005 eliminated the voluntary 

nature of the NERC reliability guidelines, charged FERC with ultimate oversight of electric reliability of 

the BPS, and established an independent ERO to develop mandatory reliability standards subject to 

FERC approval, monitor industry participants’ compliance to these standards, and levy penalties for 

non‐compliance up to one million dollars per day per violation for the most serious violations.128  The 

EPACT 2005 language was based on a report by the National Energy Policy Development Group that 

recommended enforceable reliability standards by a “self‐regulatory organization subject to FERC 

oversight.”129 

 

                                                           125 See NERC and Mandatory Electric Reliability Compliance, Ch2, pg. 7. 126 Ibid., Ch2, pg. 8, citing, U.S.‐Canada Power System Outage Joint Task Force’s Final Report on the August 14, 2003 

Blackout in the United States and Canada: Causes and Recommendations (April 2004).  127 Similar actions have been taken by the regulatory authorities in the Canadian Provinces and Mexico. 128 See NERC and Mandatory Electric Reliability Compliance, Ch2, pg. 8. 129 National Energy Policy Development Group, National Energy Policy (May 2001), pg. 7‐6. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 31 October 8, 2013

Figure 8. NERC Regions130 

 

5.2  Transmission Reliability 

5.2.1  The NERC Standards and Who Must Comply 

The Reliability Standards are grouped into 14 broad categories relating to bulk‐power system operations 

and planning.  Each standard describes what measures are to be completed, who by registered entity 

function must complete them, and how compliance will be measured.131 

 

Currently, there are 102 Reliability Standards with over 1,300 requirements applicable and mandatory in 

the U.S., not including the nine regional standards that have been approved and that are only applicable 

                                                           130 Source: North American Electric Reliability Corporation website available at 

http://www.nerc.com/AboutNERC/keyplayers/Documents/NERC_Regions_BW_072512.jpg. 131 See NERC and Mandatory Electric Reliability Compliance, Ch5, pg. 51.  

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 32 October 8, 2013

in the specific Regions.132  A standard is not mandatory and enforceable in the United States unless it has 

received approval by FERC.133 

 

Within the United States, other than Alaska and Hawaii, all users, owners, and operators of the BPS134 

must comply with the reliability standards developed by the ERO.135  The ERO’s compliance registry 

process is used to identify the set of entities that are responsible for compliance with a particular 

Reliability Standard.136  The applicability section of a particular Reliability Standard determines the 

applicability of each Reliability Standard.137 

 

A clear definition of the term Bulk Electric System (BES)138 is essential to defining the scope and 

applicability of the mandatory reliability standards and is a part of the NERC entity registration process.  

The definition establishes which particular facilities will be subject to the reliability standards and, 

therefore, has a direct impact on determining which entities must register under the NERC Functional 

Model.  The definition of the BES does not include facilities used in the local distribution of electric 

                                                           132 NERC has been working to reduce this number of standards and in February NERC filed a petition to retire 34 

requirements within 19 Reliability Standards.  FERC has not yet ruled on this filing but NERC issued a guidance 

statement instructing Regional Entities to cease actively monitoring compliance to these requirements.  See NERC 

Guidance for Compliance Monitoring and Enforcement Pending Retirement of Standards and Requirements 

Pursuant to Paragraph 81 (Apr. 9, 2013).  NERC is also pursuing other efforts to eliminate standards that do not 

improve the level of BPS reliability and improve the overall standards development process. 133 16 U.S.C. §824o(d)(1); 18 C.F.R. §39.5; Mandatory Reliability Standards for the Bulk‐Power System, Order No. 693, 

FERC Stats. & Regs. ¶ 31,242 at P 26, order on reh’g, Order No. 693‐A, 120 FERC ¶ 61,053 (2007) (explaining “the ERO 

must file each of its Reliability Standards and any modification thereto with the Commission”). 134 In Order No. 743, FERC the Commission clarified that the term Bulk Power System (BPS), used in the FPA, was 

distinct and more expansive than the NERC‐defined term, BES, which determines the enforcement applicability of 

the Reliability Standards.  See Revision to Electric Reliability Organization Definition of Bulk Electric System, 133 

FERC ¶ 61,150 (Order No. 743) (Nov. 2010) at P 36. 135 See Federal Power Act § 215(b), 16 U.S.C §844o(b); 18 C.F.R § 40.1. Note applicability also extends to entities 

described under 201(f) of the FPA. Section 201(f) of the FPA generally exempts the United States, a state or any 

political subdivision of a state, an electric cooperative that receives financing under the Rural Electrification Act of 

1936 (7 U.S.C. 901 et seq.) or that sells less than 4,000,000 megawatt‐hours of electricity per year from Part II of the 

FPA.  See also 18 C.F.R §§ 39.2, 40.1(a). 136 Order No. 693 at PP 92‐101. 137 Ibid., P 127. 138 On November 18, 2010, the Commission issued Order No. 743 directing NERC to revise the definition of “bulk 

electric system” and also required NERC to provide an exemption process.  See Revision to Electric Reliability 

Organization Definition of Bulk Electric System, 133 FERC ¶ 61,150 at PP 112‐113 (Order No. 743) (Nov. 2010).  

NERC has filed and FERC has approved the definition with minimal changes.  See Revision to Electric Reliability 

Organization Definition of Bulk Electric System, 141 FERC ¶ 61,236 (Order No. 773 FINAL RULE) (Dec. 2012); order 

on reh’g, 143 FERC ¶ 61,053 (Order No. 773‐A) (Apr. 2013).  The implementation date is set for July 1, 2014. See 

Revision to Electric Reliability Organization Definition of Bulk Electric System, 143 FERC ¶ 61,231 (Order on 

Extension) (June 13, 2013). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 33 October 8, 2013

energy.139  However, what constitutes local distribution was never defined by Congress and it has since 

been left to the Commission, as made clear in Order No. 773.140 

5.2.2  Role of the Registered Entities and States 

As discussed above, all users, owners, and operators of the BPS must comply with the NERC standards 

where the NERC registry process identifies the entities that must be registered.  The NERC Functional 

Model provides guidance concerning the type of function for which an entity is registered and, 

therefore, their role in maintaining reliability.  The Functional Model identifies various roles, or 

“functions” that an entity may perform with respect to the grid.141  A single utility or organization may 

perform several functions and be registered for each of those functions. 

 

Regardless of whether entities are located in regions that have centralized markets and RTOs/ISOs or a 

traditionally regulated structure, the Regional Entities and NERC will identify who must be registered 

and as what type of functional entity.  The primary difference between functional responsibilities of 

entities that exist in RTOs/ISOs and those that do not is that RTOs/ISOs often perform the functional 

roles of Balancing Authority, Reliability Coordinator, Transmission Operator, and Transmission Planner.  

Other entities in the region are then registered to perform the remaining functions. There is sometimes 

some overlap in functional roles, such as Transmission Operator (TOP).142  

 

In regions that do not have RTOs/ISOs, the investor owned utility or local public power entities often 

perform all the functions and are registered as multiple functional entity types.  Even here, however, a 

traditional utility may not perform all functions.  Where generation has been divested, the generation 

owner will be registered as the Generation Owner (GO) and Generation Operator (GOP) (and possibly as 

a TO and TOP, depending on the interconnection facilities they own).  Furthermore, in several of the 

non‐RTO/ISO regions, an operating affiliate of the Regional Entity serves as the RC.  These regions are 

WECC, Florida Reliability Coordinating Council (FRCC), and SPP. 

 

Transmission reliability is governed by FERC, NERC, and the REs.  The states still retain a role in 

resource adequacy, as described later in this section.  In addition, the states retain oversight for reliability 

of distribution facilities and may take action to ensure the safety, adequacy, and reliability within that 

state provided it is not inconsistent with any NERC reliability standard.143  The states and other 

                                                           139 Federal Power Act §215(a). 140 See Order No. 773 at P 69. 141 The Functional Model was developed to address the advent of open access and the restructuring of the electric 

utility industry to facilitate the operation of wholesale power markets.  This new industry structure reflected 

functional disaggregation under open access, that Control Areas no longer provided a single reliability structure, 

and the RTOs and ISOs did not all perform the same functions.  The functions described in the Functional Model 

include Generators, Transmission Service Providers, Transmission Owners, Transmission Operators, Distribution 

Providers, Load‐Serving Entities, Purchasing‐Selling Entities, Security Authorities, Balancing Authorities, 

Interchange Authorities, and the Compliance Monitor.  An advantage of the Functional Models is that it does not 

depend on how organizations are, or will be, structured or on how functions are implemented in the future. 142 An exception to this rule is in the WECC region, where the WECC Reliability Coordinator performs the reliability 

coordination function for the entire region, including the CAISO area. 143 See FPA 215(h)(3), Savings Clause. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 34 October 8, 2013

governmental entities that have regulatory oversight functions may participate as non‐voting members 

in NERC and RE activities, under the government sector, and may also provide comments in FERC 

proceedings.  One important distinction is in the case of the New York State Reliability Council, which 

exists as a separate entity within NPCC and may develop rules that result in greater reliability within 

New York provided they do not result in lesser reliability outside that state.144 

5.2.3  Compliance Monitoring and Enforcement 

The NERC Compliance Monitoring and Enforcement Program (CMEP) requires bulk‐power system 

owners, operators, and users to register with NERC and comply with all approved Reliability Standards.  

They must also report all violations of the Reliability Standards to their Regional Entity.  The CMEP uses 

various monitoring processes to collect information in order to make assessments of compliance, for 

example, audits, self‐certifications, spot checks, and self‐reports.145 

 

NERC, as the international ERO, has delegated authority to monitor and enforce compliance with 

reliability standards of owners, operators, and users of the BPS to qualified Regional Entities.  The eight 

Regional Entities, under NERC’s oversight, are responsible for carrying out the CMEP within their 

respective regions based on the regulatory‐authority‐approved uniform CMEP.146 

 

Section 215 of the FPA also gave the ERO the authority to levy penalties for non‐compliance, with fines 

of up to one million dollars per day per violation for the most serious violations.147  FERC also has 

separate investigation and enforcement authority under section 215 of the FPA.148  While NERC, with 

FERC approval, has the authority to assess penalties as large as one million dollars per day per violation, 

initial penalties were modest, with maximum penalties in the range of several hundred thousand 

dollars.  This trend, however, has begun to change and in late 2011 and 2012 penalties up to and 

exceeding one million dollars have been assessed to registered entities.149 

5.3  Resource Adequacy  

“The desire for resource adequacy standards is driven by a belief that electricity supply interruptions 

should be very rare, or preferably non‐existent.”150  Historically, state commissions have had regulatory 

responsibility for assuring generation resource adequacy for retail electric customers.  However, when 

changes are implemented through FERC jurisdictional tariffs to achieve resource adequacy objectives, 

                                                           144 See FPA 215(h)(3), Savings Clause. 145 See NERC and Mandatory Electric Reliability Compliance, pg. Ch8. 146 Ibid., Ch8, pg. 84. 147 The way NERC approaches compliance and enforcement is also under revision through its Compliance 

Enforcement Initiative aimed at streamlining its enforcement mechanisms and the Reliability Enforcement Initiative, 

where the focus will be to move standards development and compliance monitoring towards the assessment of 

internal compliance controls developed by the registered entities. See NERC website links: 

http://www.nerc.com/pa/comp/Pages/Reliability‐Assurance‐Initiative.aspx. 148 See FPA 215(e)(3).  Investigations are performed under Part 1b of the FERC Rules of Procedure, 18 CFR Part 1b. 149 See http://www.nerc.com/pa/comp/Pages/Enforcement‐and‐Mitigation.aspx. 150 James Bushnell, Electricity Resource Adequacy: Matching Policies and Goals, Center for the Study of Energy 

Markets (CSEM) (August 2005), pg. 2. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 35 October 8, 2013

for example through capacity markets, FERC has asserted authority over approval of the resource 

adequacy determination.151  Likewise, FERC has asserted authority over resource adequacy standards 

where they potentially affect the reliable operation of the BPS.152 

 

In the electric power sector, the term resource adequacy refers to the transmission provider’s 

probabilistic ability to meet end‐use demand for electric power during system peak hours.153  

Underlying most resource adequacy standards in the U.S. are criteria set by the REs for generation 

adequacy, typically a “1 in 10 Loss of Load Expectation” or LOLE.154  FERC has accepted this standard 

for resource adequacy design,155 although there are opponents asserting that the 1‐in‐10 objective is 

overly conservative and may impede transition from resource adequacy based on administrative 

capacity mechanisms to market‐driven resource adequacy.156  Regardless, the choice of resource 

adequacy objective and the means chosen to achieve it will have an impact on consumer electric rates. 

