Page 1 Pre-Bid Queries Sr. No. Tender Doc. Reference Tender Provisions Query/Suggestion Reply to Client 1 Please provide AUTO CAD copy Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents. 2 Please clarify. Special span mentioned in scope of work is of 60m. We presume that Special Span shall be after Electronic City Station towards end chainage. Please confirm. Refer GAD (R1) issued as Addendum no 2. 3 Requested to extend Tender Submission date by 02 (two) weeks. Refer addendum no 1 issued. 4 Vol-3 C1 : 2.1.2 (ii & iv) Vol-3 : employers Requirement : C1 : 2.1.2 (ii & iv) : May Contractor adopt his own design of viaduct standard span superstructure? Refer addendum no 2 issued. 5 Vol-3 C1 : 2.9 page-24 Vol-3 : Employers Requirement : C1 : 2.9 page-24 says construction depot area within 15 km, whereas, Appendix- 2A page-62 says 20 km. radius. Please confirm about lead within. Refer issued addendum no 2. 6 BOQ Schedule E BOQ Schedule E : Describe Construction of Employer‟s site office if required. Please confirm whether office furniture, stationary and computer with accessories shall be in scope and also confirm about monthly maintenance of the office. We request to provide details, if required. As per Tender documents only. 7 Please provide typical grid plan of Station Building. Refer tender drawings.

Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 1

Pre-Bid Queries

Sr. No.

Tender Doc. Reference

Tender Provisions Query/Suggestion Reply to Client

1 Please provide AUTO CAD copy Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents.

2 Please clarify. Special span mentioned in scope of work is of 60m. We presume that Special Span shall be after Electronic City Station towards end chainage. Please confirm.

Refer GAD (R1) issued as Addendum no 2.

3 Requested to extend Tender Submission date by 02 (two) weeks.

Refer addendum no 1 issued.

4 Vol-3 C1 : 2.1.2 (ii & iv)

Vol-3 : employers Requirement : C1 : 2.1.2 (ii & iv) : May Contractor adopt his own design of viaduct standard span superstructure?

Refer addendum no 2 issued.

5 Vol-3 C1 : 2.9 page-24

Vol-3 : Employers Requirement : C1 : 2.9 page-24 says construction depot area within 15 km, whereas, Appendix-2A page-62 says 20 km. radius. Please confirm about lead within.

Refer issued addendum no 2.

6 BOQ Schedule E BOQ Schedule E : Describe Construction of Employer‟s site office if required. Please confirm whether office furniture, stationary and computer with accessories shall be in scope and also confirm about monthly maintenance of the office. We request to provide details, if required.

As per Tender documents only.

7 Please provide typical grid plan of Station Building.

Refer tender drawings.

Page 2: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 2

Sr. No.

Tender Doc. Volume

Clause No.

Page No.

Description Provision in Tender Document

Queries Reply to Client

1 General Drawing Volume

Drawings provided for GAD are difficult to read. Kindly provide the drawings in AutoCAD format as this is part design Contract and the Bidder has to proposed the Alignment and Span Arrangements.

Soft copy in PDF

is enclosed.

However, hard

copy issued shall

form the part of

Tender

Documents.

2 General Site Access Hindrances like H.T line and on-going Construction near Electronic City Stations are found during the Site Visit. Kindly provide the status of Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the scope of Employer or not.

As per tender documents only. Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

3 Volume-1 NIT 1.1.1 1 Project Length

Name of Work:………… length 6.583…. From Chainage 0.00 to Chainage 6693.13

Are we clear in our understanding that the length 6.583 km is a typo and the same should be read as 6693.130 km? Kindly confirm.

Refer GAD.

4 Volume-1 NIT 1.1.2 1 Extension Date and Time of Tenderers are working so Refer issued

Page 3: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 3

for Tender Due Date

Submission of Tender many Bids simultaneously for other parts of country. Moreover, being a part design and construction project, our designer is asking for more time for proper evaluation of design. We request you ton kindly extend the submission date by another 2 weeks.

addendum no 1.

5 Volume-3- Employer‟s Requirements- Section-B, Functional

2.9 24 Construction Depot and Dumping Area

…. Land of 45,000 sq. m. (approx.) will be made available by DMRC…….. within 15 km from the work site free of cost……

Both the statement are contradicting to each other. Please elaborate.

6 Volume-3- Employer‟s Requirements- Appendix 2A

Appendix 2A

62 Work Areas The Employer will provide the work areas of approx. 45,000 sq. m. within 20 km radius of work site.

Refer issued addendum no 2. Page 62R Employer‟s Requirements- Appendix 2A

1 Annexure-4 33 ITT (Vol.1) Minimum Organization structure required.

Reference to the requirement for deployment of project personnel, we would like to say that the requisite manpower as shown in the table should be deployed in periodic manner in accordance with pick hour and progress of work. In view of above, we seek to modify the condition for

No change in tender condition.

Page 4: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 4

1 Vol. 4 Clause 1 This line is extension of line III. Line III is broad gauge line. However, it is mentioned in this clause that this line is standard gauge. Please confirm.

Refer addendum no 2 issued. Page 3R of DBR

2 Vol. 4 Clause 2.4.2.2 For horizontal clearance, it is mentioned that “Please refer the drawing no. 18.SS.601 for the value of „A‟”. However, the drawing 18.SS.601 has not been provided. However, this dimension „A‟ is mentioned in drawing titled “Precast Parapet Details Sheet 1 of 2” provided in tender drawings. Please clarify.

As per Tender Drawings only.

3 Vol. 4 Clause 2.5.1 Indian standard “Criteria for Earthquake Resistant design of structures – Part 3 Bridges & Retaining Walls” has been published and is now available. It is requested that this code may be specified for

No change in tender condition.

deployment of project personnel please.

2 SHE (General Instruction: DMRC/SHE/GI/ 001/MPR/200 106

94 & 97

Vo-8 Availability of Occupational Health Officer.

As per DMRC SHE Version 1.2 we have to tie up with Medical Hospital for availing medical treatment facility of labours and staff working for day & night activity. In view of this, there is no requirement of any Doctors additionally of their medical checkup. In view of above, we seek to modify and delete the above provision in Tender please.

No change in tender condition.

Page 5: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 5

assessment of seismic forces & design in place of „IITK RDSO Guidelines‟.

4 Vol. 4 Clause 2.8.1 Please confirm that an axle load of 16t is to be taken for standard gauge for the project. In all other packages of Phase-III of DMRC, for standard gauge also, axle load adopted is 17t. Please review.

As per Tender documents only.

5 Vol. 4 Clause 2.8.1 Maximum number of successive cars is mentioned as 6 for broad gauge. In Line III, station length being 185m, stations are meant for 8 cars. Please confirm the maximum no. of successive cars to be considered.

Refer Addendum no 2 issued. Page 17R of DBR

6 Vol. 4 Clause 2.18 SLS & ULS factors for G (IV) case have typographical error for earthquake, Overall T, Live Load etc. This needs to be corrected.

No change in tender condition.

7 Vol. 4 Clause 12.26.1 Please confirm that tie bar arrangement is mandatory for Box-Girder or not.

As per Tender documents only.

8 Vol. 4 Clause 12.26.1 Please confirm that whether it is necessary to adopt the tie-bar arrangement in case of Precast beam & slab superstructure or any other alternative can be adopted for transferring horizontal forces in longitude direction as being adopted for some of phase-III projects.

As per design requirements.

9 Vol. 4 Clause 12.29.1 Please confirm that whether drainage pipe is to be provided inside or

Shall be provided outside of pier.

Page 6: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 6

outside the pier.

Please refer drawing showing drainage details is being issued in addendum No. 2

10 Vol. 4 Clause 13.1.1 Please specify the distance between centre line of two tracks to be adopted for this project.

As per Tender documents only.

11 Vol. 3 Clause 2.1.1 Please confirm that the design of common pier at the interface of station & viaduct shall be provided by DMRC.

YES.

12 Vol. 3 Clause 2.1.2(ii) Can tenderer can propose his own design of standard superstructure as Box-Girder/U-Girder/Steel Concrete composite.

Refer addendum no 2 issued. Page 13R of Employer‟s Requirement/ Functional

13 Vol. 3 &6 Clause 2.1.2(ii) It is mentioned that “The appropriate quantity of concrete, reinforcement & prestressing strands for superstructure is mentioned in tender drawings”. However, no quantities have been mentioned on tender drawings. Please provide the appropriate quantities of concrete, reinforcement & prestressing strands for superstructures.

Refer Addendum no 2 issued.

14 Vol. 3 Clause 2.1.2(iii)

Can tenderer can propose his own design of non-standard superstructure /special spans as box/I-Girder/U-Girder/Steel concrete composite.

Refer Vol-3 Employer‟s requirements, functional cl. No.

Page 7: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 7

2.1.2 (iii).

15 Vol. 3 &6 Clause 2.1.2(iv)

It is mentioned that standard span for viaduct shall be in the range of 25 to 34m. However, in tender drawings, standard spans drawings for 19m to 37m have been provided. Please confirm that standard spans in the range of 19m to 37m can be adopted for this project.

Refer Addendum no 2 issued. Page 13R of Employer‟s Requirement/ Functional

16 Vol. 3 &6 Clause 2.1.2(xi)

It is mentioned to provide GI brackets on both sides of viaduct. However, in tender, the drawing for „Details of Cable Trough‟ has been provided. Please clarify whether GI brackets or cable has to be provided. If GI brackets have to be adopted, please provide the drawing for the same.

As per tender drawings only.

17 Vol. 3 Clause 2.1.2(xiv)

Please provide the type of expansion joint to be adopted for the project.

As per Tender documents only.

18 Vol. 3 &6 Clause 2.1.2(xviii)

Please provide the location of portals & cantilever pier on the alignment GAD as envisaged by DMRC for the project.

Refer Tender documents vol-3 employer‟s requirement, functional, cl. No 2.1.2 (iv).

19 Vol. 3 Clause 2.1.2(xix)

Since the common pier at the interface of station &viaduct is part of station, this clause shall be deleted from scope of works under Schedule A & shall be included in Schedule B.

No change in tender condition.

20 Vol. 3 &6 Clause 2.1.2(xxi)

It is mentioned to provide grooves on parapet. Please confirm whether groves on parapet have been

Refer Addendum no 2 issued. Revised GAD are

Page 8: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 8

removed in other projects of Phase-III.

being issued

21 Vol. 3 &6 Clause 2.1.2(xxiv)

It is mentioned that “Pier locations and span arrangement for obligatory spans have been shown in the alignment GAD drawings”. However, pier locations for obligatory spans have not been shown anywhere on tender alignment drawings. Please provide the locations of obligatory/ special spans on alignment GAD drawings.

Refer Addendum no 2 issued. Revised GAD are being issued.

22 Vol. 3 Clause 2 There is a special span of 60m as per scope of works. However, no such span has been marked on the alignment GAD drawing. Please provide the location of 60m special span on the alignment GAD.

Refer Addendum no 2 issued. Revised GAD is being issued.

23 Vol. 6 The minimum radius of viaduct as per alignment drawings is 225m. Please confirm that the standard span drawings provided in tender can be adopted upto this minimum radius of 225m.

No change in tender condition.

24 Vol. 6 Please provide the maximum length of span that can be supported on as built metro Pier P223 at Chainage 0.0m.

Shall be decided at construction stage. Information asked is not relevant at this stage.

25 Vol. 6 Drawing No. DMRC/SEC-32-SEC 62/NOIDA/ ELEV/GAD/001 (Sheet 2 of 7)

In the alignment drawing DMRC/SEC 32 - SEC 62/NOIDA/ELEV/GAD/001 (Sheet 2 of 7), a flyover is shown diverging from the road from approx. CH. 1470. Please provide the

Refer Tender documents vol-3 employer‟s requirement, functional, cl. No

Page 9: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 9

proposed span arrangement as envisaged by DMRC from CH.1470 to CH. 1570. Please confirm whether pier can be placed on the median of the flyover in this stretch.

2.1.2 (iv).

26 Vol. 6 Please provide the proposed span arrangement as envisaged by DMRC from CH. 2000 to CH 2130 considering the diaphragm wall, underpass & adjacent roads.

Refer Tender documents vol-3 employer‟s requirement, functional.

27 Vol. 6 There are 3 FOBs‟ shown on GAD along the alignment. Please confirm that there will be required to be dismantled during construction.

Shall be decided at construction stage.

