pp24-31 MS07

Embed Size (px)

Citation preview

  • MIL

    LEN

    NIU

    M S

    TEEL

    2007

    24

    AUTHOR: Alfred R. Hampel Siemens VAI Metals Technologies GmbH & Co (Siemens VAI)

    BOF steelmaking comprises several operating steps,including charging, oxygen blowing and tapping; allof which involve emissions of hot and dust-laden gas.Usually, two different off-gas systems are installed; forfume evacuation and to keep the converter environmentcool and clean.

    Major quantities of hot gases are emitted during theoxygen blowing phase, mainly in the form of hot carbonmonoxide. Specially designed primary off-gas systemscollect these gases and cool the partial or fully combustedcarbon monoxide. To evacuate the hot fumes producedduring the other converter operation steps such as scrapcharging, hot metal charging, steel tapping and slagdumping, doghouses and secondary off-gas cleaningsystems are normally installed (see Fig. 1).

    For a number of steel shops the primary off-gas systemaccomplishes the secondary ventilation via a by-passfunction. However, the evacuation performance is very

    poor during converter charging and is not carried out atall during the blowing phase.

    In the majority of steel shops independentsecondary off-gas cleaning systems are installed. Theyensure the required evacuation capacity with properlydesigned induced draught (ID) fans and meet therequired clean gas dust content using fibre bag filters.These systems are usually designed not only toevacuate the converter environment during charging,tapping and de-slagging, etc., but also other dustemission sources on the hot metal side (reladling,desulphurisation, de-slagging and scull cutting) aswell on the liquid steel side (ladle treatment stations,ladle furnaces, etc.).

    DESIGN DEVELOPMENTS IN SECONDARY DE-DUSTING SYSTEMSFor many years the design criteria for secondary off-gascleaning systems were rather simple, with the evacuationperformance based on converter tapping size only.Comparing all emission sources, the gases evacuatedduring hot metal charging via the charging hood show

    the highesttemperature profilesand are characterisedby high gas flows.Considering thelimitations with respectto the filter inlettemperature, the hotcharging gases have tobe cooled so that thefilter bags are notdamaged byoverheating. Themaximum allowabletemperature for polyesterfilter bags should notexceed 160C. This is

    The off-gases released during steelmaking operations, particularly during the charging of low-quality scrap with its inherent hydrocarbon impurities, frequently overloads the exhaust andcooling capability of conventional off-gas treatment systems. The resulting combustion of the emittedgases occasionally leads to uncontrolled fume emissions and high gas temperatures which can causeexcessive damage to the system, especially to the bag filters. An advanced off-gas treatment systemby Siemens VAI eliminates these problems thorough optimised plant design and hot metal pouringspeed, leading to increased operational safety and shorter tap-to-tap times.

    BOF secondary off-gas cleaning systems

    ar Fig.1 Schematic view of secondary off-gas cleaning system

    MS 01 Into themes(L) 4/22/07 4:11 PM Page 2

  • achieved by mixing the hot charginggases with fumes coming from `cold`evacuation sources and by activating,so-called, emergency cooling air flapsas a source of cold ambient air formixing. System designs which achievethe required temperature by mixinghigh and low temperature evacuationgases (cooling by mixing) can beclassified as `conventional`. Figure 2shows different conventional off-gascleaning systems where the ratio of theconverter suction volume and theconverter tapping capacity arecompared. The horizontal axis showsthe converter tapping weight of theplant indicated by name in the field.The vertical axis shows the total suctionvolume in m3/h. In order to enable aneutral assessment of the results, bothSiemens VAI -supplied off-gas systemsand off-gas systems from other suppliers - referenced withthe denomination OX1 to OX9, were investigated.As clearly seen, most of the reference points of theassessed systems are located within two parameter lines:

    ` Upper parameter line, which represents a highevacuation performance of 5,400m3 off-gas/hr/ttapping weight

    ` Lower parameter line representing the lowevacuation performance of 2,100m3 off-gas/hr/ttapping weight

    The figures `xx MW` of the different reference pointsdefine the cooling performance of the off-gas system inMegawatt (MW), and represent the physical magnitude ofthermal power which is absorbed from the off-gas suckedthrough the system. It can be explained as follows:

    ` The actual volumetric gas flow VA [m3/h] refers viathe gas temperature to a certain gas mass flow VM[Nm3/h]

