Upload
trankhanh
View
218
Download
0
Embed Size (px)
Citation preview
DETAILED PROJECT REPORT
IRCON INFRASTRUCTURE & SERVICES LIMITED
MINISTRY OF EXTERNAL AFFAIRS, NEW DELHI
MARCH 2013
Preparation of Detailed Engineering Project Reportfor Two Lane Road from Paletwa to Zorinpui (India
Myanmar Border) in Chin State of Myanmar
RIVER KALADAN
PROPOSED ROAD
PALETWA
NH 54
INDIAMIZORAM
RATHEDAUNG
MAGYICHAUNG
SITTWE
INDO MYANMARBORDER
SETTLEMENT
KALETWA
VOLUME IV: ENVIRONMENTALIMPACT ASSESSMENT REPORT
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Contents 1 Detailed Project Report
CONTENTS
S. No. Description Pages
1.0 INTRODUCTION 1-1 to 1-2
1.1 The Project and Project Proponent 1.1
1.2 Brief Description of the Project 1-1
1.3 Purpose of the Report 1-1
1.4 Scope of Present Report 1-2
2.0 DESCRIPTION OF THE PROJECT 2-1 to 2-27
2.1 Project Road 2-1
2.2 Silent Features 2-1
2.3 Traffic Scenario 2-2
2.4 Proposed Project Description 2-2
3.0 ANALYSIS OF ALTERNATIVES 3-1 to 3-4
3.1 Selection of Alternatives 3-1
3.2 Alignment Selection 3-1
4.0 METHODOLOGY 4-1 to 4-3
4.1 Approach to EIA Study 4-1
4.2 Steps in EIA 4-1
5.0 ENVIRONMENTAL SETTINGS 5-1 to 5-8
5.1 Introduction 5-1
5.2 Physical Resources 5-1
5.3 Ecological Resources 5-6
5.4 Socio-Economic Environment 5-7
6.0 ASSESSMENT OF ENVIRONMENTAL IMPACTS 6-1 to 6-6
6.1 Introduction 6-1
6-2 Impact During Design Phase 6-1
6.3 Impact During Construction Phase 6-2
6.4 Impact During Operation Phase 6-5
7.0 ENVIRONMENTAL MANAGEMENT PLAN (EMP) 7-1 to 7-9
7.1 Introduction 7-1
7.2 Design Phase 7-1
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Contents 2 Detailed Project Report
S. No. Description Pages
7.3 Construction Phase 7-2
7.4 Operation Phase 7-8
7.5 Environmental Enhancement 7-8
8.0 FINDINGS, RECOMMENDATIONS AND
CONCLUSION 8-1 to 8-1
8.1 Findings of the Study 8-1
8.2 Recommendations 8-1
8.3 Conclusion 8-1
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Contents 3 Detailed Project Report
FIGURES
5.1 Myanmar Map 5-1
5.2 Location of Chin State 5-1
5.3 Topographical Sheet of Chin State 5-2
TABLES
2.1 List of villages on the Project Road 2-1
2.2 List of Bus Bays 2-3
3.1 Merits and demerits of Altenative-1 & Alternative-2 3-4
4.1 Valued Environmental Components 4-3
5.1 List of Quarry Areas 5-3
5.2 Monthly Mean Temperature of Hakha Station 5-4
5.3 Monthly Mean Temperature of Hakha Station 5-5
5.4 Distribution of forest area 5-7
5.5 Administrative Districts of Chin State 5-7
5.6 Total Sex Ratio 5-8
6.1 Impact on water bodies 6-4
6.2 Details of Trees to be affected 6-5
7.1 Design Phase Measures – General 7-1
7.2 Mitigation Measures in Project Road Design 7-2
7.3 Mitigation Measures for Land Environment 7-2
7.4 General Measures for Air & Noise Pollution Control 7-3
7.5 Areas of Air Pollution and Noise Control during Construction near Settlements
7-4
7.6 Measures for Protection of Water Resources 7-4
7.7 Mitigation Measures for Tree Loss 7-5
7-8 Mitigation Measures to be adopted during construction 7-6
7-9 Safety Measures 7-6
7.10 Mitigation Measures for Workers’ Camps 7-7
7.11 Guidelines related to stone quarries, noise levels 7-7
7.12 Operation Phase Mitigation Measures 7-8
CHAPTER 1
INTRODUCTION
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Introduction 1-1 Detailed Project Report
CHAPTER 1
1.0 INTRODUCTION
1.1 The Project and Project Proponent
Under the bilateral agreement between Government of India and Government of Myanmar,
there is a proposal to develop a trade route between the two countries along the river Kaladan
known as “Chhimtuipui” river inside Indian border (Mizoram State). River Kaladan
(Chhimtuipui) emanates from central Mizoram and flows into Bay of Bengal at Sittwe, a port
located in the State of Rakhine, Myanmar. For connectivity from Sittwe Port to India-
Myanmar border, the trade route is proposed to provide transportation by two modes of
transport i.e. from Sittwe port to Paletwa by waterway and from Paletwa to India-Myanmar
border by road. The proposed road link from Paletwa to Kaletwa forms a part of the proposed
development of trade route along the river Kaladan (Chhimtuipui) between Mizoram (India)
and Chin State in Myanmar.
The connectivity would boost the trade between India and Myanmar. While India trades in
cement, bicycle parts, medicines and horticulture products of Mizoram. From Myanmar
handicrafts and clothes, apart from electronic goods and shoes, arrive in plenty.
1.2 Brief Description of the Project
The project road is located in Myanmar to link the areas namely Paletwa and Zorinpui on
India-Myanmar Border for enhancing the trade route between two countries.
1.3 Purpose of the Report
Road projects are meant for improving the quality of life for people and developing the
country’s economy. For all positive impacts of the road projects, there may be also some
significant detrimental impact on near by communities and natural environment. There may
be impact on properties of people, their livelihood and other social components. Similarly
there can be direct or indirect impact on flora, fauna, water resources, land use etc. To account
for all these issues, environmental and social impact assessment is utmost necessary. These
concerns for environmental and social issues in road projects have also become a part of legal
requirements and requirements for obtaining financial support. Environmental considerations
are therefore of prime importance in road projects.
New development may cause different types of impacts on its surrounding environment and
on human beings. To assess the impact and to ensure environmental quality, environmental
impact assessment is a very necessary exercise. The objective of the Environmental Impact
Assessment is characterization of the existing status of the environment, to identify the
probable impact on the environment due to the proposed project, delineate the mitigative
measures to reduce the impact and finally to assess the overall impact. The environment has a
limited carrying capacity and it can only sustain a negative impact up to a level without
further degradation. Several systems, however, temporarily disturb it leading to a new balance
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Introduction 1-2 Detailed Project Report
in order to re-establish the equilibrium between human activity and nature. But sensitive
systems are not so resilient to cope up with changes in physical and natural Environment, thus
not only leading to negative impact on them but also, socio-economic losses may occur. The
Environmental Impact Assessment provides tools for decision-making as well as it also helps
in ensuring the sustainable development with least environmental damage by providing
proper Management Plan.
1.4 Scope of Present Report
Environmental assessment is a detailed process, which starts from the conception of the
project and continues till the operation phases. The steps for environmental assessment are
therefore different at different phases. The present report details the environmental setting of
the project zone, collects the baseline data and then assesses the impact. Finally it offers an
environmental management plan.
The report is structured as given below:
Chapter 1 : Introduction: EIA report.
Chapter 2 : Project Description
Chapter 3 : Analysis of Alternatives
Chapter 4 : Methodology
Chapter 5 : Environmental Setting
Chapter 6 : Assessment of Environmental Impacts Identification
Chapter 7 : Environmental Management Plan: To implement the environmental
mitigation measures.
Chapter 8 : Recommendations and Conclusion.
CHAPTER 2
DESCRIPTION OF THE PROJECT
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Description of project 2-1 Detailed Project Report
CHAPTER 2
2.0 DESCRIPTION OF THE PROJECT
2.1 Project road
The project road runs, in the South - North direction in the Chin State of Myanmar, parallel to
Kaladan River. The project road takes off from Eastern bank of Kaladan River, where jetty of
waterway terminal has been proposed as part of “Waterway Project” between Sittwe port and
Paletwa and end at India Myanmar Border. The total length of the proposed alignment of the
Project Road has been estimated at 109.200 km (Package I (Paletwa to Kaletwa) is 60.7 km
and package II ( Kaletwa to Zorinpui /India-Myanmar Border) is 48.500 km). The road passes
mostly through Hilly terrain. There are twenty four villages situated nearby the proposed
alignment of the project road.
The hills are covered with jungles and thick undergrowth of evergreen bush, bamboo and kail.
The hills are steep and separated by rivers Kaladan, Milewa chaung, Daletme and Dalesta
chaung, paron Chaung, Kaletwa river, Niiti Chaung, Kannu Chaung, Twoase Chaung, Kun
Chaung, Thala Chaung, Sat Chaing Chaung, Do Chaung, Tangbel Chaung, Sulahi Chaung,
Sulewvi Chaung and Tapu Chaung, creating valleys between hill ranges.