 

                                                           151 FERC stated in PP 29‐32 of its March 23, 2005, order in Devon Power, L.L.C. et al., Docket No. ER03‐563‐030, et al., 

and in P 33 of its May 9, 2005, order in Docket No. ER05‐715‐000 et al. that the ISO New England (ISO‐NE) had the 

authority to establish generation resource adequacy standards on the grounds that the ISO‐NE’s installed capacity 

market is governed by a tariff that had been filed for approval by the FERC and that the ISO‐NE’s tariff and 

Participants Agreement authorize the ISO‐NE to seek FERC approval of the ISO‐NE’s proposed resource adequacy 

determinations. 152 In Order No. 747, FERC approved use of the 1‐in‐10 resource adequacy objective by RFC; regional reliability 

standard, BAL‐502‐RFC‐02.  See  Planning Resource Adequacy Assessment Reliability Standard, 134 FERC ¶ 61,212 

(2011) (“Order No. 747”).  However, PUCO challenged FERC’s jurisdiction that insufficient resource adequacy falls 

under its jurisdiction by supposedly impacting ʺjust and reasonableʺ wholesale prices.  PUCO asserted that FERC 

jurisdiction under FPA 215 adopting reliability standards is limited to those actions which provide for ʺreliable 

operationʺ of the bulk‐power system and that a lack of adequate resources to serve firm load does not lead to 

unreliable operation (instability, uncontrolled separation or cascading failures) since measures such as controlled 

load shedding may be taken.  FERC dismissed this argument, stating that the mere potential for instability, 

uncontrolled separation or cascading failures justifies its actions, even where such supply‐demand imbalances may 

be cured by firm load shedding. 153 See Christine Tezak, Resource Adequacy — Alphabet Soup!, STANFORD WASHINGTON RESEARCH GROUP, 

(June 2005), pg. 2 (“Resource Adequacy — Alphabet Soup!”). 154 See Resource Adequacy — Alphabet Soup!, pg. 2.  Loss of Load Expectation (LOLE) means the number of firm 

load shed events an electric system expects over a period of one or more years.  The utility industry, for decades, has 

used an LOLE of 1 day of firm load shed in 10 years (referred to as the 1‐in‐10 reliability standard) as the primary if 

not sole means for setting target reserve margins and capacity requirements in such resource adequacy analyses.  

While this standard is accepted, there is not technical justification supporting this requirement.  For example, in 

NPCC, “The probability (or risk) of disconnecting firm load due to resource deficiencies shall be, on average, not 

more than one day in ten years as determined by studies conducted for each Resource Planning and Planning 

Coordinator Area.” ʺ See NPCC Reliability Reference Directory # 1 Design and Operation of the Bulk Power System 

(December 2009), section 5.1.1. 155 In Order No. 747, FERC approved use of the 1‐in‐10 resource adequacy objective by RFC; regional reliability 

standard, BAL‐502‐RFC‐02. 156 See Energy Choice Matters, FERC Mandates Use of Conservative Resource Adequacy Standard Which Will Raise 

Retail Rates,  (March 18, 2011). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 36 October 8, 2013

In retail choice regions, resource planning has become more complex.  Prior to transmission unbundling 

and retail access, resource adequacy was part of each utility’s IRP, a process discussed briefly in Section 

5 and more thoroughly in Section 8 of this paper.   Where utilities have restructured, however, it is not 

feasible to plan for resource adequacy in this fashion.157  Under bundled service and IRP ratemaking, the 

FERC had little say over resource adequacy decisions, which traditionally were handled by the states in 

coordination with the regional reliability council.158  In retail choice regions, planners can no longer rely 

on a single entity to meet forecast system needs.  An array of merchant suppliers building generation in 

response to anticipated future market process replaced a single utility in fulfilling power supply contract 

obligations.159  This uncertainty in supply source could mean that a planner could over‐ or 

underestimate their optimal supply target.160 

 Two approaches are used in the Centralized Market model to achieve resource adequacy goals— a 

market‐based and an administrative approach.  With a capacity market, suppliers receive periodic (i.e., 

annual or monthly) payments for providing “reliable” capacity to a system and Load‐Serving Entities 

(LSEs) are required by the regulatory standard to purchase the capacity.161  One key concern for 

consumers is price volatility and uncertainty.  Examples of capacity markets are found in PJM, NYISO, 

and ISO‐NE.   

 

There are also other variations to the market‐based approach; these are energy‐only markets and 

markets with administrative resource adequacy requirements for LSEs.  An example of an energy‐only 

market is ERCOT in Texas; however, declining reserve margins are forcing a reevaluation of this 

approach.  

 

Both CAISO and MISO are examples where the market‐based mechanism uses administrative resource 

adequacy requirements.  Under the administrative approach, resource adequacy is achieved through 

traditional IRP and competitive resource solicitation.  These processes are discussed in greater detail in 

Section 8, Responsibilities for Planning and the Types of Planning Performed.  One key concern is 

increased consumer cost due to uneconomic investment decisions.  Examples of administrative 

approaches are SPP, most of WECC outside the CAISO, and the southeast U.S. 

 

Table 3 lists the key features of the market‐based resource adequacy approaches in the U.S. 

 

                                                           157 See Resource Adequacy — Alphabet Soup!, pg. 2. 158 Ibid., pg. 4. 159 See James Bushnell,  Electricity Resource Adequacy: Matching Policies and Goals, Center for the Study of Energy 

Markets (CSEM)  (August 2005), pg. 3. 160 Over‐investment of resources can result in higher costs to retail customers while under‐investment can also result 

in high costs, e.g., blackouts and in capacity markets price spikes.  See Bushnell, pg. 4.   For example, in 1998 and 

1999, the Midwest experienced significant price spikes where the price of electricity in the wholesale markets went 

to $1,000/MWh. 161 See Bushnell, pg. 4. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 37 October 8, 2013

Table 3. Examples of Market‐Based Resource Adequacy Mechanisms 

Region/ Entity

Market-Based Method Key Features

CAISO LSE Resource Adequacy Requirement

CPUC established resource adequacy obligations applicable to all Load-Serving Entities (LSEs).

Two distinct requirements: Annual and monthly System resource adequacy Filings and annual Local resource adequacy Filings

Each LSE’s system requirement is 100 percent of its total forecast load plus a 15 percent reserve.

PJM Capacity Market “Reliability Pricing Model” that has a locational (subregional) capacity mechanism 3-year capacity obligation Market clearing price paid for all resources committed in the auction with

performance-based penalties Prices determined using an offer-based supply curve and simulated downward-

sloping demand curve (Variable Resource Requirement or VRR) PJM auctions consist of a Base Residual Auctions to meet the 3-year obligation and

Incremental Auctions to meet unfilled commitments. LSEs can self-supply, but their resources must be offered in the base auctions. A Fixed Resource Requirement (FRR) allows LSEs to meet fixed capacity obligations. Minimum Offer Price Rule (MOPR) to discourage efforts to depress market clearing

prices by offering non-competitive bids with a “conduct screen” to identify non-competitive bids

PJM has a capacity deliverability requirement.

NYISO Capacity Market New York State Reliability Council sets an Installed Reserve Margin, currently 118% of peak; NYISO determines the Minimum Unforced Capacity Requirement.

The NYISO runs Capacity Period (seasonal), monthly, and spot market UCAP auctions.

NYISO also has locational capacity requirements for NYC and Long Island (LI). Market clears along an administratively determined “demand curve.” NYISO has a capacity deliverability requirement.

ISO-NE Capacity Market Has a forward reserves market Does not have a deliverability requirement for capacity

MISO LSE Resource Adequacy Requirement

Annual resource adequacy requirements (reserve margin is 11.3% in 2012) and voluntary planning resource auction

Seven local resource zones with local clearing Opt-out provision allowing participants to submit a fixed resource adequacy plan,

allowing utilities to opt out of the yearly auction Deficiency charge for entities that are short on capacity (based on the cost of new

entry) Relies on state processes for resource planning, load forecasting, demand response,

and energy efficiency investment decisions

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 38 October 8, 2013

Region/ Entity

Market-Based Method Key Features

ERCOT Energy Only Energy-only nodal market with the system-wide offer cap of $3,000 $3,000 offer cap not based on a VOLL (customers’ value of lost load) Target reliability standard of 1-in-10 (13.75% reserve margin) but target is not

enforced through specific requirements or market structures Two out-of-market reliability mechanisms: Emergency Response Service (ERS)

demand curtailment program and reliability-must-run (RMR) contracts for units needed for local reliability

Source:  Navigant Consulting, Inc. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 39 October 8, 2013

6.  Environmental Issues  

6.1  Impacts of Environmental Regulation 

The electric industry is subject to significant environmental regulation, both directly and through 

policies or requirements relating to renewable energy and energy efficiency.  For the most part, new and 

proposed regulations affect electricity generation, rather than the transmission or distribution sectors. 

This section provides an overview of relevant environmental regulations (existing and proposed) facing 

electricity generation in the United States.  It also discusses how renewable energy policies and 

requirements affect entities operating under the two market structures.   

6.2  Differing Impacts for Different Structures 

Market/regulatory structure play an important role in whether and how environmental requirements 

and policies affect electric entities.  Where the traditionally regulated  model prevails, the impacts – 

whatever they are – fall on the utility and the associated costs flow to its customers through cost‐based 

rates.  In contrast, where there has been a restructuring of utility regulation and the development of 

organized electricity markets, impacts vary widely.   

 

For example, a utility that owns no generation would not incur the direct expense of complying with 

environmental rules relating to emissions.162  Instead, generator compliance costs would be reflected in 

the cost of energy purchases.  Similarly, generation‐only entities would not normally be subject to RPS or 

policies favoring the use of renewable energy resources.  Instead, generators would feel the impact of 

these items through increases or decreases in demand for their output and, accordingly, in energy prices.  

All of this ultimately affects the prices end‐use customers pay.  However, market forces may drive 

energy prices higher or lower than would take place under the  traditionally regulated model.  If a 

vertically integrated utility is supplying its energy principally through its own coal‐fired generation, 

future environmental costs are potentially high, and may outstrip any potential production cost 

differential that would otherwise favor coal.  Similarly, if a market is dominated by coal generation, 

environmental costs may drive up the overall costs of energy.    

 

Independent generators in centralized markets are particularly sensitive to the costs of environmental 

regulation, since these generators rely on market pricing rather than cost of service rates.   Uneconomic 

generation in centralized markets may be retired rather than operated at a loss for any extended period 

of time.163  Environmental regulations facing coal plants as well as changing economics have encouraged 

the growth of natural gas generation as well as renewable resources.  Renewable resources in these 

markets – particularly where there is a high renewables requirement – are usually not competing with 

non‐renewables on the basis of cost, but instead are competing with demand response or other 

                                                           162 This excludes contractual arrangements that would subject a non‐owner to those costs. 163 While an RTO or ISO may be able to keep these units in operation for a limited period through so‐called 

“Reliability Must Run” arrangements that cover the owner’s costs, this is not intended to be a permanent or long‐

term solution to a retirement.   

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 40 October 8, 2013

renewables.  Similarly, requirements relating to renewables may affect electric service providers 

differently, depending on whether they are all subject to the same requirements. 

 

Under the traditionally regulated model, utilities are also sensitive to environmental regulation, 

including policies or regulations favoring renewables, since compliance would increase or decrease their 

costs.  While, in theory, new rate cases can be filed to reflect increased costs, in practice they are often 

expensive and may meet resistance as costs to customers increase.  “Regulatory lag” – i.e., the period 

during which recoverable costs are incurred vs. when they are actually reflected in rates – can also be a 

major concern to a vertically integrated utility.  Nonetheless, to the extent the utility is able to pass on the 

costs to its customers, the impact to the utility (though not its customers) may be muted. 

 

Therefore, the decision to retrofit to comply with environmental regulations or retire and replace with 

new generation involves different stakeholders and considerations for regulated utilities and 

independent generation owners.  For independent generation owners, these decisions are generally 

made based on whether or not the revenues from a retrofitted plant outweigh the costs of operating the 

retrofitted plant (including capital costs for the retrofit). For regulated utilities, retire or retrofit decisions 

must be approved by the state public utility commission (PUC) and weigh the rate impact of the retrofit 

compared to the rate impact of replacement generation or demand‐side options.  PUCs may also choose 

to or be required to take other non‐monetary issues into consideration, such as reliability, fuel diversity, 

and public interest.164  While each case is specific, theoretically it is easier for a merchant generation 

owner to retire a plant due to the high costs of an environmental regulation than a regulated utility.  

Also of importance is the fact that while regulated entities own just over half of all currently operational 

generation, they own nearly three‐quarters of all currently operational coal‐fired generation, the type 

that is most affected by environmental regulations.165 

 

The costs and risks from proposed environmental regulations will differ by region, largely affecting 

those regions of the country with significant amounts of existing coal‐fired generation.  Whether 

environmental costs end up being passed through in cost‐based rates or result in higher market‐based 

rates, the impact on electricity consumers in those regions will be considerable. 

6.2.1  Greenhouse Gas Initiatives 

The regulation of existing power plants has the potential to significantly affect the nation’s overall 

emission of carbon dioxide (CO2); approximately 40 percent of national CO2 emissions are from the 

electric sector.  Overall, three possible paths for CO2 policy have emerged: legislation of a cap‐and‐trade 

or tax approach, regulation by the U.S. Environmental Protection Agency (EPA), and no federal 

regulation of CO2.   

