22
Power Transformer Load Loss Measurement Gert Rietveld Ernest Houtzager Milos Acanski Dennis Hoogenboom Enrico Mohns Henrik Badura Ilija Pecelj ELPOW workshop, 31 Aug 2016

Power Transformer Load Loss Measurement

Embed Size (px)

Citation preview

Page 1: Power Transformer Load Loss Measurement

Power Transformer Load Loss Measurement

Gert RietveldErnest HoutzagerMilos AcanskiDennis HoogenboomEnrico MohnsHenrik BaduraIlija Pecelj

ELPOW workshop, 31 Aug 2016

Page 2: Power Transformer Load Loss Measurement

• Power transformers - losses

• Why loss measurements?

• Transformer loss measurement systems

• ELPOW: TLMS calibration systems

• Summary

Outline

2

Page 3: Power Transformer Load Loss Measurement

Power transformers are used toscale voltages in the grid

High Voltage low losses

Power Transformers

3

Page 4: Power Transformer Load Loss Measurement

Loss mechanisms:1. No load losses (Zb = ), caused by iron core, continuous2. Load losses (Zb = 0 ), copper loss, depends on current3. Stray losses depend on design

Power transformer losses

4

1

2

Page 5: Power Transformer Load Loss Measurement

Why loss measurements (1)

• Cost of losses in power transformers are comparable to the productcost TCO (total cost ownership)

• Environmental impact is significant

Cost of (no-)load loss equals product costs

Page 6: Power Transformer Load Loss Measurement

Consequence: regulations - EcoDesign Directive:“improve environmental performance of energy-

related products through better design”

Why loss measurements (2)

6

Saving potential in use phase through more efficient designsestimated as 16 TWh/year ( 17 % of present losses)3.7 Mt of CO2 emissions (50 % of total Danish electricity consumption)

Page 7: Power Transformer Load Loss Measurement

Consequence: more requirements in standardsIEC 60076-19 (uncertainty calculation), and upcoming IEC 60076-20:

Why loss measurements (3)

7

Tier 1: 1 July 2015Tier 2: 1 July 2021

99.1

99.2

99.3

99.4

99.5

99.6

99.7

99.8

99.9

0 20 40 60 80 100 120

Min

imum

PEI

[%]

Rated Power [MVA]

Liquid immersed - Tier 1Liquid immersed - Tier 2Dry-Type - Tier 1Dry-Type - Tier 2

Page 8: Power Transformer Load Loss Measurement

Consequence: customers (utilities) put fines on losses in excess ofguaranteed maximum losses

Example calculation for a large transformer (100 MVA)• Guaranteed maximum losses: Pgar = 500 kW (0.5 % loss)• Fine for excess losses: 10.000 €/kW

Why loss measurements (4)

8

Reliable loss measurement with low uncertaintygives confidence and less discussions

3 % measurement uncertainty (150 ppm) corresponds to500 kW · 3 % · 10.000 €/kW = 150.000 €

(manufacturer and customer have to decide who pays for uncertainty)

Page 9: Power Transformer Load Loss Measurement

Prob

abili

ty

Loss

Uncertainty matters! (compliance)

9

Actual loss

Ecodesign limit

Test resultfails to detectcompliance

Accurate test

Inaccurate test

Ecodesign allows no tolerance: if measured loss is above the limit,the transformer is not in conformity

High accuracy =low risk of incorrectdecisions

Page 10: Power Transformer Load Loss Measurement

TLMS typical measurement range: 0 – 100 kV, 0 – 2 kAUncertainty: 3 % - 5 % (IEEE C57.12.00, IEC 60076-19, Ecodesign)

Traceable to international measurement standards

Transformer Loss Measurement

Power supply P = V · I · cos

Page 11: Power Transformer Load Loss Measurement

Power: P = U · I · cos with 90

P = U · I · cos (90 - ) = U · I · with = (90 - ) 0

Measurement challenge

11

phase accuracy, not amplitude accuracy required!!

U and I are large numbers 1 % uncertainty is very easyis a very small number:for PF=0.01, = 0.57 1 % uncertainty is a big challenge!