28 Vol. 6 Drawing No. DMRC/SEC-32-SEC 62/NOIDA/ ELEV/GAD/001 (Sheet 6 of 7)

In the alignment drawing DMRC/SEC 32 - SEC 62/NOIDA/ELEV/GAD/001 (Sheet 6 of 7), at CH. 5700, road width is approx 20m. At this location, please confirm that maximum length of Portal envisaged by DMRC is not be more than 22m.

As per site condition to be decided by contractor with approval of DMRC.

29 Vol. 6 Please provide the distance between centre to centre of tracks of Stabling Line.

Refer Addendum no 2 issued.

30 Vol. 6 Please provide the cross section & alignment vertical profile for stabling line.

Refer Tender Drawing.

31 Please provide the soft copy of tender drawings.

Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender

Page 10: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 10

Documents.

1 SEC Cl.19 Page 13 Lo = Consumer Price Index for

Industrial workers, published by Ministry of Labour & Employment, Govt. of India as applicable to Ghaziabad (U.P.) area for the month in which the tender was opened. Similarly, for Wso, Wco, Wfo and Wmo….

Since the date of the tender opening falls after the date of submission of tender, Bidders need to speculate inflation for this Intervening period. Therefore, in order to quote the price with more accuracy, it is suggested to consider the base date for Price Variation as 28 days prior to final bid submission date. Similar request is for Wso, Wco, Wfo and Wmo Index also…….

No change in tender conditions.

2 ITT C2.6, SCC Cl.11.1.4 Page 11

Changes in cost due to legislation: “Change in Law” means the occurrence or coming into force of the following, at any time after the date of submission of tender. (a) Any new tax which is imposed after the due date of submission of tender. (b) Change in the rate of any existing tax. The Contract Price shall not be adjusted due to any of the above two conditions and its impact shall be considered covered in the price indices of various components and thus compensated in Price Variation Clause. Also the contract price shall not be adjusted on account of fluctuations in the rates of exchange between the foreign currencies of the

It is expected that GST may be implemented in whole of India next year onwards and this may have a big impact (positively or negatively) on the project cost. Therefore, it is requested to kindly allow adjustment of cost on a/c of GST implementation at actual.

No change in tender conditions.

Page 11: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 11

Contract and Indian Rupees from the last date of submission of tender.

3 NIT 1.1.2 Date & time of Submission of Tender – 03.02.2015 upto 15.00 Hrs.

Kindly extend the Date of submission by 3 weeks i.e upto 24.02.2015 upto15:00 hrs.

Not agreed.

4 ITT A4.2 6th Line onwards

To fulfil this requirement, the tenderer (each member in case of JV/Consortium) has to sign the declaration given as Annexure-1 of ITT.

Annexure – T ot ITT is “Requirements for Tenderer‟s Technical proposal” not declaration. Please clarify/ provide the format.

Format is provided in Appendix 11 of FOT.

5 ITT C26.2 The Tenderer should submit a list of the components to be sourced from all supplier locations and show the timing of delivery, assembly, testing and transport of Delhi.

Complete stretch of project is in the State of U.P. Please clarify whether such details are to be provided.

Refer addendum no 2 issued. Page 21R of ITT

6 CAD Drawings Please provide CAD file of alignment and other drawings.

Soft copy in PDF enclosed. However, hard copy issued shall form the part of tender documents.

7 Tender Drawings Drawings provided with the Tender Documents are not legible. Kindly provide more clear drawings.

Soft copy in PDF enclosed. However, hard copy issued shall form the part of tender documents.

1 Tender Drgs.,Vol. 6, &

Alignment drawings

The drawings in the tender document are not legible. Request to provide

the soft copy of the alignment drawings (Auto Cad file) for appropriate

planning of span configuration and bid estimate.

Soft copy in PDF is enclosed.

However, hard copy issued

shall form the part of Tender

Page 12: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 12

Documents.

2 Tender Doc. Vol.3. – Employers requirement – Functional, cl.2.0

As per the scope of works in vol.3-functional, cl. 2.0, states the viaduct length as 6.583km. However as per the alignment drawings, the viaduct length (excluding stations) is around 5.583kM. Pl. clarify

Refer Tender Drawings.

3

Tender Doc. Vol.3. – Employers requirement – Functional, cl.2.0and Tender drg.no. . DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 SH. 1 OF 7 TO SH. 7 OF 7

As per the NIT, Name of the work states „….including special span of 60m, elevated stabling line….‟ The alignment drawings do not show any span configuration or special span locations. Request to provide the 60m special span location.

Refer Addendum no 2 issued. Revised GAD is being issued.

Page 13R of Employer‟s Requirement/ Functional

4 Tender Doc. Vol.3. – Employers requirement – Functional, cl.2.1.2 (iv) And Tender drawings Vol.6

As per cl.2.1.2 (iv), standard spans for viaduct given 25m to 34m and the respective spans superstructure details are shown in the Vol.6 tender drawings. Bidder request to provide the various standard span limitations for different range of radius of curvatures of track to plan accordingly the span configuration of the alignment.

Refer Addendum no 2 issued.

5 Tender Doc. Vol.3.

cl.2.1.2 (ii) & (iv)

As per the cl. 2.1.2.(ii), Construction of super structure of standard span

shall be as per tender drawing. However cl. 2.1.2 (iv) the tenderers may

suggest their own concept and design for Box / I girder for the same

requirements. This is contradicting to the cl.2.1.2.(ii). Hence bidder

requests to clarify

a) Whether superstructure of standard span can be designed and if so

twin „U‟ girder can be adopted.

b) Whether standard box girder (tender drawing) section can be

Refer addendum no 2 issued. Contractor has to follow the tender drawings.

Page 13: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 13

modified keeping outer profile of the box girder as per tender drawing.

c) Whether two independent box girders (for two tracks) can be

adopted keeping top width and side elevation similar to tender drawing.

6 Tender Doc. Vol.3. – Employers requirement – Functional, cl.2.1.5 a

The tender document do not consists the existing utility crossings details

along the alignment. Please provide the chartered utility details for better

planning the span configuration.

Not required at this stage.

7 Tender Doc. Vol.4. – Design Basis Report

cl.1.0 states the proposed corridor is for standard guage (SG). However as

per cl.2.8, train live load is shown for standard gauge as well as for Broad

gauge line.

Bidder understands for the proposed corridor (CC-94) only Standard gauge

loading is only applicable and hence for the design of superstructure and

substructure only standard gauge loading is to be considered and broad

gauge loading is not applicable for CC94 corridor. Pl. confirm bidder

understanding.

Refer issued addendum no 2. Proposed corridor of CC-94 is Broad gauge only.

8 Tender Doc. Vol.4. – Design Basis Report

As per cl.2.5.1.3 horizontal design seismic acceleration co-efficient „alpha-h‟ / R shall not be less than „0.1‟.

Bidder understands „Ah/R‟ shall not be less than 0.1 where „Ah‟ stands for „elastic seismic acceleration coefficient‟ as per IITK-RDSO guidelines on seismic design of railway bridges). Pl. confirm bidder

understanding.

No change in tender conditions.

9 Tender Doc. Vol.4. – Design Basis Report

As per cl.2.23.1.g (pg. no.28 of DBR), bidder understands that 33% increase in pile capacity for seismic load combinations is applicable

for vertical loads only. And horizontal load capacity of pile during seismic combination governed by structural capacity of the pile. Pl.

confirm bidder understanding.

cl.2.23.1.g (pg. no.28 of DBR) is self explanatory.

Page 14: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 14

10 Tender Doc. Vol.4. – Design Basis Report

As per Cl. 2.5.1. „For seismic analysis of viaducts will be conducted as per IITK-RDSO guidelines on seismic design of railway bridges

(Nov.2010)…‟ Bidder understands for analysis purpose IITK-RDSO guidelines shall

be followed where as for the reinforcement detailing of the various structural members of viaduct (incl. piers and fdn), IS 13920 code

can be followed and accordingly the curtailment of reinforcement in piers can be carried out as per the design requirement i.e without

considering the effect of cl. C.3.1 of IITK-RDSO Nov.2010. Pl. confirm bidder understanding.

No change in tender conditions.

11

Tender drg.no. . DMRC/SEC32-

SEC62/NOIDA/ELEV/GAD/001 SH. 7 OF 7

Bidder understands from the alignment drawings sh.7 of 7, at the curve location CLC-7 as stabling line. Pl. confirm bidder

understanding, if not, provide the location of stabling line details.

Refer Tender documents Vol-6 tender drawings; Drawing No. DMRC/Noida 32-62/ELEV/GAD/ 001 Sheet 8 of 8.

12 Tender Drgs., Vol. 6, &

Alignment drawings

Before station Sector 34, One nallah crossing is shown. Pl. provide the cross section of the Nallah.

May be obtained from concerned department, if relevant.

13

Tender Drgs.,Vol. 6, General notes

drawing (sh1 of 2 and sh 2 of 2)

As per the note „Grooved profile is not required in pier services‟. Bidder understands, for the pier vertical grooves are not required in

all piers. Pl. confirm.

As per Tender Documents only.

14 NIT Page-3 Para 1

If the work of Rs 371.20 crore have been done by the foreign partner of JV and the work done in the country of the foreign partner then in addition to this, the foreign partner must have done works equal to

Rs. 185.60 crores outside the country of the foreign partner. Here the qualification requirements in terms of “WORKS” are not self

explanatory. We presume that the additional Works works may comprise of any kind of Civil Construction Works of Rs 185.60 cr.

Yes, additional works may comprise of any kind of Civil Construction Works.

Page 15: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 15

outside the Foreign Country for foreign partner. May Please Confirm.

15 NIT Page 4: Liquidity

As per the Balance sheets, out liquidity/Net Current Assets/Working Capitals is more than the requited value, i.e. 26.51 Cr. Please Clarify

if Bankers Certificate still needs to be demonstrated additionally.

NO.

Site queries

16 Bridge Details

The alignment crossing city center station, bridge has been there. The details of bridge and skew angle are required for proposal of

foundations.

May be obtained from concerned department, if relevant.

17 Exg. FOB requirement

One of the existing FOBS is at Noida 34 station. This FOB is to be considered or it is covering in the station concourse area.

This information is not required at tender stage.

18 Consideration of

Flyover

Flyover location was shown in the Drg DMRC/Sec33/sec62/Noida/Elev/GAD/001( sheet 2 of 7) crossing

Sec.52 station. Is this shall be considered for the design and proposal of Viaducts. If so please provide the details.

May be obtained from concerned department, if relevant.

19 Consideration of IGL

Gas Pipe line and nallah

Dead end of Drain and IGL gas pipe lines are crossing the alignment near MMR building site. The alignment center line is exactly at the location of Gas pipe line. Gas pipe line details are required. Shall a

portal frame shall be proposed at that location.

Refer tender documents vol-3 employer‟s requirements, functional, cl. No. 2.1.2 (iv).

20 FOB under construction

FOB is under construction at Mamural Mandi location near to sector 59 Noida station. Is this should be considered.

Refer tender documents vol-3 employer‟s requirements, functional.

21 Under pass construction

Under pass is being constructing near NH-24 crossing the Noida Electronic city. Please provide the details of underpass for planning.

Refer addendum no 2 issued.

Page 16: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 16

Revised GAD is being issued.

22 Stabling Line Details Please provide the Stabling line details like length of the stabling line,

no. of lines, location of cross over and Rail level of the stabling line

Please refer GAD.

23 Tender drg. Vol.6, DMRC/Sec33/sec62/Noida/Elev/GAD/001 (sheet 1 of 7)

In the alignment after the Noida City Centre station, there is one

road bridge crossing the proposed alignment at site. The details of

existing bridge w.r.t the proposed alignment are required to plan the

span configuration at this location. Hence bidder request to provide

the existing bridge details along with its skew angle if any.

Refer Tender drawings. Desired information may be collected from concerned departments if relevant.

24 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 1

of 7)

At the proposed Noida sector 34 station, one FOB exists. Bidder

requests to provide the details of the FOB.

As per tender documents. The information desired is not

relevant at this stage.

25 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 2

of 7)

At one end of proposed sector 52 noida station, „start of flyover‟ is

shown. Also proposed alignment is shown as crossing the „RE

Wall‟. For proper planning the substructure of viaduct at this

location, „flyover‟ details w.r.t the DMRC-CC94 alignment are

required. Bidder request to provide flyover details.

Refer Tender drawings. Desired information may be collected

from concerned departments if relevant.

26 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet

2&3 of 7)

Proposed alignment crossing the Drain and IGL gas pipe lines near

MMR building site. Bidder assumes, the proposed alignment is not

infringing with the gas pipe line. Pl. confirm.

