Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Electricity Safety Amendment (Bushfire Mitigation Civil Penalties Scheme)
Bill 2017
Powercor S120P Annual Compliance Report As at 30 April 2018
2
Document Information In the event of any inquiries with respect to this document, please contact
Bushfire Mitigation Powercor Australia Ltd 40 Market Street Melbourne 3000 Ph. (03) 9683-4747
Approval
3
1 Works carried out during the reporting period .................................................................................................4
1.1 REFCL program status [S120P(1)(a)(i)] ..............................................................................................................5
1.2 ELCA program status [S120P(1)(a)(ii)] ............................................................................................................ 19
1.3 SWER ACR program status [S120P(1)(a)(iii)] .................................................................................................. 20
2 Plans of works to be carried out during the next reporting period ............................................................... 28
2.1 REFCL program status [S120P(1)(c)(i)] ........................................................................................................... 29
2.2 ELCA program status [S120P(1)(c)(ii)] ............................................................................................................ 43
2.3 SWER ACR program status [S120P(1)(c)(iii)] .................................................................................................. 44
Version History
Revision Date Comment
1.0 1 June 2018 Submission to PAL/CP Board for approval
2.0 1 August 2018 Submission of Board approved report to ESV
3.0 13 August 2018 Minor amendments to address ESV feedback
Contents
4
1 Works carried out during the reporting period
17 to 30 April 2018
5
This section provides details of works carried out during the reporting period (1 May 2017 to 30 April 2018).
1.1 REFCL program status [S120P(1)(a)(i)]
1.1.1 Gisborne (GSB)
GSB REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 25/02/2016
100% 5%
Business Case approval 25/02/2016
Design Design commenced 26/02/2016
100% 20%
Design complete 6/06/2016
Procurement
Number of REFCL units required 1
REFCL order placed 17/03/2016 100% 15%
REFCL delivered to site 15/08/2016
Construction - Lines Line works commenced 26/02/2016
100% 25%
Line works complete 30/09/2016
Construction - Stations
Station works commenced 19/05/2016 100% 15%
Station works complete 12/04/2017
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 12/09/2016 100% 10%
REFCL commissioned and operable 23/09/2016
Close Out REFCL at "required capacity"
0% 10%
Total weighted percentage complete 90%
The zone substation is located at -37.45355146, 144.57636595 (latitude, longitude)
6
1.1.2 Woodend (WND)
WND REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 25/02/2016
100% 5% Business Case approval 25/02/2016
Design Design commenced 26/02/2016
100% 20% Design complete 6/06/2016
Procurement
Number of REFCL units required 2
REFCL order placed 17/03/2016 100% 15%
REFCL delivered to site 15/08/2016
Construction - Lines Line works commenced 26/02/2016
100% 25% Line works complete 30/05/2017
Construction - Stations
Station works commenced 12/05/2016 100% 15%
Station works complete 12/04/2017
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 15/12/2016 100% 10%
REFCL commissioned and operable 31/10/2017
Close Out REFCL at "required capacity"
0% 10%
Total weighted percentage complete 90%
This zone substation is located at -37.33449073, 144.51778650 (latitude, longitude)
7
1.1.3 Camperdown (CDN)
CDN REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5%
Business Case approval 13/07/2016
Design Design commenced 1/08/2016
100% 20% Design complete 11/01/2018
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 100% 15%
REFCL delivered to site 4/11/2017
Construction - Lines Line works commenced 9/01/2017
80% 25%
Line works complete
Construction - Stations
Station works commenced 30/05/2017 100% 15%
Station works complete 23/04/2018
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity" 0% 10%
Total weighted percentage complete 75%
This zone substation is located at -38.22702204, 143.15481663 (latitude, longitude)
8
1.1.4 Castlemaine (CMN)
CMN REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/08/2016
80% 15% Design complete
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site
Construction - Lines Line works commenced 24/06/2017
80% 20% Line works complete
Construction - Stations
Station works commenced 30/05/2017 70% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 7/02/2018 30% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 59%
This zone substation is located at -37.07236807, 144.20669317 (latitude, longitude)
9
1.1.5 Maryborough (MRO)
MRO REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/12/2016
83% 20% Design complete
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 100% 15%
REFCL delivered to site 14/12/2017
Construction - Lines Line works commenced 22/01/2018
45% 25% Line works complete
Construction - Stations
Station works commenced 22/01/2018 40% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 10%
Total weighted percentage complete 54%
This zone substation is located at -37.04952584, 143.75473022 (latitude, longitude)
10
1.1.6 Colac (CLC)
CLC REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 7/11/2016
60% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site
Construction - Lines Line works commenced 12/04/2017
50% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 6
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 34%
This zone substation is located at -38.34056225, 143.60615730 (latitude, longitude)
11
1.1.7 Winchelsea (WIN)
WIN REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/12/2016
87% 20% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 15%
REFCL delivered to site
Construction - Lines Line works commenced 12/04/2017
35% 25% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 10%
Total weighted percentage complete 45%
This zone substation is located at -38.23622505, 144.00288820 (latitude, longitude)
12
1.1.8 Eaglehawk (EHK)
EHK REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 6/02/2018
100% 5% Business Case approval 10/03/2017
Design Design commenced 27/11/2017
80% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 8
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 27%
This zone substation is located at -36.73592644, 144.27855492 (latitude, longitude)
13
1.1.9 Ballarat North (BAN)
BAN REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 3
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 9
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -37.53477699, 143.84742737 (latitude, longitude)
14
1.1.10 Charlton (CTN)
CTN REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 1
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.27399871, 143.36318135 (latitude, longitude)
15
1.1.11 Ballarat South (BAS)
BAS REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 3
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 5
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -37.57505901, 143.82751465 (latitude, longitude)
16
1.1.12 Bendigo Terminal Station (BETS)
BETS REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.78490276, 144.25368547 (latitude, longitude)
17
1.1.13 Bendigo (BGO)
BGO REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 2
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.77055176, 144.27696705 (latitude, longitude)
18
1.1.14 Geelong (GL)
GL REFCL Project Activities Completion
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced
0% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 1
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -38.12868286, 144.34043884 (latitude, longitude)
19
1.2 ELCA program status [S120P(1)(a)(ii)]
Total Electric Line Volumes At 1 May 2017 At 30 April 2018 Progress over Reporting Period
Bare conductor in ELCA Route km Route km Percentage Route km Single Phase HV bare conductor 480.03 475.24 -1% -4.79
Multi Phase HV bare conductor 491.85 487.25 -1% -4.60
SWER HV bare conductor 585.58 524.6 -10% -60.98
Covered / underground conductor in ELCA Route km Route km Percentage Route km Single Phase HV conductor 3.85 3.85 0% 0
Multi Phase HV conductor 96.94 120.05 +24% 23.11
SWER HV conductor 129.35 218.13 +69% 88.78
Supplying Substation
(System Normal) Feeder Reason for Construction
Previous Construction New Construction
Completion Date Type Phasing
Length (Route
km) Type Phasing
Length (Route
km) Winchelsea WIN011 New Electric line n/a n/a 0 Underground Cable Polyphase 0.9 11/11/2017
Bendigo Terminal Station BET004 New Electric line n/a n/a 0 Underground Cable Polyphase 0.2 14/11/2017
Eaglehawk EHK24 New Electric line n/a n/a 0 Underground Cable Polyphase 1.3 14/09/2017
Bendigo Terminal Station BET001 Augmented for load Bare Conductor SWER 0.2 Underground Cable Polyphase 0.2 13/10/2017
Woodend WND024 Proactive replacement/direction Bare Conductor SWER 38.8 Underground Cable SWER 48.0 30/06/2017
Castlemaine CMN003 Proactive replacement/direction Bare Conductor SWER 14.3 Underground Cable SWER 19.3 30/08/2017
Castlemaine CMN004 Proactive replacement/direction Bare Conductor SWER 18.7 Underground Cable SWER 21.5 30/08/2017
Winchelsea WIN011 Proactive replacement/direction Bare Conductor Polyphase 9.3 Underground Cable Polyphase 20.5 30/06/2017
20
1.3 SWER ACR program status [S120P(1)(a)(iii)]
Over the reporting period Powercor has installed 256 Automatic Circuit Reclosers (ACR) in relation to Single Wire Earth Return (SWER) lines. Details are provided in the following table.
