21
FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS INTERNATIONALE VEREINIGUNG BERATENDER INGENIEURE FEDERACION INTERNACIONAL DE INGENIEROS CONSOLTORES Standard Prequalification form For contractors

pq1

Embed Size (px)

DESCRIPTION

ere

Citation preview

Page 1: pq1

FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS INTERNATIONALE VEREINIGUNG BERATENDER INGENIEURE FEDERACION INTERNACIONAL DE INGENIEROS CONSOLTORES

StandardPrequalification formFor contractors

©Copyright FIDIC 1994

All rights reserved.No part of this publication may beReproduced or transmitted in anyForm or by any means withoutPermission of the publisher

Published by

Fédération Internationale desIngénieurs-Conseils (FIDIC)P.O. Box 861000 Lausanne 12

Phone +41 21 654 44 11Fax +41 21 653 54 32E-mail [email protected]

Page 2: pq1

Switzerland

Second edition 1994

WWW http://www.fidic.org

Page 3: pq1

Page of Total pages

Standardprequalification formfor contractors

_______________________________________________________________________________________________________

Name and address of the contractor :

_______________________________________________________________________________________________________

Name of the employer :

Title and location of the project :

Name of the engineer :

Date :

Page A

FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS INTERNATIONALE VEREINIGUNG BERATENDER INGENIEURE FEDERACION INTERNACIONAL DE INGENIEROS CONSOLTORES

Page 4: pq1

Pequalification form

Page of total pages

Project :Company :

Note to applicants

1 Please answer all questions.

2 Supplementary pages may be photocopied or copied and inserted if required.

3 Please number each page in the space provided at the top of each page.

4 Please retain a copy of your complete submission.

5 If a joint venture is proposed, all companies are to respond to all questions

6 Project financial data is to be given in US dollar unless otherwise requested.

Standard pages

A. Title pageB. NotesC. Structure and organization 1D. Structure and organization 2E. Financial statementF. Joint VentureG. Resource: personnel 1

H. Resources: personnel 2I. Resources: plantJ. Resources: otherK. Experience: geographicalL. Experience: relevant projects completedM. Experience: project in progressN. Additional information

Please list below any additional pages attached to each standard page:

Page B

Page 5: pq1

Pequalification form

Page of total pages

Project :Company :

Structure and organization 1

1 Name of company:

Address:

Telephone number: Telefax number:

Registered office address:

2 Description of company (for example, General Civil Engineering Contractor):

3 Number of years experience as a general contractor - in own country:

- internationally:

4 Number of years experience as a subcontractor - in own country:

- internationally:

5 Names and addresses of associated companies to be involved in the project – and whether parent/subsidiary/other:

6 If the company is a subsidiary, what involvement, if any, will the parent company have in the project?

Page C

Page 6: pq1

Pequalification form

Page of total pages

Project :Company :

Structure and organization 2

7 Names and addresses of any associates the company has in the country of the project, knowledgeable in the procedures of customs, immigration etc.:

8 Please indicate here or attach an organisation chart showing the company structure including the positions of directors and key personnel, if relevant

Page D

Page 7: pq1

Pequalification form

Page of total pages

Project :Company :

Financial statement

1 Capital:

Authorised:

Issued:

2 Annual value of construction work undertaken for each of the last five years and projected for current year:

Year CurrentHomeAbroad

3 Approximate value of work in hand:

4 Please attach copies of the company’s previous three years’ accounts (profit/loss, assets/liabilities) and other financial data which you consider to be useful.

List all attachments below :

5 Name and address of bankers from whom references can be obtained :

Page E

Page 8: pq1

Pequalification form

Page of total pages

Project :Company :

Joint Venture

If the company intends to enter into a joint venture for the project, please give the following information, otherwise state “not applicable”:

1 Names and addresses of joint venture partners:

2 Name of company leading the joint venture:

3 Name and address of bankers to the joint venture:

Page F

Page 9: pq1

Pequalification form

Page of total pages

Project :Company :

Resource: personnel 1

1 Number of staff: Technical: Administrative:

2 Please list present executive directors:

Name Present position Years of experience with the company/in construction

Page G

Page 10: pq1

Pequalification form

Page of total pages

Project :Company :

Resources: personnel 2

List information about other key personnel below :

Name: Present position:

Years of experience - with the company:

- in construction:

Major works for which responsible (type and value):

Linguistic ability relevant to project:

Name: Present position:

Years of experience - with the company:

- in construction:

Major works for which responsible (type and value):

Linguistic ability relevant to project:

Name: Present position:

Years of experience - with the company:

- in construction:

Major works for which responsible (type and value):

Linguistic ability relevant to project

Page H

Page 11: pq1

Pequalification form

Page of total pages

Project :Company :

Resources: contractor’s equipment and facilities

On the basis of the information provided in the prequalification documents please indicate the equipment and facilities considered by the company to be necessary for undertaking the project and whether this is already in the company’s ownership or will be purchase or hired:

Page J

Page 12: pq1

Pequalification form

Page of total pages

Project :Company :

Resources: other

1 If it is foreseen that any part of the contract will be subcontracted state the type of work to be undertaken by the subcontractor(s) and, if known, give the name and address of the subcontractor(s) to be used.

2 Fabrication facilities (to be completed only if relevant to the project):

Summary:

Description:

Location:

Capacity:

Annual throughput

Page J

Page 13: pq1

Pequalification form

Page of total pages

Project :Company :

Experience : geographical

1 Countries in which work similar to the project has been undertaken:

2 Summary of experience of company in the country of the project and/or neighbouring states:

Page K

Page 14: pq1

Pequalification form

Page of total pages

Project :Company :

Additional information

Please describe :

1 Company’s quality assurance system:

2 Company’s environmental policy:

3 Company’s history of litigation or arbitration from contracts executed in the last six years or currently under execution. Please indicate for each case year, name of employer, cause of litigation, matter in dispute, disputed amount and whether the award was for against company.

Please add any further information which you consider to be relevant to the evaluation of your application for prequalification. If you wish to attach other documents please list below.