(6 m , 0.34 min, 100 µrad)

TLMS consists of high-quality components

1 % losses

Page 12: Power Transformer Load Loss Measurement

Only a calibrated TLMS system, traceable to national standards, givesproven, reliable quality in load loss measurements

TLMS calibrations

12

Two approaches in TLMS calibrations• Component calibration (< 0.5 %; at PF=0.01 0.2 min, 3 m )

Easier to perform, larger overall system uncertainty• System calibration (< 3 %; at PF=0.01 1 min, 17 m )

Difficult to perform, low uncertainty, all effects included

Increased measurement challenge: TUR = 3 – 10

Reference measurement accurate to < 0.15 min (50 µrad, 3 m )

Page 13: Power Transformer Load Loss Measurement

Aim: system calibration of TLMS up to 100 kV and 2 kA, with anuncertainty of better than 50 µW/VA

ELPOW aim for TLMS calibration

13

Two approaches:

• Simultaneous generation of voltage V and current I

• Phase lock current I to externally applied voltage V

• Realise feedback loop

Page 14: Power Transformer Load Loss Measurement

LMS for testing power trafos

Generating part Measuring part

• “voltage and current up to 150 kV and at least 2 kA…”• “uncertainties better than 50 ppm…”

Page 15: Power Transformer Load Loss Measurement

Generation: phantom power

30 kVA0 V - 250 V

10 kVAR1: 0 A – 50 AR2: 0 A – 25 A

To do:• Stability transconductance amplifier must be optimized• Assessment of the phantom power source

2 channel source• 16 bit DACs• 10 VPK• phase lock• external synchronization

or 15 Hz … 60 Hz intern DACor 50 Hz line

Page 16: Power Transformer Load Loss Measurement

Measuring system

Voltage TransformerClass 0.02

Current TransformerClass 0.002

Power ComparatorClass 0.01

U, I, , P, Q, S

I = 2 kA

U = 150 kV

LabView Software

To do overview:1. Optimization of the software

• timing to read the comparator• automatic correction of the transformer error

2. Uncertainty calculation3. Assessment of the system

Page 17: Power Transformer Load Loss Measurement

Challenge: lock I to Vwithin 0.3 m (5 µrad)

TLMS system calibration

17

V I

DSP is a key element2nd reference CT + RD22 watt meter as check

Page 18: Power Transformer Load Loss Measurement

Actual VSL implementation

18

Control (DSP)

Power amplifier (G)

Transformer /current generator

Power reference (RD22 watt meter)

CTs(3-stage compensated)

VT (CC-based capacitive divider)

Page 19: Power Transformer Load Loss Measurement

Generation:• Rohrer wideband amplifier (20 A, 150 V) + step-up transformer

Measurement:• VT: HV capacitor (100 pF, 100 kV) + CC-based LV divider

– Uncertainty: 15 – 25 ppm (phase / magnitude)• CT: 3-stage wideband; errors < 1 ppm (uncertainty 5 ppm)

– Wideband 5 A shunt for conversion to voltage• Power: two 24-bit ADCs (NI)Expected overall phase uncertainty: < 25 ppm (25 µrad)

Verification: RD22 power meter (< 10 ppm) + CT + VT

Components of VSL system

19

Page 20: Power Transformer Load Loss Measurement

The control loop has 2 main parts:

First part: high speed. Second part: high accuracy ( feedback)(NRC analogue system needs accurate 90 reference signal)

Results:• Extensive testing with different voltage signals; different phase

shifting blocks studied• Low noise: 4 – 5 µrad; agreement with power meter < 10 µrad

Control loop

20

ADC

90°

V [n] DAC

I

Q

I [n-m]

Phaseshifting

Z-n

Page 21: Power Transformer Load Loss Measurement

• Much more noise than in lab (30 µrad vs 5 µrad)• Agreement VSL LL and RD22 reference: within 15 ppm• Agreement with NRC better than 25 ppm

First on-site trial

21

Page 22: Power Transformer Load Loss Measurement

Power transformer losses are significant– Economically: TCO and fines– Environment: CO2 emissions

Requirements from EU regulations,IEC / IEEE on both the actual lossesand measurement accuracy

Conclusion

22

Transformer Loss Measurement Systems need calibration– Proven, validated accuracy < 3 % @ PF = 0.01– ELPOW: System calibration < 0.5 % @ PF = 0.01

– simultaneous generation– current phase locking

(promising first results < 0.3 %!)