ACR NAME FEEDER COMPLETION DATE
CENTRE SPUR RD P8 ACR CDN001 22/08/2017
KYUNA NTH P2 FUSE SAVER TRG002 3/10/2017
KYUNA P17 FUSE SAVER TRG002 4/10/2017
ALHAMBRI P2 SWER ACR FS CLC003 1/11/2017
NORTH CUNDARE P11 SWER ACR FS CLC003 1/11/2017
SMART P14 SWER ACR FS CLC003 6/11/2017
SHELFORD P112 SWER ACR FS WIN013 8/11/2017
SHELLEY P3 SWER ACR FS WIN013 9/11/2017
JEFFCOTT P3 SWER ACR FS CTN006 14/11/2017
DONALD SOUTH EAST P5 SWER ACR FS CTN006 15/11/2017
TUENA P14 SWER ACR FS ART033 16/11/2017
ROLLOS RD P1 SWER ACR FS WBL012 17/11/2017
YEO P28 SWER ACR FS CLC007 19/11/2017
PEARDON P11 SWER ACR FS CLC007 19/11/2017
MELVILLE P1 SWER ACR FS CLC006 20/11/2017
BANYENA P8 SWER ACR FS CTN006 21/11/2017
NORMANVILLE P3 SWER ACR FS KGT004 21/11/2017
QUAMBATOOK ROAD P2 SWER ACR FS KGT004 21/11/2017
LEEDER P1 SWER ACR FS CTN006 22/11/2017
GILMORE P1 SWER ACR FS CTN006 22/11/2017
FENTONS CREEK P40A SWER ACR FS CTN002 23/11/2017
YEUNGROON P1 SWER ACR FS CTN006 23/11/2017
STONYHURST RD P5A SWER ACR FS CLC003 24/11/2017
CROFTON PARK P1 SWER ACR FS CTN006 24/11/2017
BULOKE P1 SWER ACR FS CTN006 24/11/2017
BRIDGEWATER P1 SWER ACR FS EHK024 24/11/2017
CHARLTON WEST P1 SWER ACR FS CTN006 24/11/2017
MINMINDIE P28A SWER ACR FS CTN002 25/11/2017
UPPER GELLIBRAND P2A SWER ACR FS CLC007 25/11/2017
21
SEDGWICK P20 SWER ACR FS BET007 28/11/2017
LITCHFIELD SOUTH P3 SWER ACR FS CTN006 28/11/2017
JUNCTION P2 SWER ACR FS CTN002 28/11/2017
KNOWSLEY P1 SWER ACR FS BGO023 29/11/2017
SEDGWICK NORTH P5 SWER ACR FS BET007 29/11/2017
WINJALLOCK P18 SWER ACR FS CTN006 29/11/2017
CADSON P1 SWER ACR FS. CTN002 29/11/2017
YEUNGROON EAST P1 SWER ACR FS. CTN002 29/11/2017
ROCKY POINT P3 SWER ACR FS ART033 29/11/2017
CATHCART P14 SWER ACR FS ART033 29/11/2017
DERRINAL TIE LINE P1 SWER ACR FS BGO023 30/11/2017
MT CAMEL P1 SWER ACR FS BGO023 30/11/2017
BURRUMBITE P4A SWER ACR FS CTN006 30/11/2017
GOOROC P1A SWER ACR FS CTN006 30/11/2017
RICHMOND PLAINS P2 SWER ACR FS CTN002 30/11/2017
HATELY P1A SWER ACR FS ART033 30/11/2017
ROE PARK P30A SWER ACR FS KYM003 30/11/2017
CROUCH P5 SWER ACR FS ART033 1/12/2017
LITCHFIELD P117 SWER ACR FS CTN006 2/12/2017
ACKERLY P2 SWER ACR FS CLC006 4/12/2017
BARONGAROOK WEST P11 SWER ACR FS CLC006 4/12/2017
TEDDYWADDY WEST P2 SWER ACR FS CTN003 4/12/2017
GREENS LAKE P81 SWER ACR FS KYM001 4/12/2017
SWANWATER P108 SWER ACR FS CTN006 5/12/2017
NULLAWIL SOUTH P12 SWER ACR FS CTN003 5/12/2017
ELVYNWOOD P9A SWER ACR FS CTN003 5/12/2017
KEELY P10 SWER ACR FS CHA003 5/12/2017
HADDON P9 SWER ACR FS CHA005 5/12/2017
BULLARD P6 SWER ACR FS ART033 5/12/2017
BERRIMAL NORTH P1 SWER ACR FS CTN006 6/12/2017
COSTERFIELD P136 SWER ACR FS BGO023 6/12/2017
CARAMWYNNE P1 SWER ACR FS ART033 6/12/2017
CAL P5A SWER ACR FS ART033 6/12/2017
WERCHON P1 SWER ACR FS ART033 6/12/2017
BUNINJON P1 SWER ACR FS ART033 6/12/2017
SMITH SPUR P1 SWER ACR FS CHA006 6/12/2017
KNOWSLEY SOUTH P12 SWER ACR FS BGO023 7/12/2017
22
TRAYNORS P19 SWER ACR FS CTN006 7/12/2017
SUMMERHAYES P20A SWER ACR FS CTN003 7/12/2017
STREATHAM P250A SWER ACR FS ART033 7/12/2017
BARWON P12A SWER ACR FS CLC007 8/12/2017
GLENORCHY SOUTH P2 SWER ACR FS STL006 8/12/2017
SWINTON P2 SWER ACR FS STL006 8/12/2017
TRAM P1 SWER ACR FS CTN003 9/12/2017
KALPIENUNG P20 SWER ACR FS CTN003 9/12/2017
BURRUM NORTH P1 SWER ACR FS STL006 9/12/2017
SWAN MARSH P17 SWER ACR FS CLC006 10/12/2017
MARNOO TOWN P11 SWER ACR FS STL006 10/12/2017
COURT P2 SWER ACR FS STL006 10/12/2017
MASSEY EAST P4 SWER ACR FS CTN006 11/12/2017
YARRON P1 SWER ACR FS ART033 11/12/2017
GLEESON P1 SWER ACR FS ART033 11/12/2017
MEAD SOUTH P1 SWER ACR FS CHA006 11/12/2017
BIGGINS P38 SWER ACR FS ART033 12/12/2017
CANAL P1 SWER ACR FS CTN003 12/12/2017
PACKER P1 SWER ACR FS CTN003 12/12/2017
MORTON PLAINS P3 SWER ACR FS CTN001 12/12/2017
