Pre Construction Meeting Project Name: ______________________________ Date of Meeting:____________________________ Introductions: MedExpress Employees VP of Construction: Don Horner [email protected] Director of Construction: Bob Basile 304-216-8007 [email protected] Senior Architect Designer: Eric Dietz 304-282-6096 [email protected] Project Manager: Ryan Rodeheaver 304-276-5001 [email protected] Project Manager: Rodney Turner 304-281-9455 [email protected] Project Manager: Jeff Beck 724-206-8494 [email protected] Project Manager: Johnny Reece 304-280-7935 [email protected] Delivery Related Questions for Owner Supplied Items: Megan Lura [email protected] 304-276-2301 or Ashley Morrow [email protected] 412-330-8903 All Vendor Contacts are located on Front Cover of Plans under Vendor Info.

Pre Construction Meeting · Unless required by GC, formal RFI’s are not needed. Architectural questions should be directed to Architectural Project Coordinator listed on Title page

  • Upload
    buidieu

  • View
    217

  • Download
    3

Embed Size (px)

Citation preview

Pre Construction Meeting

Project Name: ______________________________

Date of Meeting:____________________________

Introductions: MedExpress Employees

VP of Construction: Don Horner

[email protected]

Director of Construction: Bob Basile 304-216-8007

[email protected]

Senior Architect Designer: Eric Dietz 304-282-6096

[email protected]

Project Manager: Ryan Rodeheaver 304-276-5001

[email protected]

Project Manager: Rodney Turner 304-281-9455

[email protected]

Project Manager: Jeff Beck 724-206-8494

[email protected]

Project Manager: Johnny Reece 304-280-7935

[email protected]

Delivery Related Questions for Owner Supplied Items:

Megan Lura [email protected] 304-276-2301 or

Ashley Morrow [email protected] 412-330-8903

All Vendor Contacts are located on Front Cover of Plans under Vendor Info.

General Requirements

Completion Date: _________________________

Open Date:______________________________

Delivery Schedule: ________________________

Have Any Revisions been made to Plans since Bid, Revision Date:

_______________

Any Unusual circumstances pertaining to this job:

___________________________________________________________________

___________________________________________________________________

1. Name of Landlord and Contact info: _

__________________________________ Landlord Responsibilities:

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

2. Property Salvaged for MedExpress: ___________________________________

Property Salvaged for Landlord: ________________________________________

2. Sewer line (if existing) from Building to Main needs camera’d and video turned

into a MedExpress Representative.

3. Who is responsible for Utilities:

Electric Service: ________________________________________________

Medexpress account number: _______________________________

Gas: _________________________________________________________

Medexpress account number: ____________________________________________

Water: _______________________________________________________

Medexpress account number: ___________________________________

4. Who should the GC contact with project related questions? 1. Your designated

MedExpress PM, 2. Bob Basile. 3. Eric Dietz.

Unless required by GC, formal RFI’s are not needed. Architectural questions

should be directed to Architectural Project Coordinator listed on Title page of

drawings.

5. General Contractor is responsible for contacting the local Fire Marshal having

Jurisdiction to find out if a Knox Box is required. If required, GC is responsible for

ordering and installing in location determined by Fire Marshal.

6. Any Change Orders should be made through GC and Owner. If directed to

change or deviate from plans, written communication should be received PRIOR

to performing work, or ordering materials. Email acceptance from MedExpress

Project Manager or higher is sufficient to proceed. A formal CO must be executed

by GC and Owner prior to close out, including detailed “back up” from

subcontractor.

7. No substitutions are permitted unless authorized in writing by MedExpress PM

or higher.

8. Ordering of Owner supplied items.

List of Owner Supplied items.

1. Lighting ( GC to schedule delivery )

2. Signage

3. Millwork ( GC to schedule delivery )

4. UPS System

5. Rack , jacks , Tv’s , speakers, patch panels

6. Yellow Bin storage system ( not wire shelving )

7. Auto dispensers, manual soap dispensers , sanitizers

8. Otoscopes

9. Artwork

10. Furniture

11. Fire , Burg, access panels ( no devices )

Shortly after the start of the project the GC will be provided with a Delivery

Schedule calling out when the deliveries will hit your center. It is the GC’s

responsibility to let your designated PM know if you have any issues with the

delivery or installation dates that are provided to you. Please contact your

MedExpress Project Manager if you do not receive the delivery schedule by or

before your rough in inspections.

A. Lighting Package: General contractor or Electrician is responsible for

contacting City Lighting (see title page on plans for lighting vendor contact info) to

release and ship lighting package. Please give them 2 weeks’ notice. Electrician is

responsible for inspection of fixtures to ensure no damage has occurred in

shipping. If any damage is discovered, the electrician must notify the Supplier by

email within 24 hrs of receipt of product. Please be aware that MedExpress has a

1 year Warranty covering both Parts and Labor on their lights. Should you be

asked to replace a ballast, please contact Jeff Such (Property Manager). Under

Awning lights/Archon Box up lights/Parapet Halo LED String lights, will be supplied

by MedExpress, GC responsible for Installation.