 

In the absence of legislation (which is unlikely in the near‐term), the EPA has the obligation under a 2009 

settlement agreement to regulate CO2; however, congressional Republicans have threatened to strip the 

                                                           164 For further discussion of the role of PUCs in utility decision making related to environmental regulations, see 

Section II of: Monast and Adair, “A Triple Bottom Line for Electric Utility Regulation: Aligning State‐Level Energy, 

Environmental, and Consumer Protection Goals,” Columbia Journal of Environmental Law, 38 (1) (2013). 165 Statistics from Navigant’s analysis of data downloaded from Energy Velocity in July of 2013. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 41 October 8, 2013

EPA of the authority.166  On June 25, 2013, President Obama announced that his administration plans to 

meet the following deadlines for regulating carbon emissions from power plants: 

September 20, 2013 – modified proposed rule for new power plants 

June 1, 2014 – proposed rule for existing power plants 

June 1, 2015 – final rule for existing power plants 

June 30, 2016 – deadline for states to submit implementation plans167 

 

Given the divisiveness of opinion on this topic and the other priorities for the federal government over 

the near term, it is uncertain whether a federal greenhouse gas (GHG) program will come into effect in 

the very near term. 

 

The EPA re‐proposed New Source Performance Standards (NSPS) rules for CO2 emissions for new fossil‐ 

fuel power plants on September 20, 2013; the modified proposal limits coal‐fired and small natural‐gas‐

fired power plants to emitting 1,100 pounds of CO2 per MWh, and limits large natural‐gas‐fired plants to 

emitting 1,000 pounds of CO2 per MWh.  The original proposal set one CO2 emission standard (1,000 lbs. 

per MWh) for both new coal and new natural gas power plants.  The EPA’s analysis of the impacts of the 

regulation show that despite the fact that the rule would essentially bar new coal power plants from 

being built without carbon capture and sequestration (CCS), a technology that is not yet commercially 

operational, the rule does not disrupt any planned coal power plant construction. 

6.2.1.1  California AB 32 

California’s Assembly Bill (AB) 32, enacted in September 2006, established a comprehensive program to 

achieve quantifiable, cost‐effective reductions of GHGs by 2020.  AB 32 requires the reduction of 

California GHG emissions by 2020 down to 1990 levels, estimated to be a 16 percent decrease from the 

California Air Resources Board’s (CARB’s) projected “business as usual” 2020 levels.  CARB plans to 

obtain a significant component of GHG reductions in the energy sector, specifically via a cap‐and‐trade 

regime.  CARB’s cap‐and‐trade program has been the subject of several litigation challenges, including 

one in which CARB’s Scoping Plan was upheld in a June 2012 decision. 

 

CARB held their first GHG auction in November of 2012, and held two auctions in the first half of 2013; 

prices have remained near the floor of $10/allowance. 

6.2.1.2  Regional Greenhouse Gas Initiative 

Connecticut, Delaware, Maine, Maryland, Massachusetts, New Hampshire, New York, Rhode Island, 

and Vermont have joined the Regional Greenhouse Gas Initiative (RGGI), which is a cap‐and‐trade 

program to curb carbon dioxide emissions that began in 2009.  The overall CO2 cap was reduced in 2012, 

and will continue to be reduced each year.  Twenty RGGI auctions have been held to date, with clearing 

prices falling between $1.87/ton and $3.51/ton.  

                                                           166 See Settlement Agreement: http://www.epa.gov/airquality/cps/pdfs/boilerghgsettlement.pdf  167 See Presidential Memorandum: http://www.whitehouse.gov/the‐press‐office/2013/06/25/presidential‐

memorandum‐power‐sector‐carbon‐pollution‐standards  

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 42 October 8, 2013

6.2.2  Renewable Portfolio and Energy Efficiency Resource Standards 

Renewable Portfolio Standards (RPS) are state policies that require electricity providers to obtain a 

minimum percentage of power from renewable energy resources by specified dates.  Currently, there are 

29 states plus the District of Columbia that have mandatory RPS policies in place; 8 states have 

nonbinding renewable goals.  An overview of the RPS objectives in each state has been provided in 

Figure 9.  

Figure 9. State RPS Policies 

 Source: Database of State Incentives for Renewables & Efficiency (DSIRE.org) 

The target level of renewable penetration, deadlines, definition of renewable or alternative energy 

sources, and compliance options all vary from state to state.  Some states have provisions within the RPS 

that limit compliance costs to regulated entities, utilities, or end‐use customers.  Many states’ RPS 

policies include special carve‐outs, incentives or other provisions to address local needs; a common 

example is a carve‐out that requires a subset of the renewable target be from solar or distributed 

generation (DG) sources.  So far, most states have met or come close to meeting their RPS and carve‐out 

targets.  Many of the states that do not have RPS are located in the southeastern U.S., where there is little 

potential for low‐cost wind generation.  These states tend to have moderate solar potential and high 

biomass potential, both of which have higher costs to develop than wind.  Conversely, northeastern 

states tend to have moderate to aggressive RPS policies and also lack substantial on‐shore wind 

potential. 

The existing RPS landscape is changing as some states pass revisions through legislation; to date, no 

state has repealed its RPS.  As they require utilities and regulated entities to obtain power from 

renewable sources, which tend to have higher costs than traditional sources, RPS targets tend to increase 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 43 October 8, 2013

the costs to the entities required to meet them.168  In regulated markets, these costs are passed directly on 

to the end user, but, as described above, in deregulated markets the impact on end‐user rates is less 

transparent. 

Twenty states have mandatory Energy Efficiency Resource Standards (EERS) or similar provisions to 

ensure that cost‐effective energy efficiency measures are used to help offset growing electricity demand. 

An additional seven states have nonbinding energy efficiency goals.  Most EERS policies require a 

reduction in annual peak demand by a certain percentage through the implementation of energy 

efficiency initiatives.  An overview of the EERS objectives in each state has been provided in Figure 10.   

 

Figure 10. State EERS Policies 

 Source: Database of State Incentives for Renewables & Efficiency (DSIRE.org) 

The success of EERS programs is difficult to quantify, as they depend on estimates for demand reduction 

compared to a “business as usual forecast.”  States with EERS also tend to have lower average power 

demand growth than states without EERS that have comparable economic profiles.169  Energy efficiency 

improvements can be more cost effective than building new generation to meet demand growth; thus, 

energy efficiency measures have the potential to reduce end‐user rates. 

                                                           168 See U.S. Energy Information Administration, Levelized Cost of New Generation Resources in the Annual Energy 

Outlook 2013” (January 2013), http://www.eia.gov/forecasts/aeo/electricity_generation.cfm. 169 U.S. Energy Information Association, Electricity Detailed State Data, 1990‐

2011, http://www.eia.gov/electricity/data/state/. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 44 October 8, 2013

6.2.3  Mercury and Air Toxics Standards 

On December 21, 2011, the EPA unveiled the final version of the Mercury and Air Toxics Standards 

(MATS) rule, which sets emissions limits on mercury and other toxic pollutants from power plants.  The 

rule will affect existing coal‐ and oil‐fired units that are capable of at least 25 MW of electrical output.  

The rule requires emission reductions by April of 2015.  The policy allows for an additional year, and 

possibly two, for generators to install the necessary emission control equipment; this will likely reduce 

the cost of compliance for entities that own many affected units as retrofits can be spread among the 

entire compliance time period.  Additionally, power plants have the option to use facility‐wide 

averaging to meet mercury limits and the emissions are averaged over 90 days.  The MATS rule is 

expected to add significant retrofit costs to older coal power plants, resulting in the retirement of 

some/many.  

6.2.4  National Ambient Air Quality Standards 

As required under the Clean Air Act (CAA), the EPA has set primary, and in some cases secondary, 

National Ambient Air Quality Standards (NAAQS) for six criteria pollutants: carbon monoxide, lead, 

nitrogen dioxide, ozone, particulate matter (PM) (diameter 2.5mm and 10mm), and sulfur dioxide, which 

are updated by the EPA every five years.  Carbon monoxide and lead standards do not apply to the 

electric industry, but the other criteria pollutants are emitted or result from the combustion of fossil 

fuels.  After the EPA finalizes a NAAQS, states submit State Implementation Plans (SIPs) that outline 

how that state plans to bring areas that do not meet the NAAQS into compliance.  If the EPA does not 

approve a state’s SIP, it can implement a Federal Implementation Plan (FIP) in that state.  Therefore, 

NAAQS SIPs can have very different impacts on generators state to state or even within states, 

depending on a generator’s proximity to areas that are above the NAAQS. 

6.2.5  Clean Air Interstate Rule/Cross‐State Air Pollution Rule  

From the EPA’s NAAQS for PM, NOx, and SO2, the CAA also requires states to limit their emissions of 

pollutants that can “contribute significantly” to another state’s NAAQS nonattainment problem when 

they drift downwind.  The EPA has promulgated two regulations designed to reduce these pollutants 

that drift downwind in less than a decade, but both have been successfully challenged in court.  Most 

recently, in August of 2012, the U.S. Court of Appeals for the District of Columbia vacated the Cross‐

State Air Pollution Rule (CSAPR); the Supreme Court recently agreed to hear the EPA’s appeal of that 

decision. Several coal power plants announced their retirement due to the CSAPR, and have since 

retracted that announcement.  CSAPR, and the Clean Air Interstate Rule (CAIR) before it, used a cap‐

and‐trade mechanism to allow flexibility in meeting emission reductions.  In the next few years, either 

the CSAPR will be reinstated by the Supreme Court, thought to be an unlikely outcome, or the EPA will 

come up with a replacement rule. 

6.2.6  Regional Haze 

The EPA’s Best Available Retrofit Technology (BART) rule was finalized in 1999.  The rule is designed to 

improve visibility in national parks and applies to power plants built between 1962 and 1977.  However, 

the rule only requires NOx and SO2 emission reductions for those plants for which it is deemed 

necessary through a unit‐by‐unit study.  The regulation requires affected units to conduct analyses to 

determine the impact of its emissions on visibility in national parks.  

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 45 October 8, 2013

6.2.7  Cooling Water Intake Structures 

The EPA proposed a standard for cooling water intake structures at existing power plants on April 20, 

2011, under section 316 (b) of the Clean Water Act (CWA).  The EPA planned to issue its final rule for 

cooling water intake structures by June 27, 2013; however, they did not meet this deadline and state that 

they will finalize the rule by November 4, 2013.  The proposed rule offered several compliance options, 

including intake screen modification for impingement, and closed‐loop cooling systems or a site‐by‐site 

determination of Best Technology Available (BTA) based on closed‐loop cooling systems for 

entrainment.  This rule has the potential to introduce huge retrofit costs to a number of plants, 

potentially raising end‐user rates and causing reliability problems in the process.  

6.2.8  Coal Combustion Residuals 

Coal combustion residuals (CCRs) are residues from the power plants’ combustion of coal that are 

captured by pollution control technologies, like electrostatic precipitators or bag houses.  In June 2010, 

the EPA issued a proposal to regulate coal ash in an attempt to address the risks from the disposal of the 

wastes generated by coal plants in surface impoundments (for liquid waste) and landfills (for solid 

waste).  The EPA has not set a target date for issuing the final CCR regulation. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 46 October 8, 2013

7.  Relative Allocation of Risks over Time 

7.1  Traditionally Regulated Model 

Under the traditionally regulated model, the allocation of risks is well established.  The utility has a 

monopoly right to provide electric service to retail customers, who in turn are entitled to electricity at a 

“reasonable” cost.  Utilities are allowed to recover their prudent investments in the system, plus a 

reasonable return on investment, plus reasonable operating costs.  In return, the utility has a duty to 

serve all customers within its footprint and must expand and maintain the electric system as needed to 

meet the needs of its customers.   

 

The utility’s risk in the traditional model is that its rates will not recover its actual investment and 

operating costs or meet the rate of return required for its investors to risk their money.  The utility also 

risks that its costs will be determined to have been prudently incurred and that it will receive timely 

recovery through the regulatory process.  The customer’s risks include:   

1. Utility over‐investment or over‐building (since it gets a rate of return on its investment)  

2. Utility under‐investment (either through bad decision making or out of concern that it will not 

recover its costs)  

3. Unreliable service as a result of ineffective operations 

4. High costs due to inefficient utility operations or bad decision‐making   

 

The traditional model uses regulation and regulatory proceedings170 to mitigate these risks.   Rate cases 

are intended to protect the customer from over‐investment (and inefficient operations while allowing the 

utility and its investors to recover its prudently incurred costs plus a reasonable investment return.  Rate 

cases and other regulatory proceedings also address the utility’s reliability, operating costs, and 

management.  Regulation and mandated system requirements are also used to protect customers and the 

public at large from under‐investment, unsafe operations, and environmental impacts.  However, the 

consumer protections afforded by rate cases may are sometimes criticized because: (1) litigation is 

expensive and consumers may to be able to afford the costs of the litigation; and (2) many jurisdictions 

do not have consumer advocates. 

 

In the traditional model, utilities are generally vertically integrated, owning both the transmission and 

distribution systems within their territory, as well as the generation necessary to serve customers.  The 

traditional model also includes government‐owned and cooperative utilities that may jointly own 

transmission and generation facilities or their own facilities.  Because utilities must serve load at all 

hours of the year, they must have enough generation to serve peak demand, which may exceed what 

would be needed to serve load for most of the year.  They must also have access to additional resources 

in the event that a generator becomes unable to operate. 