If not provide the details of gas pipe line. Does this utility is required

to relocate for clearing the alignment. Pl. confirm

Please refer GAD and tender documents vol-3 Employer‟s

requirements.

27 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 3

At the Ashok Marg chowk junction, feasibility of central pier at the

road junction is acceptable. For road traffic movement, at this

junction can be made similar (if required) to existing „U‟ turn before

For location of special span Refer addendum no 2 issued.

Page 17: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 17

of 7) the proposed sector 61 station. As this will be economical than

special span (~55m) at this junction. Pl. confirm bidder

understanding.

28 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 4

of 7)

Before approaching the proposed sector 59 station, at Mamural

Mandi one FOB construction is in progress. Bidder requests to

provide the details of FOB (including elevation of FOB) for proper

planning of substructure and span configuration at this location.

Refer Tender drawings. Desired information may be collected

from concerned departments if relevant.

29 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 4

of 7)

Before approaching the proposed sector 59 station, at Mamural

Mandi, bidder assumes the clearance requirement for traffic

movement at this junction by proposing the span configuration with

the clear distance between the existing road divider ends is

sufficient in planning the special span. Please confirm bidder

understanding else provide min. clearance requirement for planning

the special span at this junction.

Refer addendum no 2 issued.

30 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 5

of 7)

a) After the sector 59 station, at Mamura Chowk, similar to Ashok marg chowk bidder proposes „U‟ turn in the road and providing the road divided at central width of the road. This will avoid special span requirement and thus standard viaduct will be economical.

b) As an alternative, if special span (~60mts) is to be provided, whether the sector 59 station can be shifted from the present location by 30mts towards sector 61 station i.e towards noida city centre i.e (ch. 4064.705m to ~4040m) to economize the special span.

Please confirm bidder understanding.

No change in tender conditions.

Page 18: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 18

31 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 7

of 7)

After the proposed Noida Electronic city station, under pass is

under construction. And the underpass is very wider consisting

central wall crossing the proposed CC-94 alignment. Bidder

understands, the proposed CC-94 alignment is planned considering

the effect of this underpass. Bidder requests to provide the details

of this underpass w.r.t the CC-94 alignment to plan appropriate

location of substructure and foundation.

Please refer GAD(R1) being issued in Addendum no 2.

32 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 7

of 7)

Approaching the „dead end‟ of the CC-94 alignment i.e near the

location of NH24, deep excavation is noticed and in progress.

However in the present alignment drawings there are no such

details available. Bidder request to provide all the necessary details

of the structure at this location to plan proper span configuration

and special span if required.

Refer Tender drawings. GAD (R1) issued in addendum no 2.

33 Tender drg. Vol.6,

DMRC/Sec33/sec62/Noid

a/Elev/GAD/001 (sheet 7

of 7)

At the stabling line location, bidder understands that the standard

available super structure with double track is applicable. Please

confirm bidder understanding.

Refer Tender drawings.

34 Additional queries after

receiving the addendum

Bidder understands additional queries if any can be queried after

receiving the addendums. Please confirm.

As per Tender conditions only

Technical points

Page 19: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 19

1

Resources Proposed for the Project – Plant & Equipment

Refer ITT Annexure - 5, page 34 of Volume 1

Equipment List: The minimum nos. of Plants & Equipment indicated in the tender document is very high. For example:- Piling Rig (6), Concrete Pump with Placer boom (2), Tailoors-75 T (6) etc. Hence, we request that the min. Numbers of Plant & Equipment as indicated in above referred list may not be insisted upon & Contractors may deploy Equipment‟s based on their own construction program. Please confirm.

No change in tender conditions.

2 Land acquisition & Site handing over schedule

Kindly provide land acquisition status and Site handing over schedule to contractor for execution of work.

As per Tender documents only.

3

Locations of Piers/ Cantilever & portal piers on the GAD

Tender drawings We request you to indicate the tentative location of piers along the proposed alignment. Please also clarify locations of cantilever & portal pier caps in viaduct (if any).

Refer GAD and Tender documents vol-3 Employer‟s requirements, Functional cl. 2.1.2 (iv). No further clarification is required.

4 Cross over spans

Please clarify the locations of cross over spans (if any).

Please refer GAD.

5

Concrete, Reinforcement & HT strands quantities of Standard span

Volume 3 : Scope under LS price, clause 2.1.2, point no. (ii) on page no. 12-13

As per tender clause, the design of superstructure for standard span shall be provided by DMRC. Hence, we request you to kindly provide the quantities of concrete & reinforcement for Standard span to be considered for tender purpose. We presume that these quantities will form the base quantities for tender purpose and any quantity above/ below

Refer Addendum no 2 issued. No change in tender condition.

Page 20: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 20

during execution shall be payable to / recoverable from Contractor. Mode of payment of above variation amount shall be based on GCC clause no. 12.5 for Extra items. Please confirm.

As per contract conditions.

6

Details of proposed designer

Refer clause Cl, C7.2 of Volume 1 page 16: The tenderer shall submit the name of designer proposed to be engaged…..

We understand that the Contractor shall has to submit the name of Designer proposed to be engaged for design of permanent & temporary works on award of work and tenderer is not required to submit it at tender stage. Please concirm.

Yes, But prior approval of DMRC is required during execution stage.

Commercial Points

1 Change in Law Sub-clause no. 11.1.4 on pagae 11 – 12 of Volume 2.

Contract Price adjustment due to Change in Law (i.e. (i) any new tax imposed after the date of submission of tender; (ii) change in the % of existing taxes) shall be applicable. Please confirm.

No change in tender condition.

2 Clearance/ Approval/ NOCs from Railways, Govt. bodies, other statutory bodies

Refer Employer‟s Requirement Functional, of Vol 3 cl xxviii page 14

In order to complete the project within stipulated period, we request DMRC to arrange all the relevant clearances / approval/ NOCs from the concerned work authorities prior to the award of the work.

As per Tender conditions only.

General Points

1 Work Areas Volume 3 – Appendix 2A, page no. 62

We request you to indicate the proposed location & dimensional details of the casting yard. Part of land for installation of Batching

Refer tender documents vol-3 Employer‟s requirement. As per tender documents only.

Page 21: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 21

Plant nearby the proposed site may be provided.

2 Location of Dumping yard

We request department to make available land (dumping Yard) for dispose of Excavated / miscellaneous material.

Refer tender documents vol-3 Employer‟s requirement. As per tender documents only.

3 Non Standard spans (CLC/ 60m span)

Tender drawings Volume 3, page 14 cl xxiv

Kindly indicate the span arrangement for CLC1 to CLC7 spans. Kindly also indicate the location of special span of 60m and type of the Superstructure. We understand that we bidder is free to adopt any type of structure i.e. either Steel/ PSC. Please confirm.

Refer tender documents vol-3 Employer‟s requirement, Functional. Refer GAD(R1) issued in Addendum no 2. Please refer Vol-3 Employer‟s requirement, Functional cl. No. 2.1.2 (iii).

4 Tender Drawings We request to kindly provide soft copy of tender drawings in Autocad format.

Soft copy in PDF is enclosed.

However, hard copy issued shall

form the part of Tender

Documents.

5 Utility drawings We request you to provide details of charted/ uncharted utilities above and below the ground level within the Battery Limit of the proposed work for our guidance.

Please refer GAD.

6 Due date of submission We request the department to extend the due date of submission of tender by at least one month from the date of issue of clarifications to the above points.

Refer addendum no 1 issued.

Page 22: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 22

1 We request to extend the submission date of this tender by at-least two weeks time.

Refer addendum no 1 issued.

1 Page 1 / Volume 1

1.1.2 of NIT Key details Date & Time of Submission of Tender 03.02.2015 at 15:00hrs

Request 28 days extension. Refer addendum no 1 issued.

2 Page 5 / Volume

1.1.3.3 of NIT Bid capacity Criteria

B= Value of existing commitments (as on 31.01.2015) for on-going construction works during period of 30 months w.e.f. 01.02.2015

The unaudited financial results of our company for the quarter ending 31st December 2014 will be approved by the Board of Directors within 15th February 2015. Being a listed Organisation, it would be difficult to produce a certificate by Chartered Accountant for the 3rd quarter of 2014-2015 till the quarterly results are announced. This would also have an effect in calculating the bid-capacity criteria. Please advise if we could produce the Value of Balance Work yet to be done as on 30.09.2014 along with the value of work done in the period 1st October 2014 to 31st January 2015 at the time of

No change in tender conditions.

Page 23: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 23

Tender submission and after the results are announced we shall produce the updated details when the bids are being evaluated

3 Page 14 / Volume 1

C 2.6 (d) of ITT

UP VAT U.P VAT is included in the contract price. The contractor shall maintain details of U.P VAT paid to „Trade and Taxes‟ department and submit:- (i) Certificate of the Chartered Accountant in regard to turnover of the contractor relating to DMRC project (ii) U.P VAT return forms of the contractor for the relevant period / periods along with detailed statement and copy of all Challans of U.P VAT in regards to deposit of tax

i) In earlier bids (Lucknow & Ghaziabad) only VAT registration certificates for UP had to be submitted at bidding stage. Please confirm if it is sufficient to submit only the VAT registration details along with the bid. We presume that the clause included is only during execution.

ii) In-case the details have to be provided in the bids, please confirm whether the certificate in regard to turnover be for completed DMRC jobs or on-going DMRC jobs. Also confirm turnover for which all financial years should be provided.

If the bidder is not executing or executed in the past any Contract for DMRC in UP State, what needs to be submitted?

As per Tender conditions. However relevant period means during execution of this work.

4 Page 20/ Volume 1

C24.3 of ITT Clarification The Tenderer is requested to submit

Request to accept the queries till 2 weeks before the date of

No change in tender conditions.

Page 24: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 24

any question in writing or by facsimile, to reach the employer not later than the last date of seeking clarification as mentioned in key details of NIT

submission and provide all responses a week before submission.

5 Page 32 & 33 / Volume 1

Annexure 3 & 4

Resources proposed for the Project Personnel

As per the Annexure 3 – Resources proposed for the project – Personnel and Annexure 4 Minimum Organization structure required.

Please confirm whether the CV‟s have to be provided at the Tender stage or post award.

As per Tender Conditions only.

6 Page 34 / Volume 1

Annexure 5 / S .No (a)

Resources proposed for the Project – Plant & Equipments

Piling Equipment Rotary Rig – Min 6 Nos

Request to reduce the minimum no.of units of equipment required as 5 Units

No change in tender conditions.

7 Page 34 / Volume 1

Annexure 5 / S .No (e)

Launching Girder / Cranes – Min 3 Nos

Request to reduce the minimum no. of units of equipment required as 2 Units

No change in tender conditions.

8 Page 37 Volume 1 Form of Tender

Sr. No 5 of Annexure 7

Form of Performance Security (Guarantee) by Bank

After the Contractor has signed the aforementioned Contract with the Employer, the Bank is engaged to pay the Employer, any amount up to and inclusive of

Request to rephrase as follows: After the Contractor has signed the aforementioned Contract with the Employer, the Bank is engaged to pay the Employer, any amount up to and inclusive of the

No change in tender conditions.

Page 25: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 25

the aforementioned full amount upon written order from the Employer to indemnify the Employer for any liability of damage resulting from any defects or shortcomings of the Contractor or the debts he may have incurred to any parties involved in the Works under the Contract mentioned above, whether these defects or shortcomings or debts are actual or estimated or expected. The bank will deliver the money required by the Employer immediately on demand without delay and demur and without reference to the Contractor and without the necessity of a previous notice or of judicial or administrative procedures and without it being necessary to prove to the bank the liability or damages resulting from any defects or shortcomings or debts of the Contractor. The

aforementioned full amount upon written order from the Employer to indemnify the Employer for any liability of damage resulting from any defects or shortcomings of the Contractor or the debts he may have incurred to any parties involved in the Works under the Contract mentioned above, whether these defects or shortcomings or debts are actual or estimated or expected. The bank will deliver the money required by the Employer immediately on demand without delay and demur and without the necessity of a previous notice or of judicial or administrative procedures and without it being necessary to prove to the bank the liability or damages resulting from any defects or shortcomings or debts of the Contractor. The Bank shall pay to the Employer any money so demanded but up to the amount guaranteed herein, notwithstanding any dispute/disputes raised by the Contractor in any suit or proceedings pending before any Court, Tribunal or Arbitrator/s relating thereto and the liability under this guarantee shall be absolute

Page 26: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 26

Bank shall pay to the Employer any money so demanded notwithstanding any dispute/disputes raised by the Contractor in any suit or proceedings pending before any Court, Tribunal or Arbitrator/s relating thereto and the liability under this guarantee shall be absolute and unequivocal

and unequivocal

9 Page 37 Volume 1 Form of Tender

Sr. No 5 of Annexure 7

Form of Performance Security (Guarantee) by Bank

At any time during the period in which this Guarantee is still valid, if the Employer agrees to grant a time extension to the Contractor or if the Contractor fails to complete the Works within the time of completion as stated in the Contract, or fails to discharge himself of the liability or damages or debts as stated under Para 5, above, it is understood that the Bank will extend this Guarantee under the same conditions for the required time on demand by the Employer and at the

Request to rephrase as follows: At any time during the period in which this Guarantee is still valid, if the Employer agrees to grant a time extension to the Contractor or if the Contractor fails to complete the Works within the time of completion as stated in the Contract, or fails to discharge himself of the liability or damages or debts as stated under Para 5, above, the Bank may extend this Guarantee under the same conditions for the required time on demand by the Employer and at the cost and written request of the Contractor.