[email protected] .

B. X-Ray: delivery of X-ray equipment will typically arrive 3 weeks prior to

Completion Date. X-Ray walls and flooring (including waxing of VCT) and Electric

associated with X-ray equipment will need to be completed prior to arrive. Please

contact Russ Nation of MedServe to verify install date or answer any installation

questions. Low voltage wire should be ran from top of jamb to Xray generator.

C. Dover Cabinets: GC is responsible for releasing Mill Work package from

Dover Cabinets. Please give two weeks notice. The GC is responsible for the

unloading of all products. It has been our experience that it is most effective to

have all exam rooms ready to accept base cabinets in order to keep storage

clutter to a minimum. Please note any damage on delivery receipt. Please contact

Dover Cabinets if any mistakes or issues are discovered upon installation.

D. YKK Entry Door’s and storefront materials: Your Glazing contractor willneed to Specifically Direct their local YKK Distributor to Contact Ron Rigsby atthe Cincinnati OH plant of YKK. The Cincinnati branch stocks our doors and hascommitted to a 2 week lead time on doors. Please contact your MedExpress PMimmediately if there is an issue with this turnaround time. Please Contact IvanZuniga with any issues related to Stock Aluminum.

Phone: (678) 838-6092Cell: (770) [email protected]

E. Armstrong Flooring and Ceiling Tile: Please contact Armstrong Rep

listed on Title page to receive MedExpress National Pricing. Please make sure you

ask distributor for MedExpress pricing! We also receive a discount from a Group

Purchasing Organization. We may occasionally need the actual invoice that your

flooring contractor receives in order to gain our discount from our GPO. Please

note that we are in the process of changing to a Tandus-Centiva Vinyl Bamboo

product. Your contact for this product is: Product X-number is: 2869 Teresa

Tanner, Tandus-Centiva Customer Service, 1 (800) 241-4902; EXT 3307 1 (256)

760-1763 fax [email protected]

F. Nichiha Panels: The GC is responsible for both ordering and purchasing

Nichiha Fiber Cement Panels directly from Nichiha contact at our Pre-negotiated

price. If your Installer chooses to have a Factory Rep. provide your take-off please

be sure that the Installer checks this order for accuracy so that shortages are not

an issue. We have had many recent issue’s with installer placing “lean” orders

and running short at completion. Please be sure that your sub is ordering

appropriate quantities to prevent long delays and unnecessary shipping charges.

G. Aluminum Canopies above Doors and Parapet Brackets: The GC is

responsible for the purchase and installation of Aluminum Canopies and Parapet

Halo brackets through Davison Manufacturing. [email protected]

724-697-4876 or 724-602-6754

H. Signs and Awnings: MedExpress will provide GC Superintendent with

the install date as completion approaches. EC is responsible for running wire to

designated junction box as well as verifying signs are operating After Sign Install.

Please be sure that the Electrician runs his wire (or adds a pull string) to the

Aluminum Canopy (above front doors) prior to installing the Canopy on the

building. Under Awning lights will be supplied by Owner and mounted and

installed by GC.

I. Phone Lines: MedExpress will place the order for the phone lines and

Verizon (or alternate carrier) will install. Please make sure that you make all

efforts to get the two, 2” conduits installed (4” if ground up build) from the

electric closet to the exterior of the building, functional Electric receptacle, as well

as plywood installed on interior wall for network box mounting ASAP. Please

notify Nolan Mills by email at [email protected]. (Please also Copy

your designated MedEx PM) as soon as this portion of work is completed so that

he can order phone lines. Obviously, lack of phone lines will hold up final

inspections and CO.

J. Security/Fire Alarm: Contractor is responsible for contracting directly

with Security Company to provide the Security/Fire Alarm/Access Control

systems. Intertech Security will monitor the system and will supply the

GC/Security vendor with the Burglar/Fire panel: Vista 128FBP by Honewell and

Access Control: HID Vertex Controllers, Genetec software. The GC’s

Subcontractor will be required to contact the Local Authority having Jurisdiction

and providing them with all requirements (shop drawing…etc.) to submit and

receive any required permits prior to installation and commissioning.

K. UPS Battery Backup System: Owner coordinate shipment of unit to site.

It will be the GC’s Site Superintendents responsibility to contact Roy Macalma of

Emerson at 885-239-4292 or [email protected] to schedule the UPS

System Start up. This must be done prior to Electrical Inspection.

10. Set Up team arrival 1 week prior to completion: We have several

MedExpress members that will arrive toward the end of the job that will start

stocking the center with ALL items needed to operate the clinic. Please also be

aware that our Set Up team has the authority to ask for changes. If directed by

our set up team to make a change that you feel deviates from the Plans, please

simply email this change to your designated MedExpress PM for approval. Please

keep in mind that the set up team typically arrives 1 week prior to the agreed

upon Completion date to start receiving all items and they will start to set up the

clinic. It is imperative that the exam room floors be waxed and ready to set up

Exam Table beds, as well as all VCT and shelving in supply rooms are installed.