 

Over the years, utilities have developed arrangements to assist one another to meet emergencies such as 

the loss of a generator or an unexpected spike in demand, such as capacity reserve sharing agreements.  

                                                           170 Including proceedings before the governing body of a utility that is not investor owned.  

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 47 October 8, 2013

In addition, utilities may purchase power from other companies on a long‐ or short‐term basis.  Where 

there is no centralized wholesale market, these are generally bilateral, negotiated transactions.  These 

purchases and sales allow utilities to manage the costs of providing for peak loads – either by selling 

excess power or by purchasing some of the utility’s requirements.  Otherwise, each utility would have to 

build and own sufficient generation to meet its peak load, plus a required reliability reserve margin. 

 

Independent power producers can be additional sources of power to utilities in areas where the 

traditional utility structure prevails.  In the absence of an centralized energy market, an independent 

wholesale generator in a region subject to traditional utility structure may require a long‐term power 

purchase agreement with a utility in order to obtain financing and to support its operations.171  For the 

utility, a purchase power arrangement may be a less expensive alternative to constructing and owning a 

power plant, and it provides certainty as to pricing over a long term.  However, the downside risk is that 

the utility may lock in prices that turn out to be too high.   

 

Thus, in a traditional model, one risk to consumers is that prices (rates) will reflect higher generation 

costs – either through over‐building or through long‐term power purchase agreements.  On the plus 

side, however, long‐term pricing agreements may protect consumers from energy price volatility.  In 

fact, FERC found that the unavailability of long‐term contracts was one of the causes of the California 

power supply crisis.172  In addition, in both traditionally regulated and centralized market models, the 

risks of long‐term contracts can be hedged through financial investments. 

7.2  Centralized Market Model 

In a centralized market, the risks for customers and the mechanisms for addressing them are the same 

with respect to the transmission and distribution system.  Rate cases and regulation are the principal 

tools to protect customers from monopoly abuses and to set the utility’s pricing for the delivery of 

electricity.  However, with respect to generation, the market (often with a price cap as a backstop) sets 

wholesale energy prices, which in turn may drive installation of new generation or new transmission.  

Utilities may or may not own generation.  In many cases, utilities in these areas have been required to 

divest their generation.  In other cases, utilities have divested some or all of their generation voluntarily.   

 

In these markets, many generators in a region compete with one another to supply electricity.  The 

centralized markets are associated with RTOs or ISOs that are responsible for regional transmission 

planning.  In the wake of FERC’s Order No. 888, requiring investor‐owned utilities to file Open‐Access 

Transmission Tariffs and requiring non‐jurisdictional entities to do so to gain the benefit of reciprocity, 

utilities must make their transmission capacity not needed to serve their own customers available to 

others on the same terms.173  They cannot favor their own or their affiliates’ wholesale transactions.   

 

Utilities in these markets are not necessarily planning and building generation.  Instead, these regions 

rely on market forces to cause needed generation to be added when and where it is needed.  Locational 

                                                           171 IPP development in these areas may also be impacted by transmission constraints, which may limit the 

generator’s ability to deliver the power to a buyer other than the local utility.   172 Investigation of Practices of the California Independent System Operator and the California Power Exchange, 93 

FERC ¶61,121 at ¶61,354. 173 See Order No. 888, pg. 370. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 48 October 8, 2013

Marginal Pricing encompasses the delivered cost of energy into an area.  In all of the existing organized 

markets, all generation offered in an area is paid the same clearing price for the given hour or service, 

with the difference being the cost to deliver the energy to the intended zone.  This is intended to drive 

overall costs down and to ensure that the lowest cost generation is dispatched first.  In theory, new 

capacity will be added in areas where prices are high.  However, some markets have found that the LMP 

differentials themselves may not be enough incentive.  PJM and ISO‐NE, for example, have adopted 

capacity auction mechanisms to ensure that there is sufficient capacity within the market.   

 

While the markets are “physical” there are many purely financial participants.  Financial participants 

provide liquidity and depth that would be difficult to achieve if the only players were utilities and 

generators.  In addition, there are a number of financial hedging mechanisms that the organized markets 

offer that help utilities and others reduce (or at least manage) risk.  These include items such as the 

Financial Transmission Rights (FTRs) offered through PJM (and comparable tools available in other 

markets) that enable participants to manage transmission congestion risks and costs.  Credit 

requirements are stringent and monitored by the market operators.  Each market has a market monitor 

whose role is to determine whether pricing is competitive.  In addition, various rules have been adopted 

by FERC to address and prevent potential market abuses and manipulation, particularly after enhanced 

civil penalty authority under Part II of the Federal Power Act (FPA)174 and the California energy crisis of 

2000 and resulting litigation.  

 

In areas where there is retail choice (which is most common under the centralized markets model), the 

presence of lightly (or non‐) regulated alternative retail energy providers presents a range of new risks 

for utilities and for customers.  These providers may be thinly capitalized or overextended.  In addition, 

the energy savings may be less than expected (or nonexistent).  Customers run the risk of higher rates if 

the alternative provider fails to perform, although in many instance retail providers are required to meet 

financial responsibility requirements which to some extent may mitigate this risk.   In some cases – 

particularly where industrial or commercial customers are concerned – the utility may charge a higher 

rate to returning customers.  In part, this is to discourage these large customers from returning to utility 

supply if there are other options.  This not only supports the growth of competition, but also protects the 

utility from large swings in energy requirements due to customers arbitraging energy costs.   

 

Figure 11 shows Navigant Research’s 2011 forecast that the rate of commercial and industrial customer 

purchases from alternative suppliers is likely to continue to outpace overall industry growth for the next 

several years.   

 

                                                           174 EPACT 2005 expanded FERC’s remedies to address market manipulation, enhancing FERC the power to impose 

civil penalties under  Part II of the Federal Power Act (16 U.S.C. § 825o‐1 (2000) (as amended by EPAct 2005, 

§1284(e)); 16 U.S.C. § 823b (2000)). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 49 October 8, 2013

Figure 11. Forecasted Energy Sales from Alternative Suppliers175 

  

Only recently have alternative suppliers begun to target the residential market in some states, aided in 

some cases by municipal aggregation.176   

 

As customers leave utilities, however, the risks to utilities and remaining customers may increase.  The 

utility in many cases must continue to procure power for these continuing customers.  In addition, the 

utility must also be prepared to resume supplying service to returning customers, even as this number 

grows.  How well utilities manage this risk may affect costs to not only its remaining electric supply 

customers but also to its delivery service customers.  As a result, the existence of a liquid market is 

essential to utilities in restructured states.     

 

As noted earlier, under the centralized market model, independent generators are not assured a return 

of their investment; rather, they are subject to market pricing.  As with other investments, the rate of 

return required to support new generation will reflect the relative risks and rewards involved.  Where 

the risks to repayment of debt or generation of a profit seem high, the generation may not be built.  In 

addition, generators are competing against other solutions, such as transmission investments.  Various 

techniques can often be used to mitigate these risks, such as power purchase agreements or other 

arrangements.  Ultimately, however, the decision to construct the generation will depend on market 

forces – i.e., expected energy prices vs. costs.   

 

                                                           175 Source:  Navigant Research (formerly Pike Research) report “Corporate and Institutional Procurement of 

Electricity,” 2011. 176 See, for example, the discussion of this topic in the 2013 Energy Procurement Plan of the Illinois Power Agency, 

http://www2.illinois.gov/ipa/Documents/IPA‐Plan_complying_with_12‐0544‐Order.pdf, pg. 3.  Municipal 

aggregation is a process by which a municipal government can combine the electricity supply needs of its residences 

and small businesses into a pool to obtain volume pricing for them.  

-

500.0

1,000.0

1,500.0

2,000.0

2,500.0

3,000.0

1998 2003 2009 2015 (Projected) 2020 (Projected)

Total Energy-Only C/I Sales (MWh Millions) Total Utility C/I Sales (MWh Millions)

Total C/I Sales (MWh Millions)

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 50 October 8, 2013

In contrast, under the traditionally regulated model, the utility determines whether to build generation 

(often with its regulator or as part of its IRP) and may choose to build generation based on its value and 

costs compared to other options including wholesale purchases.  The utility under this model does not 

have to consider generation as a standalone investment, but may view it in comparison with 

transmission or other investments.  And the “franchise” utility has clear responsibility to procure 

adequate supply to meet existing and future demand of customers.  Regulator oversight, including 

prudence reviews, takes the place of market forces under the traditionally regulated model. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 51 October 8, 2013

8.  Responsibilities for Planning and the Types of Planning Performed 

BPS planning functions encompass resource adequacy and transmission security planning.  Resource 

adequacy planning involves assessing and determining that adequate generation supply will be 

available to meet load.  Transmission security planning aims to ensure there is adequate transmission 

infrastructure to deliver generation to load centers.  There is some overlap of federal and state regulation 

with respect to these two areas.  The oversight of resource adequacy planning has traditionally been a 

state function while transmission security planning, with the important exception of transmission siting, 

has now become governed by federal law and regulation overseen by the FERC.  The planning of the 

distribution system is entirely under the oversight of state and local governments.  The key planning 

challenges to entities in both the traditionally regulated and competitive market regions are discussed 

below. 

8.1  The Transmission Planning Framework 

In recent years, FERC has issued two key Orders governing transmission planning:  Order No. 890 and 

Order No. 1000.  Both apply regardless of an entity’s RTO/ISO affiliation; however, the manner in which 

entities address their requirements differs based on whether they operate under an RTO/ISO. 

 

Order No. 890 required that transmission providers participate in open, coordinated, and transparent 

transmission planning on both local and regional levels.177  The planning process had to meet FERCʹs 

nine planning principles, which include: coordination, openness, transparency, information exchange, 

comparability, dispute resolution, regional coordination, economic planning studies, and cost allocation.  

Transmission planning processes under Order No. 890 also had to be open to customers, and customers 

must be given necessary planning information.  Future system plans were required to be coordinated 

with customers.178 

 

Order No. 1000 built upon and extended many of the ideas initially introduced under Order 890.  

Among the reforms introduced in Order No. 1000 are requirements for a regional transmission planning 

process, cost allocation, consideration of public policy requirements, elimination of the Right of First 

Refusal (ROFR) in wholesale tariffs to construct new facilities, and improvements to the coordination 

between neighboring transmission planning regions for new interregional transmission facilities.  Order 

No. 1000‐A, issued in May 2012, and Order No. 1000‐B, issued October 2012, made some clarifications.  

Each of these changes is discussed in the sections that follow. 

8.1.1  Regional Planning and the Inclusion of Non‐Incumbent Transmission Developers 

The Commission carried the Order No. 890 planning principles, designed principally to increase 

transparency, into Order No. 1000, requiring that all regional planning processes comply with those 

                                                           177 Order No. 890 at PP 3, 524. 178 Ibid., P 3. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 52 October 8, 2013

principles.  Order No. 1000 also mandated that stakeholders be provided with an opportunity to 

participate in that process in a timely and meaningful manner.179 

 

The planning requirements in FERC Order No. 1000 require that each public utility transmission 

provider participate in a regional transmission planning process that produces a regional transmission 

plan and that complies with certain transmission planning principles.  Through the regional 

transmission planning process, public utility transmission providers must evaluate, in consultation with 

stakeholders, alternative transmission solutions that might meet the needs of the transmission planning 

region more efficiently or cost‐effectively than solutions identified by individual public utility 

transmission providers in their local transmission planning process.  Public utility transmission 

providers have the flexibility to develop, in consultation with stakeholders, procedures by which the 

public utility transmission providers in the region identify and evaluate the set of potential solutions that 

may meet the region’s needs more efficiently or cost‐effectively.180  The procedures must result in a 

regional transmission plan that reflects the determination of the set of transmission facilities that more 

efficiently or cost‐effectively meet the region’s needs. 

 

In the centralized markets where RTO/ISOs have formed, transmission planning generally encompasses 

large regions and is coordinated around a centralized processes administered by the RTO/ISO.  In terms 

of identifying viable transmission solutions, several regions, including PJM,181 ISO‐NE, and CAISO, 

adopted a competitive solicitation process in their transmission planning procedures as a result of Order 

No. 1000.182 

 

In areas where a traditionally regulated model remains, planning is coordinated by the vertically 

integrated utilities within their territory.  In several non‐RTO areas planning groups were established to 

coordinate planning activities and meet Order Nos. 890 and 1000 requirements for regional planning 

processes.  For example, the Southeastern Regional Transmission Planning (SERTP) includes 

predominantly jurisdictional and non‐jurisdictional systems in SERC that have come together to form a 

group for preparing a regional planning process proposal for purposes of responding to FERC Order 

No. 1000.  Also, the California Transmission Planning Group (CTPG) includes jurisdictional and non‐

jurisdictional systems (including LADWP).  The CTPG was originally formed in 2009 to comply with 

Order No. 890, and was reorganized to address FERC Order No. 1000. 