    ` The air and fumes have a certain specific heat Cp[kJ/Nm3.C]. The temperature increase t [C] fromambient temperature to the maximum filter inlettemperature (which has to be controlled to preventdamage) multiplied by the specific heat Cp results inthe specific thermal energy content Espec [kJ/Nm3].The specific thermal energy content [kJ/Nm3]multiplied by the mass flow [Nm3/h] results in thetotal energy flow [kJ/h] equivalent to thermal powerPth expressed in kilowatts [kW] or Megawatts [MW].Espec = Cp x t, Pth = VM x Espec

    INTRODUCTORY THEMES

    25

    MIL

    LEN

    NIU

    M S

    TEEL

    2007

    As an example, the figures for the reference point ofvoestalpine Stahl (VAS), Linz, Austria (160 t tappingweight) show a cooling capacity of 43 MW. This meansthat as long as the total thermal power emission of theconverter operation (charging, tapping, de-slagging, etc.)remains below 43 MW, the off-gas system will notbecome overloaded with respect to the temperature andvolume of fumes.

    CONVERTER HEAT EMISSIONS As indicated above, the bulk of the thermal power loadto be absorbed by the secondary system comes fromthe converter during hot metal charging. The scrapusually contains combustibles, mostly in the form ofhydrocarbons such as paint, plastics, grease, oil, etc., aswell as galvanised and tin-coated metals. The specificheating values of these substances are of the order of80 - 90% of the energy content of the same quantityof oil by weight. During charging of hot metal onto thescrap in the converter, the hydrocarbons are heatedand the zinc or tin is vapourised. However, they cannotcombust due to the lack of oxygen inside the converterduring the charging period. Pyrolysis (decomposition)gases (e.g., CO, H2, CH4 compounds) and/or vapoursof Zn or Sn are produced which carry the energy in achemical phase. The pyrolysis and vapourisingprocesses are endothermic, with the required energybrought in by the hot metal during pouring. Thecomposition of the pyrolysis gases depends on thedecomposition temperature. At a lower temperaturethe dominating elements are CH4 compounds and at ahigher temperature the equilibrium moves to higher

    r Fig.2 Comparison of converter suction volume and tapping capacity inconventionally designed steel shop ventilation systems

    MS 01 Into themes(L) 4/22/07 4:11 PM Page 79

  • formulae are similar to those already outlined for thecooling capacity of a plant. The further reactions takeplace in the sequence of process steps depicted in figure3. The gases and vapours leaving the converter comeinto contact with the ambient air supplying thecombustion oxygen and begin to combust. The chemicalenergy converts to thermal energy and the permanentgas flow creates the thermal power emission of theconverter (Pconv).

    For the design of the off-gas system with respect to therequired cooling capacity (Poff), the maximum thermalpower emission of the converter (Pconv, peak,) is the keydesign factor. Only in cases where the figure Poff is higherthan the figure Pconv, peak, can the off-gas cleaning systemsafely absorb and remove the thermal power emission ofthe converter. If this is not the case, the charging hoodcannot remove all of the fumes, and secondary emissionsaccumulate in the hood which lead to fugitive emissions.

    The combusted hot gases above the converter rise andalso suck air into the combustion zone, increasing thetotal gas volume. Dilution air is required as excesscombustion air in order to avoid incomplete combustionof the emitted gas concentrations.

    INFLUENCE OF SCRAP QUALITYIn the past the major portion of scrap for BOF steelmakingcame from the steelworks as return scrap; with externalscrap accounting for only a minor portion of the charge.This situation has changed during the past 10 to15 yearsas clean return scrap from the steelworks continuallydecreased as a result of better process control in theupstream and downstream facilities. External scrap in the

    H2 concentrations with increased explosion risk. Thepresence of water charged with the scrap (liquid or ice)increases the generation of hydrogen.

    During hot metal pouring the converter emits acontinuous flow of combustible gases of a certainspecific energy (calorific) content, depending oncomposition. This energy flow is expressed by means ofthe magnitude of the thermal power. The respective

    MIL

    LEN

    NIU

    M S

    TEEL

    2007

    26

    a

    r Fig.3 Schematic diagram of thermal powerbalance factors

    r Fig.4 Trend of thermal power emission from a 295t converter

    MS 01 Into themes(L) 4/22/07 4:11 PM Page 80

  • 27

    MIL

    LEN

    NIU

    M S

    TEEL

    2007

    INTRODUCTORY THEMES

    100MW. As a result, their off-gas system was sufferingpermanently from overheating, from escaped fumeemissions at the charging hood, and from systemexplosions as a result of incomplete combustion.