2.2 Salient Features
Salient features of the Project Road are given as under:
State : Chin State
Length of Project Road : 109.200 km
Kilometerage : 0 to 60.700 km (Package I)
0 to 48.500 km (Package II)
Villages : There are 24 villages on the road.
Table 2.1 provides the list of the villages.
Table 2.1: List of villages on the Project Road
Sr. No. Name of Villages
1 Paletwa
2 Milawa
3 Leik kon
4 Mang khoil
5 Mang Ta
6 Tuki Alog
7 Urin Wa
8 Dalet Sa
9 Ye Lawa
10 Dong Lawa
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Description of project 2-2 Detailed Project Report
Sr. No. Name of Villages
11 Ke Kuwa
12 Uwfu Wa
13 We Kuwa
14 Setpyitpyin
15 Rake
16 KaunChaung
17 Kwan Taung
18 Laung Gyaing
19 Sat Gyaing
20 Kyauktan
21 Do Chaung
22 Yechantha
23 Sun Laung Pwi
24 Samai
Land use : The project road passes through agricultural land, barren/forest areas.
Some section of road passes parallel to the rivers and agricultural
land consists of Paddy, mango and orchards.
2.3 Traffic Scenario
The traffic on the project road would primarily of the International trade between India and
Myanmar. AADT, Design Service Volume, and Capacity of road have been derived as an
input for pavement design.
2.4 Proposed Project Description
Preliminary Assessment: The scope of work envisaged project road which is located in
Myanmar to link the areas namely Paletwa, Kaletwa and Indian Myanmar Border for
enhancing trade route between two countries.
2.4.1 Carriageway Width Proposed carriageway width of the project road is 7m with 2.5 paved shoulder on both sides.
2.4.2 Bus Bays It is proposed to provide bus bays with bus “Q” shelters, at identified locations. Such Bus
bays and bus “Q” shelters are proposed to be provided close to track/paths linking the
villages. A list of bus bays is given as under:
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Description of project 2-3 Detailed Project Report
Table 2.2: List of Bus Bays
S. No. Location (km)
Package I – Paletwa to Kaletwa 1 0+000
2 1+400
3 10+300
4 14+400
5 19+800
6 28+300
7 31+300
8 34+200
9 37+900
10 43+400
11 45+800
12 51+500
13 57+900
14 60+700
Package II- Kaletwa to Zorinpui / Indian – Myanmar Border
1 0+100
2 4+100
3 6+700
4 8+500
5 11+500
6 14+400
7 16+400
8 22+600
9 28+500
10 31+800
11 38+800
2.4.3 Implementation The entire project is proposed to be implemented in time span of 3 years.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Paletwa
Distance From
Alignment
: 600 m LHS across Kaladan
River
Population : 5481
Male : 2609
Female : 2872
Number of Houses : 1000
Predominant Religion : Buddhists
Social Infrastructure :
School : Primary/ Secondary
Post Office/Post Box : Post Office
Health Facilities : Hospital
Shops : 50
Weekly Market : Daily
Source of Water : Water tank
Electricity : 2 Hours
Landuse : Built up
Land cover : Agriculture
Description of project 2-4 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Mi La Wa
Distance From Alignment : 100 m LHS
Population : 400
Male : 210
Female : 190
Number of Houses : 80
Predominant Religion : Buddhists
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : 2
Weekly Market : No
Source of Water : Kaldan River
Electricity : No
Landuse : Built up/ Agriculture
Land cover : Agriculture/Forest
Description of project 2-5 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Leik Kon
Distance From Alignment : 100 m LHS
Population : 400
Male : 210
Female : 190
Number of Houses : 80
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : River Melawa
Electricity : No
Landuse : Agriculture
Landcover : Agriculture
Description of project 2-6 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Mang Khoi
Distance From Alignment : 300m from Alignment
Population : 90
Male : 45
Female : 45
Number of Houses : 20
Predominant Religion :
Social Infrastructure :
School : No
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : River Milava
Electricity : No
Landuse : Agriculture/Forest
Landcover : Agriculture/Forest
Description of project 2-7 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Mang Ta
Distance From Alignment : 200 m from Alignment
Population : 40
Male : 20
Female : 20
Number of Houses : 9
Predominant Religion :
Social Infrastructure :
School : No
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : River Melawa
Electricity : No
Landuse : Agriculture/Forest
Land cover : Agriculture/Forest
Description of project 2-8 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Tuki Alog
Distance From Alignment : 800 m from alignment
Population
: 135
Male : 70
Female : 65
Number of Houses : 30
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water :
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-9 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Urinva
Distance From
Alignment
: 1000 m from alignment
Population : 190
Male : 100
Female : 90
Number of Houses : 40
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water :
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-10 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Da-Let SA, Wa
Distance From Alignment : 2000 m across River
Population : 104
Male : 55
Female : 49
Number of Houses : 26
Predominant Religion : Christian
Social Infrastructure :
School : No
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : Kaladan
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-11 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Ye la va
Distance From Alignment : 2000 m from alignment
Population : 350
Male : 175
Female : 175
Number of Houses : 48
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : River Dalema
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-12 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Dong La Wa
Distance From Alignment : 1500 m from Alignment
Population : 505
Male : 253
Female : 252
Number of Houses : 84
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : Medical Shop
Shops : --
Weekly Market : No
Source of Water : River Kaladan
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-13 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Ket Ku Wa
Distance From Alignment : 2500 m from Alignment
Population : 295
Male : 148
Female : 147
Number of Houses : 54
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : Kaladan
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-14 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Wu Phu Wa
Distance From Alignment : 300 m from alignment
Population : 270
Male : 135
Female : 135
Number of Houses : 41
Predominant Religion : Christian
Social Infrastructure :
School : Primary
Post Office/Post Box : Yes
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water :
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-15 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Wet Ku Wa
Distance From Alignment : 600m from alignment
Population : 129
Male : 65
Female : 64
Number of Houses : 42
Predominant Religion : Christian
Social Infrastructure :
School : No
Post Office/Post Box : Yes
Health Facilities : Yes
Shops : --
Weekly Market : No
Source of Water : Paragon River
Electricity : No
Landuse : Forest/Mango/Banana trees
Land cover : Forest/Mango/Banana trees
Description of project 2-16 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Set Pyit Pyin
Distance From Alignment : 50 m from alignment
Population : 364
Male : 184
Female : 180
Number of Houses : 84
Predominant Religion : Buddhist
Social Infrastructure :
School : Primary
Post Office/Post Box : Yes
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : Kaladan
Electricity : No
Landuse : Agriculture/Orange/ Forest
Land cover : Agriculture/Orange/ Forest
Description of project 2-17 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Rake
Distance From Alignment : 300 m from alignment
Population : 100
Male : 55
Female : 45
Number of Houses : 18
Predominant Religion : Buddhist
Social Infrastructure :
School : No
Post Office/Post Box : No
Health Facilities : No
Shops : --
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/ Forest
Land cover : Agriculture/ Forest
Description of project 2-18 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Kaun Chaung
Distance From
Alignment
: 500 m from alignment
Population : 240
Male : 135
Female : 105
Number of Houses : 54
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : No
Health Facilities : No
Shops : Two
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/ Bananas Trees/
Forest
Land cover : Agriculture/Bananas Trees /
Forest
Description of project 2-19 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Kaun Chaung
Distance From
Alignment
: 400 m from alignment
Population : 528
Male : 262
Female : 266
Number of Houses : 116
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : Yes
Health Facilities : No
Shops : Three
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/ Bananas Trees/
Forest
Land cover : Agriculture/Bananas Trees /
Forest
Description of project 2-20 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Laung Gyaing
Distance From
Alignment
: 1Km from alignment
Population : 400
Male : 195
Female : 205
Number of Houses : 65
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : Yes
Health Facilities : Yes
Shops : Two
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Orange Trees/Forest
Land cover : Agriculture/Orange Trees/Forest
Description of project 2-21 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Sat Gyaing
Distance From Alignment : 600 m from alignment
Population : 395
Male : 204
Female : 191
Number of Houses : 80
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : No
Health Facilities : ----
Shops : Two
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Forest
Land cover : Agriculture/Forest
Description of project 2-22 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Kyauktan
Distance From
Alignment
: 900 m from alignment
Population : 108
Male : 56
Female : 60
Number of Houses : 52
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : No
Health Facilities : ----
Shops : Two
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Banana Trees/ Forest
Land cover : Agriculture/ Banana Trees
/Forest
Description of project 2-23 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Do Chaung
Distance From
Alignment
: 1.0K m from alignment
Population : 1118
Male : 500
Female : 618
Number of Houses : 231
Predominant
Religion
: Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : Yes
Health Facilities : ----
Shops : Five
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Orange/Bananas/Forest
Land cover : Agriculture/Orange//Bananas
Forest
Description of project 2-24 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Yechantha
Distance From Alignment : 450m from alignment
Population : 189
Male : 87
Female : 102
Number of Houses : 26
Predominant Religion : Buddhist
Social Infrastructure :
School : No
Post Office/Post Box : No
Health Facilities : ----
Shops : One
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Forest
Land cover : Agriculture/Forest
Description of project 2-25 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Sun Laung Pwi
Distance From
Alignment
: 50m from alignment
Population : 303
Male : 195
Female : 108
Number of Houses : 87
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : No
Health Facilities : ----
Shops : Two
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Forest
Land cover : Agriculture/Forest
Description of project 2-26 Detailed Project Report
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Village : Samai
Distance From
Alignment
: 300m from alignment
Population : 147
Male : 81
Female : 66
Number of Houses : 27
Predominant Religion : Buddhist
Social Infrastructure :
School : Yes
Post Office/Post Box : No
Health Facilities : ----
Shops : One
Weekly Market : No
Source of Water : Kaletwa Chaung
Electricity : No
Landuse : Agriculture/Bananas Trees/
Forest
Land cover : Agriculture/ Bananas Trees/
Forest
Description of project 2-27 Detailed Project Report
CHAPTER 3
ANALYSIS OF ALTERNATIVES
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Analysis of Alternatives 3-1 Detailed Project Report
CHAPTER 3
3.0 ANALYSIS OF ALTERNATIVES
3.1 Selection of Alternatives
The term alternatives in this context refer to the reasonable and potentially viable alternatives
for the proposed project activities. Selection of appropriate highway design decisions,
specifically from the environment point of view, is considered with different alternatives.
