pre cast technology

Embed Size (px)

Citation preview

  • 7/29/2019 pre cast technology

    1/53

    Cast Insitu

    Precast

  • 7/29/2019 pre cast technology

    2/53

    FLOW OF PRESENTATIONFLOW OF PRESENTATION

    1 NEED FOR INNOVATION IN CONSTRUCTION

    2 COMPARISON OF CONVENTIONAL AND PRECAST TECHNOLOGY

    3 PRECAST TECHNOLOGY

    4 CASE STUDIES

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    6 SUSTAINABLE GOALS

    7 RISK MANAGEMENT

    http://localhost/var/www/apps/conversion/tmp/scratch_2/Precast%20case%20studies.pptxhttp://localhost/var/www/apps/conversion/tmp/scratch_2/Precast%20case%20studies.pptx
  • 7/29/2019 pre cast technology

    3/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION--Shortage of skill & ExpertsShortage of skill & Experts

    Construction industry employs approx 49 million personnel.

    Sharp decline in skilled workers and engineers.

    The table below shows statistics from Planning Commissions 11th five year

    plan (2007-2012).

    SR NO. DESCRIPTION NOS. IN 1995(IN 1000S) % WITH TOTALNOS. NOS. IN 2005(IN 1000S) % WITH TOTALNOS.

    1 ENGINEERS 687 4.71 822 2.65

    2 TECHNICIANS &

    FOREMAN

    359 2.46 573 1.85

    3 CLERICAL 646 4.4 738 2.38

    4 SKILLED WORKERS 2,241 15.34 3,267 10.57

    5 UNSKILLED WORKERS 10,670 73.08 25,600 82.45

    6 TOTAL 14,600 100 31,000 100

  • 7/29/2019 pre cast technology

    4/53

    51.0

    52.0

    53.0

    54.0

    55.0

    56.0

    57.0

    58.0

    59.0

    60.0

    61.0

    0

    100

    200

    300

    400

    500

    600

    2011 2012 2013 2014 2015

    Supply

    Demand

    Gap(%)

    Demand for affordable housing in top seven cities is likely to outstrip

    supply by 2015, according to global consultant Cushman & Wakefield. Total demand of 3.94 million units of residential property in the next five

    years at CAGR of 11%.

    Source: Cushman & Wakefield Research

    HOUSINGUN

    ITS

    (IN

    THOUSAN

    DS)

    YEAR

    GAP(

    %)

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION--Demand & SupplyDemand & Supply

  • 7/29/2019 pre cast technology

    5/53

    Estimated supply by the use of conventional methods is expected to be

    approximately around 1 million units from top 7 cities. Demand for the top 7 cities is forecasted as 2.3 million units indicating a

    shortfall of 1.3 million units.

    Source: Cushman & Wakefield Research

    HOUSING UNITS (IN THOUSANDS)

    0 200 400 600 800

    Mumbai

    Pune

    Hyderabad

    Kolkata

    NCR

    ChennaiBangaluru

    Supply

    Demand

    Gap

    Demand Supply Projections 2011-2015

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION--Demand & SupplyDemand & Supply

  • 7/29/2019 pre cast technology

    6/53

    Simple adaptation of western ideas for processes does not supporthousing solutions for low-income parts of society.

    Use of designs that are appropriate to the economic, social, cultural

    and natural conditions of each community are of vital importance.

    Outflow of currency to purchase machinery and raw material for local

    production should be stopped.

    Standards and rules from developed world make housing unavailable

    in third world and developing countries.

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTIONPRINCIPLES IN AFFORDABLE HOUSINGPRINCIPLES IN AFFORDABLE HOUSING

  • 7/29/2019 pre cast technology

    7/53

    CONCLUSION: TechnologyCONCLUSION: Technology

    "When compared to any other discipline of building construction,

    civil construction is conventional in it's approach. We need to

    breakaway from the convention to meet the demand and de riskcritical construction activities. One such technology proven

    elsewhere in building construction is Precast

    -Innovations in other discipline

    High speed lifts Automation

    Censors to control usage of electricity and water

  • 7/29/2019 pre cast technology

    8/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION--Cost AnalysisCost Analysis