    Numerous other steelmakers - mostly in Europe, but alsoin the U.S.A. - are suffering from the same problemsbecause their systems are positioned in the`conventional` design group and because they arecharging cheap, but obviously energy-rich scrap. Figures 5and 6 reflect the situation occasionally faced by steel producers.

    ADVANCED DESIGN OF SECONDARY OFF-GAS SYSTEMSStarting in 2003, Siemens VAI improved the design ofsecondary off-gas cleaning systems by quantifying and

    form of metal cuttings, cans and alsoan increased number of scrapped carbodies has increased. This type ofscrap is mostly compressed to bundlesor blocks which typically contain 2 to4kg of combustibles per tonne ofscrap.

    An example highlights the currentsituation in steel shops, which areincreasingly encountering problems inconnection with thermally overloadedoff-gas systems, resulting insignificant visible fume emissionsduring charging and by highequipment temperatures:

    ` Considering a scrap weight of 50tonnes for charging and acombustible content of 3.0kg/t,the total weight of combustibles inthe scrap chute amounts to 150kg

    ` The energy content of thisquantity of combustibles compared with oil shows anenergy equivalent of 120kg of oil (150 litres),equivalent to nearly one barrel of oil

    ` The burning of this energy in less than one minutemeans the release of 4,800MJ, leading to an averagethermal power emission of 4,800/60 = 80MW

    Considering the reactivity of the scrap, the thermal peakpower development can increase to two or more timesthat of the average, which means 160MW, and more.Figure 4 illustrates the trend of a thermal power emissionlife during hot metal charging. The power peak shows thesame figure as shown in the example, i.e., 160MW. (Notethat the integration of the thermal power versus time -equivalent to the shadowed area - expresses the energyreleased during the observation period. On the basis ofthese figures the energy content in the scrap can bedetermined.) Even with a lower hot metal charging rate,an eruptive reaction cannot be avoided.

    This data of thermal power emissions by convertersduring hot metal charging has now to be compared withthe diagram showing the cooling performance of the off-gas system with a conventional design (see Fig. 2).The comparison makes it understandable that the thermalpower development set free by a 50 tonne scrap chargeeasily exceeds the cooling and evacuation capability of alloff-gas systems shown in figure 3. The example for 50tscrap charging corresponds with the reference point ofvoestalpine Stahl (Linz, Austria), which shows a coolingcapacity of the off-gas system of only 43MW, comparedto a typical converter emission considerably exceeding

    r Fig.5 Uncontrolled combustion and fume emissions during charging of scrap ontohot metal

    r Fig.6 Roof emissions during converter charging

    MS 01 Into themes(L) 4/22/07 4:11 PM Page 81

  • Each of the two 295t converters wasequipped with the following: ` One evacuation system designed

    for both charging hot metalfollowed by scrap charging, andvice versa. At Sidmar it was decidedto charge scrap first followed by hotmetal.

    ` One evacuation system for tapping` One roof extraction system (RE)` Exhaust system for two ladletreatment stands

    At the same time the dust emissionlevel inside the steel building had to be

    kept to below 5 mg/Nm3, the gas-cooling system had to cope with athermal load of 180 MW and the gas

    cleaning system had to ensure a clean gas dust level atthe stack to less than 10 mg/Nm3. The solution to achieve these targets was as follows (see Fig. 7):` Installation of an evacuation system with a capacity

    of 2,400,000 Nm3/h for the start of hot metalcharging (at 0C ambient temperature). During hotmetal pouring, the total gas flow can reach3,800,000 Nm3/h for all hoods.

    ` Installation of plate-type convection coolers whichcan absorb the generated heat (see Fig. 8)

    ` Development and application of a thermal powercontrol system to control the hot metal pouringspeed in order to avoid any heat overload of theplant by extremely energy-rich scrap mixtures

    The design of the patented coolers requires theapplication of sophisticated calculation programsbecause the temperature profile of the gas and the platesvaries considerably. The coolers are made of differentsized plates which enable the rapid cooling of exhaustedgases. Even during slopping, the large volumes ofgenerated gases can pass the cooler without overheatingthe filter bags. As seen in figure 9, even after 21 2 years ofoperation no major accumulations of dust on the coolerplates can be observed.