No change in tender conditions.

Page 27: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 27

cost of the Contractor.

10 Page 45 / Volume-1

Form of Tender (Appendix – 1) & CL:8.5 of the GCC

Liquidated damages

Total Maximum limit of LD including sums payable by the employer to designated contractors is 15% as mentioned in GCC

Request to revise maximum limit of LD to 10% instead of 15%.

No change in tender conditions.

11 Page 45 / Volume-1

Form of Tender (Appendix – 1) & CL:8.5 of the GCC

Liquidated damages

Liquidated damages The Maximum limit of Liquidated damages on Key Dates shall be 10 % of the Contract Value

Request to limit to maximum 5% instead of 10%.

No change in tender conditions.

12 Page 45 / Volume-1

Form of Tender (Appendix – 1) & CL:8.5 of the GCC

Liquidated damages

Liquidated damages shall be levied as per the rate given in Appendix 2B of Employer Requirements for delay

If the Contractor achieves the final completion and handing-over within the contractual milestones, request the Employer to refund the Liquidated Damages if any levied against any intermediate milestone.

No change in tender conditions.

13 Page 62 / Volume 1

Form of Tender - Appendix 16

Form of Tender - Appendix 16

Value of Balance Work yet to be done in Rupee equivalent as on 31.01.2015

Value of work to be done in 2014-15 (1st Feb 2015 to 31st March 2015)

The unaudited financial results of our company for the quarter ending 31st December 2014 will be approved by the Board of Directors within 15th February 2015. Being a listed Organisation, it would be difficult to produce a certificate by Chartered Accountant for the 3rd quarter of 2014-2015 till the quarterly results are announced.

No change in tender conditions.

Page 28: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 28

Please advise if we could produce the Value of Balance Work yet to be done as on 30.09.2014 along with the value of work done in the period 1st October 2014 to 31st January 2015 at the time of Tender submission and after the results are announced we shall produce the updated details when the bids are being evaluated.

14

Page 64 / Volume – 1

Form of Tender Appendix – 17 (Note : 1)

Work experience

This is to be substantiated with documentary evidence which clearly mentioned the length of tunnel and no. of stations along with its plan area completed

Please clarify whether it is a typographical error as this is a Tender for an elevated metro and not underground.

Refer Addendum no 2 issued Appendix-17 of FOT Page 63R

15 Page 11/ Volume 2

Clause 1.6 of General

Conditions of Contract

Care and Supply of Construction and/or Manufacture Documents

Last Paragraph: On discovery of any technical error or defect in a document intended to be used for the purpose of Contract, the

In case if the technical error or defect is substantial, then Contractor shall be allowed for suitable time and cost compensation. Please consider to provide appropriate provision in the

No change in tender conditions.

Page 29: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 29

Contractor shall promptly give notice to the Engineer of such error or defect.

contract.

16 Page 12 & 13 / Volume 2

Clause 2.2 of General

Conditions of Contract

Access to and Possession of the Site

Last Paragraph: For any such delay in handing over of site, Contractors will be entitled to only reasonable extension of time and no monetary claims whatsoever shall be paid or entertained on this account.

As per earlier experience, claims due to delay in possession of site is being experienced at other sites of DMRC. Therefore request to provide provision for suitable cost compensation in the contract if the delay incurred is totally unreasonable and unfair and cannot be foreseen by any experienced Contractor.

No change in tender conditions.

Page 30: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 30

17 Page 17 / Volume 2

Clause 4.4 (b) of General

Conditions of Contract

Facilities for and co-ordination with Others

Unless and until copies of all relevant and necessary design co-ordination statements have been submitted to the Engineer, the Engineer shall be entitled to suspend any review or further review of the Contractor‟s or the other contractor‟s design submissions. Such suspension shall not be grounds for the Contractor to claim nor shall be entitled to receive an extension of time or additional payments.

The Contractor cannot be held responsible for the failure of other Contractors design co-ordination / design submission activities. Please provide some provision for suitable time and cost compensation for delays not attributable to Contractor

No change in tender conditions.

18 Page 18 / Volume 2

Clause 4.4 (f & g) of

General Conditions of

Contract

Facilities for and co-ordination with Others

f) The Contractor shall afford all reasonable opportunities, for carrying out their work, to other contractors employed by the Employer and their workmen respectively and the workmen of the Employer who may be engaged on or near the Site of any work, ancillary to the Works, but, not included in the Contract and shall not cause them inconvenience. g) If the Contractor

In addition to time, suitable cost compensation shall also be provided in case of any delay not attributable to the Contractor. Request to modify the clause accordingly.

No change in tender conditions.

Page 31: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 31

shall suffer delay by reason of failure by any Designated Contractor to meet the specified installation interfacing and co-ordination, completion dates, which delay shall be caused otherwise than by fault of the Contractor or if compliance with sub-clause (f) herein shall involve the Contractor in delay beyond that which could be reasonably foreseen by an experienced contractor at the time of tender, then the Engineer shall take such delay into account in determining any extension of time to which the Contractor is entitled under the Contract.

19 Page 19/ Volume 2

Clause 4.4 of General

Conditions of Contract

Facilities for and co-ordination with Others

Last Paragraph: If any act or omission of the Contractor whether directly or indirectly results in the delay in the execution of the works of a Designated Contractor, the Contractor in addition to his liability

Please link this Clause with that of Clause 8.5 so that the max LD is limited to 15% (which states that the total maximum of LD including sums payable by the employer to designated contractors is 15% as mentioned in GCC)

No change in tender conditions.

Page 32: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 32

in respect of liquidated damages if they become due, shall pay to the Employer, or the Engineer may deduct from Interim Payment Certificates such amount as the Engineer shall have certified in respect of additional payments or costs to the Designated Contractor in respect of any such delay.

20 Page 20 & 21 / Volume 2

Clause 4.9 of General

Conditions of Contract

Site Data First Paragraph: The Contractor shall conduct further investigations considered necessary by him at his own cost and any error, discrepancies if found in Employer‟s data at any stage will not constitute ground for any claim for extra time and costs

As the Contract Period of 24 months is stringent, time for executing further investigations will not be available with the Contractor. Therefore, it would be appropriate to have a suitable provision for time and costs compensation in case of any discrepancy in data.

No change in tender conditions.

21 Page 21/ Volume 2

Clause 4.12 of General

Conditions of Contract

Right of Way and Facilities

The Employer will acquire and provide land for Permanent works and right of way (within DMRC‟s land) for access thereto over routes established by the Contractor. The Contractor shall bear

Please provide the expected date/schedule of handing over of land and right of way to the Contractor for permanent works (ROW). In case of any delay, then Contractor has to be suitably compensated in time and

As per Tender Documents only.

Page 33: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 33

all cost and charges for special or temporary rights of way which he may require including those for access to the Site. The Contractor shall also obtain, at his risk and cost, any additional facility outside the Site which he may require for the purpose of the Works. The Employer reserves the right to make use of these service roads/ rights of way for itself or for other Contractors working in the area, as and when necessary without any payment to the Contractor.

cost.

Please confirm the 'Width of right of way available during the construction of viaduct.

22 Page 23/ Volume 2

Clause 4.17 of General

Conditions of Contract

Protection of Environment

The Contractor shall take all reasonable steps to protect the environment (both on and off the site) …………………………………The Contractor shall ensure that air emissions, surface discharges and effluent from the Site during the Contract Period shall not exceed the values prescribed by law. The Contractor shall conform to the

Protection of the environment shall be limited to within Site premises only as the Contractor could not be held responsible for Environmental impacts in outside the site locations. Please modify the clause accordingly.

No change in tender conditions.

Page 34: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 34

Employer‟s Requirements and shall indemnify the Employer against any liability or damages or claims arising out of his operations. The Contractor shall be responsible and liable for any stoppage, closure or suspension of the works due to any contravention of statutory requirements relating to the protection of environment and shall indemnify and keep indemnified the Employer in this regard. ………….Nothing extra shall be payable to the Contractor on this account and his Tender price shall be inclusive of expenditure required to be incurred for working as per SHE manual.

23 Page 24/ Volume 2

Clause 4.21 of General Conditions of Contract

Sheds, Stores, Yards

It shall be the responsibility of the Contractor to provide at his own expense the required sheds, store houses, and yards for both Permanent and

Vide Employer‟s Requirements, Section – B, Functional, Page No.24, Sr.No.2.9, it is mentioned that DMRC will make available a plot of land approx. 45,000 sq.m for casting yard, batching

As per Tender Documents only. No change in tender conditions.

Page 35: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 35

Temporary works…………….

plant and other activities, free of cost. Please provide the expected date of handing over of the plot and in case of any delay, then Contractor has to be suitably compensated in time and cost.

24 Page 25 / volume 2

Clause 4.27 of General Conditions of Contract

Security of the site

Request to consider sharing of various cost incurred by civil contractor in case of services used by designated system wide contractor.

No change in tender conditions.

25 Page 38/ Volume 2

Clause 8.3 of General Conditions of Contract

Delay In case of delay on the part of the Contractor, the Contractor shall be liable to pay liquidated damages and any other compensation for the damages suffered by the Employer as per clause 8.5. This is without prejudice to the right of the Employer to rescind the Contract. Failure or delay by the Employer or the Engineer, to hand over to the Contractor the Site necessary for execution of Works or any part of the works, or to give necessary notice to commence the Works, or to

There is provision only for compensation of time and not cost. The Contractor should be compensated for costs arising due to delays not attributable to the Contractor.

No change in tender conditions.

Page 36: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 36

provide necessary Drawings or instructions or clarifications or to supply any material, plant or machinery, which under the Contract, is the responsibility of the Employer, shall in no way affect or vitiate the Contract or alter the character thereof; or entitle the Contractor to damages or compensation thereof but in any such case, the Engineer shall extend the time period for the completion of the Contract, as in his opinion is / are reasonable

26 Page 45 / Volume-1 & Page – 45/ Volume-2

Form of Tender (Appendix – 1) & 11.2.1 of General Conditions of Contract

Amount of Advance Payment

As per clause No.20 of SCC- 5% of the original contact value considered as a mobilization advance

Request amending the mobilisation advance to 10% instead of 5%.

No change in tender conditions.

27 Page– 45/Volume-2

Clause 11.2.2 of General Conditions of Contract

Advance against Plant & Machinery

5% of the original contact value considered as a P&M advance

Request to increase P&M advance to 10% of Overall accepted contract value instead of 5% of contract value

No change in tender conditions.

Page 37: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 37

28 Page 47/ Volume 2

Clause 11.4.1 of General Conditions of Contract

Application for Interim Payment Certificate

If any Milestone is not achieved by the end of the month in which it is scheduled to be achieved, the Engineer shall suspend the payment relating to the Cost centre in which the Milestone is included. Payments suspended under this Clause shall be resumed by being included in the next application for interim payment made after the Milestone is achieved

Suspension of payment due to Milestone non-achievement should not be carried out if; the same is not due to reasons attributable to the Contractor. Please modify the clause accordingly.

No change in tender conditions.

29 Page – 48 /Volume-2

Clause 11.6 of General Conditions of Contract

Payment- Interim & Final

After Preliminary Scrutiny and certification by the engineer, payment of 80% of the certified interim amount shall be made by the employer within 14 days

We request to consider payment of 80% of the certified interim amount within 7 days from the date of submission of monthly invoice.

No change in tender conditions.