Also social issues like displacement are to be considered in selection of alternatives. The
major issues where alternative proposals need to be considered are discussed below.
3.2 Alignment Selection
The alignments options were studied in detail based on the topographical sheets collected,
detailed contours developed with the help of the satellite imaginaries. All the options were
studied in detail with respect to the following aspects:
Easy : To construct and maintain easy gradients and curves for vehicular
traffic to ply.
Safe : During construction, maintenance and operation, passes through
Stable slopes, geometric etc.
Economical : Total cost including initial construction cost, maintenance cost and
Vehicle-operating cost is least.
Short : It is desirable to have the shortest distance between two terminal
points.
In addition to the above the following Guiding principles of route selection and location
applicable to hill roads
General
The alignment should be as direct as possible between the obligatory and control
points to be linked. A direct road link results in economy in construction,
maintenance and operation.
The route location should result in minimum interference to agriculture and industry.
It should be clear of obstructions such as cemeteries, burning ghats, places of
worship, archeological and historical monuments and public facilities like hospitals,
schools and playground etc.
Where the proposed locations interface with utility services like overhead
transmission lines, water supply lines etc., decision between changing the road
alignment or shifting the utility services should be based on the study of the relative
economics and feasibility.
As far as possible, frequent crossing and re-crossing of canals, watercourses, ridges
etc. should be avoided.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Analysis of Alternatives 3-2 Detailed Project Report
The alignment should avoid large-scale cutting and filling, and follow the lie of the
land as far as possible. Use of tunnels to avoid to deep cuts should be considered
where feasible and economical. If the road has to be in cutting, the location and the
grade lines should permit the adoption of half cut and half fill, type of cross section
which involves least disturbance to the natural ground subject however, to
considerations of economy and road stability being satisfied.
Obligatory Points
The obligatory points to be connected from administrative, strategic or other
considerations should be ascertained and taken into account while finalizing the road
alignment. Similarly, control points like mountain passes, saddles, river crossing etc.
should be kept in view when deciding the alignment.
When crossing mountain ranges, the road should preferably cross the ridges at their
lowest elevation. In certain cases it may be more expedient to negotiate high
mountain ranges through tunnels. This decision should be taken after considering the
relative economics or the strategic requirements.
Grades and Curvature
The route should enable running gradient to be attained in most of its length.
As far as possible the alignment should permit adoption of a uniform design speed
and easy curvature in the entire length.
The route should avoid the introduction of hairpin bends as far as possible and their
location in valleys avoided. The bends should be located on stable and flat hill slopes.
Also, a series of hairpin bends on the same face of the hill should be avoided.
Needless rise and fall must be avoided where the general purpose of route is to gain
elevation from a lower to a higher point. Also, deep cuts involving destabilization of
natural hill slopes should be avoided.
River Crossings
It is preferable that crossings of major rivers should be at right angles to the river
flow. Crossings of medium/minor streams may also sometimes govern the choice of
alignment in the case of hill roads due to foundation problems, though their position
will be determined generally by requirements of the road proposed, and the crossings
could be even skew or on curve if necessary.
As far as possible, efforts should be made to locate bridges where:
i. The river is straight both on the upstream and downstream side
ii. The location is sufficiently away from confluence of tributaries
iii. The channel is well defined and narrow
iv. The banks are high, rocky/firm and well-defined above high flood level (HFL)
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Analysis of Alternatives 3-3 Detailed Project Report
Areas to be avoided
As far as possible, attempts should be made to avoid the following areas:
i. Unstable hill features and areas having perennial landslide or settlement
problems
ii. Areas subject to seepage/flow from springs, hydel channels etc.
iii. Steep hillsides
iv. Areas subject to flooding or water logging
v. Areas liable to snow drift or avalanches, and
vi. Locations involving unnecessary and expensive destruction of wooded areas
Miscellaneous
Location along a river valley has the inherent advantage of comparatively gentle
gradients, proximity of inhibited villages, and easy supply of water for construction
purposes. But this solution is best with disadvantages such as the need for a large
number of cross drainage structures and protective works against erosion. These pros
and cons should be kept in view while making initial selection of the alignment.
The location should be such that the road is fully integrated with the surrounding
landscape of the area. It would be desirable to study the environmental impact of the
road and ensure that the adverse effects are kept to the minimum.
Based on the above criteria, the alignment options were studied in detail based on the
topographical sheets collected, and detailed contours developed with the help of the satellite
imaginaries.
All the possible alignment options have been marked on the topographical sheets of survey of
Myanmar obtained from the ministry of construction, Myanmar.
Based on the detailed reconnaissance survey and detailed discussions with the Ministry of
Construction, Government of Myanmar, the jetty location is proposed between the Melawa
Chaung (river) and Paletwa Chaung on the right side of the Kaladan river. Since the project
road is a part of the Kaladan Multimodal Transit Transport project, the two options on the
right side of the Kaladan River are further considered for the feasibility study.
The two alignments were studied on the aforesaid maps, which showed in general outline,
river/streams, Chaung, hill ranges, spot levels of high peaks and approximate contours at 20m
intervals. After study of the topographical features on the map, two alignments, feasible in a
general way were selected keeping in view the guiding principles given above.
Reconnaissance surveys were carried-out along the alignments. Ground reconnaissance
consists of general examination of ground by walking along or nearby probable routes and
collecting all available information necessary for evaluating the same.
Points on which data were collected during reconnaissance are given below:
Details of route ( Topography of the area)
Terrain and soil condition ( geology of the area, nature of soil, cliffs and gorges, total
length passing through steep hills, rocky stretches, slip prone area)
Existing transportation tracks
Sources of materials and their availability
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Analysis of Alternatives 3-4 Detailed Project Report
Based on the desk study and field reconnaissance, proposed alignment were analyzed and
evaluated, the comparison is presented in Table 3.1
Table 3.1: Merits and demerits of Alternative-1 & Alternative-2 for Package I (from
Paletwa to Kaletwa)
S.No Item Alternative I Alternative II
1 Length of Road 60km 62km
2
Number of bridge
Major Bridge 1 1
Minor Bridge 20 24
Cross Drainage works 120 180
3 Existing / known paths yes no
4 Approximate plain / rolling
terrain 10 km ( approx) 2.0 to 2.5 km
5 No. of villages connecting 14 12
6 Prone to land slide 1 km 3km
7 Tress Cutting 5150 7250
8 Availability of construction
material
Use of Kaladan River
material (lead is less)
Use of Kaladan River
material (lead is more)
9 Construction cost Rs 700 Crores Rs 800 Crores
The first alignment (Alternative 1) follows the established foot paths and passes through the
tribal villages all along side. Hills along the proposed alignment are stable and consist of
alternate beds of brownish sandstone and carbonaceous shales. The alignment runs parallel to
Me La Chaung and Daletma Chaung. Construction materials are available along the Kaladan
River and Melawa Chaung and other Chaung crossing the road alignment.
The second alignment (Alternative 2) follows the same alignment as option1 for the first 2 km
and moves towards Paletwa Chaung and runs parallel to Paletwa Chaung. To move towards
the Paletwa Chaung the alignment is passing through steep hills between Me la Chaung and
Paletwa Chaung which is prone to landslide and would be difficult for construction and
requiring high cost.