WICKLIFFE P1 SWER ACR FS ART033 13/12/2017
PARKER P1 SWER ACR FS CTN003 13/12/2017
QUAMBATOOK SOUTH P14 SWER ACR FS CTN003 13/12/2017
ROONGA P4A SWER ACR FS ART033 14/12/2017
MALIN P21 SWER ACR FS ART033 14/12/2017
TUXION P12 SWER ACR FS CLC007 14/12/2017
NARRAPORT EAST P4 SWER ACR FS CTN001 14/12/2017
HOREFIELD STH P10 SWER ACR FS CHA006 14/12/2017
CROSBIE P1 SWER ACR FS CTN001 14/12/2017
BOX SWAMP P1 SWER ACR FS CTN001 14/12/2017
MINCHA P12 SWER ACR FS CHA006 14/12/2017
WERNETH P18A SWER ACR FS CLC003 15/12/2017
STAVEAST P14 SWER ACR FS ART033 15/12/2017
PHILLIPS P1 SWER ACR FS KGT003 15/12/2017
KELLY P1 SWER ACR FS CTN003 15/12/2017
MINYIP SOUTH WEST P2 SWER ACR FS STL006 15/12/2017
CARRS PLAINS P4 SWER ACR FS STL006 15/12/2017
23
BANYENA P1 SWER ACR FS STL006 15/12/2017
MACORNA WEST P4 SWER ACR FS CHA006 15/12/2017
MACORNA P35 SWER ACR FS CHA006 15/12/2017
CONSTABLE P1 SWER ACR FS CTN001 15/12/2017
BARRYS RD P2 SWER ACR FS CLC006 16/12/2017
LINTSOUTH P2 SWER ACR FS BAS021 16/12/2017
COOPER P3 SWER ACR FS STL006 16/12/2017
DONALD RD P29 SWER ACR FS STL006 16/12/2017
SKIPNORTH P10 SWER ACR FS BAS021 16/12/2017
ROCHESTER QUARRY P9 SWER ACR FS KYM001 16/12/2017
TYRELL P2 SWER ACR FS CLC007 17/12/2017
CALLWADDA P42 SWER ACR FS STL006 17/12/2017
CALLAWADDA EAST P7 SWER ACR FS STL006 17/12/2017
DORANSOUTH P12A SWER ACR FS BAS022 17/12/2017
DUNNE P2 SWER ACR FS BAS022 17/12/2017
LAL LAL P6 SWER ACR FS BAS022 17/12/2017
YANDO NORTH P1 SWER ACR FS CTN002 18/12/2017
MALAKOFF P5 SWER ACR FS STL007 18/12/2017
GLADFIELD PARK P11 SWER ACR FS CHA006 18/12/2017
LINDON P2 SWER ACR FS CLC003 19/12/2017
LALBERT WEST P1 SWER ACR FS CTN003 19/12/2017
LODDON RIVER P89 SWER ACR FS KGT004 19/12/2017
ROKEWOOD P1 SWER ACR FS BAS021 19/12/2017
THALIA P3 SWER ACR FS CTN001 19/12/2017
BUNGULUKE P1 SWER ACR FS CTN001 19/12/2017
COROP WEST P1 SWER ACR FS KYM001 (SHP021) 19/12/2017
GREENHILL P15 ISO BAS023 20/12/2017
KINIMAKATKA P1 ACR NHL015 20/12/2017
SANDY LANE P3 SWER ACR FS CLC003 20/12/2017
BERRINGA SOUTH P19 SWER ACR FS BAS021 21/12/2017
CHARLTON EAST P1 SWER ACR FS CTN001 21/12/2017
BALLAPUR P1 SWER ACR FS CTN001 21/12/2017
MCGRATHS RD P25 SWER ACR FS CTN001 21/12/2017
O'DONOGHUE P2 SWER ACR FS EHK024 3/01/2018
TCHAM LAKES NORTH P1 SWER ACR FS CTN001 3/01/2018
TCHAM LAKES SOUTH P1 SWER ACR FS CTN001 3/01/2018
DONALD RD P1 ACR STL006 3/01/2018
24
NEILBOROUGH EAST P6 SWER ACR FS EHK024 4/01/2018
WARMUR P33 SWER ACR FS CTN001 4/01/2018
WARMUR P1 SWER ACR CTN001 4/01/2018
MERAN P4 SWER ACR FS KGT004 5/01/2018
GLENLOTH P17 SWER ACR FS CTN003 5/01/2018
YENDOLLOCK P2 SWER ACR FS ART033 8/01/2018
KALANOWA P1 SWER ACR FS ART033 8/01/2018
MARNOO P15 SWER ACR FS STL006 9/01/2018
LANCASTER P6 SWER ACR FS KGT003 10/01/2018
CURYO EAST P1 SWER ACR FS CTN001 10/01/2018
CURYO WEST P1 SWER ACR FS CTN001 10/01/2018
DONALD P238 SWER ACR FS CTN006 11/01/2018
MILNES BRIDGE P14A SWER ACR FS KGT003 12/01/2018
HEEL P2 SWER ACR FS KGT003 12/01/2018
THALIA SOUTH P3 SWER ACR FS CTN001 12/01/2018
SHANROAD P1 SWER ACR FS BMH003 12/01/2018
HAVELOCK P24 SWER ACR FS MRO005 12/01/2018
SKELTON P10 SWER ACR FS BAS023 12/01/2018
KOFOED P3 SWER ACR FS BET007 16/01/2018
WOOROONOOK SOUTH P1 SWER ACR FS CTN006 16/01/2018
WOOROONOOK NORTH P1 SWER ACR FS CTN006 16/01/2018
KERANG EAST P6 SWER ACR FS KGT003 16/01/2018
BOIGBEAT EAST P1 SWER ACR FS CTN003 17/01/2018
GREDGWIN P17A SWER ACR FS CTN002 17/01/2018
BARRAPORT P2 ACR CTN002 17/01/2018
CAMPBELLS CREEK P2 SWER ACR FS CTN004 17/01/2018
KOOREH EAST P2 SWER ACR FS CTN004 17/01/2018
WALLINDUC P1 SWER ACR FS BAS021 17/01/2018
MOSVALE P4 SWER ACR FS ART031 17/01/2018
CHAMPION P3E SWER ACR FS ART031 17/01/2018
PIAVELLA P2 SWER ACR FS EHK024 17/01/2018
DWIGHT P1 SWER ACR FS CTN004 18/01/2018
FREEMAN P1 SWER ACR FS CTN004 18/01/2018
BALLARD P1 SWER ACR FS CHA003 18/01/2018