30 Page 51/ Volume 2

Clause 11.20 of General Conditions of Contract

Recovery of money due to the Employer

All damages (including, without limitation, liquidated damages), costs, charges, expenses, debts, or sums for which the Contractor is liable to the Employer under any provision of the Contract may be

Please confirm: 1. The damages mentioned will be limited to liquidated damages only and not to be “without limitation”. 2. Any recovery will be carried out within the purview of this Contract and not be combined with other Contracts.

As per Tender Documents only.

Page 38: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 38

deducted by the Employer from monies due to the Contractor under the Contract (including, without limitation, liquidated damages) and the Employer shall have the power to recover any balance not so deducted from monies due to the Contractor under any other Contract between the Employer and the Contractor………

31 Page-53/ Volume-02

Clause 12.5 (ii) b of General Conditions of Contract

Variation in the Bill of Quantities

In case of foundation work, no variation limit applies and contractor shall carry out the work, at rates stipulated in the Contract irrespective of any variation

Foundation being a lumpsum amount, we understand that the quantity variation shall not be applicable. However, if there is any variation in location and/or number of piers which would result in variation in scope of sub-structure, variation must be paid for foundation in such cases. Request to include this condition as a Clause in Special Conditions of Contract.

No change in tender conditions.

32 Page 57/ Volume 2

Clause 13.3.5 General Conditions of Contract

Payment on Termination

In case termination/ foreclosure of the Contract under whatsoever circumstances, any remaining tools, plants, equipment and surplus materials of Employer

As per Sr.No.10, Page No.7 of Special Conditions of Contract, Sub-clause 4.19, the Employer will not provide any machinery or materials under this Contract. Hence, request to delete this clause from this contract.

No change in tender conditions.

Page 39: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 39

with contractor will be returned to the Employer in good condition at Employer‟s depot at Contractor‟s cost. In case of the failure of the contractor to do so, the Employer will be entitled to recover their cost from the contractor from the amount becoming due to the contractor or from any other money due in any other contracts………

33 Page 60/ Volume 2

Clause 15.3 of General Conditions of Contract

Insurance against injury to Persons and Damage to Property

The Contractor shall insure against liability to third parties in the joint names of the Employer, the Contractor and Sub-contractors, (wherever applicable) for any loss, damage, death or bodily injury which may occur to any physical property (except things insured under Sub-Clause 15.2) or to any person (except persons insured under Sub-Clause 15.4), which may arise out of the performance of the Contract and occurring

Please consider having limitation for the number of incidents (say 4 nos.). For any further incidences, then the same shall be suitably compensated by the Employer.

No change in tender conditions.

Page 40: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 40

before the issue of the Performance Certificate. Such insurance shall be at least for the amount specified in the Appendix to Form of Tender. As per S.N. ix, Form of Tender – Appendix – 1 Amount of Third Party Insurance – INR 0.50 Million for any one incident, with no. of incidents Unlimited.

34 Page 2/ Volume 2

Sub-Clause 4.9 of Special Conditions of Contract

Site Data The Geotechnical and other related data provided by the Employer are based on the investigation conducted by DMRC and are for reference purposes only. The Tenderer should satisfy himself with the data furnished and make his own investigations if required for submitting his offer. Any change in design or construction methodology later during execution on account of change will

The Contract is for 30 months and the Tendering period is also limited. As time for carrying out any prior investigation (pre-award/post-award) is not available and as the scope of part design is with the Contractor, the provision for additional time and cost has to be included in the Contract conditions for deviation of Geotechnical and other related data from that of provided in tender documents.

No change in tender conditions.

Page 41: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 41

be borne by the Contractor. The Contractor shall not be relived from any risk or obligation imposed on or undertaken by him under the Contract or any such ground or on ground that he did not or could not foresee any matter which may affect or have affected the execution of the Works, or compliance with his other obligations under the Contract.

35 Page 2 &3/ Volume 2

Sub-Clause 4.11 of Special Conditions of Contract

Access Route

Paragraph 2, Second sentence: If there is any delay or damage or injury, the cost of rectification or reconstruction of highways or bridges shall be borne by the Contractor.

The Contractor shall be responsible for any delay or damage, if it occurs due to reasons attributable to the Contractor. If not attributable to the Contractor, the Contractor shall be suitably compensated in time and cost. Please change the clause accordingly.

No change in tender conditions.

36 Page 10 Volume 2

Sub-Clause 5.3 of Special Conditions of Contract

Submission of Design Data

Last Paragraph: Neither an objection raised to the Design Data nor revisions of

In case of any substantial delay in approval of design data, then suitable time and cost compensation has to be provided to the Contractor.

No change in tender conditions.

Page 42: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 42

minor design significance under this Clause will, under any circumstances, constitute an Employer‟s Variation.

Request to modify the clause accordingly.

37 Page 11 Volume 2 Special Conditions of Contract

Sub-Clause 8.5 of Special Conditions of Contract

The total contract value used in the GCC sub clause 8.5 for the purpose of levy of liquidated damages on failure to achieve key dates shall mean the „Fixed Lump Sum Contract Price‟.

As per BOQ, for only Schedule A, the Lump sum price has to be quoted and the rest are Item Rate. Therefore, please clarify that the above said “Fixed Lump Sum Contract Price‟ means Lump Sum price at Schedule “A” only.

As per Tender Documents only.

38

Page 11 / Volume 2

Sub-Clause 11.1.4 of Special Conditions of Contract

Changes in taxes/Duty

Change in law means the occurrence or coming into force of the following, at any time the date of submission of tender. A) any new tax which

is imposed after the due date of submission of tender

B) change in the rate of any existing tax. The contractor price shall not be adjusted due to any of the above two conditions

Request to consider compensation for variations resulting from change in law as escalation does not cover all component of change in law (especially since GST may get implemented in near future and the impact cannot be predicted at this stage).

No change in tender conditions.

39 Page 12 & 13 / Volume 2

Sub-Clause 11.1.3 of

Price Variation

Wfo= whole sale price index (Average) for fuel

Request to follow IOCL bulletins instead of change

No change in tender conditions.

Page 43: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 43

Special Conditions of Contract

& power, as published in the RBI bulletins for the month in which the tender was opened

RBI bulletins (a prevalent practice in Government and major contracts)

40 Page 14 Volume 2

Sub-Clause 19.1 of Special Conditions of Contract

Price Variation for Varied Items

Second Paragraph: It shall, however be open to the Engineer to accept price variation clause in such cases where the rates are not based on actual and work is likely to continue for more than one year.

Please confirm that the varied / deviated items being operated under BOQ rates / prices are eligible for considering price variation (as they are not based on actual cost inputs).

No change in tender conditions.

41 Page 15 Volume 2

Sub-Clause 11.2.2 of Special Conditions of Contract

Advance against Plant & Machinery

Last Paragraph: The total advance for Plant and Machinery shall be limited to 5% of the fixed Lump Sum price quoted in Schedule „A‟ of BOQ/Price document and shall be paid against 12 acceptable Bank Guarantees of equal amount from a Schedule Commercial Bank of India.

Please confirm whether for availing Plant & Machinery advance, Bank Guarantees is needed?

As per Tender Documents only.

42 Page 16 Volume 2

Sub-Clause 12.3 of Special Conditions of Contract

Employer‟s Variation

Paragraph 1: Changes to any sequence, method or timing of construction, manufacture or installation and

In case the change in sequence was occurred due to reasons not attributable to the Contractor, then Contractor shall be suitably compensated for time and cost. Request to

No change in tender conditions.

Page 44: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 44

changes to any part of the Site or the Works Areas or access thereto will not constitute Employer‟s Variation.

modify the clause accordingly.

43 Page 16 Volume 2

Sub-Clause 12.3 of Special Conditions of Contract

Employer‟s Variation

(c) If the Engineer withdraws the request for an Employer‟s Variation, the Contractor shall have no claim of any kind whatsoever arising out of the amount determined above. In case the Employer‟s Variation involves omission of part of the Works, the agreement shall address the issue of reduction in the Contract Price.

If the Engineer withdraws a Variation after substantial works are executed for the same, then suitable time and cost compensation has to be provided to the Contractor. Please change the clause accordingly. Also the mechanism to be adopted while omission of part of the Works is not clearly available in the documents. Please add a suitable sub-clause.

No change in tender conditions.

44 Page 17 Volume 2

Sub-Clause 11.2.5 of Special Conditions of Contract

Interest in case of delay in repayment of advances

(i) Interest will be charged on the balance outstanding advance after the original date of completion at the rate of 3% above State Bank of India Base rate or 12% whichever is higher.

The Contractor should be compensated for any delays that occurred due to reasons not attributable to the Contractor, in case of recovery of any advances paid earlier. Please modify the clause accordingly.

No change in tender conditions.

Page 45: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 45

45 Page 12 & 13

/ Volume 3

Employer‟s

Requirements

SECTION-B/

Functional /

2.1.2 (xviii)

Scope of

Works

Cantilever design

Please clarify the maximum

eccentricity to be adopted for

design of cantilever pier.

Refer addendum no 2

issued.

Page 13R of Employer‟s

Requirement/ Functional

46 Page 13 / Volume 3 Employer‟s Requirements

SECTION-B/ Functional / Clause 2

Scope of works - General

special span of 60 mts Please provide the start & End chainage of special span of 60 m

Refer Tender drawings. GAD (R1) issued in Addendum no 2.

47 Page 13 / Volume 3 Employer‟s Requirements

SECTION-B/ Functional / Clause 2.1.2 IV

Employer Requirement –functional

Standard span in the range of 25m to 34m

19m, 22m & 37m are to be considered as standard span or non – standard as details of spans are provided in the volume 6 tender drawings

Refer addendum no 2 issued.

48

Page 13 / Volume 3 Employer‟s Requirements

SECTION-B/ Functional / Clause 2.1.2 (viii)

Scope of works – Viaduct

Elastomeric bearings (both horizontal and vertical) on standard span including bearing pedestals, seismic devices, shear key restrainer

Please provide the details of elastomeric bearing on standard span. Also clarify if design of non-standard span elastomeric bearing is in contractor‟s scope.

Refer Vol-3, Employer‟s requirement. Scope of work.

49 Page 13 / Volume 3 Employer‟s Requirements

SECTION-B/ Functional / Clause 2.1.2 (XXI)

Scope of works - Viaduct

Grooves on the parapet

Please provide the groove details in the parapet

Refer addendum no 2 issued.

50 page 14/Volume 3

SECTION-B/ Functional /Clause 2.1.2 Notes (3)

Its obligatory for the contractor to provide the single pier structure in the viaduct of minimum dia 1.8m

Please clarify if the circular pier is mandatory for substructure or rectangular can be proposed?

No change in tender conditions.

51 Page 15/ Volume 3 Employer‟s Requirements

SECTION-B/ Functional/ Clause 2.1.5 (a)

Through Alignment plans and obligatory pier locations are provided by the

Please provide the obligatory locations In the alignment drawings

Please provide the

As per addendum no 2 issued.

Page 46: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 46

employer to the contractor

details of divertible and non-divertible utilities

As per Tender documents. The information desired is not relevant at this stage.

52 Page 15/ Volume 3 Employer‟s Requirements

SECTION-B/ Functional/ Clause 2.1.5 (j)

Scope of Works

Maintenance of the completed Work during the period as specified.

Please confirm that once the viaduct is completed and handed over to track-laying/systems Contractor, maintenance of such section shall not be within the scope of the Contractor.

No change in tender conditions.

53 Page 16 /Volume 3 Employer‟s Requirements

Section –B/ Functional/Clause 2.1.5 (o)

Scope under Lump Sum price

Results of sub-surface investigations conducted at project site are enclosed with the tender document. This information about the soil and sub-soil water conditions is being made available to the contractor in good faith and the contractor shall have to obtain the details of sub soil investigation independently. No claim whatsoever on account of any discrepancy between the sub surface conditions that may be actually encountered at the time of execution of the work and those

In case of any discrepancy in sub surface conditions, then the Contractor has to be suitably compensated in time and cost as this type of Contract is (Part) Design & Build only not an EPC. Hence the Contractor should not be forced to bear this risk.

No change in tender conditions.

Page 47: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 47

given in these tender documents shall be admissible to the contractor under any circumstances…

54 Page 16 /Volume 3 Employer‟s Requirements

Section –B/ Functional/Clause 2.2.1.2 (v)

Stations

Please provide the GI bracket details

Refer Tender documents Vol-6 Tender Drawings.

