AV-04 Case Study:CF Industries - Utilizing Avantis toManage Turnarounds
Presenter: Mark Dubreuil
© 2013 Invensys. All Rights Reserved. The names, logos, and taglines identifying the products and services of Invensys are proprietary marks of Invensys or its subsidiaries.All third party trademarks and service marks are the proprietary marks of their respective owners.©
Invensys00/00/00
Invensys proprietary &confidential
Slide 2
Slide 3
CF Industries is a global leader in fertilizer manufacturing anddistribution, the second largest nitrogen fertilizer producer in theworld and the third largest phosphate fertilizer producer amongpublic companies. CF Industries owns and operates world-scalenitrogen and phosphate plants and serves agricultural and industrialcustomers through its best-in-class distribution system.
Donaldsonville Nitrogen Complex
• Donaldsonville operates:
– 5 Ammonia Plants
– 4 Urea Plants
– 3 Nitric Acid Plants
– 2 UAN Plants
• CF Industries' nitrogen complex atDonaldsonville, LA is North America’slargest and, in many respects, itsmost flexible nitrogen operation.
• It can produce and ship approximately 5 million tons of nitrogen foragricultural and industrial uses each year.
Slide 4
• Donaldsonville operates:
– 5 Ammonia Plants
– 4 Urea Plants
– 3 Nitric Acid Plants
– 2 UAN Plants
• CF Industries' nitrogen complex atDonaldsonville, LA is North America’slargest and, in many respects, itsmost flexible nitrogen operation.
• It can produce and ship approximately 5 million tons of nitrogen foragricultural and industrial uses each year.
Outage Cycle Strategy
• To improve flexibility, outage cycles have been extended to multipleyears, resulting in the ability to capture various continuous runrecords:
– Ammonia 4 achieved a 995 day continuous run record which at the time wasa world record for a Kellogg ammonia plant.
– Urea 4 established a 936 day continuous run record which was only daysshort of the world record for a Stamicarbon urea plant.
• But even the best maintenance and operating plans couldn’tovercome…
Slide 5
• To improve flexibility, outage cycles have been extended to multipleyears, resulting in the ability to capture various continuous runrecords:
– Ammonia 4 achieved a 995 day continuous run record which at the time wasa world record for a Kellogg ammonia plant.
– Urea 4 established a 936 day continuous run record which was only daysshort of the world record for a Stamicarbon urea plant.
• But even the best maintenance and operating plans couldn’tovercome…
Over time, Turnaround Cycles have lengthened considerably
• Ammonia Plants are scheduled for major outages every 5 years
• Urea/UAN/Nitric plants are scheduled on a 4 year cycle
CF’s Turnaround Cycle Progression
1 year 4 years 5 years
Slide 7
28 days10 days 21 days
1 year 4 years 5 years
Outages have expanded from 10 to 28 days as a result
Breaking Down the Time Line
Major Outage – Entire Time Line
Pre-Turnaround Turnaround Post -Turnaround
Locate, Verify, & TagPre-stage materialsBuild ScaffoldsPre-Fabricate ItemsRemove InsulationPrep Worksites
Replace InsulationTear Down ScaffoldsWork Site Clean-upStow TemporaryEquipment
Install BlindsRemove PipingOpen VesselsPull Valves for Inspection and Repair
Equipment InspectionsMisc RepairsClean Vessels
Found WorkReplace ValvesClose VesselsReplace PipesRemove Blinds
Slide 12
Locate, Verify, & TagPre-stage materialsBuild ScaffoldsPre-Fabricate ItemsRemove InsulationPrep Worksites
Install BlindsRemove PipingOpen VesselsPull Valves for Inspection and Repair
Equipment InspectionsMisc RepairsClean Vessels
Found WorkReplace ValvesClose VesselsReplace PipesRemove Blinds
Breaking Down by AreaSchedule Plant Plant Operating Area Tasks
18794-Urea 2 T/A 2009 (Not Assigned) 718794-Urea 2 T/A 2009 Nitric Acid Plant Process Piping & Vessels 218794-Urea 2 T/A 2009 UAN Plant Steam System 118794-Urea 2 T/A 2009 Urea Plant 6118794-Urea 2 T/A 2009 Urea Plant Atmospheric Absorption 1618794-Urea 2 T/A 2009 Urea Plant Boiler Feed Water 5118794-Urea 2 T/A 2009 Urea Plant Clean Condensate System 3518794-Urea 2 T/A 2009 Urea Plant CO2 Compression 13018794-Urea 2 T/A 2009 Urea Plant Cooling Water 5118794-Urea 2 T/A 2009 Urea Plant Desorption 2518794-Urea 2 T/A 2009 Urea Plant Effluent 418794-Urea 2 T/A 2009 Urea Plant Evaporation 65
Slide 13
18794-Urea 2 T/A 2009 Urea Plant Evaporation 6518794-Urea 2 T/A 2009 Urea Plant Granulation 22718794-Urea 2 T/A 2009 Urea Plant High Pressure Synthesis 10418794-Urea 2 T/A 2009 Urea Plant Instrument Air & Plant Air 2118794-Urea 2 T/A 2009 Urea Plant Low Pressure Reflux 26
18794-Urea 2 T/A 2009 Urea Plant Low Pressure Synthesis (Recirculation) 7418794-Urea 2 T/A 2009 Urea Plant NH3 Buffer Tank & Piping 518794-Urea 2 T/A 2009 Urea Plant NH3 Compression 3718794-Urea 2 T/A 2009 Urea Plant Package Boiler 6718794-Urea 2 T/A 2009 Urea Plant Safety 718794-Urea 2 T/A 2009 Urea Plant Steam System 184
Breaking Down by Work Category
Schedule Work Category Tasks
18794-Urea 2 T/A 2009 (Not Assigned) 14
18794-Urea 2 T/A 2009 Fixed Equipment 119
18794-Urea 2 T/A 2009 I&E 525
18794-Urea 2 T/A 2009 Misc Maint 230
18794-Urea 2 T/A 2009 MOC 17
Slide 14
18794-Urea 2 T/A 2009 MOC 17
18794-Urea 2 T/A 2009 Paint 2
18794-Urea 2 T/A 2009 PSO 230
18794-Urea 2 T/A 2009 Rotating 63
Export Default Linking Behavior
Work Order
Work Task w/o Activities
Work Task w/Activities
Activity
Slide 15
Work Task w/Activities
Activity
Activity
Activity
Activity
Export Default Schedule Rollups
Schedule
Plant
Plant Operating Area
Slide 16
Work Task / Activity
Plant Operating Area
Entity
Work Order
Resources
Assigning Phase, Category,and Plant Operating Areas
Operating Area of Plant
Slide 17
Phase of Outage
Work Category
Alternate Phase Specification forActivities
Activity Type is used toOverride the Phase of theoutage when Activities aredefined for a work task
Slide 18
Specifying Labor Requirementson Tasks
Crew Size and PlannedHours are entered aslabor requirements onTasks w/o Activities.
If a task has Activities,these entries summarizethe total need from allactivities for the task
Slide 19
Crew Size and PlannedHours are entered aslabor requirements onTasks w/o Activities.
If a task has Activities,these entries summarizethe total need from allactivities for the task
Specifying Labor Requirements onTasks with Activities
A ‘creative’ use ofthe downtime tabfor activities isused to record thenumber of hours,trade, and crewsize needed
Slide 20