    The cooling performance of Sidmar's coolers is depictedin figure 10. The gas temperature trend (red line) shows apeak temperature of 540C at the cooler inlet and atemperature of only 90C at the cooler outlet. The coolersare designed for a maximum outlet temperature of 250Cat a maximum inlet temperature of 750C whichrepresents a cooling performance of 95MW per converter.

    After the off-gas cooling phase the cooler commenceswith a regeneration phase, which means the removal of

    MIL

    LEN

    NIU

    M S

    TEEL

    2007

    28

    qualifying thermal power emissions, by applying highperformance cooling capabilities, integrating thermalpower emission control systems and by reducing the flowresistance in the duct systems. The engineering of thisadvanced design includes the determination of thecontent of combustibles in the scrap, the maximumthermal power emission of a converter (based on theamount of scrap charged, the energy content in the scrap,and the hot metal pouring speed), the required coolingcapabilities as well as the combustion requirements witha controlled hot metal pouring speed. The charging hoodsand duct systems were designed using computationalfluid dynamics (CFD) techniques.

    The first major application was the off-gas systemdesigned and supplied for the BOF plant of Sidmar inGent, [1] Belgium.

    r Fig.8 Sidmar, Gent, Belgium - outside view of coolers

    r Fig.7 3D plant layout of advanced secondary off-gas cleaning system

    MS 01 Into themes(L) 4/22/07 4:12 PM Page 82

  • 29

    MIL

    LEN

    NIU

    M S

    TEEL

    2007

    INTRODUCTORY THEMES

    a

    where double-evacuated charging hoods for twoconverters will be installed and where one cooler will beprovided for both converters (red coloured). The filterplant, fans, stack and the major part of the ductworkremain unchanged. This new system is now underdesign and will boost the cooling capacity by more than100%.

    At voestalpine Stahl the installation of additionalcoolers within the charging ducts of the off-gas systemboosted the cooling capacity by approximately 50%and the evacuation capacity by nearly 100% (referred tothe gas mass flow).

    The improved heat removal efficiency that results byinstalling coolers in conventional steel shop ventilationarrangements are shown in figure 13. Figure 2 has beenenlarged in the ordinate direction with respect to thesuction volume and a parallel scale was included toshow the equivalent cooling capacity in MW. Therespective arrows show the increased cooling capacities

    accumulated heat energy by an air stream suckedthrough the coolers to cool down the plates. As seen infigure 10 the regeneration phase starts when the outlettemperature (blue line) shows a higher value than theinlet temperature. Regeneration takes approximately 25minutes. The air stream sucked through the coolersduring regeneration additionally evacuates fumesescaping during blowing and tapping, eliminating theneed for doghouse doors.

    Figure 11 illustrates the thermal power flow, showingthe distribution of generated power, absorbed powerand passing power as designed for the Sidmar coolingsystem. Scrap charging releases 180MW of thermalpower, of which, the ducts between the hood and thecoolers absorb 22%. The gas temperature duringcharging can rise to 1,000C which results in a largeheat transfer to the cold ducts. The coolers reduce thegas temperature to 250C by removing a further 50%of the input energy, which is absorbed by the coolerplates. The tapping exhaust and roofexhaust are included in the balance(accounting for approximately 25MW).A few further percentages areabsorbed by the filter, so only 30%(approximately 60MW of the totalinput power passes to the stack. Thecorresponding exit-gas temperature isbelow 80C.

    APPLICATIONS IN EXISTINGPLANTSThe described cooler design is not onlyapplicable for new steel plants, but isalso highly suitable for retrofitting toexisting plants. Figure 12 shows thebasic layout of a steel shop in Germany,

    r Fig.10 Inlet and outlet gas-temperature trendswith advanced cooler designr Fig.9 Cooler plates after 2.5 years of operation

    r Fig.11 Thermal power balance of advanced cooler system

    MS 01 Into themes(L) 4/22/07 4:12 PM Page 83

  • MIL

    LEN

    NIU

    M S

    TEEL

    2007

    30

    with the cooler installations for the following plants:` Sidmar (Belgium): +90MW originally installed ` Alchewsk, Ukraine: +75 MW originally installed` Thyssen-Krupp CSA, Brazil: +65MW originally installed` voestalpine Stahl, Linz (Austria): +28MW post

    installation` Steel shop in Germany: +80MW post installation

    The comparison of thermal power versus flow explainsthe amount of air required as a substitute for cooling airif no coolers are applied: 1MW cooling capability ofcoolers substitutes 20,000 m3/h of cooling air for`cooling by mixing` purposes.