55 Page 27 / Volume 3 Employer‟s Requirements

Section–B/ Functional/Clause 4. (4).(b)

Construction limits / Right of Way

Please specify the minimum ROW that will be provided by the Employer for viaduct portion & station portions for construction works. If achieving Key Dates is affected as a result of delay of providing ROW or providing ROW in parts, then such delays shall not be accounted for LD and the Contractor shall be compensated for time and cost due to change in sequence of construction.

No change in tender conditions.

56 Volume 3 Design Requirements

Please clarify the minimum no of pile to be adopted for portals?

As per Tender conditions only.

57 Volume 3

Employer‟s Requirement

Please provide the min width of Traffic to be allowed for metro construction (station and viaduct portion).

As per Tender conditions only.

58 Page 62 / Appendix-2A Works The employer will Please clarify whether the Refer addendum no 2

Page 48: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 48

Volume 3 Employer‟s Requirements

Areas

provide the work area approx.45000 sqm.

45000 Sqm land is within 15kms or 20kms from work site (since it is mentioned as 15kms in Volume-3/Section-B/Functional/Clause 2.9).

Within how many days from issue of Letter of Acceptance the Employer will hand-over the area to the Contractor?

Please confirm that the Contractor will receive a land that is levelled with approach road.

Please provide a map indicating the location(s) and/or possible location(s) the Employer has identified.

Please confirm that the entire land will be given to the Contractor at once and not in parts.

Request to provide the dimensions of such area to be allotted to enable the bidder to plan the casting yard layout.

As the area could be 20Km away from the alignment, request the Employer to provide additional 10,000 Sq.m area along the alignment to set-up project office.

Please confirm whether 4-Tier stacking of girders is acceptable in the pre-cast

issued. As per tender documents only.

It can be agreed provided fulfillment of design/ Technical requirements.

Page 49: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 49

yard. Considering the area proposed to be provided by the Employer, a 4-Tier stacking system may be required.

Please provide the bore-log details of the Work Area.

Refer Tender documents.

59 Volume 3 Employer‟s Requirements

Design

Please provide MS hand rail epoxy painting technical specification.

As per Tender conditions only.

60 Page 4&5 / Volume 4 of Design basis report

Clause 2.2.1.2

Compressive Strength

Please clarify if the foundation adjacent to the nalla , needs to conform to 90mm cover and M45 grade requirements.

As per Tender conditions only.

61 Page 16 / Volume 4 of Design basis report

Clause 2.8

Live Loads: Trains & Foot paths

Please clarify if the proposed CC-94 alignment is standard gauge or broad gauge

Proposed CC-94 alignment is Broad gauge.

62 Page 16 / Volume 4 of Design basis report

Clause 2.8.1

Vertical Train Live load

Please clarify the axial load configuration

As per Tender documents only.

63 Page 60 / Volume 5 of Technical Specification

Section-S.04 – Clause 4.2

Ply & Timber Formwork

For Designated areas prominently in public view only steel shuttering shall be used

Please confirm whether Ply & timber formwork confirming to IRC87/IS14687 can be used for designated areas prominently in public view

No change in tender conditions.

Page 50: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 50

64 Page 60 / Volume 5 of Technical Specification

Section-S.04 – Clause 4.2

Steel Formwork

For Designated areas prominently in public view like piers, pier caps, portals, viaduct (cast-in-situ or pre-cast),parapet etc., only steel shuttering shall be used

Request to change the clause as” For Designated areas prominently in public view like piers, pier caps, portals, viaduct (cast-in-situ or pre-cast),parapet etc., Formwork (confirming to Clause:1.8 of SectionS.01 of Volume 5) shall be used”. Since use of Ply & Timber formwork can be used in areas as specified in Table 4.1 of IRC:87-2011 without affecting the Quality of construction.

No change in tender conditions.

65 Page 65 / Volume 5 of Technical Specification

CL:4.8 -13

Erection of formwork

Technical Specification

Please provide the drawing for station portal staging

As per Tender documents only.

66 Page 136 / Volume 5 of Technical Specification

Clause 8.6

Pile Top projection into Pile Cap

Mentioned in clause 8.6 that top of pile after stripping shall project at least 150mm into the pile cap.

Please clarify whether we have to follow this clause, that top of pile after stripping shall project at least 150mm into the pile cap or 50mm as per IRC: 78.

No change in tender conditions.

67 Page 138-141/ Volume 5 of Technical Specification

Clause 8.7 (9)

Technical specifications

Sonic Integrity test

Please clarify that in how many piles in a group sonic tube has to be provided & also clarify testing requirement. Since technical specification is

25% pile in each pile group should be tested for Sonic Integrity Test &100% pile should be tested for pile integrity test.

Page 51: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 51

not clear for the same.

68 Page 156 / Volume 5 of Technical Specification

Clause E

Expansion Joints

Please show the other expected expansion/contraction joints in the drawing.

As per Tender documents only.

69 General

Super structure Drawings/ Technical Documents

Request to issue Good for construction (GFC) drawings of super structure for standard spans within 7 days from the issue of LOI.

Request that approval to all Contractors‟ engineering and technical submittals shall be given within 7 days of submission of the same.

As per Tender documents only.

70 Volume 6

Dwg No: DMRC/Sec32-Sec62/Noida/Elev/GAD/001

Foot Over Bridge @ Ch:360,1340,5150

Please provide the level of FOB from the ground level

May be obtained from concerned department if relevant.

71 Volume 6

Dwg No: DMRC/Sec32-Sec62/Noida/Elev/GAD/001 – Ch:825m

Span Configuration

Please confirm whether Intermediate Pier can be introduced at CH:825 without affecting road geometry / Traffic movement

Refer Tender documents vol-3 Employer‟s requirements, Functional.

72 Volume 6

Dwg No: DMRC/Sec32-

Diverging Line

Please provide the GAD of the line Diverging at Ch:1500

Refer Vol-6 Tender drawings.

Page 52: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 52

Sec62/Noida/Elev/GAD/001 – Ch:1500m

73 Volume 6

Dwg No: DMRC/Sec32-Sec62/Noida/Elev/GAD/001 – Ch:3230m

Span Configuration

Please confirm whether Intermediate Pier can be introduced at CH:3250 without affecting road geometry / Traffic movement

Refer Tender documents vol-3 Employer‟s requirements, Functional.

74 Volume-6

Alignment drawing sheet 1 of 7

Interface to existing track

Please provide the sub structure and foundation details of P223

Information will be provided at construction stage, if relevant.

75 Volume-6

Alignment drawing sheet 1 of 7 / Ch: 280

Please clarify if permanent liners for the pile foundation adjacent to the nalla are to be provided or not

Refer Tender documents vol-3 Employer‟s requirements, Functional, Cl. No. 2.1.2 (vi).

76 Volume-6

Alignment drawing sheet 1 of 7 / Ch: 280

Site Observation

Please provide levels of HT lines crossing in alignment , also confirm if its fouling to the metro movement/metro erection works, will it be shifted by DMRC

Refer Tender documents Vol-3 Employer‟s requirement. DMRC plans to shift HT lines by its own.

77

Volume-6

Alignment drawing sheet

1 of 7 / Ch: 280

Site Observation

Please clarify the minimum clearance required to be

maintained below the HT lines crossing the alignment.

As per Tender documents only.

Page 53: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 53

78 Volume 6

Alignment drawings sheet 4 of 7

Chainage 3200

Please clarify if the HT lines & electrical lines shall be removed to facilitate the metro construction is in DMRC‟s scope?

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

79 Volume 6

Alignment drawings sheet 4 of 7

Chainage 3200

Please provide the HT lines & electrical lines levels with respect to road levels

Desired information may be obtained from concerned department, if relevant.

80 Volume 6

Alignment drawings sheet 4 of 7

Chainage 3200

Please clarify the minimum working distance required to be maintained below the HT lines/electrical lines

As per IE (Indian Electrical) rule.

81 Volume 6

Alignment drawings sheet 5 of 7

Chainage 4220.317 & 5100

Without affecting the current traffic flow an intermediate pier at “mamura chowk” is permitted? Please clarify

Refer GAD. No change is permitted.

82 Volume 6

Alignment drawings sheet 5 of 7

Chainage 5100

Without affecting the current traffic flow an intermediate pier at police boothis permitted? Please clarify

Refer GAD. No change is permitted.

83

Volume 6

Alignment drawings sheet 5 of 7

Chainage 4084.705 & 4974.905

In Sector 59 & Sector 62 stations nalla is fouling to the stations entry exist structures, please clarify diversion of nalla is in contractor‟s scope?

If required nalla shall be diverted and paid as per BOQ item.

Page 54: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 54

84 Volume 6

Alignment drawings sheet 5 of 7

Chainage 4084.705 & 4974.905

In Sector 59 & Sector 62 station electrical lines/HT lines are fouling to the station entry exist structures; please clarify if diversion/shifting electrical lines are in DMRC‟s scope?

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

85 Volume 6 Alignment drawings sheet 6 of 7

Chainage 5880 to 6693.13

Electrical Plylon and Electrical lines run closer to the alignment please clarify if the shifting of electrical pylon and electrical lines is in DMRC‟s scope?

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

86 Volume 6 Alignment drawings sheet 6 of 7

Chainage 6135.305

Electrical Pylon is fouling to the Noida electronic city station, Please clarify if shifting of pylon will be done by DMRC

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

87 Volume 6 Alignment drawings sheet 6 of 7

Chainage 6520

Electrical Pylon is fouling to the alignment please clarify shifting of pylon will done by DMRC

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

88 Volume 6 Alignment drawings sheet 6 of 7

Subway U/C

Since alignment is crossing the proposed subway, Please provide the profile & D wall details of under construction subway.

Refer addendum no 2 issued.

89 Volume 6 Alignment Profile

Elevated stabling line

Please provide the Alignment profile for the Stabling line

Please refer GAD.

90 Volume 6 Tender Drawings

Elevated stabling line

Please provide the Superstructure GAD for the Stabling line

Please refer GAD.

Page 55: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 55

91 Volume-6 Tender drawings

Stations please provide the structural details of station at each levels ( concourse , track & platform level)

Refer Tender documents. Vol-6 Tender Drawings.

92 Volume-6 Tender drawings

Please conform whether station layout as per tender drawing is final or may be changed after award of tender?

Please refer GAD which is clear.

93 Volume 6 Alignment Drawings

Please indicate with different colour codes private and government lands. Also confirm that the Employer has completed the approvals.

Please refer contract conditions. No further clarification is required.

94 Volume 6 Tender Drawings

Please confirm the type of beam at concourse & platform level of stations (pre cast / cast in situ).

This shall be provided during construction stage.

95 Volume -6 Tender drawings

Provide us Autocad drgs of Box Girder GA / Reinforcement / Cable Profile

Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents.

96 Volume 6 Drawings Please provide the track layout details for the cross over portions with the varying SIDL details.

Please refer GAD and contract conditions. No further clarification is required.

97 Volume-6 Tender drawings

Please confirm station concourse slab is adequate to take the loads from track and platform level beam and slab

Design of concourse slab shall be carried out during construction stage.

Page 56: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 56

construction

98 Volume 6 Drawings Whether POT bearings should be provided over the cross over and turn out portions?

Bearing shall be provided as per contractual requirement.

99 Volume 6 Drawings Please specify maximum cantilever allowable in cantilever pier caps?

Refer addendum no 2 issued.

100 Volume 6 Drawings Please specify the minimum thickness for structural members for Stations

As per design requirements.

101 Volume 6 Drawings Whether columns with beam arrangement is acceptable for Lift core

As per design requirements which shall be decided at construction stage.

102 Volume 6 All drawings Please confirm if the alignment and GAD proposed in the tender drawings is final?

Please refer GAD.

103 Volume 6 Drawings Please provide Topographical drawings for Station location along with land take boundary.

Please refer GAD. As per design requirements which shall be decided at construction stage.

104 Volume-6 Station Drawings

Please provide the piling and pile cap drawings of stations.

Also provide the depth of piles for the stations

As per design requirements. All details shall be provided during construction stage.

105 Volume 6 Expansion joint between platform girder and

Please provide the drawing for expansion joint coming in between platform girder and viaduct girder and also mention the type and technical

As per tender documents only. Refer Technical specification cl. 9.1.1 (G).

Page 57: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 57

viaduct girder.

specifications of the joint.

106 Volume 6

Access Staircase

Please provide the details of

access staircase from platform

to viaduct.

Refer tender drawings for stations. Further details shall be provided at tender stage.

107 Volume 6

Drawings

Please provide the station I girder numeration details.

Refer tender drawings for stations. Further details shall be provided at tender stage.

108 Volume 6

Drawings

Please provide the casting yard shape and dimension

Refer vol -3 Employer‟s requirement, Appendix 2A.