As observed from the merits and demerits of two alternatives, it is seen that Alternative 1
meets the basic requirements of the ideal alignment for Kaladan Multimodal Transit Transport
project and also goes straight vertical from Paletwa to Kaletwa. Therefore alternative I have
been selected for the project road.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Analysis of Alternatives 3-5 Detailed Project Report
LEGEND
Kaladan River
Port Location
Alignement Option 1
Alignement Option 2
Alignement Option 3
Proposed Alignment options from Paletwa to Kaletwa Section of the Paletwa -Indian Myanmar Border Road
Figure 3.1
Proposed Alignment
Kaladan River
Start of the Alignment
Proposed Alignment Options from Paletwa to Kaletwa
Bridge Near Setpyit pyin
End of Alignment
Paletwa Port Tentative Location
CHAPTER 4
METHODOLOGY
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Methodology 4-1 Detailed Project Report
CHAPTER 4
4.0 METHODOLOGY
4.1 Approach to EIA Study
Environmental Impact Assessment is a holistic process, which requires considering all aspects
of environment which may be impacted due to the proposed project. The major issues of
consideration are i) identification of potential impacts due to the project; ii) baseline scenario;
iii) assessment of impacts; iv) mitigation measures and v) environmental management plan.
4.2 Steps in EIA
EIA process mainly consists of following steps:
Study of Background information on project
Preparation of Screening Report
Baseline Data Collection
Assessment of Impact
Mitigation Measures
Public Consultation
Environment Management Plan
The steps are detailed below:
(a) Study of Background information
First task is to study the project documents to have the understanding of the project
objectives, its main components, boundary etc. Unless the project is well understood, its
different impacts on environment and social issues cannot be properly identified.
(b) Preparation of Screening Report
A Screening Report was prepared to identify the important issues on environment from a
preliminary study. This included:
Collection of data from secondary sources: After having the background information about
the project and its environmental aspects from policy points, guidelines on such studies, next
step involves collection of data from secondary sources. The data are collected on
meteorology, demography, forests, wildlife, biodiversity, geology and related aspects, landuse
pattern, topography etc. Following are some important information available from secondary
sources.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Methodology 4-2 Detailed Project Report
Information Source
Demography Census Handbook
Landuse District Census Handbook
Report and Maps of Soils
Meteorology Data collected by Meteorology Department
Topography Toposheets by Ministry of Construction
Rivers, Nullah etc. Toposheets by Ministry of construction
Geological Data Geological Survey and Maps
Geology department
Reconnaissance survey of the project impact zone: Reconnaissance survey along the
project road was carried out by a team of environmental experts. Important environmental
components along the corridor of impact zone were identified. These were trees, forests,
wildlife, biodiversity, and community resources. Discussions with local people, people from
Forest and wildlife department and administrators were also conducted to obtain their opinion
about the project.
(d) Baseline Data collection
The study was carried out in details for the environmental components. The findings were
used to evaluate the impact.
(e) Assessment of Impacts
Reviewing the project activities and baseline conditions, the design was improved to consider
environmental aspects. The impacts can be assessed both qualitatively and quantitatively.
Project impacts on different environmental components are generally identified in a checklist
matrix (known as Leopold Matrix also) method, which is a qualitative approach. The present
trend is to quantify the impact using a common unit of measurement. This methodology
called weighing-scaling checklist method has been developed by a number of groups. The
approach assigns some relative value to the environmental components also called valued
environmental components (VEC). Then it assigns importance weights to impact scales for
each alternative activity relative to each environmental component. The basic concept can be
expressed as
EIV = m i=1 n j=1 (IS)i (PI)j
Where, EIV = Environmental Impact Value
(IS)i = Impact Scale value for ith activity
(PI)j = Environmental component value for jth environmental component
m = No. of activities
n = No. of environmental components
However actual quantification is difficult because of subjective nature of the valuation of
environmental component and the impacts. Both environmental and social impacts are
difficult to quantify, specifically to judging a project. So, quantification approach has not been
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Methodology 4-3 Detailed Project Report
considered further. However valued environmental components have been identified and the
impact assessed based on the impact on these components. Environmental components
considered for assessment of impact for this project are given below:
Table 4.1: Valued Environmental Components
Environmental
components
Detail of Components
Physical Environment
Land
Soil
Water Resources
Noise
Ecological Environment
Roadside Plantation
Forest flora
Forest Fauna
Social Environment
Rehabilitation
Employment
Housing
Agriculture
Culture
(f) Mitigation Measures
Mitigation measures have been suggested based on environmental and social criteria and also
relying on best engineering practices. Besides the mitigation measures, environmental
enhancement programmes have also been considered.
(g) Public Consultation
Public opinion is an important criterion in development programme. Any development
activities need grassroot level suggestions to be implemented right from design phase. Public
consultation was done with the villages following along the alignment to discuss the merits
and demerits of the alignment, normally the meeting were conducted at village head men
house.
(h) Environment Management Plan
Finally an environmental management plan has been developed to ensure the implementation
of the mitigation measures and other environmental improvement activities underling specific
responsibilities of different participating organisations. A budgetary cost for environmental
measures has also been presented.
CHAPTER 5
ENVIRONMENTAL SETTINGS
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-1 Detailed Project Report
CHAPTER 5
5.0 ENVIRONMENTAL SETTINGS
5.1 Introduction
The present chapter aims to describe existing environmental conditions of the influence area
of the project. It deals with physical, natural and human components of the environment.
However, as a specific socio-economic report has been produced and available, the reader is
pleased to refer to it to find more detailed elements on this issue.
5.2 Physical Resources
5.2.1 Location
Chin State is located in the north-west of Myanmar between 200 40' N and 240 06' N latitudes
and 920 37' E and 940 09' E longitudes. To the north and east of Chin State is Sagaing
Division, to the south are Magway Division and Rakhine State, and to the west are
Bangladesh and India. The area of the State is 13,907 square miles and capital is Hakhar.
Fig 5.1: Myanmar Map Fig 5.2: Location of Chin State
5.2.2 Geography
Many natural watercourses are flowing among mountain ranges running from north to south
forming a number of valleys and gorges. Mount Khawnusoum (also known as Mount
Victoria), 10,500 feet (3,200 m) or Khonumthung, or Khonuamtung high is the highest peak
in Chin State and the second highest peak in Myanmar. The state has a lot of rivers and the
Manipura River flows through its northern territory. Longest water fall in Chin state is
Bungtla water fall it is located in Matupi. The Chin state located in the Northwest of
Myanmar is a very ragged land. Its eastern border faces Sagaing Division and Magwae
Chin state
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-2 Detailed Project Report
Division, while the west faces the state of Mizoram in Bangladesh, north the state of Assam
in India and south the state of Rakhine.
Population is approx. 450,000 and they spread around within some 9 provinces, which cover
some 130,907square miles. Mountain regions start in the north where steep peaks and valleys
continue towards south. The highest peak is Mt. Victoria (10,200feet/ 3,109m).
There run many rivers including River Manipur, River Kaladam in the southwest of the Chin
state which starts in India going through Chin state into River Rakhine. Rivers in the south-
east area of Chin such as River Yaw Creek, Salin Creek and Mon Creek run toward east.
Those streams are fast and strong as they run in the hills and valleys. In recent years due to
the deforestation for forest resources and cultivation, lot of mud pour into the stream, causing
the frequent flood after heavy rain.
Fig 5.3: Topographical Sheet of Chin State
CHIN STATE
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-3 Detailed Project Report
5.2.3 Geology
The Chin State is found to be made up of 8 different rock types as shown below:
Sedimentary: (1) Irrawaddian type of rocks
(2) Peguan type of rocks
(3) Kennedy Sandstone
(4) Chunsung Mudstone Turbidite
(5) Falam Mudstone Micrite
(6) Pane Chaung Group
Metamorphic:
(7) Kanpetlet schist and khwekha metamorphic
Lgneous: (8) Ultra - basic rock (Nickel and Chromite bearing rock)
5.2.4 Soil and Land Use
Soil is the most valuable life supporting natural resource for the society since it produces
food, fiber and fodder, which are basic to our very existence. Knowledge of different soils in
respect of their characteristics, extent, productive capacity and use potential, is therefore
extremely important for their sustained utilization for optimum land use. The state has
diversity of climate and is endowed with varied litho logy, geomorphology and vegetation,
which have considerable effect on soil genesis.
The project area falls in region of Chin state. The whole region is made up of high hills and
deep valleys, and there is hardly any plain or plateau. The highest peak is Nat Ma Taung or
Mt. Victoria in southern Chin state at 3100 meters above sea level. The Project road passes
through the elevation of 100 to 300 meters.
5.2.5 Quarries and Borrow Areas
Road construction requires stones, soil and sand. These are to be obtained from suitable areas,
which will be suitable for quality. Also environmental issues are considered. Table 5.1
presents the list of quarry areas.