CULGOA WEST P8 SWER ACR FS CTN003 19/01/2018
EMU P11 SWER ACR FS MRO005 19/01/2018
MOUNTWILL P68A SWER ACR FS ART033 22/01/2018
25
KOROOP P1 SWER ACR FS CHA006 22/01/2018
FRONTAGE P4A SWER ACR FS KGT003 23/01/2018
HULL P1 SWER ACR FS STL005 23/01/2018
GLENLOFTY P2A SWER ACR FS ART023 24/01/2018
BURRUM P12A ACR STL006 24/01/2018
GOODBUN P1 SWER ACR FS KGT003 25/01/2018
GOORNONG NORTH P1 SWER ACR FS KYM001 25/01/2018
FAWCETT P1 SWER ACR FS CHA006 25/01/2018
DURHAM OX P126A SWER ACR FS CHA006 25/01/2018
BEN NEVIS P18 SWER ACR FS ART023 30/01/2018
BOORT P319 SWER ACR FS CTN002 30/01/2018
SALISBURY WEST P11 SWER ACR FS EHK024 30/01/2018
MINMINDIE P9 SWER ACR FS CTN002 31/01/2018
DURHAM OX P79 SWER ACR FS CHA006 31/01/2018
QUAMBATOOK P89 SWER ACR FS CTN003 31/01/2018
MURRABIT P93A SWER ACR FS KGT003 1/02/2018
MITIAMO EAST P6 SWER ACR FS CHA006 1/02/2018
TIMOR WEST P6A SWER ACR FS MRO005 2/02/2018
GERANGAMETE P10 SWER ACR FS CLC007 5/02/2018
HORDERN VALE P61A ACR CLC006 6/02/2018
KINYPANIAL P1 SWER ACR FS CTN002 6/02/2018
SNAKE P9 SWER ACR FS KGT003 6/02/2018
BUDGERUM WEST P4 SWER ACR FS CTN003 7/02/2018
BAEL BAEL NORTH P2 SWER ACR FS KGT004 7/02/2018
JAMES P7A SWER ACR FS MRO005 7/02/2018
KERRY P3 SWER ACR FS BET007 9/02/2018
CAPELS P1 SWER ACR FS KGT003 9/02/2018
FRASER P3 SWER ACR FS CTN001 9/02/2018
BURRUM SILO P38 SWER ACR FS STL006 12/02/2018
TULOONA P3 SWER ACR FS HSM004 12/02/2018
LODDON RIVER P5A SWER ACR FS KGT004 13/02/2018
WARRANOOKE P4 SWER ACR FS STL006 13/02/2018
BERRIWILLOCK SOUTH P12 SWER ACR FS CTN003 14/02/2018
LAEN NORTH P1 SWER ACR FS STL006 14/02/2018
LAEN SOUTH SWER ACR FS STL006 14/02/2018
LAEN P69 SWER ACR FS STL006 14/02/2018
CULGOA EAST P9 SWER ACR FS CTN003 15/02/2018
26
PERNS LANE P6 SWER ACR FS HSM002 16/02/2018
RUNNYMEDE P1 SWER ACR FS KYM001 16/02/2018
BERRI EAST P4 SWER ACR FS CTN003 18/02/2018
CHERRY P5 SWER ACR FS CTN001 19/02/2018
RABIT P138 SWER ACR FS KGT003 20/02/2018
WIMMERA PARK P1A SWER ACR FS STL006 20/02/2018
BARTON P1 SWER ACR FS ART033 21/02/2018
LODDON RIVER P24 SWER ACR FS KGT004 21/02/2018
WATCHEM WEST P10 SWER ACR FS CTN001 22/02/2018
STUART MILL P68 SWER ACR FS MRO005 22/02/2018
HODGSON P1 SWER ACR FS CTN003 26/02/2018
HOMEWOOD P23 SWER ACR FS CTN003 26/02/2018
WITCHIPOOL P1 SWER ACR FS CTN006 28/02/2018
MEERING WEST P2 SWER ACR FS KGT004 28/02/2018
YARRAWALLA SOUTH P5A SWER ACR FS CHA006 28/02/2018
KOROOP WEST P4E SWER ACR FS KGT003 2/03/2018
GEEROAD P7 SWER ACR FS BAS021 2/03/2018
CLIFTON ESTATE P2 SWER ACR FS CTN003 2/03/2018
WYCHEPROOF P450A ACR CTN003 2/03/2018
MOLOGA P1 SWER ACR FS CHA006 5/03/2018
CARAPOOEE P36 SWER ACR FS CTN004 7/03/2018
BENJEROOP P9 SWER ACR FS KGT003 7/03/2018
CARWARDINE RD P1 SWER ACR FS CHA006 7/03/2018
DOBOOBETIC P8A SWER ACR FS CTN006 8/03/2018
JOEL MARTIN P5A SWER ACR FS STL007 8/03/2018
SEA LAKE SOUTH P16 SWER ACR FS CTN003 8/03/2018
MT HOOGHLY P8 SWER ACR FS MRO005 9/03/2018
WILLAURA P240 SWER ACR FS ART033 9/03/2018
GLENORCHY P387 SWER ACR FS STL006 9/03/2018
MURRABIT WEST P1 SWER ACR KGT003 14/03/2018
APPIN SOUTH P1 SWER ACR FS KGT004 16/03/2018
DURHAM OX P35 SWER ACR FS CHA006 20/03/2018
KAMAROOKA P50 SWER ACR FS EHK024 22/03/2018
REMOVED WARE P2 ACR, CONVERT SWER LINE TO POLYPHASE CLC006 26/03/2018
BORUNG P81 SWER ACR FS CTN001 28/03/2018
WILLOWVALE P1 SWER ACR FS BAS021 29/03/2018
WETTENHALL P1 SWER ACR FS & BAS021 29/03/2018
27
HUNTER SOUTH P21A SWER ACR FS KYM001 29/03/2018
HAM P1 SWER ACR FS KYM001 29/03/2018
PARD P3 SWER ACR FS KGT003 10/04/2018
WANGANIP P2 ACR ART033 11/04/2018
GLENTHOMPSON P122 SWER ACR FS ART033 11/04/2018
28
2 Plans of works to be carried out during the next reporting period
29
This section provides details of works planned to be carried out during the reporting period (1 May 2018 to 30 April 2019).