    37%

    18%

    45%

    Concrete Yard set up/Erection

    28%

    63%

    2%

    5%

    2%

    Land

    ConstructionDesign Fees

    Marketing

    Admin9%

    51%

    21%

    7%

    2%10%

    Cost analysis for structure

    Sub structure super structure

    Architecture PHE

    FPS Electrical

    Cost analysis for Precast

    Margin

    25%

    Project

    Cost75%

    Yard

    40%

    Erection

    60%

    Project Costs

    Selling Rate

    75%

    4.5%

    Rebar

  • 7/29/2019 pre cast technology

    9/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- PROJECT MANAGEMENTPROJECT MANAGEMENT

    Phase 1 Phase 2 Phase 3 Phase 4

    Initiation Planning Execution Close out

    Time

    Cost of Making Change Curve

    High

    Low

    Project Life Cycle

    Plan Act

  • 7/29/2019 pre cast technology

    10/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- PROJECT MANAGEMENTPROJECT MANAGEMENT

    Phase 1 Phase 2 Phase 3 Phase 4

    Initiation Planning Execution Close out

    Time

    High

    Low

    Project Life Cycle

    Plan Act

  • 7/29/2019 pre cast technology

    11/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- PROJECT MANAGEMENTPROJECT MANAGEMENT

    Phase 1 Phase 2 Phase 3 Phase 4

    Initiation Planning Execution Close out

    Time

    Value Addition Curve

    High

    Low

    Project Life Cycle

    Plan Act

  • 7/29/2019 pre cast technology

    12/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- PROJECT MANAGEMENTPROJECT MANAGEMENT

    Phase 1 Phase 2 Phase 3 Phase 4

    Initiation Planning Execution Close out

    Time

    Amount of Stake Curve

    High

    Low

    Project Life Cycle

    Plan Act

  • 7/29/2019 pre cast technology

    13/53

    Precast Concrete construction

    a) Full Precast system

    All elements including faade are precast

    b) Precast column / walls with flat plate / flat slab

    c) Precast beam and precast slab

    Floor system could be

    Precast hollow core slab + cast-in-situ topping

    (this can be used for long span structure of 8.0m to 15.0m

    Spans) Precast plank with cast in situ topping

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTIONPRECAST SYSTEMPRECAST SYSTEM -- OPTIONSOPTIONS

  • 7/29/2019 pre cast technology

    14/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- BENEFITS OF PRECAST SYSTEMBENEFITS OF PRECAST SYSTEM

    Construction time can be reduced by 40%.

    - Layout should be suitable for mechanization

    Labour requirement can be reduced by 40%.

    High Quality Finishes.

    Design flexibility by maximizing repetition can reduce cost and

    aids speed of construction.

    Faster construction results in earlier cash flows and leads to

    reduced capital costs.- Central yard can be a strategy for huge developments

    Reduces Environmental impact.

    Enhances Energy Performance.

  • 7/29/2019 pre cast technology

    15/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- BENEFITS OF PRECAST SYSTEMBENEFITS OF PRECAST SYSTEM

    Durable and require little or no maintenance to preserve theiroriginal look.

    Fireproofing material is not required as Precast concrete is non-

    combustible.

    Acoustical isolation and vibration attenuation.

    Improved air quality

    Various kinds of architectural finishes can be easily incorporated

    in design.

  • 7/29/2019 pre cast technology

    16/53

    1.NEED FOR INNOVATION IN CONSTRUCTION1.NEED FOR INNOVATION IN CONSTRUCTION-- LIMITATIONS OF PRECAST SYSTEMLIMITATIONS OF PRECAST SYSTEM

    The system has certain limitations. Precast member sizes will be restricted by crane capacity

    Progress depends on hoisting facilities. If it breaks down

    progress of work will be affected

    Lack of planning will derail the schedule. Missing of anycomponents will affect the progress of work seriously.

    Proper logistic planning and inventory checks are required

    Requires skilled labour for erection.

    BACK

  • 7/29/2019 pre cast technology

    17/53

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    Sr No. Description Conventional technology Precast technology

    For construction of 1 Million sq.ft. G+20 (6 bldgs).