                                                           179 Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, 136 FERC ¶ 61,051 

at P 150 (2011) (“Order No. 1000”). 180 Note that the Commission uses the phrase “more efficient and cost‐effective” and “more efficient or cost‐

effective” in Order No. 1000 creating an ambiguity as to whether a project should be both efficient and cost‐effective. 181 See “With no ROFR provisions at issue, FERC mostly reaches consensus on Order 1000 Filings,” SNL Financial, 

Apr. 18, 2013. 182 The CAISO competitive solicitation process applies to lines above 200 kV.  See “FERC mostly accepts CAISO 

Order 1000 filing, but Clark dissents on two issues,” SNL Financial, Apr. 19, 2013.  The ISO‐NE process was 

introduced conditionally.  See “With no ROFR provisions at issue, FERC mostly reaches consensus on Order 1000 

Filings,” SNL Financial, Apr. 18, 2013.  For example, ISO‐NE uses its Attachment K process, where merchant 

transmission solutions can be proposed in response to a need as identified in the Regional System Plan.  

Additionally, ISO‐NE may, acting through its Board, solicit transmission solutions as alternative proposals from the 

market when no viable solutions have been proposed.  Similarly, the NYISO, through its Comprehensive Reliability 

Planning Process, may also solicit market solutions to meet reliability needs. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 53 October 8, 2013

 

While Order No. 1000 does not require non‐public utilities to participate in the planning processes, it 

does encourage them to do so.183  Some non‐public utilities have chosen to enroll184 in transmission 

planning regions depending on whether they have load in the region where they seek to sponsor a 

project.185 

 

FERC also does not require Merchant Transmission companies to participate in Order No. 1000 

processes, recognizing that the costs of those projects are recovered through negotiated rates and that 

Merchant Transmission developers assume the entire risk for development of these projects.  However, 

if a Merchant Transmission developer wishes to take advantage of the regional cost allocation 

mechanisms, it must participate in the regional planning process.186 

 

Several regions, RTO and non‐RTO, initially elected to have their state regulatory bodies decide which 

competing transmission developer projects would be selected; the Commission rejected this option.187  

While the state may participate in the decisions, it is the planning region that must make the ultimate 

decision. 

8.1.2  Interregional Planning Coordination 

In the Order No. 1000 Final Rule, FERC adopted several measures to broaden the geographic scope of 

transmission planning and enable an adequate analysis of the benefits associated with interregional 

transmission facilities that address transmission needs in an efficient or cost‐effective manner.188  FERC 

required that each public utility transmission provider, through its regional transmission planning 

process, (1) develop procedures for sharing information regarding the respective needs of neighboring 

transmission planning regions; (2) develop and implement procedures for neighboring public utility 

transmission providers to identify and evaluate transmission facilities that are proposed to be located in 

both regions; (3) exchange planning data and information between neighboring transmission planning 

regions at least annually; and (4) maintain a website or e‐mail list for the communication of information 

related to interregional transmission coordination.189  However, the Commission declined to require a 

                                                           183 See Order No. 1000 at PP 815‐822 and Order No. 1000‐A at P 774. 184 As an enrollee, the entity will have access to regional cost allocation for its accepted projects and will also have 

voting rights in the transmission planning process; non‐enrollees do not have these rights. See “With no ROFR 

provisions at issue, FERC mostly reaches consensus on Order 1000 Filings,” SNL Financial, Apr. 18, 2013.  For 

example non‐public utility enrollees include LIPA in the NYISO regional planning process, Tennessee Valley 

Authority (TVA), Associated Electric Cooperative Inc. (AECI), and East Kentucky Power Co‐op (EKPC) all joined 

the SERTP regional planning process for purposes of the FERC Order 1000.  Also, LADWP joined the California 

Transmission Planning Group for purposes of FERC Order No. 890 and for FERC Order No. 1000 regional planning 

process. 185 See “With no ROFR provisions at issue, FERC mostly reaches consensus on Order 1000 Filings,” SNL Financial, 

Apr. 18, 2013.  186 See Order No. 1000‐A at P 275. 187 See SCE&G (ER13‐107‐000), NYISO (ER13‐102‐000), and CAISO (ER13‐103‐000) Orders. 188 See Order No. 1000 at P 368. 189 Ibid. at P 345. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 54 October 8, 2013

formal planning agreement between public utility transmission providers of neighboring transmission 

planning regions, as it proposed.190 

 

Both traditionally regulated and centralized market (RTO/ISO) regions have implemented processes for 

the sharing and exchange of interregional planning data.  Furthermore, in response to the interregional 

requirements of FERC Order No. 890, and the more specific requirements of the FERC Order No. 1000 

Final Rule, there are several coordinated interregional planning initiatives underway in both RTO and 

non‐RTO regions to comply with these requirements.  One example is the Northeastern ISO/RTO 

Planning Coordination Protocol (“the Protocol”), a document, describing a set of processes and 

procedures through which coordinated planning activities will be conducted and implemented by the 

ISOs and RTOs in the northeastern United States and Canada.191  The Protocol provides a process for 

conducting interregional planning studies, and includes: the responsibilities of the stakeholder process, 

data and information exchange, the coordination of project evaluation criteria, procedures for 

conducting interregional assessments, and procedures for the evaluation of projects that can address 

regional needs consistent with FERC Order No. 1000.  The Protocol was first developed to support the 

Northeastern Coordinated System Plan, one of the first comprehensive interregional planning studies. 

 

Public utility transmission providers that are not affiliated with an RTO/ISO have responded to the 

requirements of FERC Order No. 1000 using an approach similar to the above, perhaps relying on an 

existing framework that was developed in response to FERC Order No. 890 requirements or earlier.  

These systems, whether vertically integrated utility or other transmission service provider, typically 

participate in a regional transmission planning process that provides a similar framework for addressing 

the requirements of FERC Order No. 1000.  For example, Puget Sound Energy, a utility in the Pacific 

Northwest, participates in the ColumbiaGrid regional transmission planning process, which is governed 

by the provisions of its Planning and Expansion Functional Agreement (“PEFA”).  The PEFA addresses 

member entities’ data and analyses requirements, and is designed to facilitate multi‐system planning 

through a coordinated, open, and transparent process.192  The Southeastern Regional Transmission 

Planning (“SERTP”) association is a similar organization, which includes jurisdictional and non‐

jurisdictional utilities in the southeast. 

8.1.3  Cost Allocation 

Order No. 1000 also mandated that each planning region develop a cost allocation mechanism for 

allocating the costs of projects that are selected in the planning process for inclusion in a regional plan.  

Transmission cost allocation is a subject of considerable debate among various stakeholders in the 

electricity industry.  Cost allocation raises a number of questions depending on the stakeholder’s 

perspective.  From the state regulator and end‐use customer side, issues pertain to electricity rates.  For 

other stakeholders, it is a question of who is a beneficiary of a new transmission project.  For renewable 

energy developers, cost allocation can be a significant detriment to the development and delivery of 

                                                           190 See Ibid. at P 475. 191 The parties to the Protocol are PJM, NYISO, and ISO‐NE.  Ontarioʹs Independent Electricity System Operator, 

Hydro‐Quebec, and New Brunswick Power are not parties to the Protocol but have agreed to participate in the data 

and information exchange process and in regional planning studies for projects that may have interregional impacts. 192 See ColumbiaGrid PEFA, Third Amendment and Restatement. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 55 October 8, 2013

renewable resources.193  Some stakeholders advocate “socializing,” or spreading new transmission costs 

as widely as possible while others argue that only those who receive direct reliability and/or economic 

benefits from new transmission assets should pay.  In addition, parties have argued that the socialization 

of transmission costs masks the true delivered cost of power from specific resources and therefore 

distorts the generation and consumption incentives of different resources or loads. 194 

 

Order No. 1000 adopted six principles for both regional and interregional project cost allocation, 

including that allocated costs must be roughly commensurate with benefits and the cost allocation 

process must be transparent.195 

 

A PJM paper identified five general cost allocation approaches in use in the U.S., including allocation : 1) 

between load and generation, 2) by amount of usage, 3) by peak consumption or generation, 4) by flow‐

basis, and 5) by a monetary impact basis. 196  

Table 4. Examples of Cost Allocation Approaches Used by Planning Region197 

Methodology Description RTO/ISO or Planning Region

License Plate Each utility recovers the costs of its own transmission investments (usually located within its footprint).

Southeast CAISO (< 200 kV) ISO-NE (< 115 kV)198 WECC (outside CAISO)

Beneficiary Pays Various formulas that allocate costs of transmission investments to those entities that benefit from a project, even if the project is not owned by the beneficiaries. In the case of FRCC, system benefits include avoided transmission costs.

FRCC (>230kV)199 PJM (<500 kV) NYISO (reliability and economic)200 MISO (<345 kV)

                                                           193 See “A Survey of Transmission Cost Allocation Issues, Methods and Practices,” PJM, Mar. 10, 2010, pg. 3 (“A 

Survey of Transmission Cost Allocation Issues, Methods and Practices”). 194 See A Survey of Transmission Cost Allocation Issues, Methods and Practices, at pg. 3. 195 Order No. 1000 at P 622. 196 See A Survey of Transmission Cost Allocation Issues, Methods and Practices, pg. 1. 197 Source:  Navigant Consulting, Inc. 198 Applies to non‐Pool Transmission Facilities (PTF) only.  Transmission lines that are determined to contribute to 

the reliability of the system (based on tariff criterion) that are less than 115kV are also allocated using a postage 

stamp methodology. 199 The Beneficiary Pays cost allocation method applies to FRCC’s Cost Effective and/or Efficient Regional 

Transmission Solution (“CEERTS”) Projects. 200 For reliability upgrades specific locational violations occurring in a zone or zones are allocated to the zone or 

zones in which those violations occur.  Upgrades solving reliability violations in only part of the NYISO due to 

constrained interfaces are allocated to the zones causing the violation based on each affected zone’s share of the 

coincident peak load of the affected zone.  Upgrades solving NYISO‐wide violations are allocated to all zones in the 

NYISO based on their share of the coincident peak load in the NYISO.  Costs for economic upgrades are allocated 

based upon the zonal share of total energy expenditure savings across zones that have energy savings.  Load serving 

entities identified as beneficiaries are eligible to vote on whether to continue with the project. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 56 October 8, 2013

Methodology Description RTO/ISO or Planning Region

Postage Stamp Transmission costs are recovered uniformly from all loads in a defined market area (e.g., RTO-wide in ERCOT and CAISO). Regions using load ratio share either allocate based on coincident peak demand or energy (MWh) of the member systems, as described in its tariff. Some regions use a combination of methods for allocating costs. For example, SPP uses a ratio of 33% postage stamp and 67% Beneficiary Pays for allocating costs for reliability projects. Similarly, for >=345kV projects, MISO uses 20% Postage Stamp and 80% Beneficiary Pays for reliability projects.

ERCOT PJM (>= 500 kV) MISO (>=345kV) CAISO (>= 200kV reliability and economic) SPP(reliability201; economic >345 kV) ISO-NE (>= 115 kV)

Merchant Cost Recovery

Project sponsors recover the cost of the investment (e.g., via negotiated rates with specific customers); largely applies to DC lines where transmission use can be controlled.

CAISO ERCOT PJM NYISO ISO-NE

Multi-Value Project (MVP)

100% of the annual revenue requirements for MVP are allocated on a system-wide basis to Transmission Customers that withdraw energy from the system, including export and wheel-through transactions sinking outside the region, and recovered through an MVP Usage Charge.

MISO

Tehachapi Location Constrained Resource Interconnection (LCRI) Approach

Upfront postage stamp funding of project, later charged back to interconnecting generators.

CAISO

8.1.4  Planning for Public Policy Requirements 

Prior to Order No. 1000, some regions already took into account public policy requirements to the extent 

that they drove specific actions such as plant retirements to meet federal and state environmental 

mandates.  Some single state regions also took into account state renewable resource integration targets. 

However, Order No. 1000 made it a requirement to consider these public policy requirements as part of 

a region’s planning process.   

8.1.4.1  Planning for Public Policy Requirements in Order No. 1000 

Order No. 1000 requires that regional planners consider “public policy requirements” when conducting 

their studies.  In the final rule, FERC narrowed the definition to include only “enacted statutes (i.e., 

passed by the legislature and signed by the executive) and regulations promulgated by a relevant 

                                                           201 For all upgrades at all voltage levels and with upgrade cost greater than $100,000. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 57 October 8, 2013

jurisdiction, whether within a state or at the federal level.”202  FERC did not dictate how this would be 

accomplished, permitting stakeholders to propose different approaches that it would evaluate.203 

  

While the provisions are still largely untested, several issues have arisen relating to the “public policy” 

planning requirements.  The Commission rejected the NYISOʹs intention to ask only incumbent 

transmission owners to propose solutions to meet public policy requirements, finding this to be 

discriminatory.  It also ordered that the NYISO must detail how non‐transmission alternatives can be 

submitted for consideration.204  Finally, FERC rejected the NYISO’s plan to have the New York PUC 

decide which public policy projects should be advanced, noting that this was a decision the NYISO itself 

must make.  In California, the Commission required that the CAISO have authority to order incumbent 

utilities to build economic or policy‐driven lines that no other qualified transmission owner was willing 

to build.205 

8.1.4.2  Integration of Renewable Resources 

The location of renewable resources such as wind, large‐scale solar, and geothermal generation is largely 

dictated by nature, due to the location of and the inability to transport the fuel source of renewables.  