Percentage Complete is the actual percentage complete as at 30 April 2018.
2.1 REFCL program status [S120P(1)(c)(i)]
2.1.1 Gisborne (GSB)
GSB REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 25/02/2016
100% 5%
Business Case approval 25/02/2016
Design Design commenced 26/02/2016
100% 20%
Design complete 6/06/2016
Procurement
Number of REFCL units required 1
REFCL order placed 17/03/2016 100% 15%
REFCL delivered to site 15/08/2016
Construction - Lines Line works commenced 26/02/2016
100% 25% Line works complete 30/09/2016
Construction - Stations
Station works commenced 19/05/2016 100% 15%
Station works complete 12/04/2017
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 12/09/2016 100% 10%
REFCL commissioned and operable 23/09/2016
Close Out REFCL at "required capacity" 30/05/2018 0% 10%
Total weighted percentage complete 90%
The zone substation is located at -37.45355146, 144.57636595 (latitude, longitude)
30
2.1.2 Woodend (WND)
WND REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 25/02/2016
100% 5% Business Case approval 25/02/2016
Design Design commenced 26/02/2016
100% 20% Design complete 6/06/2016
Procurement
Number of REFCL units required 2
REFCL order placed 17/03/2016 100% 15%
REFCL delivered to site 15/08/2016
Construction - Lines Line works commenced 26/02/2016
100% 25% Line works complete 30/05/2017
Construction - Stations
Station works commenced 12/05/2016 100% 15%
Station works complete 12/04/2017
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 15/12/2016 100% 10%
REFCL commissioned and operable 31/10/2017
Close Out REFCL at "required capacity" 30/06/2018 0% 10%
Total weighted percentage complete 90%
This zone substation is located at -37.33449073, 144.51778650 (latitude, longitude)
31
2.1.3 Camperdown (CDN)
CDN REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/08/2016
100% 20% Design complete 11/01/2018
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 100% 15%
REFCL delivered to site 4/11/2017
Construction - Lines Line works commenced 9/01/2017
80% 25% Line works complete 7/05/2018
Construction - Stations
Station works commenced 30/05/2017 100% 15%
Station works complete 23/04/2018
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 20/05/2018 0% 10%
REFCL commissioned and operable 15/06/2018
Close Out REFCL at "required capacity" 23/09/2018 0% 10%
Total weighted percentage complete 75%
This zone substation is located at -38.22702204, 143.15481663 (latitude, longitude)
32
2.1.4 Castlemaine (CMN)
CMN REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/08/2016
80% 15% Design complete 28/06/2018
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site 18/05/2018
Construction - Lines Line works commenced 24/06/2017
80% 20% Line works complete 27/08/2018
Construction - Stations
Station works commenced 30/05/2017 70% 15%
Station works complete 11/09/2018
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 7/02/2018 30% 20%
HV customer works complete 30/09/2018
Testing / Commissioning
REFCL testing / commissioning commenced 2/10/2018 0% 10%
REFCL commissioned and operable 29/10/2018
Close Out REFCL at "required capacity" 5/02/2019 0% 5%
Total weighted percentage complete 59%
This zone substation is located at -37.07236807, 144.20669317 (latitude, longitude)
33
2.1.5 Maryborough (MRO)
MRO REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/12/2016
83% 20% Design complete 23/05/2018
Procurement
Number of REFCL units required 1
REFCL order placed 24/03/2017 100% 15%
REFCL delivered to site 14/12/2017
Construction - Lines Line works commenced 22/01/2018
45% 25% Line works complete 18/05/2018
Construction - Stations
Station works commenced 22/01/2018 40% 15%
Station works complete 6/09/2018
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 3/08/2018 0% 10%
REFCL commissioned and operable 11/09/2018
Close Out REFCL at "required capacity" 23/10/2018 0% 10%
Total weighted percentage complete 54%
This zone substation is located at -37.04952584, 143.75473022 (latitude, longitude)
34
2.1.6 Colac (CLC)
CLC REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 7/11/2016
60% 15% Design complete 8/08/2018
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site 14/08/2018
Construction - Lines Line works commenced 12/04/2017
50% 20% Line works complete 27/11/2018
Construction - Stations
Station works commenced 28/06/2018 0% 15%
Station works complete 29/01/2019
Construction - Third Party
Number of affected HV Customer Connections 6
HV customer works commenced 30/05/2018 0% 20%
HV customer works complete 12/12/2018
Testing / Commissioning
REFCL testing / commissioning commenced 30/01/2019 0% 10%
REFCL commissioned and operable 5/03/2019
Close Out REFCL at "required capacity" 11/04/2019 0% 5%
Total weighted percentage complete 34%