    1 Construction time 34 Months 24 Months.

    2

    Cost

    (considering labour and

    construction costs)

    100% 95%

    3 Labour requirement 5 Lakh man days/year 2.5 Lakh man

    days/year

    4 Quality

    Quality control at site is

    difficult owing to variable

    parameters.

    Factory production

    ensures quality

    product.

    5 Safety

    Safety at site requires

    more attention and

    comparatively more

    expensive

    Less safety

    measures needed

    when compared

    with conventional.

  • 7/29/2019 pre cast technology

    18/53

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    Accumulatedcosts/pa

    yments

    Design Period

    Mobilization

    Construction Time

    Conventional

    Construction

    Precast

    Construction

    Construction Payment Schedule

  • 7/29/2019 pre cast technology

    19/53

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    ting of Precast Elem

    Substructure

    Superstructure

    Finishing

    Handing Over

    Proposed Tentative Construction Schedule-Precast

    ActivityMonth

    Mobilization

    Design

    Precast Yard Set up

    2M

    3M

    6 M

    10M

    6M

    11M

    11M

    1

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

    Finishing

    Handing Over

    Proposed Tentative Construction Schedule-Conventional

    ActivityMonth

    DesignSubstructure

    Superstructure

    3M6M

    25 M

    20 M

    1

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    2.COMPARISON WITH CONVENTIONAL

    CONSTRUCTION

    BACK

  • 7/29/2019 pre cast technology

    20/53

    3.PRECAST TECHNOLOGY3.PRECAST TECHNOLOGY

    Following are the two widely accepted systems suitable for Residential buildingconstruction:

    1. Large Panel System.

    2. Framed System.

    PrecastTechnology

    Large PanelSystem

    Panel

    System

    ModularSystem

    Combinationof Both

    FramedSystem

  • 7/29/2019 pre cast technology

    21/53

    3.PRECAST3.PRECAST TECHNOLOGYTECHNOLOGY

    --LARGE PANEL SYSTEMLARGE PANEL SYSTEM

    Consists of large concrete walls and slab panels

    Horizontal slabs acts as a diaphragm in transferring load.

    Height of panels is one floor high.

    Gravity load is resisted by vertical panels.

    Panel connection are the key structural components.

    Seismic shear forces are resisted by horizontal and

    vertical joints.

    Horizontal panels can be hollow or solid.

    Vertical panels can be load bearing and non load bearing

    Vertical panels can be solid or sandwich panels.

  • 7/29/2019 pre cast technology

    22/53

    3.PRECAST TECHNOLOGY3.PRECAST TECHNOLOGY

    --FRAMEDFRAMED SYSTEMSYSTEM

    CONCEPT:

    All elements including facade are precast.

    Precast column, precast beam and precast slab.

    Nonstructural Infill walls were also cast along with Precast column and

    beam.

    Foundation Cast in situ, Few non typical elements can be cast insitu.

    Floor system consists of Precast plank with cast in situ topping.

  • 7/29/2019 pre cast technology

    23/53

    Columns, beams and slabs are factory made precast elements.

    SCHEMATIC DIAGRAM OF FRAMED SYSTEMS.SCHEMATIC DIAGRAM OF FRAMED SYSTEMS.

    3.PRECAST TECHNOLOGY3.PRECAST TECHNOLOGY

    --FRAMEDFRAMED SYSTEMSYSTEM

  • 7/29/2019 pre cast technology

    24/53

    3.PRECAST TECHNOLOGY3.PRECAST TECHNOLOGY

    --FRAMEDFRAMED SYSTEMSYSTEM

    3 PRECAST TECHNOLOGY3 PRECAST TECHNOLOGY

  • 7/29/2019 pre cast technology

    25/53

    3.PRECAST TECHNOLOGY3.PRECAST TECHNOLOGY

    --FRAMEDFRAMED SYSTEMSYSTEM

    BACK

  • 7/29/2019 pre cast technology

    26/53

    Full advantage of precast concrete construction is

    achieved when the building has been designed for high

    construction speed and maximum repetition.