Table 5.1: List of Quarry Areas
S. No. Location Chainage (Km)
Package I – Paletwa to Kaletwa
1 Lymyo 112 km (from Project Road)
2 Sin Ma (Yellow) 200 km (from Project Road)
3 Sin Ma (Blue) 200 km (from Project Road)
4 Milawa River 3 km (on Project Road)
5 Milawa River 7.0 km (on Project Road)
6 Milawa River 8.0 km (on Project Road)
7 Rock sample 13 km (on Project Road)
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-4 Detailed Project Report
S. No. Location Chainage (Km)
8 Milawa River 17.0 km (on Project Road)
9 Dalesta River 26.0 km (on Project Road)
10 Dalema River 31.0 km (on Project Road)
11 Ket Ku Wa C River 41.0 km (on Project Road)
12 Paron Chaung 50 km (on Project Road)
13 Vaku Chaung 56 km (on Project Road)
Package II- Kaletwa to Zorinpui / Indian – Myanmar Border
1. Kan Chaung 7.5 km (on Project Road)
2. Twaose chaung 10.9 km (on Project Road)
3. Thala chaung 14.6 km (on Project Road) 4. Sat Chaing chaung 18.9 km (on Project Road) 5. Dou chaung 22.7 km (on Project Road) 6. Tangbel chaung 26.8 km (on Project Road) 7. Sulahi chaung 28.8 km (on Project Road) 8. Sulewvi chaung 33.1 km (on Project Road) 9. Phuhlai Chaung 37.7 km (on Project Road) 10. Tapu Chaung 48.5 km (on Project Road)
11. Water Fall 14.6 km (on Project Road)
5.2.6 Climate
Chin state owns a tropical climate with three seasons – the summer season from mid-February
to mid-may, the rainy season from mid-may to mid- October and the cold season from mid-
october to mid- February . Basically, it has a mild hot, wet climate. April and May are the
hottest months of the year.
5.2.6.1 Temperature
The average temperatures of the months range from 60°F (10.5 Degrees Centigrade) to 70°F
(19.5 Degrees Centigrade). In the cold season, temperatures fall as low as freezing point of
water in the higher parts of towns like Haka, Foshaik and Kanpetlet. The monthly mean
temperature at selected stations is given in Table 5.2.
Table 5.2: Monthly Mean Temperature of Hakha Station
S.no. Months Average Temperature
(1999-2008) in C0
1 January 10.6
2 February 12.7
3 March 15.7
4 April 18.6
5 May 18.7
6 June 19.3
7 July 19.2
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-5 Detailed Project Report
8 August 19.0
9 September 18.5
10 October 17.1
11 November 13.1
12 December 10.4
Source: Department of Metrological, Myanmar
5.2.6.2 Rainfall
Average annual rainfall is 80-100 inches. The southern part of Chin State gets more rain due
to the storms that come from Bay of Bengal. The monthly rainfall at selected towns is given
in Table 5.3.
Table 5.3: Monthly Mean Temperature of Hakha Station S.no. Months Average Rainfall (1999-2008) in mm
1 January 17
2 February 5
3 March 12
4 April 54
5 May 203
6 June 256
7 July 317
8 August 357
9 September 339
10 October 217
11 November 36
12 December 17
Source: Department of Metrological, Myanmar
5.2.7 Water Resources
Water resources can be classified in two broad categories: Surface water and ground water.
The following sections have elaborated on the available water resources.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-6 Detailed Project Report
5.2.7.1 Surface water
The river Kaladan arises in central Chin State as the Timit, 22° 49′ 28″ N 93° 31′ 57" E, and
flows south and is soon joined by the Chal, after which it is known as the Boinu River. It
continues south until just before it is joined by the Twe River at 22° 08′ 40″ N 93° 34′ 30″ E,
when it swings west. It continues west until 22° 05′ 20″ N 93° 14′ 12″ E, when it heads
northwest. At 22° 11′ 06″ N 93° 09′ 29″ E, below Mount Phabipa, it turns north and becomes
the international border between India and Burma. It flows north to 22° 47′ 09″ N 93° 05′ 47″
E, where the international border continues north along the Tyao River and the Boinu heads
northwest into Mizoram State, at which point it is known as the Kaladan.
At 22° 56′ 21″ N 92° 58′ 55″ E it reaches its northern-most point, and turns south west, is
joined by the Tuichong River from the right and then heads south. The Kaladan is joined from
the right by the Mat River at 22° 43′ 39″ N, 92° 54′ 46″ E. It continues south and is joined by
the Kawrthingdeng River from the right. It again enters Chin State, Myanmar, at Raithaw
Ferry, 22° 03′ 40″ N 92° 51′ 05″ E, just northwest of Khenkhar. The Mi River joins from the
left at 21° 06′ 56″ N 92° 57′ 42″ E. At Ngame the river enters the Rakhine State of Burma and
continues south to Sittwe where it enters the Bay of Bengal. Beside the river Kaladan, its
tributuries comoprising of Milewa, Dalesta, Dalme, Parong and Vaku also drains the project
area.
5.2.7.2 Ground Water
The impact on ground water is different from that of surface water. In case of ground water
the impact can be quantitative as well as qualitative. The probability of contamination of
ground water due to leaching is rare in this type of development project. However, extraction
of ground water would temporarily affect the quantity available but as the water table is high
in the area the water would flow from the surrounding areas. Since construction of road
requires considerable amount of water, as abundant surface water sources are available, as far
as possible the ground water should not be utilized for road construction work. In case the
ground water is to be utilized for construction work the prior approval of the concerned
ministry would be taken before usage of ground water.
5.3 Ecological Resources
5.3.1 Flora
The project road passes through light jungle with bushes and trees such as mango, banana,
teak, oak etc. The alignment have been selected considering that the teak and mango
plantation in the area and proposed alignment is not passing through these plantation areas.
The flora, directly or indirectly, provides a resource base for livelihood of the people, and
fundamentally accounts for all the economy of this province. It is intricately woven with the
social, cultural and religious customs of the inhabitants, and satisfies their bio-aesthetic and
ethical needs. Besides, all the animals depend on floristic primary producers.
Forest Resources: An integral part of the economy, forests in Chin state occupies great
importance in the raising the economy. Several plant species are utilized to meet the
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-7 Detailed Project Report
requirements of timber, fuel wood, and fodder, from the wild as well as from the plantations
maintained for these purposes.
5.3.2 Fauna
Chin state is having greatly rich in the variety of faunal diversity, which consist mainly
elephants, tigers, black bears, leopards, wild boars, monkeys, barking deers, mountain goats,
porcupine, mythan and a great variety of birds.
However, along the project road area between Paletwa and Indian Myanmar Border the fauna
such as monkey, deers, snake and birds are available in scatter manner.
5.4 Socio-Economic Environment
5.4.1 Administrative divisions of Chin State
The Chin State is divided into districts and townships. It consists of two district Falam in
northern Chin state and Mindat in southern Chin state and was further subdivided into nine
townships. The districts and the number of townships are shown in the Table 5.4.
Table 5.4: Administrative Districts of Chin State
Administrative Districts of Chin State
Districts No. of Townships
Falam 5
Mindat 4
Total 9
5.4.2 Area and Land Use
The total area of the State of Chin State within the Myanmar Union is
30, 019 Sq. km, which is 4.4 percent of Myanmar total area (678500 Sq. km). The project
road passes through the district of Paletwa.
5.4.3 Demographic features of Chin State
5.4.3.1 Population
The project state has an estimated total population of 510000. The population, area and
population density in the project districts is given in Table 5.5.
Table 5.5: Total Population, Area and Density in Project Area
Name of the State Total Area (in Sq.
Mile)
Total Population Density (persons per Sq.
mile)
Chin state 130,907 510000 3.89
Source: Department of Population, Myanmar
The chin state is having very low density i.e. 3.89 person per sq mile. The major factor
responsible for this density pattern is its mountainous terrain that is mostly inhabitable.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Environmental Setting 5-8 Detailed Project Report
5.4.3.2 Sex Ratio
The Statewide sex ratio (number of females per 1000 males) is 1049 as per estimate by
department of population in 2008 so it depict that the percentage of women is more in the
project area. The Table 5.6 gives the details of total sex ration in the state.
Table 5.6: Total Sex Ratio
Name of the state Total Sex Ratio
Chin state 1049/1000 male
Source: Department of population, Myanmar
5.4.4 Socio-Cultural Environment
There are Fourteen Villages along the Project road impacts that are envisaged to be affected.
There would be no structures which would require shifting with the proposed alignment.
CHAPTER 6
ASSESSMENT OF
ENVIRONMENTAL IMPACTS
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-1 Detailed Project Report
CHAPTER 6
6.0 ASSESSMENT OF ENVIRONMENTAL IMPACTS
6.1 Introduction
This chapter identifies and assesses the probable impacts on different environmental
parameters due to planning, construction and the operation of the proposed development.
After studying the existing baseline environmental scenario, initial field surveys, reviewing
the process and related statutory norms, the major impacts can be identified and assessed
during the design, construction and the operation phases.
Road construction related impacts occur at three stages of the project:
(i) Planning and Design
(ii) Construction
(iii) Operation
Planning and Design plans the road alignment, required bypasses, construction details,
materials of construction etc. which ultimately decides the impact during later phases. Most of
the impacts are during construction and operation phase. While some of the construction
phase impacts are temporary, some also are permanent. Operation phase impacts are
continuous in nature. To identify these impacts broadly on physical, ecological and social
environment Impact Identification Matrix are developed.