Connecting these location‐constrained resources to the transmission network in the most cost‐effective 

manner can present special challenges. 

 

In the Northeast, state regulators and regional planning authorities acknowledge the hurdles of 

transmission development to integrate renewable resources.  The six New England states206 and New 

York have adopted some form of RPS, which require utilities and other suppliers of retail service to 

obtain specified percentages of their electricity from power plants that run on renewable fuels.  An 

overview of the RPS objectives in each state has been provided in Figure 9, in Section 6.2.2 of this paper. 

 

Transmission infrastructure development in the Mid‐Atlantic region is almost exclusively driven by 

PJM’s Regional Transmission Expansion Planning Process (RTEP).  As part of that process, PJM 

evaluates alternatives that integrate emerging aggregated power resource areas including projects that 

address reliability issues posed by clusters of development based on renewable energy sources. 

 

Texas leads the nation in wind power, most of which comes from its remote western plains, and it has 

made development of supporting transmission infrastructure a priority.  Transmission upgrades to 

support additional wind generation are planned by ERCOT with all transmission system construction 

costs being borne by the ERCOT grid and ultimately by load within ERCOT.  All costs for wind 

generation interconnections are rolled into the ERCOT system‐wide transmission costs and assigned to 

load in the same manner as system upgrades.   

                                                           202 Order No. 1000 at P 2. 203 See “With no ROFR provisions at issue, FERC mostly reaches consensus on Order 1000 Filings,” SNL Financial, 

Apr. 18, 2013. 204 See “FERC orders changes to NYISO Order 1000 filing, including public policy provisions,” SNL Financial, Apr. 

22, 2013. 205 See FERC mostly accepts CAISO Order 1000 filing, but Clark dissents on two issues, SNL Financial, Apr. 19, 2013. 206 The RPS in Vermont are goals, not mandatory requirements at this time. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 58 October 8, 2013

In the South Central region, while there are several transmission projects being developed by 

Transmission Owners, like the Mid‐Atlantic region, transmission system development is led primarily 

by the region’s RTO, the Southwest Power Pool (SPP). 

 

Renewable resource development in the Southeast has been limited.  Renewables, like solar power and 

wind turbines, are faced with several challenges to their consistent and widespread use in the Southeast.  

Solar energy requires large tracts of open land to install, which are not readily available, and cloud cover 

limits its reliability.  In addition, on‐shore locations with good wind profiles are generally not available 

in this region.  Unlike the states in other geographic regions of the United States, those in the Southeast 

generally lack RPS requirements that would further encourage the development of renewable resources. 

 

The Midwest has several large‐scale studies underway.  The Regional Generation Outlet Study 

(RGOS)207 identifies major areas of renewable energy development zones, where transmission can be 

built in a “build it and they will come approach.”  Finally, the Joint Coordinated System Plan (JCSP) was 

a multi‐RTO/ISO initiative208 led by the Midwest Independent System Operator (MISO) to determine 

transmission infrastructure that could be constructed to support the delivery energy and capacity from 

renewable resources in the Midwest to load centers in the east. 

 

Transmission construction in the West to integrate renewable resources is best typified by the 

development of numerous, large transmission line projects intended to tap vast renewable resource 

reserves.  California has initiated the Renewable Energy Transmission Initiative (RETI) to help identify 

the transmission projects needed to accommodate the State’s renewable energy goals, support future 

energy policy, and facilitate transmission corridor designation and transmission and generation siting 

and permitting. 

 

The processes used to identify transmission solutions are strikingly different between some RTO and 

non‐RTO interregional planning regions.  Some interregional transmission planning approaches for RTO 

regions have proposed a systematical approach for identifying transmission solutions to meet a public 

policy or reliability need.  For example, as mentioned earlier a few RTOs will solicit transmission 

solutions using a RFP approach.  In contrast, some non‐RTO planning regions will receive input from 

stakeholders on a public policy requirement, and evaluate the currently proposed transmission projects 

to determine which solution may best meet the requirement. 

 

                                                           207 Background information on the RGOS is located at 

https://www.midwestiso.org/Planning/Pages/RegionalGenerationOutletStudy.aspx. 208 Members are MISO, PJM, SPP, and TVA.  This effort performed a long‐term planning study incorporating both 

economic and reliability analysis of system performance for the combined four JCSP areas in collaboration with the 

parallel Department of Energy Eastern Wind Integration & Transmission Study, which will provide underlying 

input assumptions for generation scenarios.  There was a subsequent Eastern Interconnection wide study performed 

under the Eastern Interconnection Planning Collaborative.  The final reports for this study are available at: 

http://www.eipconline.com/. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 59 October 8, 2013

8.1.4.3  ROFR and Non‐Incumbent Transmission Owners 

Order No. 1000 envisions a level playing field where new transmission developers can compete with 

established transmitting utilities for the right to build new transmission lines.  The Commission 

determined that incumbent utilities must remove provisions from their Commission‐jurisdictional tariffs 

and agreements that grant them a right of first refusal (ROFR) to construct transmission facilities.209  

These provisions, FERC stated, have the potential to undermine the evaluation of more efficient or cost‐

effective solutions to regional transmission needs.210 

 

In a May 17, 2013 ISO‐NE Compliance Order, the FERC stated it would eliminate the ROFR requirement 

in many instances.  The Commission, however, did agree that to avoid delays in the development of 

transmission facilities needed to resolve a time‐sensitive reliability criteria violation, certain reliability‐

related transmission projects should be exempt from the competitive solicitation ʺin certain limited 

circumstances.ʺ211  One such circumstance would be when a project is needed in three years or less to 

solve a reliability issue.212  Also, while the ROFR for incumbent TOs to build and own new transmission 

facilities with costs allocated regionally has been eliminated, the TOs retain ROFR to build and own local 

transmission facilities (under 200 kV) located within the existing service territory of the TO.213 

8.2  Transmission Siting and Transmission Grid Expansion 

The authority over transmission siting is a patchwork quilt of overlapping and sometimes unclear 

divisions of authority between numerous governmental bodies deriving authority under several bodies 

of law.  While the majority of siting authority currently lies with the states, there are a number of 

instances where federal approvals are required. 

 

Under current law, the state PUCs often have the primary authority to issue certificates of public 

convenience and necessity, which permit electric utilities to construct transmission lines.  Although prior 

certification from FERC is required for pipeline facilities under Section 7 of the NGA,214 there is no 

analogous certification requirement under the FPA.  Furthermore, at the federal level, there is currently 

no comprehensive program for regulating the construction of electric utility facilities except in the 

instance of nuclear and hydroelectric projects.215 

                                                           209 See Order No. 1000 at P 226. 210 Ibid. at P 253. 211 See UPDATE: FERC explains reasons for finding public interest standard overcome in ISO‐NE ROFR decision, 

SNL Financial. May 21, 2013.  See also, ISO New England Inc., 143 FERC ¶ 61,150 at P236 (May 17, 2013). 212 See UPDATE: FERC explains reasons for finding public interest standard overcome in ISO‐NE ROFR decision, 

SNL Financial. May 21, 2013.  This decision appears to support part of PJM’s approach to ROFR, which provides that 

its ROFR would still apply to projects that did not have enough time to go through the competitive solicitation 

process.   213 Both MISO and CAISO both proposed this exception to the elimination to ROFR.  See “With no ROFR provisions 

at issue, FERC mostly reaches consensus on Order 1000 Filings,” SNL Financial, Apr. 18, 2013. 214  Natural Gas Act § 7, 15 U.S.C. § 717f (2001). 215  In fact, for non‐hydroelectric and nuclear projects the FPA expressly excludes the regulation of generating 

facilities.  Federal Power Act § 201(b), 16 U.S.C. § 824(b) (2001). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 60 October 8, 2013

At the state level, a certificate of public convenience and necessity for the construction of high‐voltage 

transmission facilities is required by many states.  The majority of states have at least one agency/board 

that has authority to issue or deny construction permits.216  About two‐thirds of the states that issue 

certifications focus primarily on lines greater than 60 kV in size.217 

 

EPACT 2005 established a limited role for DOE and FERC in transmission siting.  The act directed DOE 

to create “transmission corridors” in locations with adequate transmission capacity that had “national 

interest” implications.218  The act also granted FERC secondary authority over transmission siting in 

these corridors.219  This authority may not be exercised by FERC unless the state where the facility would 

be sited lacks the authority to issue the permit, the applicant does not qualify for the permit in the state, 

or the state has “withheld approval” of the permit for more than one year.220  Since the passage of this 

law there have been proposals to both expand FERC’s authority as well as contract it.  There have also 

been several court cases which have further limited FERC’s backstop authority.221 

8.3  Adequacy Planning and Integrated Resource Planning 

The oversight of adequacy (resource) planning remains primarily a state function; however, FERC has 

introduced some regulation governing the interconnection of generation resources to establish an open 

and transparent process. 

8.3.1  Integrated Resource Planning and Procurement Plans 

Many states developed and retained approaches to address increases and decreases in demand and 

changes in their generation fleets, while doing so in a cost‐effective manner that maintains required 

levels of reliability.  Integrated resource planning222 began in the late 1980s as states began to respond to 

the oil embargos of the 1970s and nuclear cost overruns that occurred during the same time period and 

into the 1980s.  

 

                                                           216  Those states that do not have oversight of transmission siting except where it pertains to specific locational 

attributes (i.e., river crossings) are Georgia, Indiana, Louisiana, and Oklahoma.  Several states have multiple agency 

processes.  See Edison Electric Institute  

State Generation & Transmission Siting D I R E C T O R Y (2012) available at 

http://www.eei.org/issuesandpolicy/transmission/Documents/State_Generation_Transmission_Siting_Directory.pdf. 217 Ibid. 218 Energy Policy Act 2005, § 1221. 219 Ibid. 220 Ibid. 221 See, e.g., Piedmont Envtl. Council v. FERC, 558 F.3d 304 (4th Cir. 2009), cert. denied sub nom, Edison Electric Institute v. Piedmont Envtl Council, 130 S. Ct. 1138 (2010); California Wilderness Coalition, et al. v Dept. of Energy, 631 F.3d 1072 

(9th Cir. 2011). 222 The integrated resource plan (IRP) is a comprehensive planning process designed to provide insight into how a 

utility may best meet its resource needs over a long‐term (10‐20 year) planning horizon while considering all 

resource options and a range of risks and uncertainties that are inherent in the utility industry.  An IRP is typically 

developed with considerable public and other stakeholder involvement, and results in a preferred implementation 

plan. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 61 October 8, 2013

IRPs are typically long‐term, with a 20‐year period being the most common planning horizon and 

periodic updates to reflect changing conditions every 2‐5 years.223  Steps taken in an IRP include 

forecasting future loads, identifying potential supply side and demand‐side resource options to meet 

those future loads and their associated costs, determining the optimal mix of resources taking into 

account transmission and other costs, receiving and responding to public participation (where 

applicable), and creating and implementing a resource plan.224  IRPs consider system operation, such as 

diversity, reliability, dispatchability, and other factors of risk.225  Commissions do not actively monitor 

utility actions that are taken based on the IRP, but rather review the results of the IRP during rate cases, 

prudence reviews, fuel cost adjustments, certificates of public convenience and necessity, review of 

utility power purchases, and resource acquisition cases.226     

Many states began to reconsider the IRP approach in the mid‐1990s as the electric industry began to 

restructure.227  Several states either repealed them with restructuring laws, or began to ignore them.228   

Recently, however, there has been interest in returning to integrated resource planning in some of the 

states that have restructured.229   

 

The presence and status of IRP procedures vary with some state IRP rules remaining unchanged, other 

states have amended or repealed their rules, and some have reinstated their IRP rules.  Figure 12 shows 

those states that currently have IRP rules, states that are developing or revising IRP rules, and states that 

do not have an IRP rule. 

 

                                                           223 See Rachel Wilson and Paul Peterson, “A Brief Survey of State Integrated Resource Planning Rules and 

Requirements Prepared for the American Clean Skies Foundation”, Synapse Energy Economics, Inc. (April 28, 2011),  

pp. 7‐8 (“A Brief Survey of State Integrated Resource Planning Rules and Requirements”). 224 See A Brief Survey of State Integrated Resource Planning Rules and Requirements, pg. 3. 225 Energy Policy Act of 1992, §111(d)(19).  Text available at: http://www.ferc.gov/legal/maj‐ord‐reg/epa.pdf. 226 See A Brief Survey of State Integrated Resource Planning Rules and Requirements, pg. 4. 227  Ibid. at p. 13. 228 Ibid. at p. 13. 229 Ibid. at p. 16. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 62 October 8, 2013

Figure 12. States with Integrated Resource Planning (or similar planning process) 

 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 63 October 8, 2013

9.  Innovation and the Levels of Research and Development Pursued 

Innovations in the electric industry, technical and economic, have come about through the application of 

research and development of projects by the electric sector, governments, and other industrial, 

communications, and technology sectors.  These have affected the electric sector’s regulatory model in a 

number of ways.  This section reviews several key major innovations and their relative impacts on the 

traditionally regulated and centralized market models.  In addition, this section reviews the ongoing 

impact of these market models on innovation, including research and development.  