    In every precast concrete projects the following aspects

    are important for the design team:

    Architecture

    MEP services

    Structure

    Manufacturing

    Erection

    5. DESIGN ASPECTS OF PRECAST CONCRETE

    CONSTRUCTION

    5. DESIGN ASPECTS OF PRECAST CONCRETE

    CONSTRUCTION

  • 7/29/2019 pre cast technology

    27/53

    The architect should be considering the following

    points:

    Simple and symmetrical layout and elevations.

    Achieve standardization and repetition.

    Modular grids.

    Modular design has big impact on costing.

    Design with larger floor spans.

    Minimize joints.

    Keep precast elements as large as possible, but

    maximum around 5 to 6 Tons.

    ELEVATION

    HOLLOW CORE SLAB FINISHES

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    ARCHITECTURAL ASPECTSARCHITECTURAL ASPECTS

  • 7/29/2019 pre cast technology

    28/53

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    ARCHITECTURAL ASPECTSARCHITECTURAL ASPECTS

  • 7/29/2019 pre cast technology

    29/53

    Integrate architecture services and structure .

    Avoid last minute changes.

    Modular Design modular principles can be

    strictly followed.

    A balance should be found between modular

    design and customized prefabrication.

    Flexibility Flexibility in precast concrete building

    projects can be achieved by creating larger floor

    spans with larger open spaces.

    HOLLOW CORE SLAB FINISHES

    HOLLOW CORE SLAB FINISHES

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    ARCHITECTURAL ASPECTS

    Precast Architectural Designs

    http://localhost/var/www/apps/conversion/tmp/scratch_2/Precast%20Architectural%20Designs.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_2/Precast%20Architectural%20Designs.ppt
  • 7/29/2019 pre cast technology

    30/53

    In precast concrete building projects, it is important that the MEP service

    consultants and the MEP vendors are part of the design team. Services like airconditioning, electrical and plumbing have to be an integrated part of the precast

    design.

    MEP SERVICES IN HOLLOW CORE SLABS

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    MEP SERVICES

  • 7/29/2019 pre cast technology

    31/53

    Wall panels can be provided with electricity conduits , electricity boxes and

    openings for ducts. Hollow core slabs (HCS) can be provided with electricity boxesand block outs.

    Precast planks with RCC toppings can be provided with electricity boxes and

    conduits.

    PLUMBING WORK IN HCS WITHOUT SUNK

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    MEP SERVICES

    MEP SERVICE IN HOLLOW CORE SLABS.

  • 7/29/2019 pre cast technology

    32/53

    India being an earthquake prone country the seismic resistant requirements

    are the most important criteria of the structural design.Looking at the requirements, the following design rules should be followed:

    Simple and symmetrical layout.

    Uniform distribution of mass and structural stiffness over the height.

    Avoid torsion.

    Ductile behaviour of the structure.

    Transfer of vertical loads between wall panels can be achieved by direct

    structural connection.

    The precast floor units should be properly joined together to act as a floor

    diaphragm that transfers the lateral load to the shear walls.

    The shear walls will transfer the lateral loads to the foundation by acting as

    cantilevered walls.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    STRUCTURAL ASPECTS

  • 7/29/2019 pre cast technology

    33/53

    Customization according to the requirements of the project

    Capabilities of manufacturing unit to be considered in

    design stage

    Standardization of embedded parts, lifting anchor,

    reinforcement etc.

    Reduction of damage by chamfering the edges of the wall.

    Tapering of block outs.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    MANUFACTURING ASPECTS

  • 7/29/2019 pre cast technology

    34/53

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    MANUFACTURING ASPECTS

    Mould Design.

    Suitable material including steel, timber/

    plywood is selected on the basis of

    No of repetitions.

    Required surface finish.

    Complexity of Precast Element.

    Cost competitiveness is enhanced by

    using adjustable moulds.

    Adequate no of braces, ties and struts

    should be provided for proper casting

    of elements.

    3 D Pod Mould

    Adjustable Mould

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    35/53

    Crane position and lifting capabilities.

    Lifting speed and speed of erection.

    Space for mobile cranes / Crawler cranes.

    Easy access to connections.

    Tolerances (Ref:IS 15916:2010, PCI 117,Appen I).

    Erection Sequence.

    Easy and fast erection.

    Filling of joints with grout / mortar.

    Position of Props and supporting structures.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    ERECTION ASPECTS

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    36/53

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    DESIGN ASPECTS

    Design of Precast elements. Involves understanding the method

    of fabrication.