Other important criterion for identification of impact is identification of the impact zone. For
present screening studies, a Corridor of Impact (COI) of 60 m width of road alignment has
been considered.
Environmental parameters are broadly classified into three groups.
(i) Physical Environment
(ii) Biological Environment
(iii) Human Environment
Physical environment includes Water Resources, Water Quality, Air Quality, Noise and Land
environment, Biological Environment includes, Flora and fauna and Plantation. Social
Environment includes Rehabilitation, Employment, Agriculture, Housing, Culture etc.
6.2 Impact during Design Phase
The major impact associated with Design or Pre-construction phase deals with loss of land,
properties and livelihood due to acquisition of properties. The design of alignment also
decides the acquiring or impacting water bodies, flora and fauna, cultural sites etc. Design
phase study these issues along with environmental and social specialists to minimize the
impact. Besides the impact on environment and social factors, there should also be
consideration for legal issues so that the project can be operated with ease.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-2 Detailed Project Report
6.3 Impact during Construction Phase
6.3.1 Possession and Displacement
Construction phase starts from taking possession of the site. The possession of land is the first
major step in the project construction. Being a new alignment while land need to be
developed. The alignment has been selected keeping in view that there is no rehabilitation of
people living along the alignment.
6.3.2 Land Requirement
It is calculated that total land requirement for the Package 1 from (Paletwa to Kaletwa) is
273.15 hectares and for package II (Kaletwa to Zorinpui / Indian – Myanmar Border ) is
about 218.25 hectares.
6.3.3 Soil Erosion
The most important issue in land environment for road construction or improvement is the
soil erosion. The construction activities require excavation of soil and removal of vegetation.
These activities lead to loss of topsoil leading to localized ecological degradation. The soil
erosion and landslides become a very important issue in the high embankment and elevated
section of road. The soil erorision will be limited to the Right of Way of the project road.
Suitable measures such as turfing, plantation of tree, stone pitching, breast wall and retaining
walls have been provided to minimise the impact.
Soil erosion potential of an area depends on the slope of that area and the geological structure,
soil type and climate variation. However, slope is predominant factor amongst these. The road
passes through land slide prone area for about 500mts. The retaining walls and breast wall has
been proposed in these area to minimise the impact.
Excavation of borrows pits and quarries are the other important activities, which has impact
on land environment. Extraction of fill materials from hilly area or riverbed can cause
significant environmental impacts due to erosion and affecting local ecology. Unplanned
excavation of borrow pits can waste good agricultural land. Under the management plan the
excavated pit sites are required to be restored and reclaimed in a satisfactory manner on
completion of mining operations. As the quarry will be restored and reclaimed by the
contractor, impact on land environment will be of short duration and could be managed by the
management plans
A mitigation measure for soil erosion has been suggested in Chapter 7. Borrow pits and
queries have been identified. Mitigation measures for borrow pits and quarries have also been
suggested in Chapter 7. With the proper mitigation measures these impacts can be
minimized.
6.3.4 Noise
Major noise pollution will be generated during construction phase from operation of heavy
machineries; movement of heavy vehicles will also generate some noise. A lot of this problem
can be reduced by proper mitigation measures. Also construction phase noise is a very much
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-3 Detailed Project Report
temporary affair. Each type of activity can generate different type and level of noise but that
continue for a short period during the construction phase. The Construction activities are
expected to produce noise levels in the range of 72-98 dB(A) at 50 ft distance which will
decrease with increase in distance. The major construction works will be carried out during
the day time. The noise produced during the construction will however not have a significant
impact on existing ambient noise levels. Due to the high noise levels of construction
machinery, the personnel operating the machines and the workers stationed close to the
machines are prone to exposure of high levels of noise. Use of proper personal protective
equipment can mitigate the adverse impacts of noise generated by such equipment on
personnel.
6.3.5 Water Resources
The construction of the proposed road will not have any major impact on the surface water
quality in the area. Contamination of water bodies may result due to spilling of construction
materials, oils and greases and paint during transportation and at the equipment yards and
asphalt plants. But the quantity of such spill will be negligible. Care however, needs to be
taken to provide adequate sanitary facilities and drainage in the temporary colonies of the
construction workers. Provision of adequate washing and toilet facilities with septic tanks and
appropriate refuse collection and disposal system should be made obligatory.
Ground water contamination can take place only if chemical substances get leached by
precipitation of water and percolate to the ground water table and by dumping of the used
water from construction colony. This is not the case with the present project, as the activity
does not contain any harmful ingredients, which could leach down to water table. Therefore,
no impact on ground water quality is anticipated from the project during the construction and
operation phase.
The water requirement will be increased during construction phase. Sufficient water for
construction purpose is available by surface water of river, digging borehole / borewell all
along the project road. All these activities shall have to be located within the vicinity of the
project site during construction phase, hence proper care have to be taken while deciding the
location of these activities. Identification of suitable locations shall have to be carried out
based on the present ground water table which is quite high in the area in order to safeguard
the nearby environment.
Water resources can be impacted in different ways during construction of the roads.
Construction work close to this River can cause significant disturbances to the users of
Kaladan. The piling or storing of earth, aggregates or other construction materials close to the
River can be source of pollution. The materials can settle by wind, by surface runoff or
accidentally during transfer or handling in the River. The storing of aggregates and other
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-4 Detailed Project Report
construction material has been planned away from the river along the alignment at the plant
locations.
Areas where sensitive issues are likely to have impact on water bodies are given in Table 6.1.
Table 6.1 : Impact on Water bodies
Chainage (km) Sensitive issues Remarks
Package I – Paletwa to Kaletwa
0 to 1.2 Kaladan River May be affected
2.8 to 3.0 Milawa River May be affected
17.9 to 18.0 Milawa River May be affected
30.6 to 30.8 Dalesta River May be affected
50.4 to 50.6 Pargon River May be affected
56.2 to 56.3 Vaku River May be affected
59.9 to 60.6 Kaladan River May be affected
Package II- Kaletwa to Zorinpui / Indian – Myanmar Border
2.800 to 2.900 Kannu Chaung May be affected
7.300 to 7.400 Kan Chaung May be affected
10.400 to 10.700 Twoase Chaung May be affected
14.000 to 14.100 Thalan Chaung May be affected
17.100to 17.250 Sat Chaing Chaung May be affected
21.100 to 21.200 Do Chaung May be affected
25.200 to 25.300 Tangbel Chaung May be affected
27.150 to 27.250 Sulehi Chaung May be affected
31.850 to 31.950 Sulewvi chaung May be affected
36.850 to 36.950 Phuhlai Chaung May be affected
Mitigation measures to reduce impact on these rivers have been suggested in Chapter 7. It is
envisaged with proper implementation of the suggested mitigation measures and proper
monitoring, the impact will be negligible.
6.3.6 Trees
The road passes through the hilly terrain and therefore the tress falling on the alignment needs
to be cut. The impact will depend on the number, density, and type of species of trees on each
road.
As discussed before that this area is blessed with so many natural resources and greenery is
one of them. Table 6.2 provides the total number of trees on the roadside. Also compensatory
plantation and plantation along the total road will be carried out as detailed in chapter on
mitigation measures. With the proposed mitigation measures, there will be several times more
trees after the project is completed.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-5 Detailed Project Report
Table 6.2: Details of Trees to be affected
Chainage Number of Trees
Package I – Paletwa to Kaletwa
0-5 300
5-10 350
10-15 450
15-20 375
20-25 400
25-30 425
30-35 450
35-40 450
40-45 500
45-50 500
50-55 450
55-60 500
Sub Total 5150
Package II- Kaletwa to Zorinpui / Indian – Myanmar Border
0-10 700 10-20 750 20-30 750 30-40 850
40-48.5 750 Sub Total 3800
Total 8950
6.4 Impact during Operation Phase
6.4.1 Air Quality
During the operation phase of the project the air quality impacts due to the project will be
primarily due to the flow of traffic on the project road. The extent of these impacts will
depend upon i) the rate of vehicular emission and ii) the prevailing meteorological conditions
and iii) number of vehicles. As the traffic plying of the road would be of low level the impact
on the air quality would be minimal.
6.4.2 Noise
During the operation phase of the project uninterrupted movement of heavy and light vehicles
is expected to give rise to higher ambient noise levels. The sensitive receptors such as schools
and hospitals are not situated in the near vicinity of the project site. As the traffic plying of the
road would be of low level the impact on the surrounding area would be negligible.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Assessment of Environmental Impact 6-6 Detailed Project Report
6.4.3 Water Quality
During operation phase there is less possibility of any impact on waterbody. However water
quality can be impacted due to washing of the vehicles near the rivers, water bodies etc.
Washings from road can contain oil, which may end up in local water bodies.
6.4.4 Flora and Fauna
During operation phase there is least possibility of impact on flora and fauna.