This zone substation is located at -38.34056225, 143.60615730 (latitude, longitude)
35
2.1.7 Winchelsea (WIN)
WIN REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 1/05/2016
100% 5% Business Case approval 13/07/2016
Design Design commenced 1/12/2016
87% 20% Design complete 26/06/2018
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 15%
REFCL delivered to site 14/08/2018
Construction - Lines Line works commenced 12/04/2017
35% 25% Line works complete 5/09/2018
Construction - Stations
Station works commenced 28/06/2018 0% 15%
Station works complete 11/10/2018
Construction - Third Party
Number of affected HV Customer Connections 0
HV customer works commenced 0% 0%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 17/11/2018 0% 10%
REFCL commissioned and operable 30/11/2018
Close Out REFCL at "required capacity" 7/03/2019 0% 10%
Total weighted percentage complete 45%
This zone substation is located at -38.23622505, 144.00288820 (latitude, longitude)
36
2.1.8 Eaglehawk (EHK)
EHK REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 6/02/2018
100% 5% Business Case approval 10/03/2017
Design Design commenced 27/11/2017
80% 15% Design complete 29/06/2018
Procurement
Number of REFCL units required 2
REFCL order placed 24/03/2017 95% 10%
REFCL delivered to site 14/08/2018
Construction - Lines Line works commenced 25/06/2018
20%
Line works complete 31/10/2018
Construction - Stations
Station works commenced 2/07/2018
15%
Station works complete 26/10/2018
Construction - Third Party
Number of affected HV Customer Connections 8
HV customer works commenced 15/10/2018 0% 20%
HV customer works complete 30/11/2018
Testing / Commissioning
REFCL testing / commissioning commenced 5/11/2018 0% 10%
REFCL commissioned and operable 10/12/2018
Close Out REFCL at "required capacity" 21/12/2018 0% 5%
Total weighted percentage complete 27%
This zone substation is located at -36.73592644, 144.27855492 (latitude, longitude)
37
2.1.9 Ballarat North (BAN)
BAN REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 1/06/2018
0% 15% Design complete 26/10/2018
Procurement
Number of REFCL units required 3
REFCL order placed 13/08/2018 0% 10%
REFCL delivered to site 13/02/2019
Construction - Lines Line works commenced 12/11/2018
0% 20% Line works complete
Construction - Stations
Station works commenced 12/11/2018 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 9
HV customer works commenced 12/11/2018 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -37.53477699, 143.84742737 (latitude, longitude)
38
2.1.10 Charlton (CTN)
CTN REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 1/06/2018
0% 15% Design complete 26/10/2018
Procurement
Number of REFCL units required 1
REFCL order placed 13/08/2018 0% 10%
REFCL delivered to site 13/02/2019
Construction - Lines Line works commenced 12/11/2018
0% 20% Line works complete
Construction - Stations
Station works commenced 12/11/2018 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 12/11/2018 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.27399871, 143.36318135 (latitude, longitude)
39
2.1.11 Ballarat South (BAS)
BAS REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 17/09/2018
0% 15% Design complete 28/02/2019
Procurement
Number of REFCL units required 3
REFCL order placed 30/11/2018 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced 1/03/2019
0% 20% Line works complete
Construction - Stations
Station works commenced 1/03/2019 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 5
HV customer works commenced 1/03/2019 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -37.57505901, 143.82751465 (latitude, longitude)
40
2.1.12 Bendigo Terminal Station (BETS)
BETS REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 17/09/2018
0% 15% Design complete 28/02/2019
Procurement
Number of REFCL units required 2
REFCL order placed 30/11/2018 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced 1/03/2019
0% 20% Line works complete
Construction - Stations
Station works commenced 1/03/2019 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 4
HV customer works commenced 1/03/2019 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.78490276, 144.25368547 (latitude, longitude)
41
2.1.13 Bendigo (BGO)
BGO REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 1/03/2019
0% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 2
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -36.77055176, 144.27696705 (latitude, longitude)
42
2.1.14 Geelong (GL)
GL REFCL Project Activities Forecast
Date Percentage Complete
Weighting
Initiate Business Case commenced 11/09/2017
100% 5% Business Case approval 27/10/2017
Design Design commenced 1/03/2019
0% 15% Design complete
Procurement
Number of REFCL units required 2
REFCL order placed 0% 10%
REFCL delivered to site