    SAFETY ASPECTSWith the described advanced design, enough coolingcapacity is provided so that the plant can operatewithout the need for emergency cooling air flaps whileassuring a high enough air flow through the system toensure safe combustion conditions. With increasingthermal power development the temperature in thesystem rises and the increasing volumes of gas create ahigher pressure drop which results in a reduction of theair mass flow passing through the system. This means areduced oxygen mass flow despite an increasingdemand for oxygen. Due to this fact under-ventilatedsystems are quickly overloaded, not only with respect tothe temperature profile, but also in connection with theconsumption of available oxygen. The gases emitted bythe converter are thus incompletely combusted and theremaining non-combusted gases can lead to potentiallydangerous situations.

    The trend of oxygen consumption can be seen infigure 14 during two weeks of recordings. The red line`stalactites` show the remaining oxygen in the gasdownstream of the charging hood. The content ofoxygen in the air is 21% before charging which drops

    during hot metal chargingaccording to the quantity of oxygenconsumed during combustion. Ifthe remaining oxygen contentdrops to below 10%, the content ofnon-combusted gases (visible onthe `stalactites` line in blue) cango higher than 3%, which is thelowest explosion risk limit. Thecomputer can calculate the actualpower developmentinstantaneously as well as theactual oxygen consumption beforereceiving the O2 analysis results(usually 15 - 20 seconds delaytime). The designed thermal power

    r Fig.12 Basic layout of off-gas cleaning system fora steel plant in Germany

    r Fig.14 Content of remaining oxygen and non-combusted gases in the charging duct

    r Fig.13 Improved thermal cooling capabilities withinstallation of coolers

    MS 01 Into themes(L) 4/22/07 4:12 PM Page 84

  • INTRODUCTORY THEMES

    removal by the off-gas system is the set point forcontrolling the hot metal pouring speed (reduced orinterrupted). This means that a total consumption ofthe available combustion oxygen can be avoided withthis type of control.

    SUMMARYWith the application of absorption coolers in secondaryoff-gas cleaning systems the following advantages canbe achieved:Operational and safety benefits` Higher gas throughput due to a low gas temperature

    profile downstream of the plate-type cooler` Emergency cooling air is not required, meaning that

    the high gas flow will not be diminished by theopening of a cooling air flap

    ` Reduced fume emissions at the charging hood` No spark arrestors are required (hot particles are

    cooled to harmless temperatures by the coolers)` In combination with the charging power control

    system there is no risk to operate at under-stoichiometric combustion conditions and no risk ofexplosion

    Commercial benefitsShorter pouring times result, on average, because a highpouring speed can be applied which is controlled by thecontrol system. With less contaminated scrap fasterpouring speeds can be used, resulting in shorter pouringtimes of 40 seconds or less. This allows more heats to beproduced on a daily basis. Cheaper scrap, usually with ahigher content of impurities, can be charged to theconverter without risk of overloading the system. Theevacuation capacity and cooling performance ofexisting systems can be increased at relatively lowinvestment costs.

    REFERENCES[1] L. Pieters, Secondary Dedusting of the LD (BOF)Converters at Arcelor Gent, IS 06 Iron and steelConference, Linz, Austria, October 2006.

    Alfred R. Hampel is Senior Expert, EnvironmentalEngineering with Siemens VAI Metals TechnologiesGmbH & Co (Siemens VAI), Linz, Austria

    CONTACT: [email protected]

    MS 01 Into themes(L) 4/22/07 4:12 PM Page 85

    /ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 300 /GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 300 /GrayImageDepth -1 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 1200 /MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 1200 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile () /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False

    /Description > /Namespace [ (Adobe) (Common) (1.0) ] /OtherNamespaces [ > /FormElements false /GenerateStructure false /IncludeBookmarks false /IncludeHyperlinks false /IncludeInteractive false /IncludeLayers false /IncludeProfiles false /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe) (CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector /DocumentCMYK /PreserveEditing true /UntaggedCMYKHandling /LeaveUntagged /UntaggedRGBHandling /UseDocumentProfile /UseDocumentBleed false >> ]>> setdistillerparams> setpagedevice