There is a tremendous amount of supplies that will arrive so it is strongly advised

to push for substantial completion prior to their arrival.

11. The GC is required to provide 2 dumpster pulls for our Set Up team trash

(called out in Project Manual Page SC-7). There is a significant amount of trash

that accumulates from our stocking and setting up of the clinic.

12. If applicable, Please verify that existing parking lot light bases and poles are

adequate to reuse. If found to be inadequate, we may need to submit drawings

for permit as well as long lead times on poles and heads if found to be

inadequate. Please also make sure to Contact City Lighting soon after the start of

job to give them a date you would like the light poles and head delivered. Please

make sure to give them a date 1 week sooner than you need them. There always

seems to be an issue getting these on site.

13. If project involves an existing building and roof repair or replacement is not

called out in the plans… please identify any roof leaks. Please let MedExpress PM

know immediately upon inspection to ensure proper party responsible for

corrective action is contacted.

14. All wall hung items will be fastened with screws penetrating into the blocking

that should be previously installed. In no instance should double faced tape be

used.

15. Vinyl plank flooring will be installed using a: Full piece, 24”, 12” pattern.

16. HVAC Air Balance report needs to be provided to the MedExpress PM prior to

closeout.

17. As-builts: please have all subs mark up their plans in red (or highlighted) with

any field changes. GC is responsible for turning in as part of close out.

18. Extra Stock: Please leave a full box of ceiling tile, Vinyl plank flooring, and 1

gallon of both P1 and P2 colors of Interior Paint.

Also included Revised Picture Package.

Wood Pre-Panelized System

General Overview,

This project will utilize a Wood Panelized System. All exterior walls, trusses, tower, tower roof

and parapets, will be pre-built by a MedExpress vendor and shipped direct to the site. The

delivery will need to be coordinated with Vendor upon award of project. The General

Contractor will need to provide a cost to erect wall panels, roofing system, and tower upon

delivery. General Contractor will need to have equipment on site in order to unload materials

upon arrival. Please review shop drawings of the specific details and sizes of panels. Please

contact Ryan Arblaster (724-355-9475) [email protected] with any questions.

1. It is extremely important that foundation be square and plumb. GC to supply and install

Foundation Anchors per Note on S-2.1, Section 101, and End Post Detail 103 of same

page. It is required that a Professional Surveyor Establish the Corners as well as Elevation

to ensure that the foundation is perfectly square and level.

2. It is required that floor slab be in place prior to arrival of Panel System as panels will need

to be temporarily braced to concrete slab.

3. All Structural Steel should be in place prior to Panel System arrival.

4. The GC will be responsible for equipment necessary to unload panels and trusses. Straps

will be provided for unloading.

5. Each panel will be labeled in accordance with the drawing layout. Walls will arrive

sheathed and vapor barrier installed.

6. 40= 2x6x16’s temporary bracing will need to be provided by General Contractor. 3”x3” x

12”Pre-Drilled Angle Iron Brackets will be provided by Panel Company (see Sketch at

bottom of page) to be anchored to the floor slab with 3/8” Lags and Shields. 2x6 bracing

will be through bolted through 2x6 with 2= ¼ bolts provided. Anchor Brackets will be

shipped prior to panel delivery so that they may be installed prior to panel arrival. Please

contact Michael Mendicino (724-787-3586) if you would like Anchor Brackets delivery

prior to arrival of the Panels.

7. The following material list will be supplied by General Contractor. See next Page

8. Please be sure to provide a Labor Cost for GC to install the Wood Panelized System on

your Bid Form upon submission. MedExpress will have the option to use an alternate

installation crew. MedExpress Representative will notify General Contractor if the wish

for the General Contractor to Install the Wood Panelized Shell System upon awarding

of project. In either case, General Contractor will be responsible to supply loose

lumber per material list below.

Material List to Be Supplied by GC

Description: Type QTY

Temporary Wall Bracing 2x6x16’ 45pcs

Bottom of Truss Bracing 2x4x12’ 96pcs

Truss Splice Connection 2x4x8’ 20pcs (review Truss Shops for exact qty)

Roof Cover Flat Edge 2x6x16’ 26pcs

Interior Tower Floor ¾ Plywood 10sheets

Roof Sheeting 5/8” Plywood 154sheets

Parapet Sheeting (back side) 5/8” Plywood 45sheet

Tower Floor Joists 2x10x18’ 18pcs

Tower Floor Joist Hangers 2x10 Joist Hngrs 28pcs

Truss hangers on tower 2x6 Joist Hngrs 16

Hurricane Anchors 180

Anchor Bolts 1”dia x 16” epoxy 5pcs

Anchor Bolts ½”x 7” Wedge Anchors 155pcs

Strap Ties mst148 14pcs