Upload
lacey-allison
View
29
Download
0
Embed Size (px)
DESCRIPTION
Power System Restoration. Kevin Schneider, Chen-Ching Liu University of Washington Department of Electrical Engineering. Status Data and Analog Measurements. Voltage, Current, Power Limit Checking. All Operating Constraints Satisfied. Operating Constraint's) Violated. Loss of Load. - PowerPoint PPT Presentation
Citation preview
Power System Restoration
Kevin Schneider, Chen-Ching Liu
University of Washington
Department of Electrical Engineering
Overview
Voltage, Current, Power Limit Checking
Status Data and Analog Measurements
All Operating Constraints Satisfied Operating
Constraint's) Violated
Emergency Control /Load Management
Security Assessment System Restoration
Loss of Load
Restoration Constraints
Main power converter startup time Communications start up time Maximum dv/dt Node voltage limits
Main Power Converter Startup Time
10-15 second startup delay from when power is applied to the backbone
During this time:o Startup supply capacitor charges to 48Vo SCRs begin to fire at 45Vo Startup power supply energizedo Main power converter control circuits
energized
Communications Startup Time
Approximately ½ to 1 minute for the communications system to power up
Maximum DV/DT
PN junctions in solid state components are sensitive to high values of DV/DT
DI/DT will not be a concern for the NEPTUNE systems backbone solid state components
Node Voltage Limits
If node voltage drops below≈ 5600V the control circuit will drop out and the converter will turn off
Voltage cannot exceed certain levels or there could be arc over
There will be an acceptable band of operation that must be adhered to
Security Analysis
Secure
Insecure
Emergency RestorativeEmergency Control Action
RestorativeControl Action
Normal Conditions
Security Analysis Cont.
Switching Action- For a restorative action there may be several possible ways to restore the system.
Feasibility- A portion of these actions will place the system in insecure configuration for some period of time. Only switch actions which do not violate any constraint can be allowed.
Note: a system may meet all 4 constrains but be operating in an insecure condition
Contingency Selection
Before a switching action is performed the effect of the following must be considered for the new topology Loss of shore station Loss of shallow water links or deep water
links Significant load increase Node failures Others
Black Start Example
Only the shore stations have power After a node is fully energized, 4 kW of
scientific load is applied to that node
Victoria
Nedonna Beach
System Start-up From Black Start
Ensuring Voltage Limits
942
185V
72V18V
Summary
Before every switching action Ensure all 4 constraints are meet Ensure transition is to a secure situation