109 Volume 6 Drawings Please clarify whether drainage is inside or outside the structure.

Drainage is outside of pier. Refer addendum no 2 issued.

110 Volume 6 General Please clarify, whether

contractor can change the

alignment to avoid obligatory

span, if it yes what is the

procedure.

No change in alignment is permitted.

111 Volume 6 Tender drawings

, whereas levels shown in the station drawing does not meet the , minimum height clearance requirement of 5.5m from the ground level, please clarify with corrected station levels in the tender drawings

Refer station drawings vol-6. Which is clear.

112 Volume-6 Tender drawings Stations

Please provide the Beam & column tentative sizes for the Various Levels of Station

Not required at tender stage.

Page 58: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 58

Buildings

113 Volume-6 Alignment Drawings Sheet 1 of 7

Ch. : 454.117

Construction of proposed metro station sector 34 fouls to the bus stand at sector 10, please clarify

If required bus-stand shall be shifted.

114 Volume-6 Alignment Drawings Sheet 1 & 2 of 7

Stations Sector 34 & Sector 52 station entry structure are fouling to the nalla , please clarify if diversion of nala is in contractor scope please clarify

If required nalla shall be diverted and paid as per BOQ.

115 Volume-6 Alignment Drawings Sheet 3 of 7

Ch : 2825.51

Sector 61 station electrical lines are fouling to the station entry exist structures , please clarfiy if shifting of electrical lines shall be done by DMRC

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

116 Volume-6 Alignment Drawings Sheet 3 of 7

Ch : 2825.51

Sector 61 station nala is fouling to the station entry exist structures , please clarify if diversion of nala is in contractor scope

Refer Tender documents Vol-3 Employer‟s requirement. HT lines shall be diverted by DMRC.

117 Volume 4 Design basis report

General To pass the launching girder over the station area, please clarify whether station concourse beams were designed to take the loads from launching girders.

Shall be provided at construction stage.

118 Volume 7 Pricing Document

General The rates provided in the BOQ‟s do not seem to be in-line with the current market

No change in tender conditions.

Page 59: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 59

rates of various commodities/ materials. Request your review and provide the revised rates to avoid any high variations between the bidders price and department estimate of DMRC.

119 Volume 9/ Geotechnical Report

Water Table

Please define the level of fluctuation in water table to be considered from existing water table for Liquefaction analysis

As per tender documents only.

120 Volume 9 Other Information

In addition to the Geotechnical details, please provide the following information:

A schedule of trees (along with the species) along the alignment and station locations that need to be cut and that needs to be re-planted and location of re-planting the tress.

Buildings and structures adjacent to the alignment and station locations. Also provide a schedule of structures/ buildings that needs to be demolished and if any needs to be re-instated provide the schedule for such buildings too.

Area handover

This shall be provided during construction stage.

Page 60: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 60

schedule from the Employer to the Contractor.

121 Page No.5/ Volume 7

Head A-2 Viaduct Based on our experience, cost incurred in the A-2.14 sub-head as per below table. Request to kindly change the % bifurcation as per the below table.

No change in tender conditions.

A-2.14

All other balance works….final bill

5% A-2.14 All other balance works…..final bill

1.5%

Sl. No.

Section / Section

Reference Page / Clause No. Description Bidders Queries

CLARIFICATION from client

Commercial:

1 Vol-1 ITT Page 1 / 1.1.2 Key Details

Completion period of the work 30 Months.

Looking into the entire scope and quantum of works bidder requests to increase the duration of job to "36 months" from existing "30 months". Please confirm your acceptance.

NOT Agreed.

Page 61: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 61

2 Vol-3 Employers Requirement / Works Area

Page 62 / Appendix 2A

The employer will provide the work area of 45000 sqm within 20KM radius of work site as per availability for construction of box girders for viaducts construction & stacking depot.

Bidder request to confirm the following:- i) Land provided by DMRC is free of cost ii) Dimensional extend of land that will be provided so as to enable us to plan the precast yard layout iii) Location of casting yard with the lead distance from the either end of the strech i.e. start and end of the strech.

As per Tender conditions only.

3 Vol -2 GCC & SCC / Mobilization Davance

Page 45 of GCC & 15 of SCC / 11.2.1

Mobilization advance shall be generally 5% of original contract value payable in two equal instalments and second installments shall be paid on production of effective and proper utilization of first installments. Mobilization advance shall be paid interest free against accepatable Bank gurantee.

Bidder request to considered interest free mobilization advance as 10% of CV in two equal installments against Bank Gurantee. Please confirm your acceptance.

As per Tender conditions only

4 Vol -2 GCC / Advance against plant and machinery

Page 45 of GCC & 15 of SCC / 11.2.2

Plant and Machinery advance shall generally be 5% of original CV. Advance shall be paid against 12 accepatable bank gurantees of equal amount.

Bidder understand that such mobilization advance is interest free. Please confirm.

As per Tender conditions only.

Page 62: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 62

5 Vol-2 GCC / Access to and prossession to the site

Page 12 / 2.2

The employer shall grant the contractor right of access to and / or prossession of the site progressively for completion of work…………

Bidder under stand that the Site handing over, in parts or in full, both the provisions are not available in the contract. An appropriate provision should be included to cater delay in handling over of land. Please provide the schedule of handing over of possession of site.

Refer tender documnts Vol-3 Employer's requirement .

6 Vol-2 GCC / Changes in Taxes/Duty

Page 45 / 11.1.4

The contract price shall not be adjasted to take into account any increase or decrease in cost resulting from any changes in taxes, duties, levies from the last date of submission of the tender to completion date including the date of the extended period of the contract.

As you are aware that Union budget for this year will come within next 2 months, where we expecting a dustical change in the Tax strcuture of the country perticularly for the proposal of introduction of GST. It is not possible to bidder to anticipated the change in taxes imposing by the Govt. later stage. Hence bidder request ot to allow for reimbursement for change in cost due to all subsequent legislation/law affecting the Contract Price after the date of submission of tender . Please confirm.

No change in Tender conditions.

7 Vol -2 GCC /Payment-Interim and Final

Page 48 / 11.6 After preliminary scrutiny and certification by the engineer, payment of 80% of certified interim amount shall be made by the Employer within 14 days and the balance 20% shall be made within 28 days from the date of preliminary certification of the bill by the engineer.

Interest on payments delayed by the Employer : Bidder request to pay Interest @ SBI PLR +2% in case of interim and final payments are delayed by the Emploer beyond the period stipulated in the tender documents.Please confirm your acceptance.

No change in Tender conditions.

Page 63: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 63

8 Vol-3 Employers Requirement

Page 12 / Section B-1.4

The Contarctor shall be responsible for obtaining all necessary approvals from all public/government/ocl/statutory agencies with regards to design and construction of works.

Bidder request for provision of obtain all required permits and approvals from the concerned department / agencies with regards to the designs and construction of works, to be secured by DMRC. The contractor shall assist the DMRC in obtaining the same, which shall be more appropriate to avoid the associated procedural delays thereof. Please confirm your acceptance.

No change in Tender conditions.

9 Vol-3 Employers Requirement / Approval for temporary traffic arrangement and control

Page 48 / Section B

The Contractor shall take permission from transport authorities and police department for temporary traffic arrangemnts and control on public roads. The employer will use its best endeavours to assist contractor to secure such approval without responsibility on the part of employer to do so.

Bidder request for provision such approvals from concernced authorities to be secure by the employer and on behalf of the Contractor for speedy materilization of the issues. Please confirm your acceptance.

No change in Tender conditions.

10 Vol-2 GCC / Maintaning records and availing exemptions

Page 44 / 11.1.2

In the event of exemption of custom duties, excise, CST/VAT or any other cess/ levy being granted by the government in respect of the work, the benefit of the same shall be passed on to Employer.

Please Confirm whether excise and costoms duty exemption shall be available for this project or not.

As per Tender conditions only.

Page 64: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 64

11 Vol -2 SCC / The contract price

Page 11 / 11.1.2 The contract price, subject any adjustment thereto in accordance with the contract shall be all inclusive(including all taxes, duties, royalties etc) including Value Added Tax(VAT) paid under state govt VAT act work is done in that state.

Please Confirm whether U.P. VAT will be reimbursed for this project or not.

No, It will not be reimbursed.

12 Vol -2 GCC / Performance security Amount

Page 15 / 4.2

The performance Bank Gurantee is 10% of contract value in the form of Bank Gurantee shall be valid upto 6 months beyond the defect liability period.

Bidder request to considered the performance bank gurantee as 5% of the contract value in the form of bank gurantee with validity as per stipulation in the contract documents. Please confirm.

No change in Tender conditions.

13 Vol -2 GCC / Extension of Time for completion

Page 38 & 39 / 8.4

Bidder request to include the following provisions for grant extension of time for completion as per the standard norms and practice: 1. Any delay, impediment or prevension caused by or attributable to the Employer, Employer personnel or Employer's other contractor to the site 2. Delay caused by authorities. Please confirm.

No change in Tender conditions.

Page 65: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 65

14 Vol-1 Form of tender-Appendix-1, Vol-3, employers requirement &Vol -2 GCC /Liquidated damages for delay

Page 45 of vol-1, 63 of vol-3 & 39 of GCC(vol-2) / 8.5 of GCC

Liquidated damages shall be levied as follows:-i) 0.01% of total contract value per week of delay for key dates.Ii) The maximum limit of LD on Key dates shall be 10% of total contract value.Iii) Total maximum limit of LD including sums payable by the employer to the contractor is 15% of total contract value.

The rate of imposition of liquidated damages is too high. Bidder request to considered the rate of LD imposition as follows:i) 0.005% of total contract value per week of delay for key dates.Ii) The maximum limit of LD on Key dates shall be 4% of total contract value.Iii) Total maximum limit of LD including sums payable by the employer to the contractor is 5% of total contract value.Please confirm.

No change in Tender conditions.

15 Vol -2 GCC / Force Majeure

Page 61 / 16.1

The force majeure means an event beyond the control of Engineer and the contractor, which makes it impossible or illegal for a party to perform…………….

Bidder under stand that Act of God includes natural catstrophes such as earth quake, Hurricane, Typhoon or volcanic activity,etc Please Confirm Bidder also under stand, the existing clause also includes the following as Force Majeure i. After effects of the monsoon ii. Local unrest by villages affected by the project iii. Mitigation of Labour due to Political unrest. iv. Any other events or circumstance which both party could not resonably have provided against entering into the contract. Please Confirm.

No change in Tender conditions.

16 Vol -2 GCC /Interest on Arbitration award

Page 66 / 17.1 Where the arbitral award is for the payment of money, no interest shall be be payable on whole or any period, till the date on which the award is made.

Bidder request to include the provision of interest payable on arbitral award amount on account of delay in award/payments from the submission of the Claims/variations @ SBI PLR

No change in Tender conditions.

Page 66: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 66

+2%.Please Confirm.

17 Vol -2 GCC / Consequences of suspension

Page 40 / 8.8

….In case of If the suspension is ordered by the engineer for the reasons other than those mentioned in sub clause 8.8…: i) Upto 14 days no Extension & No compensation for the suspension period. Ii) 15 to 30 days Extension of time is applicable but no compensation for suspensation period. iii) ............

If the suspension is ordered by the engineer for the reasons other than those mentioned in sub clause 8.8…: Since the suspension effect the Contract Cost and Contract Time, and Bidder will not able to estimate the same during the Bidding, Bidder request to considered for Extension of time and cost both for suspensation of work beyond 2 days Please confirm.

No change in Tender conditions.

18 Vol-3 Employers Requirement

Page 14 / 2.1.1 (xxviii)

The contractor has to get necessory permission /NOC from the road and other concerned regulatory authorities for block and working such location. DMRC will facilate for getting them permission from concerned regulatory authorities for working in such locations.

Bidder request for provision of obtaining necessory permission /NOC from the road and other concerned regulatory authorities as well as required shutdown period from Northern Railway to be secured by DMRC. The contractor shall assist the DMRC in obtaining the same, which shall be more appropriate to avoid the associated procedural delays thereof. Please confirm.

No change in Tender conditions.

Page 67: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 67

19 VOL-1 ITB Page 10 / B2.2- Utilities, The Tenderer shall note the existance of over ground, at grade and under ground structures, utilities and infrastructure in the near vicinity of the works to be constructed.

Bidder request to provide the details of existing utilities that require temporary supporting/shifting or permanebt shifting/ diversion. Bidder under stand that the payment should be made to the contractor for temporary supporting/ shifting works. Please confirm.