CHAPTER 7
ENVIRONMENTAL
MANAGEMENT PLAN (EMP)
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-1 Detailed Project Report
CHAPTER 7
7.0 ENVIRONMENTAL MANAGEMENT PLAN (EMP)
7.1 Introduction
Environmental Management Plan (EMP) is the key to ensure that the environmental quality
of the zone under impact does not deteriorate beyond the expected level due to the
construction and operation of the project. As discussed in the previous chapters, the road
design, construction and operation activities can have various levels of environmental
impacts. The Environmental Management Plan (EMP) covers all aspects of the construction
and operation phases related to environment.
The Environmental Management Plan (EMP) needs to be implemented right from the
conception and should continue till the end. The Plan can be divided into three phases - (a)
Design phase (b) Construction phase and (c) Operational phase.
7.2 Design Phase
Design will also be based on social and environmental criteria. Important environmental
components e.g. soil erosion points, water resources, drainage, trees, wild life, sensitive
locations etc, and social components e.g, school, hospitals, religious places, residential areas,
commercial place etc. will be preliminarily identified on existing road plan. While finalizing
alignments and deciding on corridor of impact, this data will be considered and based on same
design will be incorporated to minimize the impact on environment.
Table 7.1: Design Phase Measures – General
Impacts Mitigation Measures
Land Acquisition Alignment design to minimize the land acquisition
(inevitable as project road is new alignment)
Major Displacement None
Removal of Trees Alignment has been designed to reduce the number,
alignment selected to avoid forest, Orchid etc.
Compensatory plantation has been planned.
Impact on public utilities. Alignment design to consider. In case of removal alternate
arrangement to be done before.
Impact on Cultural Sites None
Borrow pits Locations to be selected considering minimum loss of
productive land and redevelopment
Environmental
Specifications for
Contractors
Environmental qualifications specification should be
included in pre-qualification packages for the contractors
These mitigation measures have been considered during finalizing the road design. Table 7.2
shows some special mitigation measures adopted in project design.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-2 Detailed Project Report
Table 7.2: Mitigation Measures in Project Road Design
Impacts Mitigation Measures
Major Displacement None
Removal of Trees Alignment design has saved 6000 trees with selection of
project road.
Compensatory plantation of double the number of trees will
be carried out. Besides the total road section will be planted
with ten thousand trees.
Impact on public utilities
e.g. community wells etc.
In case of removal alternate arrangement will be done
before.
Kaladan and other Rivers The road section is parallel to the tributaries of Kaladan
River at some locations. Wherever required retaining wall
has been proposed.
Borrow Pits and queries Due to environment sensitivity, the project has plan for
borrow pits, far away from hills, so that there is no direct
impact on environment.
Air Quality and Noise The compensatory plantation along the project road would
reduce the impact of air and noise pollution.
7.3 Construction Phase
7.3.1 Land Environment
The impact of road construction starts with land environment. General mitigation measures
are suggested in Table 7.3.
Table 7.3: Mitigation Measures for Land Environment
Impacts Mitigation Measures
Soil Erosion Proper planning for slope stabilization, topsoil storage, plantation
and turfing on slopes.
Loss of topsoil Most of the earth work would be done from the cut volume of the
project road.
Borrowing of fill
materials
Excavation from pre-selected locations. After excavation, the
borrow pits will be dressed to match with surroundings. In
specific cases borrow pits can be excavated in consultation with
local people to use those pits as water harvesting points.
Disposal of
Construction waste
No haphazard dumping of construction waste. Only pre-selected
location maintaining local environmental regulations will be used.
Disposal of human
waste by
construction
workers.
Specific landfill sites should be identified to manage solid waste
generated from habitation of construction workers.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-3 Detailed Project Report
7.3.2 Air Quality and Noise
Construction activities at different phases can generate significant air quality problems. So
air quality and noise will be one of the major environmental issues. Mitigation measures
would be taken to reduce the impact as presented in Table 7.4. Specific areas for air and
noise pollution control have been identified and given in Table 7.4.
Table 7.4: General Measures for Air & Noise Pollution Control
Impact Measures
Generation
of Dust
Water will be sprayed during construction phase, in earth handling sites,
asphalt mixing sites and other excavation areas for suppression of dust.
Dust emission from piles of excavated material should also be controlled
by spraying water on the piles.
Special care should be taken when working near schools and medical
facilities.
Dust emission is a high-risk problem in the Stone Crushing activities.
Workers are exposed to high level of dust pollution. It will be
responsibility of the project proponent to ensure that stone crushers
supplying materials for this project implement air pollution control and
workers are provided with masks.
Gaseous
Pollution
Vehicles and machineries will be regularly maintained to conform to the
emission standards stipulated under Environment (Protection), Rules
1986.
Asphalt mixing sites should be sufficiently away from residential quarters
and not in forest area.
Workers working in asphalt mixing and subsequent application of asphalt
mix on road surface are exposed to high level of carcinogenic emission.
These workers should be provided with masks and it will be
responsibility of the supervising officers that the workers use the masks.
Noise Workers shall not be exposed to noise level more than permitted for
industrial premises, i.e. 90 dBA (Leq) for 8 hours. Workers exposed to
high noise level should use ear plugs
Construction work generating noise pollution near the health facilities
and residential areas should be stopped during night.
Noise attenuation measures e.g. planting of trees, noise attenuation
structures to be done as required.
However some specific areas need to be identified for air and noise quality control. Table
7.5 provides the locations and measures for air and noise quality control.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-4 Detailed Project Report
Table 7.5: Areas of Air Pollution and Noise Control during Construction near
Settlements
Chainage (km) Settlement Sensitive issues
10.3 (Package I) Likeo School – RHS
19.8 (Package I) Mang Ta PHC – LHS
7.3.3 Water Resources
The project work will have some impact on water environment along the roadside and also
the requirement of water for construction activities may have some impact on local water
resources. Mitigation measures would be taken to reduce the impact as presented in Table
7.6.
Table 7.6: General Measures for Protection of Water Resources
Impacts Mitigation Measures
Loss or impact on
water bodies
The water body or a part if lost will be replaced immediately.
The embankments of water bodies will be raised to prevent any
contamination from road run-off.
Flooding due to
siltation of
drainage channel
Excavated earth and other construction materials should be
stored away to prevent washing away.
Water use for
construction
Water sources would be selected so that local availability is not
affected. Local water bodies, tube wells, wells will not be used.
Borehole by contractors will be done with permission from
concerned department.
Contamination
from wastes
All practical measures will be taken to prevent any uncontrolled
effluent discharge from construction workers camps and
storages to water sources. The campsite will be provided with
proper drainage connected with local drain.
Contamination
from fuel and
wastes
Vehicle maintenance will be carried out in a confined area, away
from water sources, and it will be ensured that used oil or
lubricants are not disposed to watercourses.
Sanitation and
Water use in
Construction
Camps
Construction camp will be organized in a planned manner.
Workers shall be provided proper sanitation facilities including
toilets. Camps will have water supply facilities like tube wells or
from other sources without affecting the local water source.
During Construction work for the bridges over Kaladan River, it will be taken care that the
river water is not polluted due to the work. Also river should not be polluted by washing of
vehicles or use by the construction workers. Otherwise local users and aquatic ecology of the
river may be affected
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-5 Detailed Project Report
There will be impact on Kaladan River through sedimentation either due to tree cutting and
other construction activities as discussed in Chapter-6. To mitigate this problem stabilize
and elevate the riverbank before construction. Construction material should be keep away
from Riverside.
7.3.4 Flora
A tree census has been carried out noting all tree sizes and species. About 8950 trees will
have to be removed during construction activities. Major mitigation measures to be taken up
are given in Table 7.7.
Table 7.7: Mitigation Measures for Tree Loss
Impacts Mitigation Measures
Loss of
Trees
Tree felling will be restricted to requirement of construction activities.
About 8950 trees will have to be removed during construction
activities. Two times the number of trees cut will be planted. Besides
there will be more plantation on roadsides where there are no trees at
present. Total length of the road will be about 110.050 km. Plantation
will be done as near as the old site, most preferably just beyond the
existing position within Right of Way (ROW). To compensate the
felling of trees and improve environmental quality, trees will be planted
in nearby areas beyond the project site.
The species will be selected depending on site, plantation design and in
consultation with local community in the plantation program and forest
department. Tree plantation will continue as part of construction
process and will be included in Environmental Management Plan.
The trees will be planted by project authorities by the roadside within
ROW. The cost for plantation has been included in Environmental
Cost.
Medicinal
Plants
Efforts will be made to save medicinal trees. Afforestation program
will be taken up.
7.3.5 Fauna
Different fauna are affected due to construction activities. Mitigation measures for birds will
be planting of more trees, which will improve the condition much better than the present. For
wildlife in the remote areas, specific restrictions will be imposed. These include restriction in
timing of work; setting up of workers’ camp, use of water sources, traffic speed etc.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-6 Detailed Project Report
Table 7.8: Mitigation Measures to be adopted during construction Impacts Mitigation Measures
Loss of habitat for
avifauna Compensatory Plantation program will be taken up.
Impact on Wildlife No harvesting of wild foods or hunting of animals.