Construction - Lines Line works commenced
0% 20% Line works complete
Construction - Stations
Station works commenced 0% 15%
Station works complete
Construction - Third Party
Number of affected HV Customer Connections 1
HV customer works commenced 0% 20%
HV customer works complete
Testing / Commissioning
REFCL testing / commissioning commenced 0% 10%
REFCL commissioned and operable
Close Out REFCL at "required capacity"
0% 5%
Total weighted percentage complete 5%
This zone substation is located at -38.12868286, 144.34043884 (latitude, longitude)
43
2.2 ELCA program status [S120P(1)(c)(ii)]
ELCA description Project Name Bare OH retired
(kms)
Region 9 Fogarty 26.5
Region 18 Coliban 1 35.4
44
2.3 SWER ACR program status [S120P(1)(c)(iii)]
For the next reporting period Powercor plans to install 265 Automatic Circuit Reclosers (ACR) in relation to Single Wire Earth Return (SWER) lines. Details are provided in the following table.
ACR NAME FEEDER FORECAST
COMPLETION DATE
RUSSELLPARK P25 ISO BAS011 Q3 2018
STONORTH P5 ISO BAS011 Q3 2018
EURAMSOUTH 9 ISO BAS011 Q3 2018
BALMORAL SOUTH 16 ISO HSM002 Q3 2018
TELANGATUK P157 ISO HSM002 Q3 2018
GLENVALE 6 ISO HSM002 Q3 2018
DOUGLAS P37 ISO HSM002 Q3 2018
BALMORAL 234 ISO HSM002 Q3 2018
TELANGATUK EAST 35 ISO HSM002 Q3 2018
BRIMPAEN 114 ISO HSM002 Q3 2018
BRIMPAEN 79 ISO HSM002 Q3 2018
TEN MILE P268R ISO HSM002 Q3 2018
DARRAGAN SWAMP P224R ISO HSM002 Q3 2018
LOWAN ISO 5 HSM002 Q3 2018
COLRAINE 3 ISO HSM002 Q3 2018
HOTS-CHM/IKA 138R ISO HSM002 Q3 2018
CLEAR LAKE SOUTH 2 ISO HSM002 Q3 2018
GLENGLEESON P1 ISO HTN001 Q3 2018
MACARTHUR NTH P23 ISO HTN001 Q3 2018
CLOVER LEA P404A ISO HTN001 Q3 2018
BRISBANE HILL ESTATE ISO P665 HTN001 Q3 2018
CARTYS ESTATE ISO P686 HTN001 Q3 2018
ROWE P524 ISO HTN001 Q3 2018
ANNETT P36 ISO HTN001 Q3 2018
WARRABKOOK P553 ISO HTN001 Q3 2018
EMMERSON P39 ISO HTN002 Q3 2018
MORGIANA ISO HTN002 Q3 2018
45
TAHARA P108 ISO HTN002 Q3 2018
GLENORCHY 91 ISO HTN002 Q3 2018
SANDFORD SOUTH ISO HTN002 Q3 2018
PASCHENDALE 54 ISO HTN002 Q3 2018
MOCAMBORO RD P3 ISO HTN002 Q3 2018
MIAKITE 15 ISO HTN002 Q3 2018
CORNDALE P33 ISO HTN002 Q3 2018
MIRA 3 ISO KRT012 Q3 2018
TARRONE NTH ISO 38 KRT013 Q3 2018
PYE P118 ISO KRT013 Q3 2018
ORFORD 84 ISO KRT013 Q3 2018
BESSIEBELLE 129 ISO KRT013 Q3 2018
WILLATOOK P8 ISO KRT013 Q3 2018
CARRA P1 ISO MNA014 Q3 2018
MALONEY ISO 26 MNA014 Q3 2018
BALDI P2B ISO MNA034 Q3 2018
MURCHISON ISO 130 MNA034 Q3 2018
LOCHIEL P3 ISO NHL015 Q3 2018
PELLA P4 ISO NHL015 Q3 2018
JEPARIT GOLF P14 ISO NHL015 Q3 2018
RAINBOW EAST P2 ISO NHL015 Q3 2018
ALBACUTYA WEST P6 ISO NHL015 Q3 2018
GLENLEE ISO 39 NHL015 Q3 2018
RAINBOW WEST P23 ISO NHL015 Q3 2018
JEPARIT P590 ISO NHL015 Q3 2018
ANTWERP P2 ISO NHL015 Q3 2018
KENMARE P3 ISO NHL015 Q3 2018
PEPPERS PLAINS P7 ISO NHL015 Q3 2018
ELLAM P5 ISO NHL015 Q3 2018
ARKONA P5 ISO NHL015 Q3 2018
KATYIL P2 ISO NHL015 Q3 2018
JEPARIT P637 ISO NHL015 Q3 2018
TARRANYURK EAST P4 ISO NHL015 Q3 2018
ELLAM NORTH 4 ISO NHL015 Q3 2018
GERANG P22 ISO NHL015 Q3 2018
GERANG WERNER 3 ISO NHL015 Q3 2018
KINWIN 3 ISO NHL015 Q3 2018
46
WOORAK 4 ISO NHL015 Q3 2018
NETHERBY NORTH 1 ISO NHL016 Q3 2018
PROPODOLLAH 11 ISO NHL016 Q3 2018
NETHERBY ISO 155 NHL016 Q3 2018
DETPA WEST ISO 87 NHL016 Q3 2018
DOLLAH EAST ISO 2 NHL016 Q3 2018
WOORAK WEST ISO 3 NHL016 Q3 2018
LILLIMUR SOUTH ISO 7 NHL031 Q3 2018
KANIVA SOUTH P18 ISO NHL031 Q3 2018
LEEOR ISO 1 NHL031 Q3 2018
LAWLOIT TOWN 3 ISO NHL031 Q3 2018
BUNYIP 3 ISO NHL031 Q3 2018
YEARINGA P7 ISO NHL031 Q3 2018
YANAC WEST ISO 1 NHL031 Q3 2018
COVE P1 ISO NHL031 Q3 2018
YANAC NORTH ISO 4 NHL031 Q3 2018
PEECHEMBER SWAMP P2 ISO NHL031 Q3 2018
TELOPIA DOWNS 14 ISO NHL031 Q3 2018
BOYEO ISO NHL031 Q3 2018
BOYEO WEST ISO 5 NHL031 Q3 2018
HOMELEIGH 2 ISO NHL031 Q3 2018
KANIVA 184 ISO NHL031 Q3 2018
PURNIM 229 ISO WBL005 Q3 2018
WANGOOM PARK EAST P2 ISO WBL005 Q3 2018
SETTLEMENT 1 ISO WBL005 Q3 2018
PENNYROYAL CREEK P3 ISO WIN011 Q3 2018
EVANSFORD P22 ISO BAN006 Q4 2018
BUNDING 14 ISO BAN011 Q4 2018
LALFALLS 13 ISO BAN011 Q4 2018
JANCOURT EAST ISO 90 CDN001 Q4 2018
HOLLAWAY P36 ISO CDN001 Q4 2018
VITE VITE P6 ISO CDN006 Q4 2018
TRAWALLA ISO 10 CDN006 Q4 2018
PURA PURA RD ISO 134 CDN006 Q4 2018
TARRAYOUKYAN ISO 7 CHM011 Q4 2018
TALLENGOWER P79 ISO CHM011 Q4 2018
FULLERTON RD 7 ISO CHM011 Q4 2018
47
BARKALA ISO 2 CHM011 Q4 2018
MUNDARRA P3 ISO CHM011 Q4 2018
PATYAH EAST WEST ISO CHM011 Q4 2018
CHETWYND SOUTH ISO P1 CHM011 Q4 2018
AVONDALE ISO P2 CHM011 Q4 2018
CONNEWIRRECOO ISO 16 CHM011 Q4 2018
PATYAH ISO 53 CHM011 Q4 2018
YARALLA ISO 236 CHM011 Q4 2018
BRINGALBERT ISO 274 CHM011 Q4 2018
ROSEVILLE 2 ISO CHM011 Q4 2018
JALLAKIN 10 ISO CHM011 Q4 2018
MULLINGER ISO 48 CHM011 Q4 2018
ULLSWATER ISO 1 CHM011 Q4 2018
SCRUBBY LAKE ISO 2 CHM011 Q4 2018
WARTOOK 181 ISO HSM001 Q4 2018