9.1  Declining Costs and Increasing Flexibility of Generation Technologies 

Expansion of combined heat and power (CHP) and natural gas‐fired combined cycle (CC) plants in the 

late 1970s into the 1990s was a strong contributing factor to growth in the class of non‐utility generation. 

Much of the early impetus for CHP and CC might be attributed to the PURPA (1978) provisions that 

required utilities to purchase power at “avoided cost” from cogenerators, and to federal legislative and 

regulatory actions that led to open access to gas supplies.230 

 

But just as significant have been the technical and economic strides of these technologies relative to other 

thermal and nuclear generation.  In its 2013 Annual Energy Outlook, the U.S. Energy Information 

Administration (EIA) estimated that a new, advanced CC power plant would cost approximately 

$1,006/kW (2011$) to build and would generally be around 400 MW in size, whereas a new scrubbed coal 

power plant would cost approximately $2,883/kW (2011$) to build and would generally be around 1,300 

MW in size.231  In addition to reduced overnight costs, the levelized cost of many of these sources has 

dropped near or below that of a new coal plant, as seen in Table 5.  The levelized cost is the cost per unit 

of electricity generated, including capital costs, fixed and variable operations and maintenance (O&M) 

costs, fuel costs, and transmission investment costs.  Note that the values provided in Table 5 do not 

include tax credits, nor do they assume any potential CO2 emission‐related costs. 

                                                           230 Natural Gas Policy Act of 1978, Pub. L. No. 95‐621, 92 Stat. 3351 (codified at 15 U.S.C.§§ 3301‐3432 (1982)). 

Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, Order No. 436, 50 FR 42408 (Oct. 18, 1985), FERC 

Stats. & Regs. [Regulations Preambles 1982‐1985] 30,665 (1985), vacated and remanded, Associated Gas Distributors v. 

FERC, 824 F.2d 981 (D.C. Cir. 1987), cert. denied, 485 U.S. 1006 (1988), readopted on an interim basis, Order No. 500, 52 

FR 30334 (Aug. 14, 1987), FERC Stats. & Regs. [Regulations Preambles, 1986‐1990]  30,761 (1987), remanded, 

American Gas Association v. FERC, 888 F.2d 136 (D.C. Cir. 1989), readopted, Order No. 500‐H, 54 FR 52344 (Dec. 21, 

1989), FERC Stats. & Regs. [Regulations Preambles 1986‐1990]  30,867 (1989), rehʹg granted in part and denied in part, 

Order No. 500‐I, 55 FR 6605 (Feb. 26, 1990), FERC Stats. & Regs. [Regulations Preambles 1986‐1990]  30,880 (1990), 

affʹd in part and remanded in part, American Gas Association v. FERC, 912 F.2d 1496 (D.C. Cir. 1990), cert. denied, 111 S. 

Ct. 957 (1991); Pipeline Service Obligations and Revisions to Regulations Governing Self‐Implementing Transportation and Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, Order No. 636, F.E.R.C. STATS. & REGS. ¶ 30,939 

(1992), order on reh’g, Order No. 636‐A, F.E.R.C. STATS. & REGS. ¶ 30,950 (1992), order on reh’g, Order No. 636‐B, 61 

F.E.R.C. ¶ 61,272 (1992), notice of denial of reh’g, 62 F.E.R.C. ¶ 61,007 (1993), aff’d in part and vacated and remanded in 

part, United Dist. Cos. v. FERC, 88 F.3d 1105 (D.C. Cir. 1996), order on remand, Order No. 636‐C, 78 F.E.R.C. ¶ 61,186 

(1997).. 231 U.S. Energy Information Administration, Assumptions to the Annual Energy Outlook 2013: Electricity Market Module.  

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 64 October 8, 2013

 

Table 5. Estimated National Average Levelized Cost of New Generation Resources in 2018 

Technology Total System Levelized Cost (2011 $/MWh)

Conventional Coal $100.10

Advanced Coal $123.00

Advanced Nuclear $108.40

Natural Gas Conventional CC $67.10

Natural Gas Advanced CC $65.60

Geothermal $89.60

Biomass $111.00

Wind $86.60

Solar PV $144.30

Source: U.S. Energy Information Administration, Annual Energy Outlook 2013, December 2012 

The cost‐effectiveness of smaller increments of generation has reduced the need for utilities to 

periodically have large “lumpy” capital‐intensive investments and corresponding large additions to 

their rate base leading to large one‐time rate increases.  Since generation can be added in smaller 

increments and with lead times closer to the time of anticipated need, the investment cycle has become 

smoother.  As compared with large generation installations, combined cycle technology is more 

modular, has relatively lower capital costs than base‐load coal and nuclear plants, has been widely 

adopted across the spectrum of regional markets, and has a decades‐long track record of performance.  

These factors reduce the risks relating to capital and construction, making it easier for merchant 

generation developers to get funding and for regulated utilities to go through the rate case process. 

However, the same widespread adoption of this technology, coupled with high levels of retirement in 

the coal fleet, may diminish supply diversity over time and increase volatility of electric energy prices.  

An indicator of this development may be seen in the high electricity market prices that were experienced 

in conjunction with high natural gas prices during 2003‐2008, followed by low power prices during the 

past four years as gas prices dropped back to pre‐2000 levels. 

 

Overall, competitive entry in wholesale markets, whether centralized or bi‐lateral, has likely bolstered 

investment in combined cycle plants.232  The converse argument, that continued improvement of 

combined cycle technology has augmented the movement away from the vertically integrated utility 

model in deregulated states, might be deduced from the coincidence of the technology’s expansion with 

the opening of markets, but the causal argument is not firm. 

                                                           232 Peter Kind, Disruptive Challenges: Financial Implications and Strategic Responses to a Changing Retail Electric 

Business, Edison Electric Institute (January 2013); Paul L. Joskow, “Regulation and Deregulation After 25 Years: 

Lessons Learned for Research in Industrial Organization,” Review of Industrial Organization, 26 (2) (March 2005), P. 

169‐193.  Joskow observes that “the adoption and rapid diffusion of efficient CCGT [Combined Cycle Gas Turbine] 

generating technology was stimulated by allowing competitive entry into electricity generation.” 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 65 October 8, 2013

9.2  Emergence of Demand Side Alternatives 

Active load control and application of energy management technologies gained prominence as utility 

tools in the 1980s, and continue to see technological and economic improvements today.  There has also 

been near‐continual improvement in the energy efficiency of most classes of energy‐using equipment, 

including but not limited to residential and commercial lighting, residential and commercial appliances, 

heating, ventilation, and air conditioning (HVAC), electric motors, electronics, and external power 

supplies.233  These active energy management efforts as well as efforts by utilities, regulators, and 

government energy agencies to incent or mandate adoption by electricity end users of higher efficiency 

equipment are collectively referred to as DSM.234  The active programs allow for the balancing of electric 

supply and demand on the system by adjusting the load, rather than the traditional balancing method of 

only adjusting the supply, and adoption of efficient products helps to reduce the growth rate of 

electricity demand. 

 

These technologies have affected utility operations, the electric sector’s regulatory model, and customers 

in distinct ways – on the scale of scope of utility investment, on the structure of retail rate tariffs, and on 

the nature of utility planning and utilities’ interaction with customers and other interest groups.  

 

DSM‐induced reductions in load growth reduce or defer the need for new generation plant investment 

and the costs of the DSM alternatives may be less than the cost of new generation.  By extension, these 

also reduce additions to utility rate base and the rate‐based earnings, all other things being equal.   

 

Traditional tariff structures for electric service include monthly fixed charges, per‐kW demand charges, 

and per‐kWh energy charges, and the rates under these tariffs are typically set to be sufficient to allow 

the utility to recover their ongoing operating costs as well as earn an allowed rate of return on their fixed 

investment.  However, it is also rare that the fixed (monthly and per‐kW) and volumetric (per‐kWh) 

charges  are fully in alignment with actual fixed and variable costs since most rate structures recovered a 

sizable portion of fixed costs and return on rate base from volumetric charges.  Recognition of this raised 

parallel concerns among utilities and DSM advocates – reductions in kWh sales could result in under‐

recovery of allowed earnings and/or fixed costs, and the risk of this under‐recovery could create 

disincentives for utilities to participate in or embrace DSM initiatives. In some states, an early solution 

for this included implementation of DSM rate adjustment mechanisms to levy surcharges on remaining 

kWh sales in order to correct for the “lost” fixed cost recovery.  While this approach is attractive to some 

utilities and to DSM advocates and fairly easy to implement, it also led to complaints from various 

parties that the customers employing DSM and receiving rate savings were being subsidized by 

customers that were not employing DSM and had been generally abandoned. 

 

                                                           233 U.S. Energy Information Administration, Annual Energy Outlook 2013 (May 2013). 234 Traditional demand side management has been practiced by utilities for many years, with and without load 

control technology.  Utilities have long used “interruptible” rates that provide large customers price breaks in 

exchange for allowing the utility to interrupt service – or request load reductions – on a limited basis.  These rates 

often require the utility to contact the customer in advance and seek the customer’s permission to curtail load.  

Technological advances have made DSM a much more reliable and responsive resource for utilities and grid 

operators.  Large blocks of DSM, often assembled by a “curtailment service provider,” are now being offered on a 

larger scale in several energy markets as an alternative to capacity and/or energy.   

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 66 October 8, 2013

Centralized market model regions are gradually implementing market rules that seek to place supply‐ 

and demand‐side options on equal footing with respect to bidding into capacity and energy markets.   

For instance, PJM allows energy efficiency and demand response (a type of DSM) to bid into its capacity 

market, thus competing with generation to ensure capacity is available to meet future demand needs.  

Traditionally regulated model regions seek to maintain equal footing for these two types of options 

through integrated resource plans vetted by state regulators.  In states with traditional regulation, 

agreements to provide demand response other than in arrangements directly with the utility may be 

viewed as the impermissible equivalent of exercising retail electric supplier choice.   

 

Similarly, trends in energy efficiency have contributed to predictions of much lower electricity demand 

growth in the future than were historically observed.235  The federal government has mandated or 

incentivized energy efficiency improvements in lighting, residential boilers, clothes washers, 

dishwashers, dehumidifiers, electric motors, walk‐in refrigerators and freezers, and external power 

supplies among others, with the result that these items use far less energy as compared to earlier models.  

In addition, 20 states have set utility Energy Efficiency Resource Standards (EERS) for electric (and 

sometimes natural gas) consumption, mandating specific reductions in future demand or demand 

growth, while an additional 7 states have nonbinding goals for such reductions.236  Additionally, federal, 

state, and local governments are encouraging energy efficiency through appliance standards, building 

codes, and energy efficiency standards for public buildings.  Again, the traditional paradigm in which 

vertically integrated utilities obtain earnings through the capital invested to install the infrastructure to 

supply electricity is challenged by these trends.  But some also argue that current trends toward lower 

growth are more a result of current economic conditions rather than a long‐term trend. 

9.3  Smart Grid 

In the last decade, or less, ”Smart Grid” has become a hot topic in political and academic circles as well 

as other groups not traditionally involved in the regular processes of the electric sector.  The term 

generally refers to a more integrated, information‐based, and adaptive electric system, usually involving 

communication flows among users, operators, devices, and systems.  Integration of the Smart Grid is 

growing, as Smart Grid technologies continue to be developed, promising better grid management and 

improvements to DSM.  The expectation is that Smart Grid implementation will generate potential 

savings to customers by providing them the tools to manage their energy consumption habits and costs, 

as well as providing potential savings to utilities and their customers through operating efficiencies.   

The utility savings would inure to the benefit of utilities in both types of markets.  Similarly, customers 

can benefit from smart meters and usage information under both models.  Time of Use pricing, including 

peak and off‐peak pricing, would enhance the potential for savings.  To the extent that unbundled 

pricing is generally only available in the retail choice structure, customers may have greater 

opportunities to generate savings based on energy pricing options.   

 

                                                           235 U.S. Energy Information Administration, Annual Energy Outlook 2013 (May 2013). 236 EERS states: Arkansas, Connecticut, Delaware, Florida, Hawaii, Illinois, Indiana, Iowa, Maine, Maryland, 

Massachusetts, Michigan, Missouri, New York, Ohio, Pennsylvania, Rhode Island, Texas, Vermont, Virginia, 

Wisconsin. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 67 October 8, 2013

The implementation of Smart Grid, and particularly advanced metering infrastructure (AMI), also 

creates the possible need for these companies to outsource at least a portion of the associated data 

management with no addition to rate base for expanded system costs.  These risks are the same in both 

market models.  Since Smart Grid technologies are still relatively new, there is a risk to companies that 

implement Smart Grid that pressure to incorporate full expectations of promised benefits will expose 

utilities to unrecoverable costs if benefits do not materialize.  Finally, but perhaps most substantially, 

Smart Grid technologies have the potential to open up the electric system to greater risk of cyber‐attacks.  