Speed restriction in night.
7.3.6 Safety
Safety at different stages of construction is an important issue both for local people as well as
for the construction workers.
Table 7.9: Safety Measures
Impacts Mitigation measures
Information to Public Signs will be posted on road before construction areas
informing public and travelers about the work and
safety provisions.
Restriction to Access Safe and convenient passage for vehicles, pedestrians
and livestock to and from the side roads and property
across the road will be arranged during construction
work
Occupational Safety for
Construction Workers
Contractor will arrange all safety measures for workers
as per Factories Act
Occupational Safety for
Asphalt plant workers and
Crusher plant.
All workers employed on mixing asphaltic material,
cement, lime mortars, concrete etc., will be provided
with protective footwear and protective goggles. For
crusher workers, masks should be provided.
Explosive use The Contractor shall at all times make full liaison with
and inform well in advance and obtain such permission
as is required from all Government Authorities, public
bodies and private parties whatsoever concerned or
affected or likely to be concerned or affected by
blasting operations.
7.3.7 Storage Site
Storage of construction related materials, like machineries, materials etc. will not be stored
near any waterbody, school, health facilities and residential areas. The discarded materials
from the storage site will be kept in a specific place at the storage site and disposed according
to environmental laws and regulations. Especially, two relevant rules – Manufacture, Storage
& Import of Hazardous Chemicals Rules and Hazardous Waste (Management and Handling)
Rules – should be always considered. For storage of explosives, Explosives Act should be
followed. Storage site should have proper signs for safety.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-7 Detailed Project Report
7.3.8 Workers’ Camp
Construction workers are a much neglected group in the country. Unless the workers are
provided proper amenities to live at the construction site, the environmental issues of road
construction cannot be properly met. Following mitigation measures are suggested in Table
7.10. In accordance with Environment (Protection) Act, for any environmental pollution from
the workers’ camp, the responsibility would lie with the project authority and subsequent
penal action can be taken against them.
Table 7.10: Mitigation Measures for Workers’ Camps
Issue Measures
Location Workers’ camps will be located away from water bodies,
schools, and residential areas.
Construction Camp will be constructed with proper accommodation
facilities, should look aesthetically good as this will be a
roadside feature during construction period
Water Contractor will arrange for potable water supply for the
workers so that local water sources are not disturbed. Bore
well for the camp will be suitable for this region.
Sanitation Workers’ camp will be provided with proper sanitation
facilities, toilets with septic tank and soak pits.
Other amenities Crèche, first aid etc as required under Factories Act
Some important guidelines related to stone quarries, noise levels of machineries and vehicle
standards are given in Table 7.11.
Table 7.11: Guidelines related to stone quarries, noise levels
Source Regulations
Stone Crusher i) Implementation of following pollution control measures:
a) Dust containment cum suppression system for the equipment.
b) Construction of wind breaking walls.
c) Construction of metalled roads within the premises.
d) Regular cleaning and wetting of the ground within premises
e) Growing of a green belt within the periphery
ii) Quantitative standard for SPM:
The SPM contribution value at a distance of 50 meters from a
controlled isolated as well as from a unit located in a cluster should
be less than 600 mg/m3. The measurements are to be conducted at
least twice a month for all the 12 months a year.
Vehicles Petrol driven: 4 wheelers: Idling CO not to exceed 3 % by volume.
3 & 2 Wheelers: Idling CO not to exceed 5.5 % by volume
Diesel driven: Smoke Density
a) At full load and 70% maximum speed: 3.2 Light Absorption Co-
eff
b) At free acceleration: 2.3 Light Absorption Co-eff
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-8 Detailed Project Report
Source Regulations
General Emission Particulate matters: 150 mg/Nm3
Automobiles 2 and 3 wheeler : 80 dB (A)
Passenger car : 82 dB(A)
Passenger or commercial vehicles upto 5T : 85 dB(A)
Passenger or commercial vehicles 5-12 T : 89 dB(A)
Passenger or commercial vehicles 5-12 T : 91 dB(A)
Machineries Compactors, Front loaders, Concrete
mixtures, Cranes, Vibrators, Saws : 75 dB(A)
7.4 Operation Phase
Environmental issues change during operation phase and its mitigation plan also has to look
towards a longer period of time. Operation phase environmental aspects are thus more
related to vehicular emission. The mitigation measures for different environmental aspects
are discussed below in Table 7.12.
Table 7.12: Operation Phase Mitigation Measures
Impacts Mitigation measures
Dust Bad road maintenance of road gives rise to dust pollution. Road surface
will be maintained properly.
Gaseous
Pollution
All vehicles should be checked for “Pollution Under Control” certificates
and occasional spot testing of emission from vehicles will be carried out.
Surface
runoff
Surface runoff from the road will not be disposed directly in the water
bodies used by people for bathing etc. It should also not be disposed
directly in to any watercourse with good water quality.
Wild Life There should be speed restrictions through specific area in the night to
prevent accident with wild animals. There will be proper sign for the
drivers to inform about this.
Flora Tree plantations will be monitored continuously.
Safety Safety signs should be kept always clean and updated
Public
amenities
Bus Stops, Underpasses etc. should be kept in order.
7.5 Environmental Enhancement
Environmental enhancement considers additional provisions, which can be included in the
execution of highway widening project to enhance better road service facilities, public
amenities, safety provisions and environmental quality. Also it suggests improvement of
aesthetic qualities of the project corridor. Following are the provisions for the environmental
enhancement.
7.5.1 Road Service Facilities
Bus lay-byes: Bus Lay-byes are also proposed to be set up near the villages.. The location
will be developed aesthetically with ornamental plantations, shade trees and shrubs.
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Setpyitpyin (Kaletwa) in Chin State of Myanmar
Environmental Management plan 7-9 Detailed Project Report
7.5.2 Public Amenities
Bus Stops: New bus stops with sitting bench and shade will be provided at all the settlement
areas. The shades will be of aesthetic design improving the visual quality of the highway.
Traffic Safety Signs: Traffic safety signs will be provided prominently at all places where
it is required for public safety like schools, heath centers, market area etc.
7.5.3 Water bodies
As discussed before, a number of water bodies will be affected by proposed alignment.
There will be mitigation measures as also discussed earlier. However there will be further
effort to enhance the aesthetics of these water bodies as well as public utility.
Landscaping: The slopes of the Kaldan River and its tributaries particularly near bridges
will be vegetated and landscaping will be done to improve the aesthetics of the place. The
slope will rise slowly from the roadside and there will be plantation of trees, which will
reduce soil erosion.
Improvement of Navigation Points: The Kaladan River has Navigation points along the
road. These navigation points will be improved with maintenance. Local styles will be
adopted developing new navigation points.
7.5.4 Workers’ Camps
As said before workers’ camps are most neglected. One of the important tasks of
environmental enhancement will be to build model workers’ camps, which then can be
replicated in all road construction projects. The workers’ camps will be clean, the camp
houses will be properly painted, the housing area nicely separated from the surroundings.
There may be flower plants etc to make the place beautiful. There should be sign stating it as
workers’ camp so that people traveling along the road can learn about the model camps.
CHAPTER 8
FINDINGS, RECOMMENDATIONS
AND CONCLUSION
Preparation of Detailed Engineering Project Report for Two Lane Road from Paletwa to Zorinpui (India Myanmar Border) in Chin State of Myanmar
Findings, Recommendations and Conclusions 8-1 Detailed Project Report
CHAPTER 8
8.0 FINDINGS, RECOMMENDATIONS AND CONCLUSIONS
8.1 Findings of the Study
The major findings of the study are:
a) This project is a part of Kaldan Multimodal Project between India and Myanmar
Government. Once the road is developed, the traffic, mainly freight and passenger can
travel with ease and in less time from Sittwe to Mizoram.
b) As road passed through a number of villages, which would improve connectivity to the
project area.
c) The selection of alignment option has significantly reduced the number of trees to be
cut.
d) River Kaladan and its tributaries by the side of the road, which may be partly impacted.
Environmental Management Plan has taken care of this aspect.
8.2 Recommendations
The EIA report has discussed the environmental issues in details and then suggested an
Environmental Management plan. The plan with proper implementation monitoring
schedule needs to be followed. Major recommendations in these plans are given below:
a) An Environmental Management Group should be established to implement
Environmental Management Plan and regular monitoring of environmental quality.
b) No campsite, extraction of water and work after evening within social forest area.
c) Air pollution and noise pollution control measures to be implemented during
construction, specifically in the identified sensitive areas.
d) Water bodies will not be impacted as far as possible.
e) Workers camp will be located away from water bodies and will have proper water
supply and sanitation facilities.
f) All machineries should conform to noise and emission limits as per Indian laws or
Myanmar Laws.
8.3 Conclusion
It has been discussed at the onset that this road is a part of bilateral agreement between
Government of India and Government of Myanmar, there is a proposal to develop a trade
route between the two countries. The road development will no doubt have some impact on
environmental components. However with EMP as suggested in this report would reduce
the impact on the project surroundings.