CITY OF PHOENIX

WATER SERVICES DEPARTMENT

AIRPORT INFRASTRUCTURE MASTER PLAN

STUDY SERVICES

PROJECT NO. WS85509058-1

March 5, 2018

Pre-Submittal Meeting

Julie B. Smith, Contract Specialist

[email protected] (602) 534-2418

Nicolas Zavala, Civil Engineer II (Project Manager)

Water Services Department

Mario Brown, Civil Engineer III* Team Leader

Water Services Department

Welcome and Introductions

Vendor Registration

To do business with the City you MUST register in

procurePHX at https://www.phoenix.gov/procure.

It takes the city about two business days to approve the

registration.

The City will email confirmation with vendor number.

For questions about procurePHX, please send an email to

[email protected]

Sign-in please

Sign-in sheet and PowerPoint will be posted on Procurement’s

website:

http://phoenix.gov/streets/procurement/current-opportunities

Click on respective project, then click on:

■ Planholder List ■ RFQ ■ Notifications (if applicable)

Please hold questions until the Q&A period

This is the ONLY opportunity to discuss this project

with City staff

Meeting Overview

Project Description and Scope of Work

Evaluation Criteria

SOQ Due Date

Questions

Agenda

Project Description

LS 40

The WSD is responsible for much of the sanitary sewer & potable

water infrastructure at the Phoenix Sky Harbor International Airport

(PSHIA) located both, airside and landside

Multiple security restrictions and accessibility issues impact WSD

ability to operate and maintain public water/sewer infrastructure

on both airside and landside

Requirements pertaining to repair access, timing, transporting

materials and equipment are much more restrictive on airside

Due to restrictions, WSD proposes to develop a strategy to

eliminate pubic water and sewer lines within the Aviation

properties, where possible.

Consider multiple options to accomplish this task

Project Description Airside and Landside boundary is defined by red lines

Airside

Airside

Landside

24

thSt

Washington St

Scope of Work

LS 40

Water Infrastructure

Option 1: This is the ultimate desire, installation of a looped water

distribution main or branch system owned by WSD. The WSD would

own/operate all water mains and service connections within the City R/W.

The Aviation Department would own on-site water lines and appurtenances.

Option 2: Remove/relocate all public waterlines underneath the runways.

Option 3: Remove/relocate all public waterlines underneath airplane taxi

ways plus option 2.

Option 4: Remove/relocate all public water lines on the airside of the

Airport plus options 2 and 3.

Option 5: Remove/relocate all public water lines on the landside of the

Airport.

Other options to be develop during the study.

Scope of Work

LS 40

Sewer Infrastructure

Option 1: Explore options for transferring ownership and maintenance

of local existing sewer segments that serve PSHIA only.

Option 2: Diversion of upstream flows through new sewer(s) around

PSHIA, so existing sewer remaining on PSHIA property becomes local

sewer (see Option 1).

Option 3: Explore options to relocate collection sewer lines that cross

through PSHIA on airside to landside locations.

Other options to be develop during the study.

NOTE: Transfer of ownership of some sewer lines is clearly not feasible.

The most apparent example is the Salt River Outfall (SRO) which

crosses PSHIA along side of 3rd runway. Relocation of this 72”-84”

diameter Sub-Regional Operating Group (SROG) is highly unlikely.

Scope of Work 2015 Aviation Property Map

24

thSt

Washington St

16th

St

7th

St

SR

143

Air Lane

Scope of Work

Project boundary: Salt River and I-10 to south, Air Lane to north, 44th St to

east and I-10 to west

Identify any public water and sewer ownership/mapping issues/discrepancies

Identify the on-site public water and sewer lines and appurtenances that

would be turned over to Aviation for their ownership and maintenance

Identify any new water/sewer main/loop alignments, including size and costs

Identify the new water/sewer service connection locations (combined fire

and domestic services would be allowed)

Develop preliminary cost estimates for water and sewer design and

construction phases

Develop preliminary design plans (plan view only): for all the recommended

new water and sewer main alignments and identify major utility conflicts

Scope of Work

Study Report: documenting the means and methods used to develop the

options, selecting the alignments and transferring ownership, provide all

information gathered, describe how the recommended alignments were

selected, etc. Provide Draft and Final versions

Provide possible aerial survey

Coordinate with other departments on all the options within the right-of-way

and/or on City owned property

Coordinate with the Aviation Department on the requirements part of the

Comprehensive Asset Management Plan (CAMP)

CAMP is a 20-year plan for airport facilities, infrastructure and land

development

General Information – 10 points

Study Experience of the Prime Firm – 25 points

Experience of Key Personnel & Subconsultants - 30 points

Project Understanding & Approach – 30 points

Overall Evaluation of the Firm – 5 points

Statement of Qualifications Criteria

Each page side with criteria information will be counted.

Pages that have photos, charts, and graphs will be counted toward maximum number of pages.

Information Sheet, front and back covers, Table of Contents and tab dividers will NOT be counted toward the maximum page limit, UNLESS they include information that may be considered by the selection panel.

Statement of Qualifications Criteria

Information Sheet

Legal company name with physical address

Primary contact person name/title/email/phone numbers

Additional Content (resumes or other information)

+ Evaluation Criteria (including organizational chart)

= 10 MAXIMUM pages permitted

Statement of Qualifications Criteria

Submit 8 copies of the SOQ.

SOQ due: 12:00 pm Noon – Arizona local time

Friday, March 16, 2018

Phoenix City Hall

200 W. Washington Street, 6th Floor

Submittal Box

Statement of Qualifications Criteria

Receipt of SOQ after the specified cut-off date

and time

Too few copies of the submittal

Deposit of SOQ in the wrong location

Violating the “Contact with City Employees” policy

Grounds for Disqualification

RFQ

Notifications

Plan Holder List

Pre-submittal Power Point Presentation

Pre-Submittal Sign-in sheet

Award Web Page

https://www.phoenix.gov/streets/procurement/bid-results

Sign-up for Newsletter

https://www.phoenix.gov/streets/procurement/current-opportunities

Design & Construction Procurement

E-mail your questions to:

[email protected]

Thank You !!!

Julie B. Smith

Contract Specialist

(602) 534-2418

Questions After Today

OPEN FOR QUESTIONS

&

THANK YOU FOR ATTENDING