ASHENS 7 ISO HSM001 Q4 2018
COROMBY SOUTH ISO 3 HSM001 Q4 2018
BUNGALALLY 6 ISO HSM001 Q4 2018
JUNG NORTH ISO 17 HSM001 Q4 2018
MOOR PARK 5 ISO HSM001 Q4 2018
TAYLORS LAKE 1 ISO HSM001 Q4 2018
TAYLORS SOUTH 2 ISO HSM001 Q4 2018
WARTOOK P131 ISO HSM001 Q4 2018
DIGBY WEST P217 ISO HTN002 Q4 2018
DORODONG 68 ISO HTN002 Q4 2018
BAHGALLAH P58 ISO HTN002 Q4 2018
KILLARA P28 ISO HTN002 Q4 2018
MYARING ISO HTN002 Q4 2018
LAKE MUNDI P4 ISO HTN002 Q4 2018
MERINO DOWNS P193 ISO HTN002 Q4 2018
MERINO 173 ISO HTN002 Q4 2018
SANDFORD EAST P31 ISO HTN002 Q4 2018
PORTLAND RD P2 ISO HTN002 Q4 2018
WALLACEDALE NTH P4 ISO HTN002 Q4 2018
WALLACEDALE NTH P17 ISO HTN002 Q4 2018
CHERITTA P9 ISO HTN002 Q4 2018
RETREAT P1 ISO HTN002 Q4 2018
48
TIMBER P1 ISO HTN002 Q4 2018
BARBER P1 ISO HTN002 Q4 2018
BRANXHOLME P334 ISO HTN002 Q4 2018
STRATHDOWNIE P265 ISO HTN002 Q4 2018
STRATHLIN P16 ISO HTN002 Q4 2018
TARRANLEA 2 ISO HTN006 Q4 2018
SHARAM P86 ISO HTN006 Q4 2018
SHINE P81 ISO HTN006 Q4 2018
CARAPOOK P2 ISO HTN006 Q4 2018
COLERAINE P177 ISO HTN006 Q4 2018
COLERAINE P373 ISO HTN006 Q4 2018
VERDANT HILLS P3 ISO HTN006 Q4 2018
COLERAINE P437 ISO HTN006 Q4 2018
POVEY P2 ISO HTN006 Q4 2018
WANDO VALE P4 ISO HTN006 Q4 2018
WANDO VALE P14 ISO HTN006 Q4 2018
COLERAINE 246 ISO HTN006 Q4 2018
PLD-HTN P209 ISO HYT011 Q4 2018
PLD-HTN P301 ISO HYT011 Q4 2018
PAIGNIE ISO 6 OYN001 Q4 2018
WALPEUP SOUTH ISO P2 OYN001 Q4 2018
BOULKA SOUTH ISO 8 OYN001 Q4 2018
KATTYOONG P20A ISO OYN001 Q4 2018
GALAH NORTH ISO 10 OYN001 Q4 2018
OUYEN WEST ISO 3 OYN001 Q4 2018
DUDDO ISO 15 OYN001 Q4 2018
UNDERBOOL SOUTH ISO OYN001 Q4 2018
BOINKA NORTH ISO P2 OYN001 Q4 2018
TORRITA NORTH ISO 7 OYN001 Q4 2018
BOINKA SOUTH ISO 9 OYN001 Q4 2018
COWANGIE SOUTH ISO OYN001 Q4 2018
PANITYA SOUTH ISO 15 OYN001 Q4 2018
TUTYE SOUTH ISO 33 OYN001 Q4 2018
UNDERBOOL NORTH ISO OYN001 Q4 2018
BOLTON 70 ISO OYN003 Q4 2018
COCAMBA ISO 291 OYN003 Q4 2018
WINNAMBOOL ISO 3 OYN003 Q4 2018
49
PIER MILLAN ISO P2 OYN003 Q4 2018
LEITPAR ISO 2 OYN003 Q4 2018
KIAMAL EAST ISO 1 OYN003 Q4 2018
BOLAND ISO 2 OYN003 Q4 2018
POHLNER ISO 3 OYN003 Q4 2018
HOPETOUN EAST ISO OYN005 Q4 2018
JOLLY ISO 2 OYN005 Q4 2018
TURRIFF WEST ISO 4 OYN005 Q4 2018
TYRRELL ISO 8 OYN005 Q4 2018
TEMPY NORTH ISO 1 OYN005 Q4 2018
TEMPY EAST ISO 3 OYN005 Q4 2018
EDLESTON ISO 371E OYN005 Q4 2018
BANYAN ISO 3 OYN005 Q4 2018
DERING ISO 1 OYN005 Q4 2018
WATCHUPGA EAST ISO P3 OYN005 Q4 2018
OATS ISO 5 OYN005 Q4 2018
WOOMELANG NORTH ISO OYN005 Q4 2018
WATCHUPGA WEST ISO 2 OYN005 Q4 2018
NYALLO ISO 2 OYN005 Q4 2018
NANDALY WEST ISO 73 OYN005 Q4 2018
NUNGA EAST 1 ISO OYN005 Q4 2018
CLEARY P1 ISO RCT022 Q4 2018
CARWARP WEST ISO 1A RCT022 Q4 2018
HATTAH LAKES ISO 32E RCT022 Q4 2018
YARRARA NTH ISO 311 RCT023 Q4 2018
CULLULLERAINE ISO RCT023 Q4 2018
PIRLTA SOUTH ISO 3 RCT023 Q4 2018
MERRINEE NTH ISO P1 RCT023 Q4 2018
BENETOOK ISO 102 RCT023 Q4 2018
MALLANBOOL ISO 265 RCT023 Q4 2018
MERRINEE SOUTH ISO P3 RCT023 Q4 2018
TUNART ISO 1 RCT023 Q4 2018
LANE ISO 8 SHN024 Q4 2018
MARIONVALE ISO 36 SHN024 Q4 2018
MUNDAY ISO 33 SHP012 Q4 2018
APPLEBY P1 ISO SHP012 Q4 2018
LEES P36 ISO SHP012 Q4 2018
50
MEAG ISO 13 SHP014 Q4 2018
TILTON P2 ISO SHP021 Q4 2018
CLARKSON ISO 13 SHP021 Q4 2018
VAN EVERY ISO 8 TRG002 Q4 2018
CREARERS LANE 1 ISO TRG002 Q4 2018
BERRAMBOOL ISO 3 TRG002 Q4 2018
HOPKINS HILL ISO 5 TRG002 Q4 2018
CARAMUT NTH ISO 5 TRG002 Q4 2018
BARWIDGEE EAST 1A ISO TRG002 Q4 2018
TOURAC ISO 1 TRG002 Q4 2018
GASPOWER P4 ISO TRG002 Q4 2018
CAIRNLEA P27 ISO TRG002 Q4 2018
ROCK GROVE P6 ISO TRG002 Q4 2018
EWING P2 ISO TRG002 Q4 2018
ELLERSLIE P55 ISO TRG002 Q4 2018
MATS 7 ISO TRG004 Q4 2018
MCCONNELLS RD 1 ISO TRG004 Q4 2018
BRUCKNELL 1 ISO TRG005 Q4 2018
KOOLOONONG ISO 50 BBD014 Q1 2019
ARNOLD ISO 15 BET001 Q1 2019
DULLARD RD P1 ISO ECA012 Q1 2019
STONECHURCH ISO 2 HSM003 Q1 2019
YELLANGIP 2 ISO HSM003 Q1 2019
LAH EAST ISO 4 HSM003 Q1 2019
ROSEBERY EAST 3 ISO HSM003 Q1 2019
HOPEVALE ISO 384 HSM003 Q1 2019
BEULAH WEST ISO 3 HSM003 Q1 2019
GLENORE ISO 4 HSM003 Q1 2019
LONGERENONG P7 ISO HSM003 Q1 2019
AREEGRA ISO P1 HSM003 Q1 2019
AUBREY ISO HSM003 Q1 2019
HOMECROFT ISO 30 HSM003 Q1 2019
BRIM ISO 23 HSM003 Q1 2019
GOLF HILL ISO 326 HSM003 Q1 2019
HOMECROFT P102 ISO HSM003 Q1 2019
BURROIN 7 ISO HSM003 Q1 2019
GALAQUIL EAST ISO 1 HSM003 Q1 2019
51
BRIM EAST ISO 3 HSM003 Q1 2019
ROSEDALE ISO 67 HSM003 Q1 2019
WERRIGAR ISO 15 HSM003 Q1 2019
BYRNEVILLE 2 ISO HSM005 Q1 2019
KELLALAC EAST P3 ISO HSM005 Q1 2019
WARRACKNABEAL P280 ISO HSM005 Q1 2019
AILSA P10 ISO HSM005 Q1 2019
KAPUNDA 4 ISO HSM005 Q1 2019
SHEEP HILLS ISO 7 HSM005 Q1 2019
DOOEN NORTH P2 ISO HSM005 Q1 2019
CANNUM P3 ISO HSM005 Q1 2019
SEACH ISO 2 STN011 Q1 2019
KARRA SCHOOL ISO 1 STN011 Q1 2019
HOARE 4 STN024 Q1 2019
MONTI ISO 4 STN024 Q1 2019
GOOCHS LANE P59 ISO WND013 Q1 2019