Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1 | Powering the Central West Forum October 2014
Powering the Central West Forum
TransGrid
October 2014
2 | Powering the Central West Forum October 2014
Contents
1. TransGrid overview
2. Unlocking our planning process
3. Regional projects – completed and upcoming
4. Engaging you in the energy conversation
5. Q&A session
3 | Powering the Central West Forum October 2014
TransGrid overview Greg Garvin, General Manager Strategy
and Stakeholder Engagement
1. Our role in the electricity chain
2. Our reliability standards
3. Cost to consumers
4 | Powering the Central West Forum October 2014
TransGrid’s role in electricity supply
> 13,000 km high voltage transmission lines
> 47 km of underground cables
> 97 substations
> 89 radio towers
> 1,200 km of optical fibre
> Supplying electricity to:
• 7 million residents
• 30,000 businesses
• 20 network customers
> Connection to Qld and Vic
5 | Powering the Central West Forum October 2014
Where do we fit in the electricity chain?
6 | Powering the Central West Forum October 2014
You can rely on us
Reliability standards are set by the NSW Government
National Electricity Regulator (NER) sets processes for developing
networks and minimum performance requirements
TransGrid is expected to plan and develop our transmission network
on an “n–1” basis.
TransGrid’s current reliability level is
xx.xx%
7 | Powering the Central West Forum October 2014
The cost to consumers
11%
34%20%
21%
Transmission
Distributors
Generators
Retailers
*Correct as at end of July 2014, without a
carbon price.
The breakdown of an average electricity bill:
8 | Powering the Central West Forum October 2014
Our planning processGordon Burbidge,
Consultations Manager
1. Demand forecasts
2. How we plan the network
3. Demand management
9 | Powering the Central West Forum October 2014
A changing environment for load growth
10 | Powering the Central West Forum October 2014
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Max
imu
m D
em
and
(M
W)
Summer Winter
11 | Powering the Central West Forum October 2014
Current forecast
12 | Powering the Central West Forum October 2014
Forecast for your region – Central West
0
20
40
60
80
100
120
140
160
Maxim
um
Dem
an
d (
MW
)
Bathurst / Orange Area (excl. Cadia Mine) Summer Maximum Demands
Actual Corrected Actual Diversified Forecast
13 | Powering the Central West Forum October 2014
Forecast for your region – Central West
0
20
40
60
80
100
120
140
160
180
Win
ter
Maxim
um
Dem
an
d (
MW
)
Bathurst / Orange Area (excl. Cadia) Winter Maximum Demands
Actual Diversified Forecast
14 | Powering the Central West Forum October 2014
How we plan the network
Review of need drivers to inform decisions
Typically when updated forecast become available
Less frequently other factors such as changes to
Generation
Capability and performance of the existing network
15 | Powering the Central West Forum October 2014
A shift in focus for capital works
16 | Powering the Central West Forum October 2014
Demand Management – Our commitment
TransGrid is committed to delivering cost-effective non-network
options
These options can defer or avoid investment in the electricity
transmission network, delivering benefits to consumers.
Investment in innovation is crucial in order to unlock the full potential
of demand management in NSW.
TransGrid is proposing to invest $18 million in demand management
innovation from 2014 to 2019.
17 | Powering the Central West Forum October 2014
Upcoming ProjectsSachin Singh, Acting Central
Regional Manager
1. Transmission Annual Planning Report 2014 overview
2. Completed works
3. Committed works
18 | Powering the Central West Forum October 2014
Transmission Annual Planning Report
The Transmission Annual Planning Report is a key output from
the NSW Annual Planning Review, the central vehicle by which
TransGrid provides an assessment of the capabilities and
constraints of our network for the upcoming 10 year period.
The 2014 Transmission Annual Planning Report includes:
outcomes of the annual planning review including planning analysis
of network capabilities and constraints, and potential solutions within a
10 year planning horizon;
completed, committed and planned projects;
energy and demand forecasts;
network replacement projects; and
opportunities to collaborate with providers of non-network solutions.
19 | Powering the Central West Forum October 2014
Recently completed works
20 | Powering the Central West Forum October 2014
Committed works
> Orange substation – 66kV rebuild 2015-16
> Beryl substation – Essential Energy new Substation
connections and upgrades
> Molong substation – Essential Energy additional
transformer bay
> Panorama substation – Oil containment and capacitor
banks
> Central West Optic Fibre Ground wire upgrade – upgrade
of communications (2015-19)
21 | Powering the Central West Forum October 2014
Projects under review
> Line 944 Wallerawang to Orange North – currently
reviewing options to rebuild or other
> Beryl – Mudgee area support – capacitive capacity
> Minor asset replacements at a number of sites
22 | Powering the Central West Forum October 2014
Engaging you in the energy ConversationLaura Stewart, Community Relations
Manager
1. Our new engagement approach
2. Have your say
23 | Powering the Central West Forum October 2014
What the public have been saying...
24 | Powering the Central West Forum October 2014
Responding to change
Established a new, comprehensive consumer engagement program –
giving consumers a voice in developing TransGrid’s plans
Opening up the planning process
Conversations with the community will start in the early planning
stages
Our new process is based on meaningful, open and honest
engagement, focusing on:
Listening to feedback
Incorporating and addressing stakeholder views
Responding to and acting upon stakeholder feedback
25 | Powering the Central West Forum October 2014
Four-stage engagement process
26 | Powering the Central West Forum October 2014
Q&A
27 | Powering the Central West Forum October 2014
Confidentiality
The information contained in
this Presentation is confidential
information and should not be
disclosed without TransGrid’s
written permission. Please treat
it accordingly and do not forward,
republish or permit unauthorised
access.
Disclaimer
Although TransGrid has made every effort to ensure the accuracy of
the information, it does not give any warranty or representation as to
the accuracy, reliability or completeness of the information. To the extent
permitted by law, TransGrid and its respective employees, officers and
contractors shall not be liable for any loss or damage arising in any way,
including by way of negligence, from or in connection with any information
provided or omitted or from anyone acting or refraining to act in reliance on
this information.