Refer Tender Document Vol-3

Employment requirements,

Functional Cl.No. 2.11 . No further

clarification required.

20 Vol-7 Bill of quantities

Page 42 / item no. 8.8

Providing, making connection to appropriate bulk….20% extra shall be payable over the purchase invoice.- Bidder seek clarification,whether this 20% will be payable over and above the % quoted by bidder against the Lumsum amount or not. Please confirm.

As per Tender conditions only.

21 Vol-7 Bill of quantities

Page 27 / item no. 3.3

Yellow visibility vitrified tiles of 200x100x8- Vitrified tile of 200mmx100mm is very difficult to get, as some of the approved vendor confirm that they are not producing this size in vitrified tiles. So bidder request to check the size of the tiles.

No change in Tender conditions.

Page 68: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 68

22 Vol-7 Bill of quantities

star marked items in BOQ. In the BOQ, there are several items, where the quantity has not been given only item rate has been put, but the effect of total quantity has been taken in the sub-head total amount. As we have to quote the % above /below only for this section, without getting the quantity, we can not quote the overall % in the section. so bidder request to provide the quantity of each star marked item.

No quantities are given at tender stage. Qoute percentage above/below/at par at lump-sum amount.

23 Vol-2 Cl No-11.13-SCC /Price Variations

Page 13 / 11.1.3 of SCC Wso = All India Price Index (with base Oct' 12=100) for Reinforcement bars (TMT-500) for primary manufacturers, issued by Central Public Works Department (CPWD) for the month in which the tender was opened.

Till 12.01.2015, CPWD published only Oct'14 Indices. Hence it is not possible to bidder to guess the CPWD indices for the month of in which the tender was opened. Hence Bidder requested to change the clause as follows :Wso = All India Price Index (with base Oct' 12=100) for Reinforcement bars (TMT-500) for primary manufacturers, issued by Central Public Works Department (CPWD) in the Month of Oct'14 Please confirm.

No change in Tender conditions.

Page 69: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 69

24 Vol-2 Cl No-11.13-SCC / Price Variations

Page 13 / 11.1.3 of SCC

Wco = All India Price Index (with base Oct' 12=100) for Cement (OPC) issued by Central Public Works Department (CPWD) for the month in which the tender was opened.

Till 12.01.2015, CPWD published only Oct'14 Indices. Hence it is not possible to bidder to guess the CPWD indices for the month of in which the tender was opened. Hence Bidder requested to change the clause as follows : Wco = All India Price Index (with base Oct' 12=100) for Cement (OPC) issued by Central Public Works Department (CPWD) in the Month of Oct'14 Please confirm.

No change in Tender conditions.

General:

25 Vol-1 ITB /Date and Time for submission of Tender

Page 1 / 1.1.2 Key Details Date and Time for submission of Tender: 03. 02.2015

As evident from the tender document there are several complexity and variations in the project. Hence, an elaborate planning and detail design of all the major components is required to arrive at the most economic solution. The available time shall not be sufficient for completion of design and estimates for the pre-bid stage. Considering this, the Bidder requests for extending the last date of submission of the tender up to two (2) weeks in addition to present date of submission in order to do justice to the project scope.Please confirm.

Please refer Addendum no 1.

Page 70: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 70

26 Form of Tender / Letter of Undertaking

Appendix 12 We, (name of tenderer/joint venture) hereby undertake that the tender drawings, both in hard copy and digitised format, and the tender documents purchased as a necessary part of our preparation of this tender........

Bidder received tender drawing hard copy only, digitised copy not yet received. Kindly provide the same.

Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents.

Technical:

27 Vol-4, "Design Basis Report"

Page 29 / Cl 12.23.1 (n), "Foundations Capacity"

Limiting values for computation of safe pile load

Please specify whether f values should be restricted upto 32 degrees ignoring the actual values from GIR and whether the top 3m soil, irrespective of the actual soil condition, has to considered as filled-up soil and potentially liquefiable and whether the designer may consider "C" and "f" both from GIR, or either of the two has to be considered for pile load carrying capacity calculation. Please clarify.

No change in Tender conditions.

28 Vol-4, "Design Basis Report"

Page 18 / Cl 2.8.2.2, "Centrifugal Force"

Centrifugal Force For determination of Centrifugal force in curvature, please clarify whether the designer can consider the Design speed based on radius of curvature follwed by Schedule of dimensions provided by you.

As per Tender conditions only.

Page 71: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 71

29 Vol-4, "Design Basis Report"

Page 19 / Cl 2.8.1, "Vertical Train Live Load"

Vertical Train Live Load Please clarify whether the train live load has to be considered with 16 t axle loading or with 17 t axle loading with two alternative axle configurations as considered in our current DMRC metro projects.

As per Tender conditions only.

30 Vol-6 , "Tender Drawings"

Pier Cap Please specify whether the designer may adopt pier cap size based on their design calculations.

As per Tender conditions only.

31 Vol-4, "Design Basis Report" (ED/Tech)

Page 30 /Cl 12.25.1, "Soil Static Stiffness"

Soil Static Stiffness Please clarify whether the designer should consider the "soil type" based on the "N"values obtained (as per IS: 2911-Part-1/Sec-2, table-3, cl. C-2.1) or it is mandatory to consider "medium sand" in all the cases irrespective of "N" values for computation of soil spring stiffness.

As per Tender conditions only.

32 Vol-4, "Design Basis Report" (ED/Tech)

Page 29 / Cl 2.23.1 (n), "Foundations Capacity"

Limiting values for computation of safe pile load

In all the shearing tests on sand it is not practicable to prepare undisturbed shear strength (triaxial/ direct shear) test samples. The soil samples are to be made approximately to the same density as it exists in-situ and tested either by direct shear or triaxial compression tests, it was meant that a sample of equivalent density has been prepared. Hence, it is requested that shear strength parameters for the tested samples should be considered in GIR.

As per Tender conditions only.

Page 72: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 72

33 Vol-9, "Geotechnical Report"

"Liquefaction Potential Evaluation"

Liquefaction Potential Evaluation

The peak ground acceleration value (amax/g) as shown in Geotechnical Report for liquefaction potential analysis i.e. 0.24g is verymuch on higher side. Peak ground acceleration (amax/g) value of 0.143 was stated in the bulletin of the Seismological Society of America, Vol-92, No.2,pp-555-569,March 2002. Hence, the bidder proposes to consider Peak ground acceleration (amax/g) value as 0.143. Please confirm.

No change in Tender conditions.

34 Vol-6 of 8, "Tender Drawings"

AutoCAD Drawings Please provide AutoCAD drawings for better clarification.

Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents.

35 Vol-3, "Scope of Works"

Page 13 / Cl 2.1.2 (ii)

Superstructure quantity It is stated that the appropriate quantity of concrete, reinforcement and prestressing strand for superstructure is mentioned in tender drawing, but is not found in drawings. Please provide the same.

Refer addendum no 2 issued.

Page 73: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 73

36 Vol-6 of 8, "Tender Drawings"

Drawing no- DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 sheet 1 of 7

General Alignment plan a) Please mention the start chainage in the alignment plan layout. Also please state whether ramp is in scope of the bidder. (b) Please confirm the bed levels / EGLs of the nullah region between chainage 240 to 300 as no variation is here with the adjacent ground level. (c) Elevations & Sections with levels are required for Foot Over Bridge between chainage 360 to 308.

The chainage are mentioned in GAD. No ramp is planned in the alignment. The information is not required at tender stage.

37 Vol-6 of 8, "Tender Drawings"

Drawing no- DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 sheet 2 of 7

General Alignment plan (a) Elevations & Sections with levels are required for Culvert between chainage 1300 to 1340. Please provide the same. (b) Elevations & Sections with levels are required for Culvert between chainage 1940 to 1980. Please provide the same.

May be collected from concerned department if relevant. Refer tender documents.

38 Vol-6 , "Tender Drawings"

Drawing no- DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 sheet 3 of 7

General Alignment plan (a) Elevations & Sections with levels are required at "U-turn region" between chainage 2060 to 2120. Please provide the same. Also please specify whether any flyover is there.(b) Fountain details is required at chainage 2440.(c) Elevations & Sections with levels are required at "U-turn region" between chainage 2620 to 2660. Please provide the same. Also please specify whether any flyover is there.

Refer GAD. No further detail is required at this stage.

Page 74: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 74

1

Volum6:

Drawings

• Drawings are illegible. AutoCad soft copy with all geometric details of approved alignment would be required for accessing the obligatory spans. Please confirm.

Soft copy in PDF is enclosed. However, hard copy issued shall form the part of Tender Documents.

2 Volume 3.

clause no. 2.1.1 Time limit for proof checking of the design of Substructure to be specified. Proof checking regarding foundation for standard span is silent. Please confirm about proof checking of superstructure, substructure & foundation along with time frame for obligatory spans. Also advise who would be the proof checker

As per tender conditions only

3

• In the tender submission are name of the DDC and their credential to be submitted? Please confirm.

As per tender conditions only.

39 Vol-6 , "Tender Drawings"

Drawing no- DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 sheet 4 of 7

General Alignment plan (a) Elevations & Sections with levels are required for Foot Over Bridge between chainage 3760 to 3800.

Please refer GAD. No further clarification is required.

40 Vol-4, "Design Basis Report"

Page 29 / Cl 12.23.1 (n), "Foundations Capacity"

Limiting values for computation of safe pile load

Please confirm whether the clause "Only submerged weight of the pile………………..capacity of the pile" is deleted from the Design basis report.

No change in Tender conditions.

41 Vol-6 , "Tender Drawings"

Drawing no- DMRC/SEC32-SEC62/NOIDA/ELEV/GAD/001 sheet 1 of 7

General Alignment plan Please confirm the locations of obligatory/special spans/CLC showing chainages and span lengths in the General alignment plan drawings.

Refer addendum no 2 issued. Revised GAD is being issued.

Page 75: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 75

4 Volume 3. Pg 29

cl no 4.2 it is mentioned that “Design specification ,which will be part of Particular Specification shall form a crucial part of the contractor‟s Technical Proposal- criteria for evaluation of bid”. Pls. clarify. Please confirm.

No change in tender conditions.

5 Volume 3.

clause no. 2.1.2 (xx)

Please clarify if the system contractors are not deployed in appropriate time how the same can be finalized. Please confirm.

As per tender conditions only

6 Volume 3

2.1.2 (xxiv) Piers & span arrangement for both standard & obligatory spans are missing while it is claimed as provided in GAD drawing. Please confirm.

Please refer revised GAD issued in Addendum no 2.

7 Volume 3

2.1.2 (xxiv) It is presumed that the variation of soil strata would be minor wrt the subsoil data provided in tender document. Please clarify how to assess the Cost implication due to major variation of subsoil data. Please confirm.

As per tender condition only

8 Volume 3

clause no. 2.1.5 (a)

Please clarify how much to factor in if there is inordinate delay in shifting of utilities as it is beyond the control of the bidder. Please confirm.

As per tender conditions only

9 Volume 3

clause no. 2.1.5

(b)

Please clarify how to resolve this issue if the system contractors are not on board in appropriate time. Please confirm.

As per tender conditions only

Page 76: Pre-Bid Queries - Delhi Metro · Possession of Site and the handing over schedule to the Contractor. Moreover, Kindly confirm that whether the shifting of H.T. Lines is under the

Page 76

10 Achitectural Part

• Architectural DBR or out-line design criteria • Station room schedule and area requirement • Station to Station Distance • Train crush load • Peak hour entrain load and de-train load at each station • How many stations will be interlocking and how many non-interlocking • As elevated stations, exact ROW available at the station locations • Approximate Ground level at the station locations • Rail level at the station locations • Ground level plan of traffic integration area at station locations Please confirm.

As per tender documents only

11 Structural part:

• Station DBR is missing.• Dimensions of station building are not readable from provided drawings. (Refer Dwg, No. DMRC/Noida/CON/TND- 1 to 3 & Platform Level dwgs.)• No geotechnical data has been provided for Electronic City Station in Soil Investigation Report. (Refer Vol-9 of tender Documents)• Room sizes at concourse level to be provided. (Refer Dwg . No. DMRC/Noida/CON/TND- 1 to 3 & Platform Level dwgs.)• Height of rooms at Concourse level to be provided.• Minimum Clear height between Road level & Soffit of concourse level beams to be specified.• Rail Top level for each station to be provided.• Street level Plan to be provided.• Thickness of Internal & external walls for Station buildings to be provided. Please provide.

Please refer tender drawings which is clear.