    Involves aspects that facilitate the

    erection and assembly of elements

    on site.

    Integration of different elements,

    such as beam-wall system, multi-

    tier columns and three dimensional

    units.

    Parapet Beam

    3 - D Pod elements

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    37/53

    Structural integrity - Diaphragm action

    lateral forces (seismic & wind)

    Ref : Seismic design of floor

    diaphragms - Farzad Naeim & R.Rao

    Boppana

    Designed against progressive

    collapse/Robustness/ accidental

    actions.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    CONNECTION DESIGN ASPECTS

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    38/53

    The wall panels connections can be classified into horizontal joints and

    vertical joints.

    The horizontal joints have to transfer vertical loads as well as lateral

    loads.

    The vertical joint can either be structural joints which have to transfer

    shear forces or non structural joints which dont have to transfer any

    forces.

    For fully monolithic behaviour the protruding reinforcement

    connection in combination with drop in stirrups can be used.

    The connection in Hollow core slabs should transfer the internal

    diaphragm forces and it should be designed as structural integrity tie.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    CONNECTION DESIGN ASPECTS

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    39/53

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    CONNECTION DESIGN ASPECTS

    Joints and Connections

    Joints are designed on the basis of

    Transfer of loads from a precast

    concrete element to the supporting structure

    to form the structure.

    Avoiding congestion at joints.

    Avoiding penetration of forms.

    Allow for erection and production tolerances.

    Easy assembly and accessibility.

    Column-BeamJoint.

    External wall joint.

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    40/53

    Progressive collapse / Robustness

    These effects may generally be prevented if the following precautions are

    taken. (Ref : IS 15916:2010)

    o Notional horizontal load

    o Design of ties

    Peripheral ties

    Internal ties

    Floor to wall ties

    Vertical wall ties.

    Ref : Precast concrete structures

    by Kim.S.Elliot.

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    CONNECTION DESIGN CONCEPTS

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    41/53

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    LOCATION OF TIES IN PRECAST SKELETAL STRUCTURES

    1 Internal floor ties

    2 Peripheral floor ties

    3 Gable peripheral floor ties4 Floor to wall ties

    5 Internal Beam ties

    6 Peripheral Beam ties

    7 Gable Peripheral beam ties

    8 Corner Column ties

    9 Edge Column ties10 Vertical Column ties

    11 Vertical wall ties Location of ties in Precast Skeletal Structures

    5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5 DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

  • 7/29/2019 pre cast technology

    42/53

    Typical Cross section

    Typical Plan view

    Reinforcement

    designed for chord

    forces (tension)

    5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION5. DESIGN ASPECTS OF PRECAST CONCRETE CONSTRUCTION

    CONNECTION DETAILS : FLOOR TO FLOOR DIAPHRAGM

    BACK

  • 7/29/2019 pre cast technology

    43/53

    Resource Efficient

    Concrete- made from water, sand, aggregates and cement(limestone)

    Abundantly available materials.

    Waste by products from power plants and manufacturing facilities can

    be used in concrete

    Energy Efficient

    Thermal mass of concrete saves energy by reducing temperature

    swings in buildings.

    Concrete has low energy requirements for production.

    Concrete has low transportation energy costs as it is produced by

    materials available locally.

    Light colored precast concrete roof pavers reduces Heat Island

    Effect.

    6.6. Sustainable GoalsSustainable Goals

    i bl li bl l

  • 7/29/2019 pre cast technology

    44/53

    Highly Durable

    Concrete gets stronger with age.

    Strength gained by concrete for years and even decades.

    Ecologically Preferable

    compared to wood, iron ore mining, extraction for constituents of

    concrete is less disruptive to land

    Concrete reduces construction waste and can be recycled.

    Recyclable

    Concrete- crushed and used as aggregate in new concrete mixtures for

    infrastructure projects.

    Steel reinforcement can be recycled again.

    6.6. Sustainable GoalsSustainable Goals

    66 S i bl G lS i bl G l

  • 7/29/2019 pre cast technology

    45/53

    6.6. Sustainable GoalsSustainable Goals

    Reduction of CO2 emissions.