Again, these risks are the same under both market models, with the difference being that a “wires only” 

company, as compared to a vertically integrated utility, may have a smaller cushion with which to 

absorb these risks without seeking rate relief. 

 

From a traditional regulated versus centralized markets model perspective, the most important impact 

of a smarter grid is the potential ability for market prices for generation to be reflected at the smart 

meter.  The increased price transparency and the potential response by customers must be managed 

directly by the traditionally regulated utility, or through market interactions in the centralized markets. 

9.4  Research and Development Investment 

A forecast by Battelle estimates that industrial R&D in the energy sector as a whole (not just the electric 

sector) was $6.7 billion in 2012.237  The Battelle document also states that R&D investment by electric 

utilities (including their contributions to the Electric Power Research Institute [EPRI]) is small when 

compared to other industrial sectors and when observed in the context of the role electricity plays in our 

national economy and society.  These findings are based on estimates, as many electric utilities may not 

be required to disclose the detail of their R&D activities.  Since its formation in 1965, EPRI has provided a 

vehicle that allows electric utilities to pool their resources on R&D.  According to its website, EPRI’s 

membership represents approximately 90 percent of all electricity generated in the United States.  

However, historically, electric equipment manufacturers have provided the majority of the R&D in the 

sector; this is primarily because utilities cannot necessarily internalize the benefits of the innovations 

developed through R&D.238 

 

Several studies have noted a decline in R&D investment in some areas and concluded that utility 

restructuring is the likely cause.239  For the period between 1993 and 2000, R&D investment dropped 

among the four entities involved in the electric sector: R&D spending from utilities dropped by nearly 74 

percent, R&D spending by EPRI dropped by approximately 71 percent, government spending dropped 

by 30 percent (state) and 3 percent (federal), and spending by electric equipment manufacturers declined 

                                                           237 Battelle, 2012 Global R&D Funding Forecast (December 2011). 238 Sanyal and Cohen, “Powering Progress: Restructuring, Competition and R&D in the U.S. Electric Utility 

Industry,” The Energy Journal, 30 (2) (2009). 239 See Burtraw et al. Electricity Restructuring: Consequences and Opportunities for the Environment. Resources for the Future, Discussion Paper 00‐39 (September 2000); Jamasb and Pollitt, “Liberalisation and R&D in network 

industries: The case of the electricity industry,” Research Policy, 37 (6‐7) (July 2008); Sanyal and Cohen, “Powering 

Progress: Restructuring, Competition and R&D in the U.S. Electric Utility Industry,” The Energy Journal, 30 (2) (2009); 

Kim et al., “R&D investment of electricity‐generating firms following industry restructuring,” Energy Policy, 48 

(September 2012); Sanyal and Ghosh, “Product Market Competition and Upstream Innovation: Evidence from the 

U.S. Electricity Market Deregulation,” The Review of Economics and Statistics, MIT Press, 95 (1) (March 2013). 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 68 October 8, 2013

(though by how much is unknown).240  Of particular interest is that overall energy R&D spending (public 

and private, and not exclusive to the electricity sector) decreased from $5.8 billion in 1994 to $4.5 billion 

in 2003.241  However, there are also studies that have come to the conclusion that the centralized market 

model encourages more innovation than the traditionally regulated model.242  

 

                                                           240 Sanyal and Cohen, 2009. 241 See Jan Martin Witte, State and Trends of Public Energy and Electricity R&D: A Transatlantic Perspective, Global 

Public Policy Institute (2009).  Additionally, Sanyal and Cohen found that among the aspects of restructuring, the 

introduction of competition to the electric sector had the greatest negative effect on R&D investment.  See Sanyal and 

Cohen, 2009.  Additionally, Burtraw et al. (2000) found that many analysts attribute an increase in the “availability 

factor,” of generators to competition and that funding levels at major research institutions, particularly the EPRI, are 

down.  See Burtraw et al., 2000.  Jamasb and Pollitt (2008) agreed that reforms in the electricity sector coincided with 

a significant decline in R&D investment, but also notes that the productivity and innovation output of R&D in the 

sector appear to have improved at the same time.  See Jamasb and Pollitt, 2008.  Kim et al. (2012) looked at the 

impact of deregulation at 70 electric companies in 15 Organization for Economic Co‐operation and Development 

(OECD) countries and found that deregulation was associated with a decline in R&D and that the existence of 

wholesale markets appears to be the biggest driver of that decline.  See Kim et al., 2012.   The OECD member 

countries are: Australia, Austria, Belgium, Canada, Chile, Czech Republic, Denmark, Estonia, Finland, France, 

Germany, Greece, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea, Luxembourg, Mexico, Netherlands, New 

Zealand, Norway, Poland, Portugal, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Turkey, United 

Kingdom, United States.  Sanyal and Ghosh (2013) looked closely at the impacts deregulation have on upstream 

suppliers, and found that deregulation in the electricity sector led to a decline in innovation in upstream electric 

equipment manufacturers.  See Sanyal and Ghosh, 2013. 242 Joskow and Kahn, among other economists, wrote an open letter to policymakers in 2006 in which they stated 

that “among economists, it is almost universally accepted that well‐functioning competitive electricity markets yield 

the greatest benefits to consumers in terms of price, investment and innovation especially when regulated alternatives 

are no longer warranted.”  See Joskow and Kahn, Open Letter to Policymakers, June 26, 2006 (emphasis added).  

Schmitt and Kucsera observed that deregulation of European utilities lead to a decline in R&D, but that once the 

competitive structures were established, increased competition had a positive impact on R&D.  See Schmitt and 

Kucsera, “The Impact of the Regulatory Reform Process on R&D Investment of European Electricity Utilities,ʺ 

Vienna University of Economics and Business: Research Institute for Regulatory Economics Working Paper: October 

2012.  One report found evidence of the opposite in Texas.  Regulation of rate of return did not go into effect in 

Texas until 1975, and Frank (2003) found that technological progress to decrease costs was more prevalent prior to 

regulation and declined significantly afterwards.  See Frank, Mark W., “An Empirical Analysis of Electricity 

Regulation on Technical Change in Texas,” Review of Industrial Organization, 22 (4): June 2003. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 69 October 8, 2013

Public funding of energy R&D increased significantly for the first time in decades between 2006 and 

2007, and again saw boosts in 2009 and 2010 due to the American Recovery and Reinvestment Act and 

other policies pushed by the Obama administration.243  EPRI’s 2014 R&D plan shows a slightly higher 

level of investment ($297.7 million) over that of 2013 ($288.12 million); a general breakdown of that 

spending by topic is given in Table 6. 

 

Table 6. EPRI Planned R&D Funding for 2013 and 2014 

2013 R&D Funding ($million) 2014 R&D Funding ($million)

Environment $40.87 $45.00

Generation $49.75 $54.30

Nuclear $136.00 $135.80

Power Delivery & Utilization $61.50 $62.60

Source: EPRI 2014 R&D Portfolio 

                                                           243 Witte, Jan Martin, State and Trends of Public Energy and Electricity R&D: A Transatlantic Perspective, Global Public 

Policy Institute: 2009. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 70 October 8, 2013

10.  State and Federal Government  

The topic of Federal and State government jurisdiction is discussed other times in this paper, for 

instance, Sections 3 and 4 address rate setting and markets jurisdiction, Section 5 discusses jurisdiction 

over electric reliability and Section 8 addresses jurisdiction over resource adequacy and transmission 

security planning as well as transmission siting.  This section covers those aspects of jurisdiction not 

discussed elsewhere in this paper.  Furthermore, there are numerous articles and other texts that provide 

detailed histories of the development of the current bifurcated regulatory structure.244  The focus of this 

section is not on how the industry got to this point, but rather what it means for the traditionally 

regulated and centralized market model participants. 

 

The electric utility industry in the United States is regulated at the state and federal level.  State 

regulation extends to most areas of utility operations, rates, and end‐user issues.  Federal regulation, 

founded on interstate commerce impacts, generally relates to the wholesale side of the utility business, 

including interstate transmission and sales of electricity for resale.   

Investor‐owned utilities are subject to state regulation as to their duties to customers, system 

requirements, financing arrangements, and retail rates.  State law or regulation determines whether 

retail access is permitted (or required).  Government‐owned utilities are not generally subject to 

regulation under state utility laws, but must follow the requirements of the ordinance or law establishing 

them.  The state regulator (for investor‐owned utilities) or the governing authority for a public power 

entity is responsible for approving the ultimate rates charged to retail customers.   

 

Under both the traditionally regulated model and the centralized market model, unbundled 

transmission service rates are approved by FERC.  FERC regulates the interstate transmission and 

generation activities of “public utilities.”  The terminology can be confusing, since utilities can be 

“publicly held” in the sense of having a class of securities owned by a large group of investors, or 

“public” in the sense that they are government‐owned or owned by customers.  For FERC purposes, 

“public utility” includes “any person who owns or operates facilities subject to the jurisdiction of the 

Commission,” i.e., facilities for “the transmission of electric energy in interstate commerce” or “the sale 

of electric energy at wholesale in interstate commerce.”245 

 

Despite this broad language, however, there are numerous exclusions, with the effect that FERC does not 

regulate government‐owned utilities or most cooperatives, which are often referred to as “non‐

jurisdictional” entities.  To the extent government‐owned utilities participate in market transactions that 

are regulated by FERC, they are subject to the same rules as other utilities, but they do not become 

subject to general FERC jurisdiction.246  As a result, the “public utilities” FERC regulates for transmission 

                                                           244 See, e.g., Appendix A, “History of the U.S. Electric Power Industry, 1882‐1991” and Appendix B, “Historical 

Chronology of Energy‐Related Milestones, 1800‐1994,”  The Changing Structure of the Electric Power Industry: An 

Update, U. S. Energy Information Administration (December 1996). 245 16 USC 824(e). 246 FPA 201(f), United States, State, political subdivision of a State, or agency or instrumentality thereof exempt, but 

see, FPA 215(b), Jurisdiction and Applicability. 

 

 

 

 

 

 

© 2013 Navigant Consulting, Inc. Page 71 October 8, 2013

purposes consist primarily of investor‐owned utilities and entities such as RTOs and ISOs.  In addition, 

because most of the Texas transmission grid is not interconnected with the rest of the interstate 

transmission grid except by limited DC interties, transmission in most areas of Texas is not subject to 

FERC regulation.   

 

In Texas, the state regulator is responsible for approving transmission rates (because most of Texas 

transmission is intrastate) as well as regulating all other aspects of the electric utility business in Texas.  

Texas has adopted full retail choice for most of the state247 and has separated ownership of wires from 

generation, with the wires companies continuing to be subject to full state regulation.  Transmission for 

most of the state is operated by a state‐created transmission organization, ERCOT, and costs of new 

transmission facilities are socialized across the entire ERCOT footprint.  This is a different approach from 

that used in other areas of the country, where each utility’s share of costs is determined according to 

various factors, which may include a determination of the specific benefits to the utility’s customers or a 

combination of socializing some costs while allocating others specifically. 

 

Thus, FERC’s authority over the transmission grid is far from complete.  The EIA calculated in 2000 that 

investor‐owned utilities own approximately 73% of the transmission in the United States, with the 

remainder divided between federal utilities (13%) and other public power entities, including 

government‐owned utilities and cooperative utilities (14%).248    

 

However, FERC has effectively extended many of its regulations to non‐jurisdictional utilities through 

reciprocity carrots and sticks.  Thus, for example, if a non‐jurisdictional utility wants to take advantage 

of the terms of a public utility’s OATT, then it must itself have an OATT – the difference being that the 

transmission rates will not be set by FERC.  However, the other terms of service, including use of an 

OASIS, must comply with FERC requirements.  Similarly, under Order No. 1000, FERC did not attempt 

to compel non‐jurisdictional utilities to participate in regional planning or cost allocation.  However, in 

order to be part of the planning process and to take advantage of proposed cost allocation mechanisms, 

these non‐jurisdictional entities had to agree to participate. 

 

                                                           247 Retail competition has been implemented for IOUs within the ERCOT zone of Texas.  Municipally owned utilities 

and electric cooperatives in ERCOT were given the choice to opt‐in to retail competition but in the past 11 years only 

one cooperative has elected to do so.  These entities are known as “non opt in entities” or NOIEs.   Most of the 

NOIES that owned generation did not divest their generation assets and some have built additional generation 

during this time frame.   Most of these entities still operate under the vertically integrated utilities business model.  

IOUs in ERCOT unbundled their businesses into generating companies (either structurally or through divesting of 

assets), Transmission and Distribution Service Providers (TDSPs), and Retail Electric Providers (REPs).  Energy 

Future Holdings and CenterPoint are good examples of this, with subsidiaries participating in each of those 

segments.  Retail choice has not been instituted in the Texas areas outside of ERCOT. 248 The Changing Structure of the Electric Power Industry 2000: An Update, Energy Information Agency (October 

2000), http://www.eia.gov/FTPROOT/electricity/056200.pdf.  There have been many changes in the structure of 

the electric industry in intervening years, and these numbers may have changed slightly as new transmission has 

been added; however, the fundamental proposition – that FERC does not regulate all of the owners of the 

interconnected transmission grid – is the same.