    Industrial wastes such as slag cement and silica fume reduces the

    amount of cement which in turn reduces CO2 emissions

    Reduces the amount of materials used.

    Precast concrete is designed to optimize the amount of concrete

    used. For ex: hollow core slabs.

    0

    20

    4060

    80 Total self

    weightGravel & Steel

    Cement

    Water

    45% savings in hollow

    core slabs

    66 S i bl G lS i bl G l

  • 7/29/2019 pre cast technology

    46/53

    Reduces the toxicity of materials.

    As a manufactured product under controlled conditions in the plant,

    precast concrete generates less waste and waste generated has low toxicity.

    Indoor Air Quality.

    Concrete contains low to negligible VOCs.

    Also, concrete has resistance to moisture.

    No renders and plasters required for internal applications.

    6.6. Sustainable GoalsSustainable Goals

    BACK

    7 RISK MANAGEMENT7 RISK MANAGEMENT

  • 7/29/2019 pre cast technology

    47/53

    Risk Management is the process of planning, leading and controlling

    the resources and activities of the organization to

    To fulfill its objectives cost effectively

    To protect and grow corporate assets

    To enhance shareholder value.

    Risk Management Techniques in Construction:

    Structural design principles

    Codal standards against Progressive collapse

    Case study Effective Progressive collapse design

    7. RISK MANAGEMENT7. RISK MANAGEMENT

    7 RISK MANAGEMENT7 RISK MANAGEMENT

  • 7/29/2019 pre cast technology

    48/53

    7. RISK MANAGEMENT7. RISK MANAGEMENT-RONAN POINT, LONDON

    22 storey block of flats built in 1966-68 (one

    of nine identical blocks).

    Precast concrete walls and floors with in

    situ joints between units. No in situ core or

    shear walls.

    Collapse of south east corner over full

    height of building caused by a gas explosion

    in corner flat on the18th floor in May 1968.

    5 people died. Emergency strengthening

    works carried out.

    South east corner of building rebuilt and

    occupation of building continued.

    7 RISK MANAGEMENT7 RISK MANAGEMENT

  • 7/29/2019 pre cast technology

    49/53

    Precast floor units 7in thick and reinforced.

    Wall panels 6in thick with little or no

    reinforcement.

    Diagram shows typical connection detail with

    emergency strengthening angles.

    5th Amendment to the Building Regulations

    in 1970 (includes requirements for the

    prevention of progressive collapse).

    Evacuation of Ronan Point and 8 sister blocks

    1984.

    Detailed survey carried out 1984.

    Building dismantled 1986.

    7. RISK MANAGEMENT7. RISK MANAGEMENT-RONAN POINT, LONDON

  • 7/29/2019 pre cast technology

    50/53

    7 RISK MANAGEMENT7 RISK MANAGEMENT

  • 7/29/2019 pre cast technology

    51/53

    Detailing

    The code adopted addresses progressive collapse,

    ties and ductile detailing.

    Protruding reinforcement from floor planks

    overlap with the reinforcement in adjacent plank.

    After erection overlapping bars are threaded with

    11mm steel strands effectively interlocking them

    and are grouted.

    Wall panels were casted with protruding loops

    which is threaded with steel bars and grouted

    with adjacent wall panels.

    Bars from one level to another were connected

    with nuts inside connecting bracket.

    7. RISK MANAGEMENT7. RISK MANAGEMENT- KHOBAR TOWERS, SAUDI ARABIA

    7 RISK MANAGEMENT7 RISK MANAGEMENT

  • 7/29/2019 pre cast technology

    52/53

    Performance

    The code addresses progressive collapse, ties and

    ductile detailing.

    Collapse was limited to the external facade wall.

    Exterior shear wall was completely destroyed

    but no progressive collapse.

    Interior walls and slab panels had extensive

    damaged but did not collapse

    The precast elements had sufficient ductility

    detailing to with stand the impulse force.

    The interlocked ductile connections maintained

    integrity of the structure preventing progressive

    collapse.

    7. RISK MANAGEMENT7. RISK MANAGEMENT- KHOBAR TOWERS, SAUDI ARABIA

    BACK

  • 7/29/2019 pre cast technology

    53/53

    THANK YOU